This is a Design-Build contract bid packet issued by the Town of West Hartford, Connecticut for the Design-Build of 2 Storage Facilities (Bid #270007). The project involves construction of two storage facilities at the Town of West Hartford Public Works Municipal Complex: a vehicle storage facility for the Police and Fire Departments at 12 Brixton Street (approximately 14,500 square feet) and a Public Works equipment and material storage facility at 17 Brixton Street (approximately 6,700 square feet). The facilities will incorporate security features, durability, energy efficiency, and low maintenance as key requirements. A pre-bid conference was scheduled for November 17, 2026 at 10:00 AM EST at 17 Brixton Street. Electronic bid submissions were due by December 3, 2026 at 2:00 PM EST through the Town's bidding portal. Questions were required to be submitted in writing through the bidding portal by November 22, 2026. The project is structured in two phases: Phase 1 involves relocating Police Department vehicles from their current location at 17 Brixton Street to the newly constructed facility at 12 Brixton Street, followed by Phase 2 redevelopment of the 17 Brixton Street site for Public Works operations. Final completion is required by September 1, 2027, with liquidated damages of $500 per calendar day assessed for failure to achieve substantial completion.

The contract requires a 10 percent bid surety (Bid Bond, Certified Check, or Treasurer's Check) submitted with each proposal. For contracts exceeding $50,000, the successful bidder must furnish Performance, Labor, and Material Bonds in the full amount of the estimated total base bid. Connecticut prevailing wage rates apply to all work, with rates effective October 27, 2026, subject to annual adjustments each July 1st. The contract will be awarded on an AIA Document A141 - 2024 Design-Build Agreement form. Evaluation criteria include firm ownership and leadership qualifications, location (preference for central Connecticut presence), responsiveness to all RFQ/P provisions, evidence of similar Design-Build successes in industrial projects, innovation in sustainable design, and cost and risk containment proposals. Bidders must comply with all state requirements, including Connecticut General Statutes 4a-60, 4a-60a, 4a-60g, and 46a-68b through 46a-68f, and an Affirmative Action Plan must be filed with and approved by the Commission on Human Rights and Opportunities prior to construction commencement. A minimum 25 percent of the state-funded portion of the contract must be awarded to DAS-certified subcontractors, with 25 percent of that portion directed to DAS-certified Minority, Women and/or Disabled-owned businesses. Comprehensive insurance requirements are mandated, including Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Commercial Umbrella/Excess Liability ($5,000,000/$10,000,000), Professional Environmental Liability ($2,000,000 each), and Contractor's Pollution Liability ($2,000,000 per occurrence/aggregate).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT BIDDING DOCUMENTS

FOR

TOWN OF WEST HARTFORD

DESIGN/BUILD OF 2 STORAGE FACILITIES

BID # 270007

Bid Submission Due Date

December 3, 2026, at 2:00PM EST

1 - 1

INFORMATION

TOWN OF WEST HARTFORD

DESIGN-BUILD OF 2 STORAGE FACILITES

17 BRIXTON STREET

WEST HARTFORD, CT

BID# 270007

ALL QUESTIONS TO

All questions must be submitted in writing through the Town’s Bidding

Portal by November 22, 2026. Please do not call or email the Project

Manager or Purchasing Office with questions.

00101

INVITATION TO BID

Electronic bids for Design-Build of 2 Storage Facilities BID # 270007 will be received electronically until 2:00PM on December 3, 2026.

In order to provide an electronic submission, you must be registered in our vendor database.

Please see the vendor registration instructions. Once registered, you will gain access to the bid and the bid documents. Please follow the prompts when submitting your price structures. Please reference Design-Build of 2 Storage Facilities BID # 270007

There will be a pre-bid conference will be held for this project on 11/17/2026 at 17 Brixton St, West Hartford at 10:00AM EST

No bid may be withdrawn for a period of ninety (90) days after the opening of bids without the approval and written consent of the Town of West Hartford.

The right is reserved to reject any and all bids, to waive any informalities in the bidding and to make awards in any manner that is the most beneficial to the Town.

The work described herein shall be completed as required. Unless otherwise stated, time is of the essence

All prospective Bidders are hereby notified that blasting is not permitted on this project.

Bidder Response Form 2 | P a g e

BIDDER RESPONSE FORM

BOND INFORMATION if applicable

Bid Surety - 10% Bond Attached (yes/no) Cashier Check Attached (yes/no)

Cost of Performance Bond included in base bid (if applicable) $ Per thousand

List up to six past contracts of this type/size your firm has completed within the last three (3) years

Project Date Contact Person Phone No.

PLEASE COMPLETE THE FOLLOWING INFORMATION.

FAILURE TO RESPOND TO ALL ITEMS MAY RESULT IN THE REJECTION OF YOUR RESPONSE.

Vendor Name Trade Name if applicable

Address

Phone # Email Address

Contact Person Tax ID#

Number of years in business: Bid# Project Name:

STATUS OF THE BUSINESS AND ITS CURRENT STANDING WITH THE SECRETARY OF STATE'S OFFICE

Connecticut Businesses Yes No

Are all required filings current with the Secretary of State and will the Secretary of State be able to issue a Certificate of Legal Existence?

Out of State (foreign) Businesses Yes No

Have you filed a Certificate of Authority / Application of Registration with the Connecticut Secretary of State? If so, submit a copy of your filing with your response. If not, submit a copy of your Certificate of Good Standing from your state of incorporation.

