27006 _ Attachment C _ CMAR Contract.pdf

PDF 1 MB Posted

Attached to
27006 CMAR Services - Judicial Center
Solicitation number
PE-62960-NONST-2027-000000138
Issued by
Clayton County, Georgia

About this file

Contract Summary

This is a Construction Management Agreement (Base Contract) for the Athens-Clarke County Judicial Center and Parking Deck project involving the Unified Government of Athens-Clarke County, Georgia. The contract establishes the framework for a Construction Manager at Risk (CMAR) delivery method, with the contractor providing comprehensive services across pre-construction and construction phases. The project will be constructed in multiple phases and components, with specific milestone dates required throughout execution. The contractor must submit detailed Construction Cost Estimates at key intervals (within 21 days of Notice to Proceed or receipt of Schematic Design Documents, within 28 days after Design Development Documents completion, and prior to submission of the Guaranteed Maximum Price Proposal). The contractor is obligated to perform extensive design review and consulting services, prepare a construction progress schedule using Critical Path Method software, develop a comprehensive construction management plan including staffing, security, and safety programs, and provide ongoing construction supervision and cost monitoring throughout the project lifecycle. The contract identifies key stakeholders including the Design Professional (Croft and Associates, Inc.), Program Manager (Jacobs Project Management Company), and specifies that the contractor must coordinate all work while protecting existing operations on public property.

The contract establishes a Guaranteed Maximum Price (GMP) structure with specific compensation mechanisms including a Pre-Construction Sum, a Construction Phase Fee calculated as a percentage of Allowable Costs, and a General Conditions Amount. Liquidated damages are set at $24,733.04 per day for failure to meet the Substantial Completion Deadline. The contractor must obtain performance and payment bonds, maintain comprehensive insurance coverage, and comply with Georgia Security and Immigration Compliance requirements. All Trade Contractors must be competitively selected through a formal bid process requiring a minimum of three proposals for work exceeding $5,000, with Owner retaining the right to reject any proposed Trade Contractor. The contractor bears full responsibility for quality control, warranty compliance, and correction of any non-compliant work at no additional cost to the Owner. The contract emphasizes the contractor's indivisible obligation to inspect all work for compliance with Contract Documents and requires coordination with existing building operations, with no extensions granted for delays caused by Owner operations or public use of the site.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

CONSTRUCTION MANAGEMENT AGREEMENT

This Construction Management Agreement (“Base Contract”) is made this day of , by and between (Insert Contractor) (“Contractor”) and the Unified Government of Athens-Clarke County, a political subdivision of the State of Georgia (“Owner”), for the construction of Athens-Clarke County Judicial Center [and Parking Deck] (the “Project”). Contractor and Owner agree as follows:

1. Scope of Work. Contractor shall provide all of the Work described in the Contract Documents and shall do everything required by or reasonably inferable from the Contract Documents to construct the Project. This Project will be constructed in multiple Phases and Components. The general scope of the Work is more particularly described in the Existing Documents described in Section 2, which documents are incorporated herein by reference. Contractor shall construct the Project in accordance with the terms, conditions, obligations, and provisions of this Agreement and the Contract Documents as defined in Section 6.3.2.26 of the Standard Terms.

2. Existing Documents. Contractor affirms that iFt has reviewed the Owner’s Project Criteria, attached hereto as Exhibit A, and the Preliminary Schedule, attached hereto as Exhibit B; that it has taken them into consideration in preparing its proposal for the General Conditions Amount and Construction Phase Fee; and that it knows of no reason why the Project could not be completed within the current Owner’s Budget by the Substantial Completion Deadline.

3. The Contract. The Contract includes Exhibits and Standard Terms, including all amendments or addenda to any of the foregoing, each of which are incorporated herein.

4. Owner’s Budget. The Guaranteed Maximum Price, which shall be the maximum Contract Sum established in accordance with Section 2.2.1 of the Standard Terms, shall not exceed the following amount: Dollars ($ ) (the “Owner’s Budget”). The Owner’s Budget is subject to modification by Owner until execution of the GMP Change Order as provided in Section 2.2.2.2 of the Standard Terms.

5. Pre-Construction Sum. Contractor’s compensation for the Pre-Construction Phase Services (“Pre- Construction Sum”) shall be: Dollars ($ ).

6. Construction Phase Fee. The Construction Phase Fee is the product of the Allowable Costs and the Construction Phase Fee Percentage. The Construction Phase Fee Percentage is %.

7. Contractor General Conditions Amount. The General Conditions Amount is the product of the Allowable Costs and the General Conditions Percentage. The General Conditions Percentage is %.

8. Substantial Completion. The Substantial Completion Deadline will be set forth in the GMP Change Order.

The Construction Phase shall commence upon the Notice to Proceed Date, and the Work shall reach Substantial Completion no later than the Substantial Completion Deadline.

9. Liquidated Damages. The agreed amount for Liquidated Damages, as set forth in Section 6.4.1.3 of the Standard Terms, is Twenty-Four Thousand, Seven Hundred Thirty-Three and 04/100 Dollars ($24,733.04) per day.

10. Anticipated Weather Delay Days. As referenced in Section 6.4.2.1(c), the following number of Weather Delay Days are anticipated each month and will not be the basis for extensions of Contract Time or adjustment to the Contract Sum:

(Insert Chart) Commented [DD1]: I was unsure if we needed to provide chart now - so draft chart we have used in the past is included in email if needed. I defer to Cook & Assoc if needed at this time

11. Notice. Notice in accordance with Section 6.1.7 of the Standard Terms shall be given to the following addresses:

CONTRACTOR:

Attention:

Phone Number:

OWNER:

Unified Government of Athens-Clarke County 301 S. College Ave.

