27045RFI - MPCS_Preschool_Expansion_RFI_eVA.pdf

PDF 245 KB Posted

Attached to
RFI - Preschool Building Expansion
Solicitation number
RFI-131978
Issued by
Prince William County, Virginia

About this file

This is a Request for Information (RFI) issued by Manassas Park City Schools (MPCS) seeking architectural, engineering, and project management services to assess the feasibility, cost, and schedule for expanding its preschool building located at 9296 Cougar Court, Manassas Park, Virginia. The project proposes adding a second story to the existing 12,120-square-foot building constructed in 2009, which would house four classrooms and a multipurpose room mirroring the first-floor configuration. The RFI is nonbinding and intended for planning purposes only to establish a realistic budget and determine whether further investigation is warranted before proceeding to a Request for Proposal. An optional site visit is scheduled for November 23, 2026, at 3:00 PM EST, with questions due by November 24, 2026, at 4:00 PM EST. MPCS will respond to questions by December 3, 2026, and RFI responses are due December 10, 2026, at 4:00 PM EST. Submissions must be made through eVA (https://eva.virginia.gov). The projected construction start date is summer 2029, with no specific award date or contract term applicable to this information-gathering phase.

Respondents must provide low, most likely, and high nonbinding budget ranges in current U.S. dollars supported by stated assumptions and evidence, with separate identification of design development and construction contingencies. The estimate must address construction costs, professional services across five project phases (programming and feasibility, schematic design, construction documents, construction administration, and closeout), owner costs, escalation, operating costs, and optional alternatives. Respondents should identify missing information that prevents estimation of material items and explain the limitations of their estimates. The RFI does not establish any set-asides, and no compensation will be paid to vendors for responding. All data, materials, and documentation prepared in response become the exclusive property of MPCS and are subject to public inspection under the Virginia Freedom of Information Act, unless vendors invoke trade secret protections by specifically identifying proprietary information in writing at the time of submission. Vendors may submit one searchable PDF organized by specified sections, with the cost and schedule tables optionally provided in an editable spreadsheet.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MANASSAS PARK CITY SCHOOLS | PRESCHOOL EXPANSION RFI

Preschool Expansion RFI | Page 1

Request for Information Preschool Building Expansion

Architectural and Engineering Services and Preliminary Total Project Budget

1 Project Overview and Purpose Manassas Park City Schools (MPCS) seeks information from architectural, engineering, and project management firms to assess the feasibility, likely total cost, and schedule of adding a story to its existing preschool building. The proposed addition would house four classrooms and a multipurpose room.

Our primary purpose is to establish a realistic planning budget and determine what further investigation is needed before deciding whether to proceed to a future Request for Proposal (RFP). Provide nonbinding budget ranges supported by stated assumptions. No design work or completed feasibility study is required in response to this RFI.

The second-story concept has not been confirmed as feasible. Respondents should identify material uncertainties and may recommend alternatives for comparison.

RFI information MPCS entry

RFI number and project title RFI #27045RFI – Pre-K Expansion

Release date November 19, 2026

Optional site visit November 23, 2026, at 3:00 PM EST (Please email Primary Contact to register)

Questions due November 24, 2026, at 4:00 PM EST

MPCS response to questions due December 3, 2026, at 4:00 PM EST

RFI responses due December 10, 2026, at 4:00 PM EST

Primary contact Andrew Neff, Finance & Purchasing Specialist (andrew.neff@mpark.net)

Submission method https://eva.virginia.gov

2 Common Estimating Basis MPCS will complete the following information before release and identify unavailable information as unknown. All respondents must use this common basis, explicitly identify assumptions for unknown items, and separately explain deviations.

Project information MPCS entry

Building and site 9296 Cougar Ct, Manassas Park, VA 20111, Built in 2009, 12,120 SqFt

Addition size and capacity Mirror first floor

Existing records Unknown

Schedule and operations Construction starts projected to begin in summer of 2029.

mailto:andrew.neff@mpark.net

Preschool Expansion RFI | Page 2

3 Existing Building Feasibility and Alternatives Using the information provided, identify the principal feasibility questions, likely cost consequences, and records or investigations needed to resolve them. Distinguish known information from assumptions. Do not represent unverified conditions as established facts.