DAS CONTRACTOR PREQUALIFICATION if applicable

(required for construction / infrastructure projects only) (non-highway construction projects >$1,000,000)

Circle one

DAS prequalified? (yes/ no) Certificate attached (yes/no) Update Statement attached (yes/no)

You certify that there has been no substantial change in your financial position or corporate structure since your most recent prequalification certificate was issued or renewed, other than those changes noted in the update statement (attached).

Yes No

Bidder Response Form 3 | P a g e

CERTIFICATION

The Undersigned hereby certifies that they are the only duly authorized representative/agent of the vendor and have the authority to sign this form and make these certifications on behalf of the vendor.

Vendor acknowledges receipt of all bidding documents and addenda, if applicable during the bidding period, issued during the bidding period and understands that they are a part of the bidding documents.

The undersigned hereby declares that they are thoroughly familiar with the specifications, the various sites, the Town’s requirements, and the objectives for each element of the project item or service and understands that in signing this proposal all right to plead any misunderstanding regarding the same is waived. The undersigned further understands and agrees that they will furnish and provide all the necessary material, machinery, implements, tools, labor, services, and other items of whatever nature, and to do and perform all the work necessary under the aforesaid conditions, to carry out the term of the agreement and to accept in full compensation therefore the amount agreed to by the vendor and the Town of West Hartford.

The undersigned further declares that these bidding documents are made without any connection with any other person or persons making any proposal for the same work and made without collusion or fraud; that no person acting for or employed by the Town of West Hartford is directly or indirectly interested therein, or in the supplies or works to which it relates, or will receive any part of the profit or any commission there from in any manner which is unethical or contrary to the best interest of said Town of West Hartford.

The undersigned additionally declares that they are not debarred or suspended, or otherwise excluded from, or ineligible for, participation in Town of West Hartford, State of Connecticut or federally funded projects. The vendor agrees that by affixing their signature to this request for bids, the authorized signatory grants approval to the Town of West Hartford to obtain third party credit reports for the purposes of assessing the financial capacity of the business entity tendering such bid to the Town

The undersigned certifies under penalty of false statement that the information provided in this response is true.

Submitted by (Signature)

Printed name and title Date

(Authorized Agent of Company)

ORGANIZATIONAL STRUCTURE OF BUSINESS ENTITY (select one)

Limited partnership (LP) General partnership (GP)

Limited liability corporation (LLC) Limited liability partnership (LLP)

Corporation Individual doing business under a trade name (sole proprietor)

BUSINESS AFFILIATIONS if applicable

Indicate the principal place of business of the parent company and the name of agent for service.

Is your local organization an affiliate of a Parent company? Yes No

Parent Company Business Name

Address

City State Zip

Name of Agent

List all Affiliated Businesses if applicable (attach additional sheets as necessary):

Business Name Address Ownership Interest %

SUMMARY OF WORK HISTORY

1. The bidder is required to state in the spaces provided below work that the bidder has performed of a similar character to the work described in the Contract Bidding Documents.

Contract Award

Project Name Project Description Amount Client Contact Person Telephone #

SUMMARY OF WORK HISTORY

2. The bidder is further required to furnish a complete list of all projects for which he has signed a construction contract within the past 36 months.

Contract Project Name Project Description Award Amount Client Contact Person Telephone #

1 | P a g e

Town of West Hartford Request for Qualification/Proposal: Design-Build of two storage facilities

Executive Summary The Town of West Hartford is soliciting proposals from qualified Design-Build (D-B) teams to provide planning, design, engineering and construction services for two new storage facilities located at West Hartford Public Works Municipal Complex.

1. A vehicle storage facility for the Police Department (PD) at 12 Brixton Street.

and

2. A Public Works (PW) equipment and material storage facility at 17 Brixton Street.

The purpose of this project is to design and construct two storage facilities with security, durability, energy-efficiency and low maintenance as the underlining requirements to improve operational efficiencies and readiness.

Overview The design and build of two storage facilities will be treated as a single project, to be delivered under a single Design-Build contract.

The order of construction is important:

Phase 1 – PD storage facility at 12 Brixton Steet.

The plan is to relocate PD vehicles from their existing location to the newly constructed depot. These vehicles are currently stored on the site of 17 Brixton Street (#2).

Phase 2 – PW storage facility at 17 Brixton Street.

Once PD vehicles are relocated, redevelop the site to afford the housing of PW equipment and staging of materials to support PW operations.

2 | P a g e

Operational Requirements Police Vehicle storage (12 Brixton St) The parcel earmarked for this facility is located at 12 Brixton Street, West Hartford CT. The premises are currently open field with approximately 14,500 square feet of surface area.

• The subject area is directly in front of a single-story warehouse, accessible from Brixton Street.

• The site will serve as storage area for vehicles associated with Police and Fire departments.

• Location has power and communication in place as infrastructure. Additional wiring system will be needed to distribute power and communication to device level.

Security Considerations

• Outer perimeter will be secured with fencing, accessible from Brixton St.

• Gate clearance will be at least 40 feet to accommodate commercial tow trucks and

PW snow removal equipment.

• Entrance will be equipped with networked access control system to open and close the gate and to track users.

• System will also have the capability for users to vend the gate remotely from another location.

3 | P a g e

Security Considerations (cont.)

• Credentials to open gate on site will be in the form of HID cards and key fobs.

Preferably, the system should integrate with Town’s current access control system for configuration, detection and reporting purposes.

• Fencing design is to be determined with regards to height and level of privacy.

• Security cameras will be installed and be integrated to the Town’s existing video surveillance system. Cameras may include 1 License Plate Recognition camera at the gate.