Athens, GA 30601 Attention: Josh Hawkins Phone Number: 706-613-3025

DESIGN PROFESSIONAL:

Croft and Associates, Inc.

3380 Blue Springs Rd.

Kennesaw, GA 30144 Attention: Earl Smith Phone Number: 770-529-7714

PROGRAM MANAGER:

Jacobs Project Management Company 125 W. Washington Street Suite 775 Athens, GA 30601 Attention: Keith Sanders Phone Number: 706-613-3025

12. Program Manager. The Owner has elected to hire the Program Manager to serve as the owner's strategic advisor, coordinating the Project to align scope, budget, schedule, and risks with the Owner's goals across all phases. The Program Manager will oversee planning, design, procurement, construction, and closeout process while managing stakeholder communication, contracts, and performance on behalf of the Owner. Program Manager shall have no authority or responsibility for design decisions unless expressly provided in the Contract.

13. Existing Operations. Contractor acknowledges that the Project will be performed on public property. The protection of persons, as well as the property of Owner, is of paramount importance to Owner and is of the essence of this Base Contract.

Contractor warrants and represents that it has reviewed the existing site and conditions of the Project, along with any operations at the site. Accordingly, Contractor covenants that it will perform the Work in such a manner that will not interfere with or inconvenience Owner’s operations, will coordinate with Owner and the Owner’s Representative to schedule and sequence the Work in such manner, and will take all measures to protect the public. Contractor shall confine operations at the site to areas permitted by applicable laws, statutes, ordinances, codes, rules and regulations, lawful orders of public autho rities, and the Contract Documents, and shall not unreasonably encumber the site with materials or equipment. No extension to the Contract Time or increase in Contract Sum will be granted for any delay or impact of Owner’s operations or the use of the existing site or buildings by Owner or the public.

14. No Assignment. This Contract and the performance hereunder shall not be assigned or delegated by Contractor without the prior written consent of Owner. Any attempted assignment without such prior written consent shall be void.

15. Publicity. Contractor shall not release, without prior written approval from Owner, any publicity regarding the Project or its services provided to Owner, including but not limited to notices, information pamphlets, press releases, research, reports, signs, and similar public notices prepared by or for Contractor, identifying Owner receiving services under the Contract.

16. Work Product, Intellectual Property, and Information. Except as may be expressly provided in the Contract, Owner shall retain ownership of all work product and deliverables created by Contractor pursuant to the Contract . All records, documents, notes, data, and other materials required for or resulting from the performance of Work hereunder shall not be used by Contractor for any purpose other than the performance of Work hereunder without the express prior written consent of Owner. All such records, documents, notes, data, and other materials shall be considered “work for hire” and shall become the exclusive property of Owner when Contractor has been compensated for the same as set forth herein, and Owner shall thereafter retain sole and exclusive rights to receive and use such materials in such manner and for such purposes as determined by it.

17. Full Performance; No Waiver. The failure of Owner at any time to require performance by Contractor of any provision will not affect the right of Owner thereafter to enforce such provision or any other provision of the Contract. The failure o f Owner to enforce or exercise remedies as a result of any breach of any provision shall not be considered a waiv er of such provision, such remedies, any subsequent breach of such provision, or any other provision, or a modification or rescission of the Contract. In any case, the Contract shall continue in full force and effect, and Contractor shall be liable for full performance, as though such previous waiver or failure to enforce any rights had not occurred. No provision of this Contract, or right or remedy of Owner, will be deemed waived unless such waiver is in writing and executed by Owner.

18. Severability. If any provision of this Contract, or the application thereof to any person or circumstance, is declared invalid or unenforceable to any extent, then the remainder of this Contract, or the application of such provision to persons or circumstances other than those as to which it is held invalid or unenforceable, shall not be affected thereby, and each provision of this Contract shall be valid and enforced to the fullest extent permitted by law.

19. Titles, Captions, and Headings. The titles, captions and paragraph headings in the Contract Documents are inserted for convenience only and are in no way intended to interpret, define, or limit the scope or content of the Contract or any provision hereof.

20. No Drafting Presumption. No presumption of any applicable law relating to the interpretation of contracts against the drafter shall apply to the Contract.

21. Survival. Any provision of the Contract which contemplates performance or observance subsequent to any termination or expiration of the Contract, or which must survive to give effect to its meaning, shall survive the expiration or termination of the Contract.

22. Full Agreement. The Contract supersedes all prior negotiations, discussions, statements, and agreements between Owner and Contractor and constitutes the full, complete, and entire agreement between Owner and Contractor. There can be no changes to this Contract by oral means, by course of conduct of the parties, or by custom of the trade. No change to this Contract will be binding on either party unless such change is properly authorized, in writing, and in accordance with the terms of this Contract. Contractor may not unilaterally amend or modify the Contract by including provisions in its invoices, or other business forms, which shall be deemed objected to by Owner and of no force or effect.

23. Counterparts. The Contract may be executed in two or more counterparts, each of which taken together shall constitute one and the same instrument. The Contract shall be fully executed when each Party whose signature is req uired has signed at least one counterpart, even though no one counterpart contains all the signatures of all the Parties to the Contrac t.