3.1 Conditions to Evaluate

• Existing foundations and structural framing, including whether the original building was designed for an additional story and whether strengthening may be needed.

• Roof removal or reconstruction, temporary weather protection, construction sequencing, crane access, staging, and protection of occupied areas.

• Stairs, accessible vertical access, emergency exits, circulation, and effects on the existing building layout.

• Capacity and potential upgrades to heating, cooling, ventilation, electrical, plumbing, fire protection, technology, and security systems.

• Applicable code, zoning, accessibility, life safety, and permitting considerations; identify potential requirements for work in the existing building that require confirmation.

• Site, utility, parking, drainage, and stormwater impacts, as applicable; identify potential hazardous materials investigations based on building age and records.

• Preschool operations, child safety, noise, dust, access control, temporary classrooms, relocation, and limits on work during the school year.

3.2 Initial Feasibility Study

Describe a practical initial study that would allow MPCS to confirm whether the concept warrants further design.

Identify the disciplines, records, site access, field investigations, and testing needed; the anticipated deliverables;

and the major decisions the study would resolve.

Provide a nonbinding low, most likely, and high cost range and duration for this study. State whether testing, destructive investigation, surveys, and concept alternatives are included or separately estimated. Identify what level of project cost estimate the study could reasonably support.

3.3 Alternatives for Comparison

Identify whether a ground-level addition, reconfiguration of existing space, or another approach merits comparison.

Explain the main feasibility, operational, schedule, and cost differences. Price any alternatives separately using comparable capacity and scope assumptions. Identify any site or building information needed before a meaningful comparison can be made.

3.4 Risks and Next Steps

List the most significant risks to feasibility, cost, and schedule. For each, identify the unresolved condition, its potential effect, and the investigation or decision needed. Recommend which questions should be resolved before MPCS establishes a project funding amount or issues a future RFP.

Preschool Expansion RFI | Page 3

4 Anticipated Professional Services Comment on the following five phases for this project. Identify recommended deliverables, participating disciplines, scope gaps, and services that would be additional. Explain how the proposed services would support budget decisions at each stage.

4.1 Phase I Programming and Feasibility

Describe stakeholder interviews, site visits, space and functional programming, and review of existing records.

Address the feasibility questions in Section 3, preliminary code and zoning review, conceptual alternatives, and preparation of an initial total project budget. Identify decision points before detailed design.

4.2 Phase II Schematic Design and Design Development

Describe development and comparison of schematic layouts, building massing, and architectural, structural, and mechanical, electrical, and plumbing systems. Identify the proposed cost-estimating milestones, estimate methodology, and process for reconciling the scope with the approved budget. Explain how alternatives would be evaluated if estimates exceed available funding.

4.3 Phase III Construction Documents and Procurement Support

Describe preparation of coordinated construction drawings and specifications, permit submissions, and a pre-bid construction estimate. Address bidding documents, pre-bid meetings, responses to bidder questions, addenda, bid review, and support if pricing exceeds the budget. State assumptions about the project delivery method and explain how another method would affect services or costs.

4.4 Phase IV Construction Administration

Describe the anticipated frequency and purpose of site observations, progress meetings, and written field reports.

Address review of contractor submittals and shop drawings, responses to construction Requests for Information, review of change requests and payment applications, and tracking of cost and schedule issues.

Distinguish architectural and engineering construction administration from owner project management, construction management, continuous inspection, and independent testing or special inspections. State who would provide each service, whether it is included, and what additional owner services may be needed.

4.5 Phase V Closeout and Occupancy Support

Describe substantial completion reviews, punch lists, verification of corrective work, review of contractor record drawings and operation and maintenance manuals, staff training, warranty transfer, final payment review, and coordination supporting occupancy approvals. Identify responsibility for required submissions and approvals, and whether warranty-period reviews are included.

Service Assumptions

State assumptions about project duration, meeting frequency, site visits, design revisions, consultant disciplines, and reimbursable expenses. Identify additional services and conditions that could increase professional fees. Any fee percentages must identify the construction cost basis and the services covered.

