This Invitation to Bid (ITB 2628BIMH154) is issued by the Connecticut Department of Administrative Services (DAS) Construction Services for construction services at the Greater Bridgeport Community Mental Health Center located at 1635 Central Avenue, Bridgeport, Connecticut. The project involves replacing the roof and rooftop HVAC systems at the facility. The solicitation operates on a two-round bidding process, with specifications and drawings released only to qualified general contractors that complete Round 1 and attend the mandatory pre-bid meeting scheduled for December 2, 2026 at 1:00 p.m. at the project site. Vendor questions are accepted through December 23, 2026 at 10:00 a.m. EST, and bids close on January 6, 2027 at 10:00 a.m. EST. The contract term is 300 calendar days, with liquidated damages assessed at $3,551 per calendar day beyond substantial completion and $2,651 per calendar day beyond 90 days after substantial completion.
Bids exceeding $1,000,000 require the bidder to hold current DAS prequalification for General Building Construction (Group C). Responsive bids must include nine documents: the Bid Proposal Form, Certificate of Authority, standard bid bond, General Contractor Bidder's Qualification Statement, DAS Contractor Prequalification Certificate (for bids exceeding $1 million), DAS Update Statement (for bids exceeding $1 million), and Named Subcontractor Signature Pages for subcontractors performing work over $100,000. All bids are submitted electronically through CTsource. The estimated contract value ranges from $4.96 million to $5.48 million. Payment terms are Net 30 days. The project is subject to prevailing wage requirements under Connecticut General Statutes Section 31-53. State law requires minimum spending allocation goals for subcontractors holding current DAS certification, and bidders must demonstrate good faith effort to meet Small Business Enterprise (SBE) goals of 8.10% and Minority Business Enterprise (MBE) goals of 3.06%. Additionally, all bidders must sign and accept a Project Labor Agreement with the Greater Hartford-New Britain Building and Construction Trades Council before contract award. The project receives no federal financial assistance and is not subject to Build America, Buy America Act requirements. The project contact is Jaime Cardinale at DAS Construction Services, Jaime.Cardinale@ct.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00 11 16 DAS-CS Invitation to Bid.pdf | ||
| Specification Volume 1 of 1.pdf | ||
| 00 41 00 DAS-CS Bid Proposal Form LOCKED 07.01.2026.docx | DOCX document | |
| 2628BIMH154_Nov_26_26_solicitation_doc.pdf | ||
| Drawings - Volume 1.pdf | ||
| 00 40 14 CertOfAuthority 20231001.docx | DOCX document | |
| 2628BIMH154_Nov_24_26_solicitation_doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number: 2628BIMH154
Invitation to Bid for Construction Services
DAS-CS Invitation to Bid (CITB)
DAS Construction Services
November 23, 2026 - January 06, 2027
Page:2
General Header Information
2628BIMH154
No. 2628BIMH154 Title: Invitation to Bid for Construction Services Start Date: November 23, 2026 at 3:30:00 PM EST End Date: January 06, 2027 at 10:00:00 AM EST Vendor Q&A Start Date: November 23, 2026 at 3:45:00 PM EST Vendor Q&A End Date: December 23, 2026 at 10:00:00 AM EST Estimated Total Value:
Who can respond to this bid? : All Vendors Description: GBCMHC Replace Roof & Rooftop HVAC
1635 Central Ave.
Bridgeport, CT 06610
BI-MH-154
Delivery Terms: N/A: Not Applicable Payment Terms: Net 30 Days
Page:3
Contact Information: DAS Construction Services Jaime Cardinale 450 Columbus Blvd Hartford CT, 06103 United States Jaime.Cardinale@ct.gov
FREQUENTLY ASKED QUESTIONS:
Where can I find the Specifications and Drawings for Department of Correction (DOC) Projects?
The Specifications and Drawings will be made available to the qualified General Contractors who successfully complete Round 1 of the Invitation to Bid and attend the Mandatory Meeting. Once the Mandatory Meeting is concluded, Round 2 of the bid will be posted on CTsource and the Specifications and Drawings will be made available to the qualified General Contractors who attended the Mandatory Meeting.