Reproduced or electronic signatures shall be considered the same as an original signature. Delivery of a copy of the C ontract bearing an original signature by digital transmission, by electronic mail or by any other electronic means will have the same effect as physical delivery of the paper document bearing the original signature.

24. Electronic Representation and Records. The Parties agree to regard electronic representations of original signatures as legally sufficient for executing the Contract and scanned signatures emailed by PDF or otherwise shall be as valid as the original. Parties agree not to deny the legal effect or enforceability of the Contract solely because it is in electronic form or because an electronic record was used in its formation. Parties agree not to object to the admissibility of the Contract in t he form of an electronic record, or a paper copy of an electronic document, or a paper copy of a document bearing an electronic signature, on the ground that it is an electronic record or electronic signature or that it is not in its original form or is not an original.

25. Authority to Execute. The person or persons executing the Contract represent and warrant that they are fully authorized to sign and so execute the Contract and to bind their respective entities to the performance of its obligations hereunder.

26. Contractor Execution Under Seal. Contractor executes this Contract under seal.

IN WITNESS WHEREOF the parties hereto have executed this Contract under seal on the day and year first written herein.

Contractor

By: (Seal)

Title:

ATTEST (affix seal over secretary’s signature)

By:

(If not a corporation, signature must be notarized.)

ATHENS-CLARKE COUNTY UNIFIED GOVERNMENT

OWNER

STANDARD TERMS

1. CONTRACTOR’S SERVICES

1.1 Pre-Construction Phase Services

1.1.1 Pre-Construction Phase Services. During the Pre-Construction Phase, Contractor shall provide Pre-Construction Phase Services and shall actively participate in Design Coordination Meetings.

1.1.2 Phase Design Review and Consulting Services. During the Pre-Construction Phase, Contractor shall commence Design Review and Consulting Services and shall actively participate in Design Coordination Meetings.

1.1.2.1 Design Review and Consulting Services. Contractor shall review and advise on the following as part of its Design Review and Consulting Services. Contractor will coordinate with Program Manager and Design Professional for all Design Review and Consulting Services.

(a) Review for Constructability, Cost Savings, and Other Benefits to Owner. Contractor shall continuously review the Construction Documents for constructability and consistency for any potential conflicts, inconsistencies, ambiguities, errors, or omissions. Contractor shall consider life-cycle costs and shall conduct value-engineering analyses to recommend changes that will reduce costs or expedite the Project without reducing quality .

Contractor will make any other recommendations that may be in the best interest of Owner.

(b) Review for Code Compliance. Contractor shall continuously review the Construction Documents for consistency, errors, omissions, and non-conformance with applicable laws, statutes, regulations, and building codes.

Contractor shall give Notice upon the discovery of any such inconsistency, error, omission or non-compliance.

(c) Recommendations for Selection of Materials. Contractor shall provide advice regarding Site use and improvements and the selection of materials, building systems, and equipment. Contractor shall make recommendations to reduce costs without sacrificing quality, reduce procurement or installation time, and minimize adverse effects of labor or material shortages.

(d) Recommendations on Phasing of Components. Contractor shall make recommendations to Program Manager and Design Professional to facilitate the development of Components of the Work. In recommending phasing of Components, Contractor shall take into consideration such factors as the time of performance, the availability of labor, long lead-time items, overlapping trade jurisdictions, provisions for temporary facilities, and the reduction of areas of conflict and overlapping in the Work to be performed by Contractor or by Trade Contractors.

(e) Utilities & Environmental Review. Contractor shall advise and assist Owner and Design Professional with the preparation of all applications for water, sewer, electrical, gas, telephone, other utility services and any other environmental compliance necessary for the completion and operation of the Project.

1.1.2.2 Contractor’s Design Review Report. Contractor shall submit a design review report that summarizes the Design Review and Consulting Services provided herein (“Design Review Report”). Contractor shall submit a Design Review Report along with each Construction Cost Estimate required in Section 1.1.3.1. Contractor shall submit a Final Report of Contractor’s Design Review Services, which shall summarize the Design Review and Consulting Services provided and detail the material changes made and the impact to the Project as a result of the Services.

The Final Report shall be provided within the time specified by Owner. Each Design Review Report will contain the level of detail required by Owner.

1.1.2.3 Annotation of Potential Design Conflicts. When potential design issues or conflicts are identified during the Design Review process, Contractor shall annotate the Construction Documents and shall issue an RFI or request a Change Order, and will call for a Design Coordination Meeting to discuss the potential design issues or conflicts.

(a) Requests for Information (RFI). In the event the Construction Documents are not complete, definite, or clear to Contractor, or appear to have conflicts, Contractor shall issue in writing an RFI to Design Professional with a copy to Program Manager. Design Professional shall furnish to Contractor, with a copy to Program Manager, complete, definite, and clear instructions, interpretations, or responses in response to the RFI in writing, or by issuing drawings, or both. In the event instructions are given orally, they shall be confirmed in writing or by drawings within five days following the oral instructions. Any such additional instructions shall be consistent with the Contract Documents and reasonably inferable therefrom. Contractor shall maintain a log of RFIs and the responses received from Design Professional.

(b) Design Coordination Meetings for Material Design Issues. Contractor shall call for a Design Coordination Meeting when a potential design issue may materially affect the sequencing or accomplishment of the Work or may cause delays to the Project.

(c) Waiver of Design Defect/Unconstructability Claims. Contractor acknowledges and agrees that it shall not be entitled to a Change Order or Claim for a design issue or conflict disclosed or reasonably inferable from the Construction Documents or the nature and location of the Project unless Contractor has proceeded as provided in this section with respect to such design issue or conflict.