Preschool Expansion RFI | Page 4

5 Budget Estimate Requirements Complete the common cost schedule in Section 6 and provide supporting assumptions. Estimates are for planning only and are nonbinding. MPCS seeks the likely total funding requirement, including costs that MPCS may pay directly or through other providers.

5.1 Estimate Basis and Reliability

• Provide low, most likely, and high amounts in current US dollars. Explain the scenarios behind each range and the main sources of uncertainty. A most likely amount is a planning judgment, not a guaranteed outcome.

• State the estimate date, geographic market basis, pricing sources, assumed construction start, construction duration, and anticipated occupancy. Identify how long the pricing assumptions remain useful.

• State assumed gross addition area, area of alterations to existing space, capacity, quality level, and major building systems. Distinguish gross area from usable room area. If using cost per square foot, identify the applicable area and costs included.

• Identify the evidence supporting the estimate, such as comparable completed projects, current market information, or conceptual estimating. Explain adjustments for project size, location, completion date, and scope.

• Identify missing information that prevents estimation of a material item. Mark it unknown, explain its potential budget effect, and identify what would be needed to estimate it. Do not enter zero for an unknown cost.

• State the estimate’s limitations and the additional investigation or design needed to narrow the range. If a credible total cannot be provided, identify the available partial estimate and the unestimated scope.

5.2 Consistent Treatment of Costs

Enter each cost only once. Separate construction costs, professional services, and other owner costs. Identify contractor overhead, profit, general conditions, bonds, insurance, and applicable taxes or fees as included or excluded. Itemize reimbursable and third-party costs where applicable.

Show escalation separately from current-dollar costs and state its rate, period, and calculation basis. Separately identify design-development and construction contingencies or other recommended allowances. State the amount, percentage basis, and risks covered by each. Identify any contingency already embedded in an estimate to prevent double counting.

For each cost line, indicate whether it is included in that line, included elsewhere with a cross-reference, excluded from the estimate, or unknown. Use N/A only when the cost does not apply. Explain exclusions and use a separately identified allowance where supportable.

5.3 Operating Costs and Optional Scope

Separately estimate the incremental annual operating costs for utilities, maintenance, custodial services, inspections, and system upkeep. Identify any other staffing impacts for MPCS to evaluate. State the pricing year and assumptions. Keep these costs outside the capital project total.

Price optional improvements, enhancements, and alternative concepts separately from the base project. Identify opportunities to phase or reduce scope and explain the effects on classroom capacity, operations, schedule, and future costs.

Preschool Expansion RFI | Page 5

6 Standard Vendor Cost Response Complete every line. Enter low, most likely, and high amounts, or use the status instructions below. Add detail as needed without changing the summary categories. Carry each subtotal into the total only once.

Cost category Low $ Most likely $ High $ Status and notes

A. Construction at current prices

Addition construction

Existing building alterations and system upgrades

Site and utility work

Contractor indirect costs if not included above

Subtotal A

B. Professional and owner costs

Initial feasibility and investigations

Architecture and engineering through closeout

Owner project or construction management

Permits and fees

Independent testing and inspections

Furniture and instructional equipment

Technology and security

Temporary space moving and operational impacts

Other costs and reimbursables specify

Subtotal B

C. Escalation and contingencies

Escalation to assumed construction period

Design development contingency

Construction contingency

Other allowance specify

Subtotal C

TOTAL CAPITAL PROJECT A plus B plus C Status: IN = included in this line; ELSE = included elsewhere, identify line; EX = excluded; UNK = unknown; N/A = not applicable. Explain EX and UNK items in an accompanying note. An incomplete total must be labeled as partial.

Attach a phase-by-phase breakdown of professional services for Phases I–V, showing included disciplines, fee basis, and reimbursables. Reconcile that breakdown to Subtotal B, including any feasibility work already counted.

Separately summarize annual operating costs and optional alternatives requested in Section 5.