• Shielded lighting system will be installed to enhance security.

• The interior of the perimeter will be subdivided with additional fencing to house sensitive contents. The subdivisions will also be access controlled.

Traffic Considerations

• Subject location is earmarked to stage vehicles. Parking spaces will be designed and numbered via signage for organization and ease of retrieval.

• Driving aisles will be wide enough to accommodate commercial tow trucks and PW winter maintenance vehicles.

• Provide adequate access for large equipment to enter/exit the existing building’s overhead door.

Drainage Considerations

• The ground will be left unpaved to allow for natural infiltration of rainwater and snowmelt.

• Add drainage improvement to redirect water, to protect retaining wall and prevent structural failure.

4 | P a g e

Enclosed image illustrates the existing parcel at 12

Brixton Street.

The images below are meant to convey conceptual ideas in regards to retaining walls and fencing systems.

Wall & Fencing simulation

Wall & Fencing simulation

Existing parcel

5 | P a g e

Storage facility for Public Works (17 Brixton Street) The parcel is located on the premises of 17 Brixton Street, with approximately 6,700 square feet of surface area.

• The intent is to clean up the location and to build a storage facility to house equipment and serve as staging area for materials

• Storage facility will require protection from weather precipitation.

• Seasonal equipment will be stored away from the elements, to extend their life cycle.

• Evaluate lighting system for function and security. Redesign lighting to fit new structure configuration.

• Evaluate existing surveillance system. Add camera(s) to cover back lot and interior of new structure configuration.

• Proper stormwater management system will be in place to prevent runoff from entering the waterways.

6 | P a g e

The images below are meant to convey conceptual ideas in regards to storage systems to support Public Works operations.

PW Storage Concept 1

PW Storage Concept 2

7 | P a g e

Evaluation Criteria The Town will entertain all proposals. Interested parties are encouraged to exercise their creativity to deliver a Design-Build proposal for the formation of two storage facilities. The Town reserves the rights to reject any and all bids, to wave any informalities in the bidding and to make awards in any manner that is most beneficial to the Town.

All proposals will be evaluated on the basis of the following criteria:

• Firm ownership and leadership qualifications: Number of years in business, financial capabilities, litigation history, regulatory compliance and violation history.

• Location – Firm’s presence in central Connecticut.

• Responsiveness – Addressing all provisions outlined in the RFQ/P.

• Evidence of similar successes in Design-Build as they apply to industrial projects.

• Innovation of design with respect to sustainability and environmental stewardship.

• Innovation of proposal to contain costs and risks for the Town.

Design-Build Criteria

• Design-Build Services – The firm will deliver final design and construction of two storage facilities to support the housing of vehicles, equipment and materials as they relate to the operations of Police, Fire and Public Works.

• Project Management & Administration – The firm will provide a Project Manager to directly oversee the administration and management of the project from design through construction.

• Data Collection, Review and Evaluation – The firm will collect, analyze data and make recommendations to the Town with each phase of the project.

• Construction Plans and Specifications – The firm will prepare design drawings for review and approval by Town staff. The firm is responsible for the preparation of detailed construction plans and specifications.

• Obtain Appropriate Approvals – The firm will coordinate and obtain approvals with all appropriate governmental agencies and public utility authorities, prior to the completion of detailed construction plans.

• Construction Management – The firm will manage and perform the construction of the storage facilities in compliance with all applicable codes and safety regulations.

All Quality Control and Testing will be included in the Design-Build plans to be verified by 3rd party as testing agency.

• Record Construction Drawings – The firm will prepare electronic records and drawings that accurately reflect all modifications made in the field.

8 | P a g e

Facility Start up and Project Closeout

• Perform full system start-up, testing and commissioning.

• The firm will document all deficiencies and provide immediate repairs to the satisfaction of the Town.

• The firm will provide final certification of all materials and labors on the project in the form of Release of Liens and Affidavits of any subcontractors involved.

2.02-1

2.02 INSTRUCTIONS TO BIDDERS

TABLE OF CONTENTS

2.02.01 Time for Opening bids

2.02.02 Form of Bid

2.02.03 Submission of Bid

2.02.04 Quantities

2.02.05 Duties of Bidder

2.02.06 Underground Objects, Soils, etc

2.02.07 Bid Surety

2.02.08 Performance, Labor and Material Bonds

2.02.09 Rejection of Bids

2.02.10 Bidder to Furnish Information

2.02.11 Award of Contract

2.02.12 Execution of Contract and Bond

2.02.13 Time

2.02.14 Sales Tax

2.02.15 Out of State Contractors

2.02.16 Address of Contractor

2.02.17 Scope and Term of Insurance

2.02.18 Reserved

2.02.19 Withdrawal of Offer

2.02.20 Limitations on Surety Bond

2.02.21 Reference Specifications

2.02.22 Public Acts Related to Working Near Gas Mains and

Public Acts Related to Working Near Power Lines

2.02.23 Equal Opportunity

2.02.24 Engineering and Inspection Charges

2.02.25 Federal Requirements

2.02.26 State Requirements

2.02-2

2.02 INSTRUCTIONS TO BIDDERS

2.02.01 TIME FOR OPENING BIDS For this bid, we are requiring electronic submission to be submitted through the Town’s bidding portal. The Town maintains the right to reject any bid that does not meet these criteria. Electronic copies are to be received no later than 2:00 PM on December 3, 2026.