1.1.2.4 Limitation of Scope. Design Professional will produce fully coordinated Construction Documents and provide the design or interpretation necessary to resolve all conflicts. Nothing herein shall be deemed to impose upon Contractor any responsibilities to provide any services constituting the practice of architecture, engineering, or any licensed design profession, except to the extent required to complete performance specifications requiring the seal of a specialty consultant or to the extent expressly required by the Contract Documents.

1.1.3 Pre-Construction Cost Estimating Services. Contractor shall prepare construction cost estimates that set forth in detail Contractor's estimate of construction costs which shall be broken down by CSI category (“Construction Cost Estimates”). Contractor also shall provide reconciled Construction Cost Estimates consisting of a composite of the separately derived Design Professional's current estimate of construction costs and Contractor's Construction Cost Estimate.

1.1.3.1 Timing of Construction Cost Estimates and Reconciled Construction Cost Estimates. Construction Cost Estimates and Reconciled Construction Cost Estimates shall be provided to Program Manager and Design Professional at each of the intervals below:

(a) Within twenty-one (21) days after the later of (i) Contractor’s receipt of the Notice to Proceed; or (ii) Contractor’s receipt of the Schematic Design Documents

(b) Within twenty-eight (28) days after the completion of the Design Development Documents

(c) Prior to submission of the Guaranteed Maximum Price Proposal

1.1.3.2 Cost Exceeds Previous Estimate. If Design Professional's current estimate of construction costs and Contractor’s Construction Cost Estimate are not reconcilable or exceed any corresponding component of the Owner’s Budget, then Program Manager, Design Professional, and Contractor shall confer to resolve such differences. If such differences cannot be resolved, Contractor shall make recommendations to Owner as Contractor deems necessary or appropriate to resolve such differences.

1.1.3.3 Extent of Responsibility. Contractor does not warrant or guarantee estimates, except with regard to the CCO Maximum Price, Guaranteed Maximum Price, or as otherwise provided in the Contract Documents.

1.1.4 Pre-Construction Phase Scheduling Services. Contractor shall prepare a Construction Progress Schedule using a CPM (Critical Path Method) process, using a full-featured software package in a form satisfactory to Design Professional, Owner, and Program Manager. The Construction Progress Schedule shall have the minimum number of activities required to adequately represent the complete scope of Work and define the Project’s (and each Component’s) critical path and associated activities. The format of the Construction Progress Schedule shall have dependencies indicated on a monthly grid identifying Milestone dates. Milestone dates and activities shall be clearly indicated and sequentially organized to identify the critical path of the Project. Contractor shall provide copies of all documents, including electronic documents, related to the Overall Project Schedule.

1.1.4.1 Milestone Dates. The Construction Progress Schedule shall include but not be limited to the following Milestone dates:

- Design Coordination Meetings

- Component Construction Documents and Construction Documents receipt and approval

- Submittal of Component Change Orders and GMP Change Orders

- Construction Start

- Phase Construction (if applicable)

- NPDES Stabilization

- Foundations Completion

- Under-Slab Utilities

- Slab Completion

- Structural Top Out

- Dry-In

- Metal Stud Wall Completion

- Rough-In Completion

- Drywall Completion

- Equipment Installation

- Permanent Power

- Systems Operations

- Finishes

- 80% Completion Inspection

- Commissioning

- 100% Completion Inspection

- Equipment Training

- Substantial Completion Deadline

- Final Completion Date

1.1.4.2 Submittal Schedule. The Construction Progress Schedule shall be accompanied by a Submittal Schedule for approval by Program Manager and Design Professional. The Submittal Schedule shall correlate with the Construction Progress Schedule and shall take into account large submittal documents that will require longer review times. Design Professional’s approval shall be based on conformance of the Submittal Schedule with the Overall Project Schedule.

1.1.4.3 Approval of Construction Progress Schedule. Upon recommendation by Design Professional and approval by Program Manager, the Construction Progress Schedule shall become the Overall Project Schedule, which shall be used by Design Professional, Program Manager, and Contractor. The effect of any approval under this Section is limited by Section 1.2.13.

1.1.5 Pre-Construction Phase Construction Supervision & Planning Services. Contractor shall provide the following Construction Supervision Services.

1.1.5.1 Construction Management Plan. Contractor shall prepare a thorough and complete plan for the management of the Project which shall include, without limitation, the following information:

(a) Contractor’s Staffing Plan. The Construction Management Plan shall include Contractor’s staffing plan, an estimate of the labor requirements for each trade, and the anticipated availability of such labor. Contractor shall include in its plan the names and resumés of the Project Superintendent, Project Manager, and the person in charge of safety, each of whom shall be an employee of Contractor.

(b) Security Program. The Construction Management Plan shall include an effective security program for the Site, which shall require Contractor and the Subcontractors to take measures for the protection of their tools, materials, equipment, and structures.

(c) Safety Program. The Construction Management Plan shall include a specific safety program for the Site. Contractor shall establish and require all Trade Contractors to establish reasonable safety programs.

(d) Certificate of Competency – Fire Protection Trade Contractor. If a fire protection sprinkler system is required, Contractor shall submit to Program Manager and Design Professional the certificate of competency of the fire protection sprinkler system Trade Contractor and, if applicable, Subcontractor as required by State of Georgia Fire Protection and Safety Code. The certificate of competency shall be provided prior to any Work being performed on the fire protection sprinkler system.