Preschool Expansion RFI | Page 6

7 Schedule and Market Feedback Complete the schedule below in calendar weeks or months and state the units used. Identify overlaps, dependencies, owner decision time, review cycles, and assumptions about school occupancy. Provide an overall duration rather than simply adding overlapping phases.

Milestone Duration range Dependencies and constraints

Initial feasibility study

Phase I Programming and budget validation

Phase II Schematic design and design development

Phase III Documents permits and procurement

Phase IV Construction and administration

Phase V Closeout and occupancy

Overall authorization through occupancy Identify current market conditions affecting lead times, contractor availability, pricing, and delivery. Explain whether summer-only work is realistic, whether multiple summers or temporary relocation may be needed, and how schedule changes would affect the estimate. Identify the assumed authorization date and earliest realistic occupancy.

8 Submission Requirements Submit one searchable PDF organized by the sections below. The completed cost and schedule tables may also be provided in an editable spreadsheet. Keep firm marketing material brief and focus on project-specific information.

• Firm profile and contact: Identify the responding firm, primary contact, relevant disciplines, licensing, and proposed consultant roles.

• Relevant experience: Provide up to three comparable projects, preferably occupied school additions or vertical expansions completed within the past five years. Identify location, completion year, area, scope, delivery method, original construction budget, final construction cost, and reasons for major differences. Distinguish construction cost from total project cost.

• Project response: Address feasibility and alternatives in Section 3, scope feedback in Section 4, budget assumptions in Section 5, the completed cost schedule in Section 6, and schedule feedback in Section 7.

Include the initial feasibility study cost and duration.

• Questions and clarifications: Submit questions to the primary contact via email by the stated deadline. MPCS will distribute material clarifications via addendum through eVA by the published date. Base responses on information shared through that process.

• The MPCS will not be liable for any costs or expenses incurred by a Vendor in connection with this RFI or any response by any Vendor to this RFI. No compensation will be paid to vendors for responding to this RFI. The costs and expenses incurred by a Vendor in the preparation, submission, and presentation of the response are the sole responsibility of the Vendor and shall not be charged to MPCS.

• Ownership of all data, materials, and documentation originated and prepared for MPCS pursuant to this RFI shall belong exclusively to MPCS and be subject to public inspection in accordance with the Virginia Freedom of Information Act. Trade secrets or proprietary information submitted by the Vendor shall not be subject to public disclosure under the Freedom of Information Act, unless otherwise required by law or a court; however, the Vendor must invoke the protection of Section 2.2-4342(F) of the Code of Virginia, in writing, either before or at the time the data or other material is submitted. The written notice must SPECIFICALLY identify the data or materials to be protected and state the reason why protection is necessary. The proprietary or trade secret material submitted must be identified by some distinct method such as highlighting or underlining and must indicate only the specific words, figures, or paragraphs that constitute trade secret or proprietary information.

The classification of an entire response document, line-item prices, and/or total prices as proprietary, or trade secrets, is NOT ACCEPTABLE.

Preschool Expansion RFI | Page 7

9 Use of information and Next Steps This RFI is for information and budget planning only. It does not constitute an RFP, a request for binding fees, or a commitment to procure services or award a contract. MPCS may use responses to refine scope, assess affordability, plan further investigation, and develop a future solicitation. Responses will not be used to rank firms for contract award. Any future procurement will be conducted through a separate applicable process.

1 Project Overview and Purpose
2 Common Estimating Basis
3 Existing Building Feasibility and Alternatives
3.1 Conditions to Evaluate
3.2 Initial Feasibility Study
3.3 Alternatives for Comparison
3.4 Risks and Next Steps
4 Anticipated Professional Services
4.1 Phase I Programming and Feasibility
4.2 Phase II Schematic Design and Design Development
4.3 Phase III Construction Documents and Procurement Support
4.4 Phase IV Construction Administration
4.5 Phase V Closeout and Occupancy Support
Service Assumptions
5 Budget Estimate Requirements
5.1 Estimate Basis and Reliability
5.2 Consistent Treatment of Costs
5.3 Operating Costs and Optional Scope
6 Standard Vendor Cost Response
7 Schedule and Market Feedback
8 Submission Requirements
9 Use of information and Next Steps