2.02.02 FORM OF BID Each bid must be made in and on the form prepared therefore and attached hereto and the proposal form must be submitted complete and unchanged as furnished, except for the insertion of names, addresses, prices and other required data in the blank spaces provided therefore. All appropriate blanks must be filled out. Any changes to, or material deviations from the form provided, shall render such bid voidable at the Town's sole option.

2.02.03 SUBMISSION OF BID Bids shall be sealed in an envelope marked "Sealed Bid" with the bid proposal number and the vendor's name and address. Late bids will not be accepted.

2.02.04 QUANTITIES Bids will be compared on the basis of the Engineer's estimate of quantities as set forth in the Schedule of Bids.

These quantities are given solely as a basis for the comparison of bids. The Town does not expressly, or by implication, agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any item or portion of the work as may be required.

Attention is particularly called to the fact that some items may be largely dependent on soil or foundation conditions and therefore, may vary widely from the estimated quantities or may even be omitted. An increase or decrease in the quantity for any item shall not be regarded as sufficient grounds for an increase or decrease in the unit price, unless otherwise governed by Form 817.

Bidders must satisfy themselves, by personal examination and by such other means as they may prefer, as to the actual conditions and requirements of the work and the accuracy of the estimate of the Engineer, and shall not, at any time after the submission of a bid, dispute or complain of such statement or estimate of the Engineer nor assert that there was any misrepresentation or misunderstanding in regard to the nature or amount of work to be done.

The work has been divided into items in order to enable the Bidder to bid for the different portions of the work in accordance with his estimate of their costs individually and to provide for payment respective of quantity variations.

Bidders are especially cautioned not to submit bids, which are unbalanced. If, in the opinion of the Town, any bid submitted appears unbalanced, this action may be sufficient cause for the rejection of the entire bid or it may result in a monetary loss to the Contractor if certain portions of the work are increased or decreased as provided in the Contract.

2.02-3

2.02.05 DUTIES OF BIDDER The Bidder is required to examine carefully the site of the work, the project drawings, if any, the Notice to Contractor, Information for Bidders, General Conditions, General Specifications, Technical Specifications, Wage Rates and Certification and Bid Proposal hereinafter referred to from time to time as the Contract Bidding Documents. Bidder must satisfy themselves as to the actual conditions and requirements of the work to be performed and the materials to be furnished and shall make himself familiar with all federal, state and local laws, ordinances and regulations which in any manner affect the work or its conduct. No plea of misunderstanding or ignorance of such laws, etc., will be considered as an excuse for failure to comply with any of the requirements hereof or as reason for any additional compensation or waiver of any requirements of Contract Bidding Documents.

Every bid submitted must be based upon the Contract Bidding Documents, if any, described herein and upon the written, typed or printed texts of the Contract Bidding Documents. Oral statements by any officer or employee of the Town will not be binding. Questions shall be submitted in writing to the Division of Purchasing Services Manager at least seven (7) working days before the established date for receipt of bids. If the question involves the equality or use of products or methods, it must be accompanied by drawings, specifications or other data in sufficient detail to enable the Engineer to determine the equality or suitability of the product or method. In general, the Town will neither approve nor disapprove particular products prior to the opening of the bids; such products will be considered when offered by the Contractor for incorporation into the work.

2.02.06 UNDERGROUND OBJECTS, SOILS, ETC If any Contract Bidding Document or drawing or similar source of information furnished to prospective Bidders or to awarded Contractors purports to show underground objects or conditions or pipes, ducts or similar structures or observations or indications of soils, rock, ground water, etc., made from borings, test pits or prior excavations, such information must be considered as only advisory and not necessarily correct and complete, having been obtained, made and plotted for the benefit of the Engineer.

Bidders and awarded Contractors must recognize that, by reason of the methods commonly used for obtaining and expressing such data, this information and data is limited and subject to error or misunderstanding. The terms used to describe soils, ground water, etc. are subject to local usage and to the individual opinion of the person making the records. Ground water conditions vary from time to time. The locations, sizes, depths, etc. of underground pipes, ducts and structures are usually obtained from records of others and such data, when shown on plans of the Town, are subject to possible errors in the source of the information and also errors in transcription. The Town, together with its agents, does not warrant or represent that the indications on Contract Drawings or other documents of underground conditions, objects, etc., as described above, are either approximately correct or complete, and any party making use of such indications or basing estimates of proposals thereon must agree that they shall have no claim or right of action against either the Town or any person or party acting for or under it for the consequences, delays, expense or losses which may occur or have occurred in event that such indications shall be found to have been

2.02-4 incomplete, incorrect or misleading. Bidders must make such investigations as they deem necessary and form their own opinions of the materials, conditions and difficulties or obstacles likely to be encountered.

Contractors, as required by state law, are required to notify the utilities coordinating agency for field locations of existing underground utilities. A town permit is required for each project location. Prior to the issuance of a town permit for work within Town rights of way, the awarded Contractor shall secure a "Call Before You Dig" number and this number shall appear on the permit.

2.02.07 BID SURETY Each bid must be accompanied by a Bid Bond, Certified Check or Treasurer's Check in the amount of ten percent (10%) of the total base bid and made payable to the "Town of West Hartford". Failure to provide the bid surety will result in rejection of the bid. All surety checks shall be returned to the respective Bidders when the Contract is awarded.

2.02.08 PERFORMANCE, LABOR AND MATERIAL BONDS If the amount of the Contract to be awarded is Fifty Thousand Dollars ($50,000) or more, the successful Bidder shall furnish and pay for the required bonds in favor of the Town of West Hartford in the full amount of the estimated total base bid as determined by extending the unit prices by the estimated quantities. This bond shall provide 100% security for faithful performance and for payment of all persons performing labor or furnishing materials in connection with this Contract and shall be executed by a company authorized to transact business within the State of Connecticut.

