This document is a Statement of Work (SOW) for the procurement of exhaust insulation blankets and pads for the USCGC 270' Legare. The SOW provides details on the required materials and labor to insulate the main diesel engine, ship service diesel generator, and emergency diesel generator exhaust systems. The work is to be completed within a 4-week period of performance, with a tentative start date of July 25, 2025. Drawings and industry standards are referenced for the insulation specifications. A site survey is mandatory prior to the start of work.

The related federal contract opportunity is a combined synopsis/solicitation for the installation of the exhaust insulation on the Legare. The solicitation number is 70Z04024Q61161Y00 and it is being issued as a Request for Quote (RFQ) under simplified acquisition procedures. The U.S. Coast Guard, Surface Forces Logistics Center intends to award a firm-fixed-price purchase order for this work, with payment made upon delivery and acceptance. Quotes are due by August 28, 2024 and will be evaluated on a lowest-priced, technically-acceptable basis.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT of WORK

For

Exhaust Insulation Blankets

Procurement Request:2124404Y61A3799004 USCGC 270’ Legare Yard POC: Keith Hare (410) 636-7603 Tentative Start Date: 7/25/25 thru 8/25/25 Period of Performance: 4 Weeks

Provide all materials & Labor for insulating a potion of 2 (ea.) Main Diesel Engine Exhaust, complete 2 (ea.) Ship Service Diesel Generator Exhaust in engine room and 1 (ea.) Emergency Diesel Generator The exhaust insulation blankets and pads are required upon completing the installation of:

a) Port and Stbd MDE Exhaust Piping and Silencers

b) Port and Stbd SSDG Exhaust Piping and Silencers

c) Emergency Diesel Generator Piping and Silencer Please use the drawing(s) 901-WMEC-259-002, 905-WMEC-342-003 and Miratech Silencer attachment drawings provided as guidance for the manufacturing of piping insulation pads. Materials do not have to be 100% exact, they can be equal too.

General Information:

All exhaust piping, including mufflers and flexible joints, shall be insulated in accordance with MIL-STD-769J or Equal to Industry standard. For all piping, the insulation should have proper thickness for all temperature ratings for system to be insulated.

1. External surface temperature for exhaust piping shall not exceed 130 F. Operating exhaust gas temperatures range from 32 F to 800 F.

2. All insulation blankets shall be fabricated and installed with proper lagging anchors and attachments. The insulation blankets shall be attached with steel lacing.

***It is recommended to take measurements to pre-manufacture the pads after installation of all exhaust piping, brackets, and expansion joints are completely installed. Installations may not be 100% according to the drawings detailing both SSDG’s and the EDG. The MDE Exhaust piping is existing and will be temporarily removed to accommodate the US Coast Guard Yards scope of work. A site survey is mandatory prior to the start of work.

All work shall be completed within a timely and efficient manner. Contractor shall communicate all work via contracting officer and ship’s superintendent (Yard POC).