1.1.5.2 Quality Control Program. Contractor shall prepare a written quality control program to ensure that the Work matches the level of quality specified in the Contract Documents (“Quality Control Program”). The Quality Control Program shall describe in detail the steps Contractor will take to ensure quality and will include, without limitation, those personnel, in addition to the Project Manager and Superintendent, who will provide review and verification of the proper installation of the Work. Each Subcontractor having responsibility for more than one hundred thousand dollars ($100,000.00) of the Work shall be addressed in the program.

1.1.5.3 Contractor Site Plan and Land Disturbance Permit. Contractor is required to obtain the land disturbance permits applicable to Owner that implement the National Pollutant Discharge Elimination System (NPDES) requirements for stormwater management for construction activities from the appropriate issuing authority.

1.1.5.4 Development of Site Plan. Design Professional is responsible for providing the initial sealed Site Plan as a part of the Contract Documents. Design Professional will depict upon the Site Plan its initial recommendations for design of BMPs for the Project. During the Pre-Construction Phase, Contractor shall review the initial Site Plan and make recommendations for any changes to the initial Site Plan including Contractor’s desired Site entrance, trailer locations, laydown areas and other matters affecting the design and implementation of the BMPs. The Design Professional will incorporate all reasonable changes and produce a final sealed Site Plan, including fully designed BMPs, for submission to the permitting official. Design Professional and Contractor shall resolve with the local permitting official any deficiencies by the end of the Pre-Construction Phase.

1.1.6 Submission of Rental Rates and Unit Prices. Prior to the issuance of the Notice to Proceed, Contractor shall submit, for consideration and approval by Owner, a proposal for rental rates, wage rates, and unit prices for the items listed herein that shall apply in the event of any Change Order Work. Unit Prices shall include all costs associated with the Work, including Trade Contractor overhead and profit and Contractor’s Mark-Up.

1.1.6.1 Rental Rates for Heavy Construction Equipment and Wage Rates. Contractor shall submit rental rates for heavy construction equipment and wage rates for operation of heavy equipment and other types of Project labor.

Contractor shall include rates for hourly, daily, weekly, and monthly rental.

1.1.6.2 Unit Prices for Stormwater Management BMPs. Contractor shall submit unit prices to cover installation of additional stormwater management BMPs. The unit prices shall be calculated by type and linear foot and shall include a price for new sediment barrier silt fencing and a price for re-installation of existing sediment barrier silt fence.

1.1.6.3 Unit Prices for Unsuitable Soil and Rock and Importing Additional Fill. Contractor shall submit unit prices for excavating unsuitable soil and rock and importing suitable soil and rock in excess of the amount specified in the Contract Documents. If the Contract Documents specify an estimated amount of excavation of rock or unsuitable fill material, or importation of additional fill, and if Design Professional determines that Contractor excavates or imports more or less than such stated quantities, then any adjustment in Contract Sum shall account for such stated quantities, and Owner shall receive a credit if actual amounts are less than the stated quantities. Design Professional shall be responsible for calculating the amount of all rock and unsuitable fill material removed based upon estimated volume of in-place compacted fill material prior to removal.

(a) Calculation of Unit Prices. The unit price for unsuitable soil shall include the excavation, haul off, and disposal of all unsuitable fill material. Unit prices for removal of rock shall include excavation and removal of all rubble;

addition and removal of overburden for blasting; replacement of suitable soils in areas of overbla sting or over removal; and all costs of labor, equipment, supplies, blasting materials, safety requirements, drayage, haulage, and disposal, including offsite disposal costs. Unit price for suitable soil shall include the cost of the soil and haulage.

(b) Unit Price for Rock and Unsuitable Fill. Contractor shall submit unit prices for removal of the types of Unsuitable Fill and Rock and importing Suitable Soil as listed below.

(i) Rippable Rock. Rippable Rock is defined as any material that can be ripped with a single-tooth hydraulic ripper drawn by a crawler tractor having a minimum draw bar pull rated at not less than fifty-six thousand (56,000) pounds (Caterpillar D-8K or equivalent) and occupies an original volume of at least one cubic yard.

(ii) Mass Rock. Mass Rock is defined as any material that cannot be ripped with a single-tooth hydraulic ripper drawn by a crawler tractor having a minimum draw bar pull rated at not less than fifty-six thousand (56,000) pounds (Caterpillar D-8K or equivalent) and occupies an original volume of at least one cubic yard.

(iii) Trench Rock. Trench Rock is defined as any material that must be removed from a trench that cannot be excavated with a hydraulic excavator having a bucket curling force rated at not less than eighteen thousand , three hundred (18,300) pounds (Caterpillar Model 215 or equivalent) and occupies an original volume of at least one-half cubic yard.

(iv) Caisson Rock. Caisson Rock is defined as material that must be removed from a shaft which cannot be penetrated faster than two (2) feet per hour (fifteen minute minimum) using a rock auger with bullet-shaped hardened steel teeth (Kennametal bits or equivalent), and the drilling equipment should have the capacity to produce a continuous torque of at least one million (1,000,000) inch pounds and a downward force of at least fifty thousand (50,000) pounds (a Hughes LLDH in good working condition) for piers up to seventy -two (72) inches in diameter. Use of equipment with greater torque or downward force modifies the definition of refusal to be the point at which the equipment cannot penetrate faster than two (2) feet per hour (fifteen

(15) minute minimum). In rare cases, refusal may occur on a rock seam or boulder above the general massive rock surface. If Contractor is entitled to receive compensation for Caisson Rock under the Contract Documents, such compensation should include only material that cannot be penetrated by the rock auger at the specified rate.

