27_037 Fire Hydrants.pdf

PDF 384 KB Posted

Attached to
Bid Ref. #27-037 Fire Hydrants
Solicitation number
PE-64750-NONST-2027-000000238
Issued by
Dekalb County, Georgia

About this file

This Invitation to Bid document is issued by the City of Albany, Georgia, Finance Department Procurement Division for the procurement of fire hydrants. The bid solicitation (Bid Ref. #27-037) requests 15 units of WaterMaster 5CD250 fire hydrants in two configurations: 15 units at 3'6" depth of bury and 15 units at 4'6" depth of bury. Each hydrant features a 5¼" valve opening, is pressure-rated for 250 psi, includes a 3-way nozzle configuration with one 4½" NST pumper nozzle and two 2½" NST hose nozzles, a 1½" pentagon operating nut, 304 stainless steel hardware, yellow color with silver bonnet, and mechanical joint inlet connection. The questions deadline is 2:30 PM on November 24, 2026, and the bid submission deadline is 2:30 PM on December 8, 2026. No prebid conference is scheduled. Delivery is required within 30 days of award notification, and the contract prices are firm for one year.

Bidders must submit unit prices and extended prices for each hydrant configuration on the provided bid form with F.O.B. pricing to Albany, Georgia, with freight prepaid and included in the price. A bid bond is required, and bidders must provide manufacturer specifications, delivery timeframe estimates, warranty statements, samples, and state the make and model. Payment terms are Net 30 unless otherwise specified. The City reserves the right to award items separately or on a lump sum basis and to reject any or all bids. Local bidders domiciled within Albany City Limits receive preference in case of tie bids. Bidders must comply with multiple certification requirements including Buy America Certification, Certification of Non-Collusion, Debarred Bidders/Integrity Certification, and Indemnity Agreement. All bids are subject to Georgia law and jurisdiction in Dougherty County, Georgia.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Ref. #27-037 Fire Hydrants

INVITATION TO BID

•This is NOT an Order•

BID REF:#27-037 DATE: 11/09/2026

REQUESTING DEPARTMENT: DELIVER ORDERS TO:

Finance – Procurement 222 Pine Avenue – Suite 260

Albany, GA 31701

FINANCE -

WAREHOUSE

1726 LILY POND RD

ALBANY, GA 31701

PHONE (229) 431-3211

FAX (229) 431-2184

SALES TAX #047-175701

FED. EXEMPTION #58-6000817

JOSHUA WILLIAMS DESTINY SOLOMON

JOSHUA WILLIAMS, CPPB

PROCUREMENT MANAGER

Destiny Solomon, Buyer I

PREBID CONFERENCE: QUESTIONS DEADLINE: BID DEADLINE:

N/A 2:30PM ON November 24, 2026 2:30PM ON December 8, 2026

QUESTIONS SUBMITTED ↑ AFTER THIS DATE ↑ MAY NOT BE ANSWERED.

ALL QUESTIONS ARE TO BE SUBMITTED IN WRITTEN FORM TO: dsolomon@albanyga.gov ; cc:kross@albanyga.gov cc:jswilliams@albanyga.gov

CONDITIONS and REQUIREMENTS

% BID BOND REQUIRED PRICES FIRM FOR ONE YEAR

X STATE MAKE AND MODEL BID X ATTACH MANUFACTURER SPECIFICATIONS

X STATE DELIVERY TIME FOR EACH ITEM BID (ARO). SAMPLE REQUIRED WITH BID

X STATEMENT OF WARRANTY REQUIRED X F.O.B. ALBANY, GA.- FREIGHT PREPAID & INCLUDED IN PRICE

QTY DESCRIPTION UNIT PRICE EXTENDED PRICE

5CD250 Hydrant 3'6" MJ 1 1/2" Pent 2AD 1-5 4 1/2" NST Pumper 2-4 2 1/2" NST Hoses 304SS Hardware OL Yellow- Silver Bonnet

5CD250 Hydrant 4'6" MJ 1 1/2" Pent 2AD 1-5 4 1/2" NST Pumper 2-4 2 1/2" NST Hoses 304SS Hardware OL Yellow- Silver Bonnet

TOTAL BID $

BIDDER INFORMATION

FEDERAL TAX ID # FIRM NAME PHONE

TERM DISCOUNT: NET % ADDRESS FAX

CHECK IF NEW ADDRESS CITY/STATE/ZIP EMAIL

Must Be Signed By An Authorized Representative.