The Bidder shall deliver the required bonds to the Town not later than five (5) days from notice of the Town's intent to award the Contract to the Bidder and prior to execution of a Contract.

2.02.09 REJECTION OF BIDS The Town shall not award this Contract to a Bidder who does not furnish evidence satisfactory to the Town that he has ability, equipment and experience in this class of work, that he has satisfactorily completed work of similar character, magnitude and importance, and that he has sufficient capital and capacity to enable him to prosecute the same successfully within the time limit stated herein. Prospective Bidders who cannot fully satisfy these requirements are requested not to submit bids. Failure to qualify in this respect may be considered sufficient cause to reject any bid whatsoever.

The Town reserves the right to reject any one or more bids as it may deem to be in the best interests of the Town, and this right to reject is not limited to the specific reasons mentioned herein. A bid may, but does not have to be rejected:

(a) If it is incomplete, conditional or obscure, or if it contains additions not called for, erasures, alterations, obvious errors or irregularities of any kind, or if it does not conform in every respect to the requirements stated in these Contract Bidding Documents, or if it is on sheets removed from this pamphlet;

2.02-5

(b) If the individual unit prices bid are considered by the Town to be unbalanced in a manner likely to be detrimental to the Town;

(c) If the Town shall be of the opinion that it was prepared without adequate care or knowledge of the conditions relative to the work, or under a misunderstanding of the requirements of the Town, or if it is for work other than that shown on applicable Drawings or specified;

(d) For failure to furnish information promptly as required herein.

(e) If the Bidder has failed to satisfactorily complete prior contracts.

(f) If the Bidder has not performed work of a similar size or type in the past.

2.02.10 BIDDER TO FURNISH INFORMATION In order that the Town may have information to guide it in the award of the Contract, the Bidders whose bids are being considered shall, on request of the Town, submit the following information within four working (4) days after the receipt of such a request;

(a) A list of previous work of similar character and magnitude which has been performed or furnished by the Bidder, or by the principals to the bid, together with information as to each such job, its character, magnitude, date, location and that it was carried forward and completed in a matter entirely satisfactory to the party under whose supervision it was done.

(b) A statement of the capacity, equipment and forces of the Bidder which are or will be available to the Bidder together with a statement as to whether things are owned by the Bidder, or under lease or contract to the Bidder.

(c) A brief statement of the methods and order of work the Bidder proposes to perform and the rate of progress on the several parts of the same which the Bidder expects to accomplish.

(d) A sworn copy of the latest statement of the financial condition of the Bidder together with sworn statements as to any and every important change which may have occurred to alter the said financial condition since the date of the above statement, with supporting evidence if and as requested.

(e) References showing that the Bidder undoubtedly has ample capital, credit and other resources to finance the work throughout and without being dependent on release of portions of retained percentage before completion of work, and without having estimates for payment made more often than once each month and at such times as will conform to payment practices of the Town.

2.02.11 AWARD OF CONTRACT It is the intent of the Town to award a Contract to the Bidder providing the lowest responsible bid and is in accordance with the requirements of the Contract Bidding Documents and does not exceed available

2.02-6 funds. The Town shall have the right to waive informalities or irregularities in a bid received.

2.02.12 EXECUTION OF CONTRACT AND BONDS The Bidder to whom the Contract is awarded shall execute the Contract and required Performance and Labor and Materials Bond(s) within five (5) working days (not including Saturdays, Sundays, or holidays) from the date upon which the Town issues notice to the Bidder, that the Contract is ready for signature. If the Contractor fails to execute the Contract within said time period, the Town may determine that the Bidder has abandoned the Contract. Thereupon the acceptance of the bid and the award shall be null and void and the bid surety accompanying the bid shall be forfeited to the Town.

The Contractor shall increase the principal amount of the Performance and Labor and Materials Payment Bond(s) in direct proportion to any increase in the value of the Contract resulting from change orders.

2.02.13 TIME See Section 5.13 of the General Conditions.

2.02.14 SALES TAX Under the terms of the regulations referring to contractors and subcontractors, issued by the State Tax Commission in administration of the State Sales and Use Tax, to which the Bidder is referred, the Contractor may purchase such materials and supplies as are to be physically incorporated in and become a permanent part of the project being performed under this Contract without payment of tax and shall not include in his bid nor charge any use or sales tax thereon.

2.02.15 OUT-OF-STATE CONTRACTORS The Contractor, if not a resident of the State of Connecticut, or, in the case of a partnership, the partners, if not residents, shall appoint an approved person having permanent local residence as his or their attorney, upon whom all lawful processes, proceedings or notices may be served.

The Contractor, if a corporation not organized under the laws of Connecticut, shall comply with the provisions of the General Statutes of Connecticut regarding "Foreign Corporations" before entering upon the performance of the Contract.

Any non-resident Contractor is required to comply with the conditions set forth by the State Tax Commissioner relative to the provisions of Public Act No. 75-740, "An Act Concerning Bond Requirement for Non-resident Contractors for Purposes of Sales and Use Tax".

Public Act No. 75-740 requires a non-resident to deposit a sum equivalent to three percent (3%) of the total amount of the Contract or a Guarantee Bond in the like amount with the State Tax Commissioner to secure payment of the sales and use tax. The Contractor shall obtain a certificate from the State Tax Commissioner that the requirements of Public Act No. 75-740 have been met before entering upon the performance of the Contract.

