27016 - Addendum 2 - 10.23.2026.pdf

PDF 110 KB Posted

Attached to
Manokotak Distribution Transformer Purchase
Solicitation number
27016
Issued by
Alaska

About this file

This is Addendum 2 to Request for Quotation 27016 issued by the Alaska Energy Authority for the Manokotak Distribution Transformer Purchase project. The addendum clarifies specifications for the transformer procurement and maintains the RFQ due date and time of October 27, 2026, at 2:00 PM Alaska Standard Time. The primary modification addresses Item 4 in Appendix D Bid Schedule, correcting an identified error whereby the specification should read "50kVA Transformer Single Phase" rather than the previously listed "45kVA Transformer Single Phase." All bidders are required to acknowledge receipt of this addendum by email prior to the bid submission deadline.

The addendum specifies that all other terms, conditions, and specifications contained in the original RFQ documents remain unchanged. Prospective bidders must recognize that this clarification is now incorporated into the RFQ package as if originally contained therein, and failure to acknowledge receipt of the addendum may result in a bid being deemed non-responsive. No pricing information, set-asides, or funding sources are addressed in this addendum document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 1 Printed on 10/23/2026

Date: October 23, 2026 Project: Manokotak Distribution Transformer Purchase Solicitation No.: RFQ 27016 Addendum No.: 02

TO ALL PLAN HOLDERS:

The following changes, additions, clarifications, and/or deletions are hereby made part of the RFQ Documents for the above noted project, as if fully contained therein. All other terms, conditions, and specifications of the original RFQ remain unchanged.

Bidders must acknowledge receipt of this Addendum by email prior to the bid due date and time.

The RFQ Package is hereby clarified, changed or modified by the following:

CONTRACT PROVISIONS AND SPECIFICATIONS

The RFQ Due date and time of October 27, 2026, at 2:00 PM AKST remains unchanged.

QUESTIONS AND ANSWERS:

1. Question: Regarding the above subject RFQ 27016, Appendix D Bid Schedule, Item 4.

Please clarify if you want Single Phase 50kVA or Three Phase 45kVA.

Answer: There is an error in the Appendix D Bid Schedule. Item 4 should be “50kVA Transformer Single Phase”, not “45kVA Transformer Single Phase”.

END OF ADDENDUM #02