Commission on Human Rights and Opportunities:
The contractor who is selected to perform this State project must comply with Connecticut General Statutes Sections (C.G.S. §§) 4a-60, 4a-60g, and 46a-68b through 46a-68f. State law requires a minimum spending allocation goal of the state-funded portion of the contract for award to subcontractors holding current certification from DAS under the provisions of C.G.S. § 4a-60g. The contractor must demonstrate good faith effort to meet the spending allocation goals.
Why Can’t I Click “Select” and “Accept” in the Solicitation?
You need to select “Add New Response” and create a Quote (which you can rename) in order to “Select” and “Accept” the boxes next to the documents. If you do not see the “Attach Documents” tab, not all Solicitation Documents have been opened and accepted on the “Overview” tab.
Does My Firm Need To Be Prequalified To Bid?
All bids greater than $1,000,000 require a bidder to be currently prequalified. To find the specific prequalification requirements for a project, see page 1 of the Invitation to Bid. The Invitation to Bid can be downloaded from the DAS Construction Services Bid Board on CTsource (https://portal.ct.gov/DAS/Construction-Services/BidBoard).
How Do I Find The List of Plan Holders?
Go to the DAS Construction Services Bid Board (https://portal.ct.gov/DAS/Construction-Services/BidBoard) and select the “View Plan Holder List”.
How Do I Find The Pre-Bid Site Meeting Attendance List?
The Pre-Bid Site Meeting Attendance List will be provided in an addendum to the solicitation. To find the addendums for a solicitation, go to the DAS Construction Services Bid Board (https://portal.ct.gov/DAS/Construction-Services/BidBoard), scroll down and click on the appropriate solicitation, and click on the link(s) for the addendums. If there are no addendums, then the Pre-Bid Meeting has not yet taken place.
How Do I Find The Bid Tab (and Bids) After The Bid Has Closed?
Go to the DAS Construction Services Bid Board (https://portal.ct.gov/DAS/Construction-Services/BidBoard), scroll down and click on the appropriate solicitation, and click on the “View Award
Page:4
Report” in the top right corner, located next to the “Print/Download solicitation summary”. The Bid Tab Sheet will be available under “Award Documents”. Individual bid documents will be available under “Vendor Attachments”. Note: If “View Award Report” is not available, then it has not yet been published – check back later in the day.
Page:5
Contact Details: If you have any questions, please contact:
Jaime Cardinale 450 Columbus Blvd Hartford CT, 06103 United States Jaime.Cardinale@ct.gov
FREQUENTLY ASKED QUESTIONS:
Where can I find the Specifications and Drawings for Department of Correction (DOC) Projects?
The Specifications and Drawings will be made available to the qualified General Contractors who successfully complete Round 1 of the Invitation to Bid and attend the Mandatory Meeting. Once the Mandatory Meeting is concluded, Round 2 of the bid will be posted on CTsource and the Specifications and Drawings will be made available to the qualified General Contractors who attended the Mandatory Meeting.
Commission on Human Rights and Opportunities:
The contractor who is selected to perform this State project must comply with Connecticut General Statutes Sections (C.G.S. §§) 4a-60, 4a-60g, and 46a-68b through 46a-68f. State law requires a minimum spending allocation goal of the state-funded portion of the contract for award to subcontractors holding current certification from DAS under the provisions of C.G.S. § 4a-60g. The contractor must demonstrate good faith effort to meet the spending allocation goals.
Why Can’t I Click “Select” and “Accept” in the Solicitation?
You need to select “Add New Response” and create a Quote (which you can rename) in order to “Select” and “Accept” the boxes next to the documents. If you do not see the “Attach Documents” tab, not all Solicitation Documents have been opened and accepted on the “Overview” tab.
Does My Firm Need To Be Prequalified To Bid?
All bids greater than $1,000,000 require a bidder to be currently prequalified. To find the specific prequalification requirements for a project, see page 1 of the Invitation to Bid. The Invitation to Bid can be downloaded from the DAS Construction Services Bid Board on CTsource (https://portal.ct.gov/DAS/Construction-Services/BidBoard).
How Do I Find The List of Plan Holders?
Go to the DAS Construction Services Bid Board (https://portal.ct.gov/DAS/Construction-Services/BidBoard) and select the “View Plan Holder List”.
How Do I Find The Pre-Bid Site Meeting Attendance List?
The Pre-Bid Site Meeting Attendance List will be provided in an addendum to the solicitation. To find the addendums for a solicitation, go to the DAS Construction Services Bid Board (https://portal.ct.gov/DAS/Construction-Services/BidBoard), scroll down and click on the appropriate solicitation, and click on the link(s) for the addendums. If there are no addendums, then the Pre-Bid Meeting has not yet taken place.
How Do I Find The Bid Tab (and Bids) After The Bid Has Closed?
Go to the DAS Construction Services Bid Board (https://portal.ct.gov/DAS/Construction-Services/BidBoard), scroll down and click on the appropriate solicitation, and click on the “View Award
Page:6
Report” in the top right corner, located next to the “Print/Download solicitation summary”. The Bid Tab Sheet will be available under “Award Documents”. Individual bid documents will be available under “Vendor Attachments”. Note: If “View Award Report” is not available, then it has not yet been published – check back later in the day.
Selected Categories:
Page:7
Header Custom Fields:
2628BIMH154
DAS Construction Services – Response Requirements For This Solicitation
Invitations to Bid:
Bid Package Document Requirements:
Upload the following documents under the “Attach Documents” tab prior to the end date and time of the solicitation, as described in the attached Solicitation Documents. IMPORTANT NEW
REQUIREMENT: If the project includes Named Subcontractors, you must upload NAMED
SUBCONTRACTOR SIGNATURE PAGES (see Section 00 45 20).
•1. 00 41 00 Bid Proposal Form
•2. 00 40 14 Certificate (of Authority)
•3. 00 43 16 Standard Bid Bond
•4. 00 45 14 General Contractor Bidder’s Qualification Statement
•5. DAS Contractor Prequalification Certificate FOR BIDS EXCEEDING $1MILLION
•6. DAS Update Statement FOR BIDS EXCEEDING $1MILLION
•7. NEW: Named Subcontractor Signature Page(s) FOR BIDS WITH NAMED
SUBCONTRACTORS
If you do not see the “Attach Documents” tab, not all Solicitation Documents have been opened and accepted on the “Overview” tab.
List of Plan Holders:
Subcontractors looking for a list of contractors who have viewed the plans for a DAS Construction
Serv ices pro jec t shou ld go to the DAS Construct ion Serv ices Bid Board
(https://portal.ct.gov/DAS/Construction-Services/BidBoard), and select the “View Plan Holder
List”.
Pre-Bid Site Meeting Attendance List:
Subcontractors looking for a list of contractors who attended the Pre-Bid Meeting can find the information within the Addendums for a Solicitation. To find the Addendums for a Solicitation, go to the DAS Construction Services Bid Board (https://portal.ct.gov/DAS/Construction-
Services/BidBoard), scroll down and click on the appropriate Solicitation, and click on the link(s) for the Addendums. If there are no Addendums, then the Pre-Bid Meeting has not yet taken place.
https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fprotect-us.mimecast.com%2Fs%2FqQ1tCW6lD8hjX3BVIBJC85%3Fdomain%3Dportal.ct.gov&data=04%7C01%7CRebecca.Cutler%40ct.gov%7C1d6941000ac3431b176008d8fac3fc3a%7C118b7cfaa3dd48b9b02631ff69bb738b%7C0%7C0%7C637535067102254685%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=e3RYcrqnqBd47iLlw2fgtbfdAA%2BhHv2Cqr37ZuTo3%2FM%3D&reserved=0 https://portal.ct.gov/DAS/Construction-Services/BidBoard https://portal.ct.gov/DAS/Construction-Services/BidBoard
Page:8
This bid has no questions defined.
Page:9
Documents:
Specification Volume 1 of 1.pdf
Drawings - Volume 1.pdf
00 11 16 DAS-CS Invitation to Bid.pdf
00 41 00 DAS-CS Bid Proposal Form LOCKED 07.01.2026.docx
00 40 14 CertOfAuthority 20231001.docx
00 40 15 DAS Prequal Cert Reqts 20251001.docx
00 40 16 DAS Update Stmt Reqts 20251001.docx
00 43 16 BidBond 20240924.docx
00 45 14 GC Bidder Qual Statement 20251001.docx
00 45 20 Named Sub Signature Page 20251001.docx
Addendum 01.pdf
Page:10
Item Specifications Solicitation has been designated as having no line items.