2.02.16 ADDRESS OF CONTRACTOR Each Bidder shall indicate in his bid the address to which all notices, letters or other communications may be sent. This address may be changed only by proper delivery to the Town of written notice of such

2.02-7 change, signed by the Contractor. The mailing or delivery by messenger of any notice, letter or communication to such designated address or to the office of the Contractor at or near the site of the work or to any attorneys or attorneys appointed by non-resident principals to a Contract or by a "foreign" corporation, at any time including the full period of work under the Contract shall be deemed sufficient for any notice or service on the part of the Town in connection with the Contract or any part thereof.

2.02.17 INDEMNIFICATION AND INSURANCE The Contractor shall comply with the indemnification and insurance requirements as required and specified in Section 8.02, Indemnification and Insurance Exhibit. Failure to comply with any of the indemnification or insurance requirements may be held a willful violation and basis for immediate termination of the Contract.

2.02.18 RESERVED

2.02.19 WITHDRAWAL OF OFFER A bid offer may be withdrawn only prior to the scheduled bid opening time for the particular project, provided the Bidder first submits a written request for such withdrawal to the Division of Purchasing Services. Notice of acceptance of a bid shall not constitute rejection of any other bid.

2.02.20 LIMITATIONS ON SURETY BOND No surety bond for proposal guarantee (Bid Bond), for performance of the Contract or for payment for labor and materials will be accepted if the amount of the bond exceeds any limit which the laws of Connecticut or the regulations of the Connecticut Insurance Department impose or for which the United States Treasury Department has qualified the surety, unless co-surety for the amount of any such excess is furnished, written by a surety company or companies qualifying hereunder for the respective amounts to be covered thereby.

2.02.21 REFERENCE SPECIFICATIONS Where any materials covered by ASTM, ASI, ACI, ConnDOT, MDC or any other these specifications are used, the product, practice or test procedures shall fully comply with these specifications, including their latest revisions, except where amended.

2.02.22 APPLICABLE PUBLIC ACTS The Contractor shall be responsible for complying with all statutory obligations connected with its operations such as, but not limited to, Connecticut General Statutes §§ 16-345 through 16-356 (as those sections may be renumbered or recodified from time to time) regarding operating rear underground utilities. See Section 5.04 "Utilities" of the General Conditions.

2.02.23 EQUAL OPPORTUNITY During the performance of this Contract, the Contractor agrees and warrants that it will not discriminate or permit discrimination against any person or group of persons, including employees or applicants for employment, on the grounds of age, sex, race, color, religion, physical impairment or national origin in any manner prohibited by the law of the United States, the State of Connecticut, or the Town of West Hartford. The Contractor will take affirmative action to ensure that applicants are employed and that

2.02-8 employees are treated during employment without regard to their race, color, religion, age, sex or national origin. Such action shall include, but not be limited to, the following: layoff or termination; rates of pay or other forms of compensation; and selection for training including apprenticeship.

The provisions of the following sub sections below shall not apply where the total cost of all work to be performed by Contractors or subcontractors in connection with this project is less than thirty -five hundred dollars; also this section shall not apply when the Contractor has fewer than ten (10) employees.

(a) The Contractor will, in all solicitations or advertisements for employees, placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, age, sex or national origin.

(b) The Contractor will comply with all provisions of the State of Connecticut Executive Order No. Three of June 16, 1971 and the guidelines and rules of State Labor Commissioner implementing Executive Order No. Three, and all amendments thereto.

(c) The Contractor will furnish all information and reports required by Executive Order No. Three of the State of Connecticut of June 16, 1971 and all amendments thereto, and by the rules, regulations and orders of the Labor Commissioner, or pursuant thereto, and will permit access to his books, records and accounts by the Labor Commissioner for purposes of investigation to ascertain compliance with such rules, regulations and orders.

(d) In the event of the Contractor's noncompliance with the Equal Opportunity clause of these Contract Bidding Documents or with any of the Contract pursuant to these Contract Bidding Documents, said rules, regulations or orders, may be canceled, terminated or suspended, in whole or in part, and the Contractor may be declared ineligible for further Town Contracts in accordance with procedures authorized in Executive Order No. Three of the State of Connecticut of June 16, 1971 and the guidelines and rules of State Labor Commissioner implementing Executive Order No. Three and all amendments thereto; and such other sanctions may be imposed and remedies invoked or as otherwise provided by law.

(e) The Contractor will include the provisions of this section and paragraphs

(a) through (e) in every subcontract or purchase order, so that such provisions will be binding upon each subcontractor or vendor. The Contractor will take such action with respect to any sub-contract or purchase order as the Town may direct as a means of enforcing such provisions, including sanctions for noncompliance: provided, however, that in the event the Contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the Town, the Contractor may request the United States or the State of Connecticut to enter into such litigation to protect the interests of the United States, the State of Connecticut and the Town of West Hartford.

2.02-9

2.02.24 ENGINEERING AND INSPECTION CHARGES AND OVERTIME FEES The Contractor shall be required to reimburse the Town for engineering and inspection services performed by the Town on holidays (New Year's Day, Lincoln's Birthday, Martin Luther King Day, Washington's Birthday, Good Friday, Veterans Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Thanksgiving Day and Christmas Day) or when employees are required to work in excess of 37.5 hours per week as a result of the Contractor's work schedule.

The Contractor shall be charged at rates stated in section 2.01.10 of the Invitation To Bid.