(v) Substances Not Considered Rock. Shale, rottenstone, or stratified rock that can be loosened with a pick or removed by a hydraulic excavator equivalent to a Caterpillar Model 215, a single engine pan (Caterpillar 621 or equivalent) that is pushed by a crawler tractor (Caterpillar D-8K or equivalent), or similar equipment shall not be classified as Rock.

(vi) Unsuitable Soil. Unsuitable Soil is soil that cannot be compacted to meet the required Contract Specifications.

Unsuitable Soil shall not include soil that when dried would meet the required Contract Specifications.

(vii) Suitable Soil. Soil that meets the required Contract Specifications.

1.1.7 Submission of Documents for Issuance of Notice to Proceed. Contractor shall submit the documents listed below as a prerequisite to Owner’s issuance of each Notice to Proceed. No Work shall be performed on the Site until a Notice to Proceed is issued. A separate Notice to Proceed shall be required for each Change Order, Component Change Order, and GMP Change Order. Prior to acceptance of all subsequent Component Change Orders and the Guaranteed Maximum Price Change Order, Contractor shall update, supplement, or amend all documents previously submitted.

Contractor shall timely submit the required documents so that Work may commence in accordance with the Preliminary Schedule, or the Overall Project Schedule if it has been approved by Program Manager and Design Professional. The Owner’s failure to issue a Notice to Proceed shall not be a Delay Event under Section 6.4.2 if such delay is caused by Contractor’s failure to submit Documents necessary for Issuance of Notice to Proceed, including but not limited to:

1.1.7.1 Payment and Performance Bonds as required by Section 6.2.1

1.1.7.2 Proof of insurance for all insurance required by Section 6.2.3

1.1.7.3 Documentation necessary for receiving all land disturbance permits

1.1.7.4 List of Trade Contractors anticipated to perform the Work

1.1.7.5 Workers’ Compensation and Employer’s Liability Insurance Certificates for all Subcontractors as required by Section 6.2.3.10

1.1.7.6 Subcontractors’ Affidavit for Georgia Security and Immigration Compliance as required under Section 6.1.5.4

1.1.7.7 Construction Management Plan, which includes Contractor’s Staffing Plan, Security Program and Safety Program (required for GMP Change Order) as required by Section 1.1.5.1

1.1.7.8 Quality Control Program (required for GMP Change Order) as required by Section 1.1.5.2

1.1.7.9 Construction Progress Schedule, including Submittal Schedule (required for GMP Change Order) as required by Section 1.1.4

1.1.7.10 Off-Site Stored Materials Agreement (required if the Work includes any materials that will be stored off -site)

1.1.7.11 Proposed Rental Rates and Unit Prices.

1.2 Construction Phase Services & Other Construction Phase Requirements

1.2.1 Construction Phase Design Review and Consulting Services. Contractor shall continue the Design Review and Consulting Services for the duration of the Construction Phase and shall give written Notice to Program Manager and Design Professional of any inconsistency, ambiguity, error, or omission which Contractor or its Subcontractors may discover before proceeding with the affected Work. Contractor shall review and compare all newly issued Construction Documents to the documents previously issued by Design Professional. Contractor shall perform such review as early in the Project as practicable so that any conflicts or interpretations can be addressed in time to minimize impacts upon the Overall Project Schedule. The issuance, or the express or implied approval, by Program Manager or Design Professional of the Construction Documents shall not relieve Contractor of the continuing duties imposed hereby.

1.2.1.1 Contract Documents at Site and Recording Changes. Contractor shall keep at the Site at least one copy of the Contract Documents in good order and available to Design Professional and to its representatives. Contractor shall record all changes and shall annotate a copy of the Construction Documents to reflect the as-built condition in order to produce the Marked-up Construction Documents.

1.2.1.2 Other Project Documents at Site. Contractor shall keep at the Site records of all samples, purchases, materials, equipment, maintenance, and operating manuals and instructions, and other construction-related documents, including all revisions. Contractor shall obtain data from Trade Contractors and maintain a current set of record Drawings, Specifications, and operating manuals. At the completion of the Project, Contractor shall deliver all such records to Owner.

1.2.2 Construction Phase Cost Estimating Services. Contractor shall revise and refine the Construction Budget to aid Owner and Design Professional in monitoring the progress of the Work and evaluating any Claims by Contractor. Contractor shall revise and refine the Construction Budget at appropriate intervals as required by the conditions of the Work.

Contractor shall identify variances between actual and budgeted costs and shall advise Owner and Design Professional promptly whenever projected costs may exceed the budgeted cost. Contractor shall maintain cost accounting record of all Work in compliance with GASB 34 accounting requirements.

1.2.3 Construction Phase Scheduling Services. During the Construction Phase, Contractor shall monitor the progress of the Work for conformance with the Overall Project Schedule and keep Owner informed of such progress and shall maintain records documenting the progress of the Work.

1.2.3.1 Construction Progress Meetings. Contractor shall schedule and conduct Construction Progress Meetings with Program Manager, Design Professional, Separate Contractors, and appropriate Subcontractors for the purpose of discussing the status and progress of the Work. Such meetings shall be held not less than biweekly (i.e., every other week). Contractor shall provide and distribute minutes of such meetings, including a list of the action items, responsible parties, and action dates to maintain schedules.

1.2.3.2 Recording Daily Construction Progress. Contractor shall maintain a daily log of construction activities, approved as to form and type of entries by Design Professional. The daily construction log shall be accessible to Owner, Program Manager, and Design Professional at all times during normal business hours.

1.2.3.3 Monthly Progress Reports and Updated Overall Project Schedules. Contractor shall submit monthly progress reports along with each Payment Application which shall document the progression of the Work and shall include information on the percentage of completion. Contractor shall also provide monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations, including approved Change Orders. However, no changes in Milestone dates are to be made without written consent of Owner and Design Professional.

1.2.3.4 Contractor’s Failure to Meet Schedule Requirements. In the event Contractor is delinquent in achieving a Milestone date in the Overall Project Schedule, Owner may demand Contractor to take action to promptly bring the Work into compliance with the Overall Project Schedule. Within seven (7) days after receipt of such demand, Contractor shall cause its employees and Subcontractors to bring the progress of Work into conformance with the Overall Project Schedule, including but not limited to performing Work on hours and days in addition to the normal working hours and days or adding additional labor. Fulfillment of this requirement shall not relieve Contractor from liability for breach of the covenant as to time or failure to achieve Substantial Completion by the Substantial Completion Deadline. Contractor shall not be entitled to an increase in Contract Sum or a Claim for the costs resulting from the actions required by this Section.

1.2.3.5 Duty to Notify Owner of Delays Caused by Owner, Design Professional, or other Parties. If Owner or Design Professional, or any other person with whom Owner or Design Professional has a direct contractual relationship or for whom they are responsible, shall act or fail to act in such a manner as to delay the progress of the Work or increase the Allowable Costs, Contractor shall give prompt Notice so as to permit Owner to take corrective action.

Such Notice is in addition to any other Notice required hereunder, including but not limited to any Notice required under Section 6.1.7 and Section 5.2.2.

1.2.4 Construction Phase Construction Supervision & Planning Services. Contractor shall supervise and direct the Work using diligent skill and attention in order to ensure satisfactory progress of the Work and that the quality of the Work complies with the Contract Documents. Contractor shall be responsible for and shall coordinate all construction means, methods, techniques, sequences, and procedures.

1.2.4.1 Responsibility for Qualified Employees & Subcontractors. Contractor shall at all times enforce strict discipline and good order among its employees and Subcontractors. Contractor shall not employ on the Project any unfit person or anyone not skilled in the work assigned. Contractor shall require all Subcontractors to employ only skilled and experienced workers to perform the task assigned to them. Contractor shall require all Subcontractors to assign sufficient workers to perform their assigned Work so as not to delay the progress of the Work.

(a) Replacement of Unqualified Subcontractors. Contractor shall determine the adequacy of the Subcontractors’ personnel and equipment, as well as the availability of materials and supplies to meet the Overall Project Schedule. Contractor shall immediately replace or cause to be replaced any Subcontractor or Subcontractor’s employee whose Work, as determined by Contractor, does not meet such requirements.

(b) Failure of Subcontractor Does Not Excuse Contractor. Non-performance, improper performance, or other default by any Subcontractor or employee of Contractor shall not excuse Contractor from its obligation to assure timely performance of the Work in compliance with the Contract Documents. Contractor shall not be entitled to an extension of Contract Time or adjustment to the Contract Sum for the acts or omissions of a Subcontractor except as otherwise specifically provided in the Contract.

1.2.4.2 Responsibility for Qualified Project Manager and Project Superintendent. Contractor shall ensure that a competent Project Manager and Project Superintendent remain on the Project, on a full-time basis, until Substantial Completion. A Project Manager or Superintendent shall be present to supervise completion of all Punchlist Items and Permitted Incomplete Work. All directions given to the Project Manager or Superintendent shall be as binding as if given to Contractor.

(a) Replacement of Project Manager or Project Superintendent. The Project Manager or Project Superintendent shall not be changed except with the consent of Program Manager unless the Project Manager or Project Superintendent ceases to be in Contractor’s employ. Contractor must obtain Owner's prior written approval before engaging a replacement Project Manager or Project Superintendent and must ensure that the replacement has similar qualifications and experience to the original Project Manager or Project Superintendent.

1.2.4.3 Responsibility for Acts and Omissions & Duty to Remedy Damages. Contractor is fully responsible to Owner for the acts and omissions of its officers, employees, agents, all Subcontractors and their respective officers, employees and agents, and all other persons on the Site at the direction of Contractor or to perform Work.

Contractor shall promptly remedy damages or loss to property at the Site caused thereby.

1.2.4.4 Responsibility to Coordinate Work of Separate Contractors. Contractor is responsible for coordination of the Project Work with any Separate Contractors performing other work within the Project, or in the proximity of the Project. Contractor expressly agrees to schedule and, with the assistance of Owner, coordinate the Work with such Separate Contractors in order to assist them and permit each phase of the Project to be completed in accordance with the Overall Project Schedule.

1.2.5 Construction Phase Land Disturbance Permit Compliance. For the Construction Phase Services, Contractor shall implement and maintain the BMPs and comply with the conditions of the Land Disturbance Permit. In the event Abnormal Weather Conditions or other events cause damage to BMPs, Contractor shall re-install BMPs at established unit prices under Section 1.1.6.2.

1.2.6 Responsibility for Protection of Site and Project Safety. Contractor has a revocable license until Substantial Completion to enter and perform Work upon the Site and shall be solely responsible for the protection of the Project Site and the safety of all persons on the Project Site until Substantial Completion. Contractor shall confine the staging and storage of materials, the operations of its forces, and the Work to limits indicated by law, ordinances, permits, or the Contract Documents, and shall not unreasonably encumber the Site with its materials.

1.2.6.1 Applicable Safety Rules. Contractor shall comply with the rules and regulations of OSHA and the Department of Labor (O.C.G.A. § 34-2-6), and where not inconsistent with the foregoing, the "Manual of Accident Prevention in Construction" issued by the Associated General Contractors of America, Inc.

1.2.6.2 Designated Safety Officer. Contractor shall designate a responsible member of its organization, normally the Project Superintendent, whose duty shall be the prevention of accidents.

1.2.6.3 Duty to Protect and Warn. Contractor shall erect and properly maintain at all times, as required by the conditions and progress of the Work, proper safeguards for the protection of workers and the public and shall post danger warnings against any hazards created by the construction operations.

1.2.6.4 Accident Record Keeping and Reporting. Contractor shall maintain an accurate record of, and shall promptly report to Owner, all cases of death, occupational disease, and injury requiring medical attention or causing loss of time from Work. Contractor shall maintain standard monthly safety reports to submit to Program Manager and Design Professional.

1.2.6.5 Protection from Rain Water, Surface Water, and Back-up. Contractor shall protect all Work, including but not limited to, excavations and trenches, from rainwater, surface water, and back up of drains and sewers. Contractor shall furnish all labor, pumps, shoring, enclosures, and equipment necessary to protect and to keep the Work free of water.

1.2.6.6 Dust Control and Cleaning. Contractor shall provide dust-proof enclosures or partitions for protection of the Work wherever dusty or dirty Work is performed to avoid the need for dusting upon completion of the Work. At all times, Contractor shall keep the premises free from accumulations of waste material or rubbish caused by its employees, Subcontractors, or the Work. Prior to completion of any Trade Contract, Contractor shall require the Trade Contractor to remove from the Site all temporary systems, tools, equipment, machinery, and surplus materials not required for the continued performance of any Work. In case of dispute, after forty -eight (48) hours’ Notice, Owner may remove the rubbish and charge the cost to Contractor.

1.2.6.7 Geological and Archeological Specimens. If Contractor, any Subcontractor, employee, or agent of either should uncover any valuable material or materials, including but not limited to treasure trove, geological specimens, archival material, archeological specimens, or ore, then Contractor acknowledges that title to the foregoing is vested in Owner. Contractor shall notify Program Manager upon the discovery of any of the foregoing, shall take reasonable steps to safeguard it, and seek further instruction from Design Professional. Any additional cost incurred by Contractor shall be addressed under the provision for changed conditions.

1.2.7 Submittals. Contractor shall provide to Design Professional and Program Manager all Submittals as required by the Contract Documents in accordance with the Submittal Schedule. Contractor shall perform no portion of the Work for which the Contract Documents require Submittals until Design Professional has approved the respective Submittal.

Contractor shall maintain at the Site one copy of all approved Submittals.

1.2.7.1 Design Professional and Program Manager Review of Submittals. Design Professional and Program Manager shall each review, and Design Professional shall respond to, Submittals within the time set forth in the Submittal Schedule or, if no time is provided therein, within fourteen (14) days from receipt, provided that in all instances the Submittals are submitted by Contractor in accordance with the required Submittal Schedule, other provisions hereof, and are appropriately organized and labeled. Notwithstanding the foregoing provisio n, Design Professional may respond to large submittal documents, such as those with over fifty (50) sheets of drawings, within a reasonable time greater than fourteen (14) days, based on the volume and complexity of the Submittal as well as Design Professional’s and Program Manager’s ability to conduct a thorough review.

1.2.7.2 Corrected Submittals. Contractor shall make all corrections required by Design Professional or Program Manager and shall furnish such corrected copies. If Contractor believes that any corrections required by Design Professional or Program Manager constitute a change to the Contract Documents, Contractor shall immediately notify Design Professional, Program Manager, and Owner and request instructions. If any corrections constitute changes to the Contract Documents, Owner will issue a Change Order; provided, as a condition to an increase in Contract Sum or Contract Time arising therefrom, Contractor shall provide Notice in the form and within the time set forth in Section 5.2.2.

1.2.7.3 Cost of Additional Review. Design Professional and Program Manager shall each be responsible for an initial and one subsequent review of the Submittal. Where the subsequent Submittal is not accepted due to noncompliance with the Contract Documents, Contractor shall be responsible for payment of the additional fees arising from additional time required by Design Professional and Program Manager to complete any subsequent Submittal reviews.

1.2.8 As-Built Drawings and Data.

1.2.8.1 “As-Built” Drawings. A complete set of drawings shall be maintained by Contractor at the Site for the purpose of showing as-built conditions. The drawings shall be kept up to date to show all changes and variations and each entry shall be dated and verified as made. At the end of the project, Contractor shall furnish to Design Professional the as-built drawings for incorporation into the design documents. Electronic as-built drawings shall be furnished to Owner by Contractor at the end of the Project.

1.2.8.2 Operation and Maintenance Data and Training.

(a) Contractor shall furnish complete and necessary data for the operation, repair and maintenance of each operating component of the Work. Such data shall include prints of shop drawings, as-built conditions, sources of equipment and principal materials, specified tests and performance data, repair and maintenance data, lubrication instructions and recommendations, parts lists,…