SIGNATURE

PURCHASING FORM#12 10/98 REV.

*INCLUDE EMAIL TO ENSURE RECEIPT OF COPY OF TABULATION SHEET.

**INCLUSION OF YOUR BUSINESS CARD IS APPRECIATED.

For Proper Consideration Please Bid On This Form mailto:dsolomon@albanyga.gov mailto:;%20kross@albanyga.gov mailto:jswilliams@albanyga.gov

CITY OF ALBANY

PROCUREMENT DIVISION

FINANCE DEPARTMENT

ALBANY, GEORGIA

INSTRUCTIONS TO BIDDERS

These instructions will bind bidders to terms and conditions herein set forth, except as specifically qualified in special bid and contract terms issued with any individual bid.

1. The following criteria are used in determining low responsible bidder.

(a) The ability, capacity and skill of bidder to perform required service.

(b) Whether bidder can perform service promptly or within specified time.

(c) The character, integrity, reputation, judgment, experience and efficiency of bidder.

(d) The performance of previous contracts.

(e) The suitability of equipment or material for City use.

(f) The ability of bidder to provide future maintenance and parts service.

2. Payment terms are Net 30 unless otherwise specified. Favorable term discounts may be offered and will be considered in determining low bids if they are deemed advantageous to The City.

3. Unless otherwise specified all materials, supplies or equipment quoted herein must be delivered within thirty (30) days from date of notification of award or by exception noted on bid sheet.

4. Prospective bidders are responsible for examining the location of the proposed work or delivery and determining, in their own way, the difficulties, which are likely to be encountered in the execution of same.

5. The ESTIMATED QUANTITY given in the specifications or advertisement is for the purpose of bidding only. The City may purchase more or less than the estimated quantity, and the bidder must not assume that such estimated quantity is part of the contract.

6. All bids should be tabulated, totaled and checked for accuracy. The unit price will prevail in case of errors.

7. All requested information should be included in the sealed bid envelope. All documents and information must be signed and included for your bid to receive full consideration. Failure to submit any required information or document will be cause for bid to be rejected as non-responsive.

8. Failure of the bidder to sign the bid document or have the signature of any authorized representative or agent on the bid in the space provided will be cause for rejection of the bid. Signature(s) must be written in ink.

9. Failure to enclose bid bond, where required, will result in rejection of the bid. Bond may be in the form of cash, certified check, cashier’s check or Surety Bond issued by a Surety Company licensed to conduct business in Georgia.

10. All bidders should provide their tax identification number with the bid.

11. All bidding Corporations should provide the corporate seal, a copy of the Secretary of State’s Certificate of Incorporation, and a listing of the principals of the corporation with the bid.

12. Quote all prices F.O.B. Albany or our warehouse or as specified in bid documents.

13. If the bidder proposes to furnish any item of a foreign make or product, he/she should write “Foreign” together with the name of the originating country opposite such item on the bid.

14. When requested, SAMPLES will be furnished free of expense, properly marked for identification and accompanied by list where there is more than one sample. The City reserves the right to mutilate or destroy any samples submitted whenever it may be in the best interests of The City to do so for the purpose of testing.

15. The City will reject any material, supplies or equipment that do not meet the specifications, even though bidder lists the trade name or names of such materials on the bid or price quotation form.

16. Any alterations, erasures, additions or omissions of required information or any changes of specifications, or bidding schedule are done at the risk of the bidder. Any bid will be rejected that has a substantial variation, such as a variation that affects the price, quality or delivery date (when delivery is required by a specific time).

17. Each bid or proposal will be submitted in a SEALED ENVELOPE. Additionally, that envelope shall be clearly marked on the outside as a Sealed Bid with the Bid Number clearly printed.

18. Bids must be received and stamped by the Procurement Office before the date and time stipulated in bid documents. The City of Albany assumes no responsibility for submittals received after the advertised deadline or at any office or location other than that specified herein, whether due to mail delays, courier mistake, mishandling, or any other reason. No responsibility will attach to any City representative or employee for premature opening of bids not properly addressed or identified.

19. If only one bid is received, the bid may be rejected and/or re-advertised, except in the case of only one known source of supply.

20. Bids received late will not be accepted, and The City will not be responsible for late mail delivery.

21. Should a bid be misplaced by The City and found later it will be considered.

22. The unauthorized use of patented articles is done entirely at the risk of the bidder.

23. All bidders must be recognized and authorized dealers in the materials or equipment specified and be qualified to instruct in their application or use. A bidder at any time requested must satisfy the Procurement Office and City Commission that he has the requisite organization, capital, plant, stock, ability and experience to satisfactorily execute the contract in accordance with the provisions of the contract in which he is interested.

24. Only the latest model equipment as evidenced by the manufacturer’s current published literature will be considered. Obsolete models of equipment not in production will not be acceptable. Equipment shall be composed of new parts and materials. Any unit containing used parts or having seen any service other than the necessary tests will be rejected. In addition to the equipment specifically called for in the specifications, all equipment catalogued by the manufacturer as standard or required by the State of Georgia shall be furnished with the equipment. Where required by the State of Georgia Motor Vehicle Code, vehicles shall be inspected and bear the latest inspection sticker of the Georgia Department of Revenue.

25. All materials, equipment and supplies shall be subject to rigid inspection, under the immediate supervision of the Procurement Officer and/or the Department to which they are delivered. If defective material, equipment or supplies are discovered, the contractor, upon being instructed by the Procurement Officer, shall remove, or make good such material, equipment or supplies without extra compensation. It is expressly understood and agreed that the inspection of materials by The City will in no way lessen the responsibility of the contractor or release him from his obligation to perform and deliver to The City sound and satisfactory materials, equipment or supplies. The contractor agrees to pay the cost of all tests on defective material, equipment or supplies or allow the cost to be deducted from any monies due him by The City.

26. For multi-year contracts the following clauses pursuant to OCGA 36-60-13 apply: (1) The contract shall terminate absolutely and without further obligation on the part of The City or County at the close of the calendar year in which it was executed and at the close of each succeeding calendar year for which it may be renewed; (2) The contract may provide for automatic renewal unless positive action is taken by The City or County to terminate such contract, and the nature of such action shall be determined by The City or County and specified in the contract; (3) The contract shall state the total obligation of The City or County for the calendar year of execution and shall further state the total obligation which will be incurred in each calendar year renewal term, if renewed; and (4) The contract shall provide that title to any supplies, materials, equipment, or other personal property shall remain in the vendor until fully paid for by The City.

27. Unless otherwise specified The City reserves the right to award each item separately or on a lump sum basis, whichever is in the best interest of The City.

28. The successful bidder shall secure all permits, license certificates, inspections (permanent and temporary) and occupational tax certificate, if applicable, before any work can commence. Contractor as well as any and all known subcontractors must possess or will be required to obtain a City of Albany Occupational Tax Certificate or Registration.

29. The successful bidder on motor vehicle equipment shall be required to furnish with delivery of vehicle, Certificate of Origin and Georgia vendors shall provide Georgia Motor Vehicle form MV1.

30. The City reserves the right to reject any and all bids, to waive any informalities in the bid process, and to award the contract as may be in the best interest of the City and/or re-advertise for bids.

31. Local bidder (domiciled in Albany City Limits) will receive bid in the event of tie bids. In the case of tie bids between out of town companies or between local concerns, evaluated as equal, bid will be recommended or awarded by chance coin toss, or drawing straws. The Board of Commissioners passed a local preference ordinance on January 27, 2015. Where applicable, this ordinance will govern. Local preference will not be a basis for award on bids that are federally funded.

32. No bidder writing restrictive specifications for The City will be allowed to bid on the project.

33. Reasonable grounds for supposing that any bidder is interested in more than one bid for the same item will be considered sufficient cause for rejection of all bids in which he/she is interested.

34. A contract will not be awarded to any corporation, firm or individual who is, from any cause, in arrears to The City/County or who has failed in any former contract with The City to perform work satisfactorily, either as to the character of the work, the fulfillment of the guarantee, or the time consumed in completing the work.

35. It is mutually understood and agreed that if any time the Procurement Officer shall be of the opinion that the contract or any part thereof is unnecessarily delayed or that the rate of progress or delivery is unsatisfactory, or that the contractor is willfully violating any of the conditions or covenants of the agreement, or is executing the same in bad faith, the Procurement Officer shall have the power to notify the aforesaid contractor of the nature of the complaint. Notification shall constitute delivery of notice, or letter, to address given in bid/proposal. If after three working days of notification the conditions are not corrected to the satisfaction of the Procurement Officer, he shall thereupon have the power to take whatever action he may deem necessary to complete the work or delivery herein described, or any part thereof, and the expense thereof, so charged, shall be deducted from any paid by The City out of such monies as may become due to the said contractor, under and by virtue of this agreement. In case such expense shall exceed the last said sum, then and in that event, the bondsman or the contractor, his executors, administrators, successors, or assigns, shall pay the amount of such excess to The City on notice by the Procurement Officer of the excess due.

36. Contracts may be cancelled by The City with or without cause with 30-day written notice.

37. Any complaint from bidders relative to the Invitation to Bid or any attached specifications should be made prior to the time of opening of bids, otherwise such complaint cannot be properly considered.

38. Any bidder may withdraw his bid at any time before the time set for opening of bids. No bid may be withdrawn without cause in the 60-day period after bids are opened.

39. All questions, inquiries and requests for clarification shall be directed to Procurement.

40. Prior to submission, all bidders are encouraged to check the website at www.albanyga.gov or call the Procurement Office at 229-

431-3211 for any addendums.

PROCUREMENT FORM - Revised 11/18/2021 http://www.albanyga.gov/

CITY OF ALBANY

BID REFERENCE NO.: 27-037

SPECIFICATIONS

1. SCOPE:

This specification covers:

WaterMaster® 5CD250 fire hydrant

2. MATERIAL:

The units shall be of exact make and model as noted by the item description.

3. SUPPLIERS RESPONSIBILITY:

The supplier shall be responsible for furnishing material in accordance with the specifications regardless of inspection by the purchaser or his representative.

4. SHIPMENT:

The quantity of each item listed in the Bid Documents is for an approximate quantity, Please submit an estimated delivery time of the requested units with the Bid.

** Please reference attached documents for manufacturer specifications. **

WaterMaster® 5CD250 Fire Hydrant

WaterMaster 5CD250 Fire Hydrant:

This hydrant features a 5 1/4" valve opening and is pressure rated for 250 psi. Additionally, each hydrant is tested to twice the working pressure. The bonnet includes a 3-way nozzle configuration with one pumper nozzle and two hose nozzles. Only four bolts are required to remove the bonnet and perform maintenance. This product is UL listed and FM approved.

This dry-barrel fire hydrant meets or exceeds the requirements of ANSI/AWWA C502, UL 246, Factory Mutual 1510, and NSF/ANSI 61 & 372. Please contact your Sales Representative for material certifications.

• 4 1/2" NST pumper nozzle and 2 1/2" NST hose nozzles

• 1 1/2" pentagon operating nut

• 3'6" depth of bury

• 6" mechanical joint inlet connection

• Open left (counterclockwise)

WaterMaster® 5CD250 Fire Hydrant

WaterMaster 5CD250 Fire Hydrant:

This hydrant features a 5 1/4" valve opening and is pressure rated for 250 psi. Additionally, each hydrant is tested to twice the working pressure. The bonnet includes a 3-way nozzle configuration with one pumper nozzle and two hose nozzles. Only four bolts are required to remove the bonnet and perform maintenance. This product is UL listed and FM approved.

This dry-barrel fire hydrant meets or exceeds the requirements of ANSI/AWWA C502, UL 246, Factory Mutual 1510, and NSF/ANSI 61 & 372. Please contact your Sales Representative for material certifications.

• 4 1/2" NST pumper nozzle and 2 1/2" NST hose nozzles

• 1 1/2" pentagon operating nut

• 4'6" depth of bury

• 6" mechanical joint inlet connection

• Open left (counterclockwise)

Bid Ref. #27-037 Hydrants

*COMPLETE AND SUBMIT*

EXHIBIT I - 8

BUY AMERICA CERTIFICATION

The (Name of Supplier) Hereby certifies that each end product, except the end products listed below, is a domestic end product, as defined in 49 DFT 660.13(d).

(Supplier shall show country of origin for each excluded end product)

EXCLUDED END PRODUCT COUNTRY OR ORIGIN

By:

Signature of Company Official

Official’s Title

Date

CITY OF ALBANY

BID REFERENCE NO.: 27-037

ADDENDUM ACKNOWLEDGEMENT FORM

Instructions: Please acknowledge receipt of addenda received by completing this addendum acknowledgement form. Check the box next to each addendum received and sign below. This addendum acknowledgement form should be submitted with your bid to expedite document processing.

Acknowledgement: I, the undersigned, acknowledge receipt of the following addenda to the above referenced Invitation To Bid and have made any necessary revisions to my response or submittal. I understand that failure to confirm the receipt of addenda may be cause for rejection of this bid.

Addendum No. 1 ⃣ Addendum No. 3 ⃣

Addendum No. 2 ⃣ Addendum No. 4 ⃣ ⃣ No Addenda received for Bid Reference No.: 27-037.

I further understand that any verbal representation made or assumed to be made during any oral discussion held between Vendor’s representatives and any city personnel is not binding. Only information issued in writing and added to the specifications by an official addendum is binding.

Company Name

Print Name and Title of Authorized Signer

Authorized Signature

Date

GOVERNING LAW AND VENUE

Contractor agrees that as to any actions or proceedings arising out or related to this agreement, any such proceedings shall be governed and determined by Georgia Law.

Contractor further agrees that as to any actions or proceedings arising out of or related to this agreement, any such action or proceeding shall be resolved only in an appropriate court located in Dougherty County, Georgia.

DATE: ___ __________________

COMPANY NAME: ____________________________

AUTHORIZED REPRESENTATIVE NAME:

TITLE: _____________________________________

SIGNATURE: ____________________________ ____

CERTIFICATION OF NON-COLLUSION

The bidder being sworn, disposes and says, I, The Contractor and its agents, officers or employees have not directly or indirectly entered into any agreements, participated in any collusion or otherwise taken any action in restraint of free competitive bidding in connection with this bid.

INDEMNITY AGREEMENT

This indemnity agreement made and entered into in favor of CITY OF ALBANY (“ALBANY”), a municipal corporation, by [CORPORATE NAME].

WHEREAS, [CORPORATE NAME] has submitted a bid to ALBANY so as to provide

[describe the service, products(s)] .

NOW, THEREFORE, as an additional consideration in ALBANY awarding the bid to

[CORPORATE NAME],

[CORPORATE NAME] agrees to indemnify and hold harmless, ALBANY, its agents, principals, officers, and employees, their successors and assigns, individually and collectively, with respect to all third party claims, demands or liability for any injuries to any person (including death) or damage to any property arising out of any alleged negligence of its officers, agents, or employees in connection with the product or services involved in the bid; provided this indemnity shall not extend to any damage, injury or loss due to ALBANY’s sole negligence or willful injury.

[CORPORATE NAME] shall reimburse ALBANY for reasonable attorney fees and expenses of ALBANY in defending all such claims and shall also be responsible for payment of all judgements.

WITNESS THE HAND AND SEAL of the undersigned pursuant to proper corporate authority this, day of , 20 .

[CORPORATE NAME]

By:

Title

Attest:

Title

[Affix Corporate Seal]

DEBARRED BIDDERS/ INTEGRITY CERTIFICATION

Certification Regarding Debarment, Suspension, Ineligibility, and Voluntary Exclusion

(49 CFR, Part 29):

The Contractor must certify that neither it nor its principals are presently debarred, suspended, proposed for disbarment, declared ineligible, or voluntarily excluded from participation in this transaction by any Federal department or agency. Further, the Contractor certifies that he or she shall obtain an identical certification from all its sub-contractors. The

Contractor also agrees that when a subcontractor is unable to certify to any of the statements in this certification, the prospective participant shall submit an explanation to the Contractor.

* COMPLETE AND SUBMIT*

Advert isement Form

For Al l Fi rms Part icipat ing in the bid please answer quest ions below:

Please let us know how you heard about the BID/RFP advertisement by selecting one of the following.

1. Social Media - Facebook Yes No

2. City of Albany website Yes No

3. City of Albany local access channel (channel 16) Yes No

4. Georgia Procurement Registry Yes No

5. Other:

Please indicate if you are a DBE: Yes No

CITY OF ALBANY PROCUREMENT DIVISION FINANCE DEPARTMENT ALBANY, GEORGIA INSTRUCTIONS TO BIDDERS
10. All bidders should provide their tax identification number with the bid.
40. Prior to submission, all bidders are encouraged to check the website at www.albanyga.gov or call the Procurement Office at 229- 431-3211 for any addendums.
1. SCOPE:
2. MATERIAL:
3. SUPPLIERS RESPONSIBILITY:
4. SHIPMENT:
WaterMaster 5CD250 Fire Hydrant:
EXHIBIT I - 8
CITY OF ALBANY
GOVERNING LAW AND VENUE
CERTIFICATION OF NON-COLLUSION
INDEMNITY AGREEMENT
[CORPORATE NAME]

File details come from the government source that posted it. Updated .