2.02.25 FEDERAL REQUIREMENTS - None for this project

2.02.26 STATE REQUIREMENTS The contractor who is selected to perform this State project must comply with CONN. GEN. STAT. §§ 4a-60, 4a-60a, 4a-60g, and 46a-68b through 46a-68f, inclusive, as amended by June 2015 Special Session Public Act 15-5. An Affirmative Action Plan must be filed with and approved by the Commission on Human Rights and Opportunities prior to the commencement of construction.

State law requires a minimum of twenty-five (25%) percent of the state-funded portion of the contract for award to subcontractors holding current certification from the Connecticut Department of Administrative Services (“DAS”) under the provisions of CONN. GEN.

STAT. § 4a-60g, as amended. (25% of the work with DAS certified Small and Minority owned businesses and 25% of that work with DAS certified Minority, Women and/or Disabled owned businesses.) The contractor must demonstrate good faith effort to meet the 25% set-aside goals.

For municipal public works contracts and quasi-public agency projects, the contractor must file a written or electronic non-discrimination certification with the Commission on Human Rights and Opportunities. Forms can be found at http://www.ct.gov/opm/cwp/view.asp?a=2982&q=390928&opmNav_GID=1806.

TOWN OF WEST HARTFORD

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS

AIA Document A701, "Instructions to Bidders", 2018 Edition, American Institute of Architects, Articles 1 through 8, are bound herein and are hereby made a part of the Contract Documents and shall apply to all

Contractors and Subcontractors.

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

Certain Articles of the AIA Instructions to Bidders are revised or replaced by requirements of the

Supplementary Instructions, listed below. Such revisions are replacements and shall take precedence over the

AIA Instructions to Bidders.

The Following Articles, revised paragraphs, and clauses have the same numerical designations occurring in the

AIA Instructions to Bidders, and all additions follow in direct numbered sequence.

Article 1 - Definition

1.3 Delete paragraph 1.3 in its' entirety and substitute the following: Addenda are written or graphic instruments issued by the Architect and distributed by the Owner prior to the bid opening which modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections.

Article 2 - Bidder's Representation

Add the following as paragraphs 2.2 and 2.3

2.2 A pre-bid conference may be held prior to bidding, at which time all interested parties are requested to attend. The intent of the project and Bidding Documents will be discussed. There will be a question-and-answer period, during which time prospective bidders are invited to request clarification or interpretation of any and all parts of the Bidding Documents. See Invitation to Bid for date, time, and location of Conference.

2.3 Guided tours of the Project Site, at the discretion of the owner, may be conducted prior to the pre-bid conference. Questions and or requests for clarification will not be addressed while the tour is being conducted.

ARTICLE 3 - BIDDING DOCUMENTS

3.1.1: Delete second sentence and substitute with the following:

Refer to instructions on Invitation to Bid Page 00201-1.

00203-1

3.1.2: Delete Paragraph 3.1.2.

3.2.2: Delete the word "Architect" and substitute the word "Owner".

3.3.4: Delete paragraph 3.3.4 in its entirety and substitute with the following:

After the award of the Contract, no substitutions will be considered for the brands specified, except upon written request of the Contractor and written approval by the Architect and Owner.

Substitutions shall be submitted in accordance with the requirements listed in Article 3.3.2.

3.3.5: Delete paragraph 3.3.5 in its entirety and substitute with the following:

Approval by the Owner and the Architect of any such substitution shall not relieve the

Contractor requesting the substitution of any responsibility for additional costs incurred by other trades for changes made necessary to accommodate the substituted item.

3.4.1: Delete paragraph 3.4.1 in its entirety and substitute with the following:

Addenda will be issued by the Owner and will be mailed to all who are known by the Owner to have received a completed set of Bidding Documents.

ARTICLE 4 - BIDDING PROCEDURES

4.1.6: Add the following words to the beginning of paragraph - "Unless otherwise provided in the

Contract Bidding Documents".

4.1.7: Delete paragraph 4.1.7 in its entirety and substitute with the following:

Each copy of the Bid shall include the legal name of the bidder and a statement that the Bidder is a sole proprietor, partnership, corporation or other legal entity. Each copy shall be signed by the person or persons legally authorized to bind the Bidder to a contract. A Bid by a corporation shall further give the state of incorporation and, if the Owner so requests, have the corporate seal affixed. A Bid submitted by an agent shall have a current power of attorney attached certifying the agent's authority to bind the Bidder.

4.2.3: Delete paragraph 4.2.3 in its entirety and substitute with the following:

Surety Bonds shall be written on forms substantially similar in content to AIA Document A310 and executed by a company authorized to transact business within the State of Connecticut, and the attorney-in-fact who executes the Bond on behalf of the Surety shall affix to the Bond a certified and current copy of his power of attorney.

00203-2

ARTICLE 5 - CONSIDERATION OF BID

5.1.1: Add new paragraph 5.1.1 as follows:

Bidders are encouraged to attend the Town's bid opening at which time the public is afforded an opportunity to record bid prices received in response to the Town's solicitation. Bidders who would like the results of the bid but are unable to attend the bid opening must submit with their bid a self-addressed stamped envelope and note requesting a copy of the bid results.

BIDDERS CALLING THE PURCHASING OFFICE FOR BID RESULTS WILL BE

REFERRED TO THE ABOVE PROCEDURE.

5.3.1: Delete 1st sentence and substitute the following:

It is the intent of the Owner to award a Contract to the bidder providing the best value to the

Owner and is in accordance with requirements of the Bidding Documents and does not exceed the funds available.

5.3.3: Add new paragraph 5.3.3 as follows:

The Owner in awarding the Contract shall be guided by pertinent provisions of the "Town

Charter" and "Code of Ordinances".

