This is Addendum #2 to an Invitation for Bid (IFB 27-22-PRCS) issued by the City of Salem, Massachusetts for Forest River Park restroom renovations located at 32 Clifton Avenue. The addendum addresses nine clarifications through a Bidder Q&A format, establishing key project parameters and responsibilities. Filed sub-bids for plumbing work are due October 28, 2026 at 11:00 a.m., while general bids are due November 10, 2026 at 11:00 a.m. A mandatory pre-bid meeting and site visit is scheduled for October 21, 2026 at 10:00 a.m. The project scope encompasses comprehensive renovation of men's and women's restroom facilities, including demolition of existing components, concrete slab replacement with epoxy flooring, FRP wall finishes, ADA-compliant fixtures, new windows and doors, and upgrades to mechanical, electrical, and plumbing systems. The contractor must commence work on or around November 30, 2026, with substantial completion by March 15, 2027 and final completion by April 2, 2027.
Key clarifications in this addendum establish that the City waives or pays all permit fees for plumbing, electrical, and mechanical trades; the City's separate contractor carries all exterior sewer work beyond ten feet; code-compliant temporary heaters without continuous attendance are acceptable; no field office trailer is required; the Owner retains and pays for industrial hygienist testing and mold clearance certification; the Owner retains and pays for independent testing agencies and special inspectors for concrete testing; no infrared camera survey is required; aluminum windows are part of the general bid rather than a filed sub-bid category; and the General Contractor is responsible for trench excavation and backfill for below-slab sanitary piping and the first ten feet of exterior sanitary work, with the City to issue a future addendum containing details prior to the general bid deadline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #2
CITY OF SALEM IFB 27-22-PRCS FOREST RIVER PARK RESTROOM RENOVATIONS
OCTOBER 26, 2026
Bidder Q&A
1. Please confirm the Owner waives or pays all permit fees, including the plumbing, electrical and mechanical trade permits, per the Instructions to Bidders.
Correct. The Owner waives or pays all permit fees, including the plumbing, electrical and mechanical trade permits.
2. The plumbing drawing assigns sewer beyond 10 feet to the general/site contractor, while the floor plan has the City's site contractor making the connection. Please confirm the City's separate contractor carries all exterior sewer beyond 10 feet.
Correct. The City's separate contractor carries all exterior sewer beyond 10 feet.
3. Please confirm 24-hour, seven-day attendance of temporary heat and three-hour temperature logs are not required, and that code-compliant temporary heaters without continuous attendance are acceptable for this restroom renovation.
Correct.
4. Please confirm no field office trailer, copier, telephone or fax is required for this project, and that a jobsite plan box with current documents satisfies the field office requirement.
Correct.
5. Please confirm any industrial hygienist testing or mold clearance certification is retained and paid by the Owner, consistent with the Owner's hygienist for existing mold, to avoid a conflict of interest.
Correct.
6. Please confirm the Owner retains and pays the independent testing agency and special inspector for concrete slump, air, temperature, cylinder and shrinkage testing, with the GC coordinating only, to avoid a conflict of interest.
Correct.
7. The Thermal Insulation section assigns an infrared camera survey to the Owner's testing agency, then repeats it as Contractor work. Please confirm the Owner's agency performs and pays for the infrared survey.
No infrared camera survey is required for this project.
8. The Aluminum Windows section is labeled part of a Metal Windows filed sub-bid that is not in the Table of Contents. Please confirm aluminum windows are carried in the general bid and are not a filed sub-bid category.
Correct. The aluminum windows are carried in the general bid and are not a filed sub-bid category.
9. Please confirm the Plumbing filed sub-bidder carries trench excavation and backfill for its below-slab sanitary piping and the 10 feet of exterior sanitary, since no earthwork section is bound and plumbing sub-bids are due 10/28.
The GC is responsible for trench excavation and backfill for its below-slab sanitary piping and the 10 feet of exterior sanitary. The City will issue a future addendum with details for this work in time for the general bid deadline.
All other terms and conditions are unchanged at this time.