5.3.4: Add new paragraph 5.3.4 as follows:

A Bid may be rejected if the Bidder cannot show that he has the necessary supervisory staff, labor, capital, materials, machinery and resources to commence the work at the time prescribed and thereafter to prosecute and complete the Work at the rate or time specified; and that he is not already obligated for other work which would delay the commencement, prosecution, or completion of this work. A Bid may also be rejected if the bidder has previously failed to complete a contract within the time required, had previously performed similar work in an unsatisfactory manner, or in the judgment of the Owner is deemed unable to satisfactorily perform the Work.

5.3.5: Add new paragraph 5.3.5 as follows:

Prior to the award of a Contract, if so requested, Bidders must present satisfactory evidence that they have been regularly engaged in the business of doing such Work as they propose to execute and that they are prepared with the necessary supervisory staff, labor, capital, materials, and machinery, resources and responsibilities to conduct and complete the work to be contracted for in accordance with the Contract Documents and to begin it promptly when ordered.

00203-3

ARTICLE 6 - POST BID INFORMATION

6.3.3: Delete paragraph 6.3.3 in its entirety and substitute with the following:

Prior to the award of the Contract, the Owner will notify the Bidder in writing if either the

Owner or the Architect, after due investigation, has a reasonable objection to any such proposed person or entity. If the Owner or Architect has reasonable objection to any such proposed person or entity, the Bidder may, at his option, (1) withdraw his Bid, or (2) submit an acceptable substitute person or entity. In the event of withdrawal under this sub-paragraph, Bid

Security will not be forfeited, notwithstanding the provisions of Paragraph 4.4.1.

ARTICLE 7 - PERFORMANCE BOND AND PAYMENT BOND

7.1.1: Delete paragraph 7.1.1 in its entirety and substitute with the following:

If the amount of the Contract to be awarded is Fifty Thousand Dollars ($50,000) or more, the successful Contract Bidder shall furnish and pay for Surety in the full amount of the Contract.

This Bond shall provide 100% security for faithful performance and for payment of all persons performing labor or furnishing materials in connection with this Contract and shall be executed by a company authorized to transact business within the State of Connecticut.

The Contractor shall increase the principal amount of the performance and labor and materials payments bond(s) in direct proportion to any increase in the value of the Contract resulting from such change orders.

7.2.1: Delete paragraph 7.2.1 and substitute the following:

The Bidder shall deliver the required bonds to the Owner prior to execution of a contract and not later than (5) five days from notice of the Owner's intent to award the Contract to the bidder.

ARTICLE 9 - SUPPLEMENTARY INSTRUCTIONS

9.1: Add new paragraph 9.1 as follows:

9.1.1 - The Contractor shall agree that, except in the case of bona fide occupational qualification or need, neither he nor his Subcontractors and/or agents will refuse to hire or employ, or will bar or discharge from employment, or will otherwise discriminate against any individual in compensation or in terms, conditions, or privileges of employment because of race, color, national origin, ancestry, present or past history of mental disorder, mental retardation, or physical disability, including, but not limited to, blindness.

00203-4

9.1.2 - The Contractor shall further agree that neither he nor his subcontractors and/or agents will discharge, expel, or otherwise discriminate against any person because he/she has opposed any discriminatory employment practice or because he has filed a complaint or testified or assisted in any proceeding under Connecticut General Statutes Sections 46a-82, 46a-83, or 46a-

84 or as may be amended.

9.1.3 - The Contractor shall further agree that, except in the case of a bona fide occupational qualification or need, neither he nor his subcontractors and/or agents will advertise employment opportunities in such manner as to restrict such employment so as to discriminate against individuals because of their race, color, religious creed, age, sex, marital status, national origin, ancestry, present or past history of mental disorder, mental retardation or physical disability, including, but not limited to, blindness.

9.1.4 - The terms used in paragraphs 9.1.1, 9.1.2, and 9.1.3 shall have the definitions set forth in

Connecticut General Statutes Section 46a-51 or as may be amended.

9.1.5 - The Contractor further agrees, for himself, his subcontractors, and agents, not to otherwise discriminate or permit discrimination against any person or group of persons on the grounds of race, color, religious creed, age, sex, marital status, national origin, ancestry, present or past history of mental disorder, mental retardation or physical disability (including but not limited to blindness) in any manner prohibited by the laws and regulations of the United States, State of Connecticut or Town of West Hartford.

9.2: Add new paragraph 9.2 as follows:

Time: The Contractor to whom this Contract may be awarded, will be required to commence work at the site within ten (10) days of Contract signing unless, otherwise indicated in the sample AIA Standard Form of Agreement Form A101. The work shall be executed diligently thereafter and shall be completed in accordance with the Contract Documents.

9.3: Add new paragraph 9.3 as follows:

The Bidder is directed to the Bid Forms for additional information, instructions, qualifications and requirements.

END OF SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

(Section updated 3/20)

00203-5

D. The Bidder is required to submit a Certificate of Insurance in amounts and types specified in Insurance

Exhibit or provide a letter from the Bidder's insurance agent or broker that such insurance is obtainable at the time of execution of the Agreement and that a Certificate of Insurance shall be provided to that effect not later than the date of Contract signing. (See page #00204-7)

E. Contract award will be by AIA Agreement Form 101. A copy of the AIA Form 101 is included for the

Bidder's information. The parties shall enter into an Agreement in substantially the same form as the attached subject to technical and other modifications as the parties mutually agree.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .