261019 Tourtellotte Memorial HS Roof Restoration Project Manual 11-2026.pdf

PDF 4 MB Posted

Attached to
Gasoline
Solicitation number
801
Issued by
Hartford County, Connecticut

About this file

Tourtellotte Memorial High School Roof Restoration Project

This is a Bid Document package for the Tourtellotte Memorial High School Roof Restoration Project issued by Thompson Public Schools in North Grosvenordale, Connecticut. The scope of work includes replacing EPDM roofing, replacing select areas of wood roof deck, repairing sheet metal flashing and trim, salvaging and reinstalling mechanical equipment and gravity vents, replacing roof drains, repointing and cleaning historic masonry, providing a heat-trace system at built-in gutters, repairing cast plaster fabrications, and other related work. Sealed bids will be received until 2:00 P.M. local time on Tuesday, December 15, 2026, at which time bids will be opened publicly. A pre-bid walkthrough is scheduled for Thursday, November 19, 2026, at 10:00 A.M. at the project site located at 785 Riverside Drive, North Grosvenordale, Connecticut 06255. The Owner intends to award the contract approximately 45 days after receipt of bids. All work must be completed by July 1, 2027. The contract will be awarded using the Standard Abbreviated Form of Agreement between Owner and Contractor (AIA Document A104-2017).

Bidders must demonstrate at least five years of successful experience on comparable historic properties and submit three references from projects completed within the past five years. The bid must include performance and payment bonds in an amount not less than 100 percent of the bid amount. Retainage will be held at five percent of the amount of work completed. Connecticut sales and compensating use taxes are exempt and shall not be included in bids. The Contractor must secure the building permit and obtain worker's compensation insurance with statutory coverage, employer's liability of $500,000 each accident/$500,000 disease, commercial general liability with limits of $1,000,000 per occurrence and $2,000,000 aggregate, and automobile insurance with combined single limits of $1,000,000 per accident. Bids may not be withdrawn within 45 days after the bid opening date. Electronic contract documents are available from the Architect, Thaler Reilly Wilson Architecture & Preservation, LLP, with contact Andrew Petruzzelli at (518) 375-3349 or apetruzzelli@trw-arch.com.

View the file

Other files

File Type Posted
801_Nov_23_26_solicitation_doc.pdf PDF
801_Nov_20_26_solicitation_doc.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

25 Monroe St., Suite 202, Albany, NY 12210 518.375.1485 www.trw-arch.com

Project No. 26-027

Tourtellotte Memorial High School Roof Restoration

Project Manual November 16, 2026

Bid Documents

Tourtellotte Memorial H.S. Roof Restoration Project #26-027

North Grosvenordale, Connecticut Bid Documents

TABLE OF CONTENTS 000110 - 1

Thaler Reilly Wilson Architecture & Preservation, LLP November 16, 2026

DOCUMENT 000110 – TABLE OF CONTENTS

000110 Table of Contents

BIDDING DOCUMENTS AND FORMS

Advertisement for Bids

Instructions to Bidders

Bid Form

Statement of Bidder Qualifications

Bidder Qualifications for Historic Treatment Work

A104-2017: Standard Abbreviated Form of Agreement Between Owner and Contractor

DIVISION 01 – GENERAL REQUIREMENTS

011000 General Conditions

011000 Definitions

013591 Historic Treatment Procedures

Release Form

DIVISION 02 – EXISTING CONDITIONS

024119 Selective Demolition

028213 Asbestos Abatement

DIVISION 04 – MASONRY

040310 Historic Masonry Cleaning

040343 Historic Stone Masonry Repointing

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

061053 Miscellaneous Rough Carpentry

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

070362 Historic Sheet Metal Repair

073126 Slate Shingles

075323 EPDM Roofing

076100 Sheet Metal Flashing and Trim

077200 Roof Accessories

079200 Joint Sealants

DIVISION 09 – FINISHES

090320 Historic Treatment of Plaster

099114 Exterior Painting (MPI Standards)

DIVISION 22 – PLUMBING

220533 Heat Tracing for Plumbing Piping

221423 Storm Drainage Piping Specialties

END OF TABLE OF CONTENTS

ADVERTISEMENT FOR BIDS 001000 - 1

ADVERTISEMENT FOR BIDS

Sealed bids for the furnishing of all labor and material necessary for the Tourtellotte Memorial High School Roof Restoration project will be received at 785 Riverside Drive, North Grosvenordale, CT until 2:00 P.M. local time on Tuesday, December 15, 2026 at which time and place bids will be publicly opened and read aloud.

Bids will be received for the following:

Replacing EPDM roofing, replacing select areas of wood roof deck, repairing select areas of sheet metal flashing and trim, salvaging and reinstalling mechanical equipment, and gravity vents to accommodate roofing replacement work, replacing roof drains, repointing and cleaning historic masonry, providing heat-trace system at built-in gutters, repairing cast plaster fabrications, and other Work indicated in the Contract Documents.

Electronic Contract Documents may be obtained after November 16, 2026, from the Architect, in accordance with the Instructions to Bidders. Contact Andrew Petruzzelli at (518) 375-3349 or apetruzzelli@trw-arch.com.

A pre-bid walkthrough will be held on Thursday, November 19, at 10:00 A.M. at the Project Site, 785 Riverside Drive, North Grosvenordale, Connecticut 06255. Attending a walkthrough is optional, but all prospective Bidders are encouraged to attend.

Prospective bidders may request clarifications of the Bid Documents from the Architect by contacting Thaler Reilly Wilson Architecture and Preservation, LLP, by e-mail to Andrew Petruzzelli. All questions must be submitted via e-mail, no phone calls will be accepted. All e-mails must have subject line Tourtellotte Memorial High School Roof Restoration.

Each bid must be accompanied by a performance bond and payment bond in an amount not less than 100 percent (100%) of the amount of the bid in the form and subject to the conditions provided in the Instructions to Bidders. No Bidder may withdraw his bid within forty-five (45) days after the actual date of opening thereof.

No bidder may withdraw its bid within 45 days after the actual date of the bid opening.

By order of Thompson Public Schools.

Project Contact:

Andrew Petruzzelli Thaler Reilly Wilson Architecture & Preservation Tel: (518) 375-3349 Email: apetruzzelli@trw-arch.com

END OF DOCUMENT

INSTRUCTIONS TO BIDDERS 000112 - 1

THALER REILLY WILSON ARCHITECTURE & PRESERVATION, LLC November 16, 2026

INSTRUCTIONS TO BIDDERS

Thaler Reilly Wilson Architecture & Preservation, LLC 25 Monroe St. Suite 202 Albany, New York 12210

(518) 375-1485

To be considered, Bids must be made in accordance with these Instructions to Bidders.

1. PROJECT SITE

The site of the project is the existing building located at 785 Riverside Drive, North Grosvenordale, Connecticut 06255.

2. TIME SCHEDULE

It is the intent of the Owner to award the Contracts for the Work on or about 45 days after receipt of bids. Work may be performed on the building and the site only upon written authorization from the Owner. Immediately upon such notification to proceed, Contractor shall begin the Work of the Contract. All work on the Project must be complete by July 1, 2027.

3. DEFINITIONS

Bidding Documents include the Bidding Requirements and the Proposed Contract Documents.

The Bidding Requirements consist of the Advertisement for Bids, Instructions to Bidders, the bid form, and other sample bidding and contract forms.

The Proposed Contract Documents consist of the form of Agreement between the Owner and Contractor, General Conditions of the Contract, Drawings, Specifications, and all Addenda issued prior to execution of the Contract.

Definitions set forth in the General Conditions of the Contract or in other Proposed Contract Documents apply to the Bidding Documents.

Addenda are written or graphic instruments issued by the Architect, which, by additions, deletions, clarifications, or corrections, modify, or interpret the Bidding Documents.

A Bid is a complete and properly executed proposal to do the Work for the sums stipulated therein, submitted in accordance with the Bidding Documents.

The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents, to which Work may be added or deleted by sums stated in Alternate Bids.

An Alternate Bid (or Alternate) is an amount stated in the Bid to be added to or deducted from, or that does not change, the Base Bid if the corresponding change in the Work, as described in the Bidding Documents, is accepted.

A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials, equipment, or services or a portion of the Work, as described in the Bidding Documents.

INSTRUCTIONS TO BIDDERS 000112 - 2

A Bidder is a person or entity who submits a Bid and who meets the requirements set forth in the Bidding Documents.

4. QUALIFICATIONS OF BIDDERS

Work must be performed by a Contractor with not less than five (5) years successful experience in comparable projects on historic properties. Trades people assigned to the job must have a similar background with experience on historic properties. Bidders must submit the name and location of three (3) different projects the firm has completed within the past five (5) years, the scope of the associated work, and the name of the building owner or project contact for each project who can act as a reference.

The Owner may make such investigation as it deems necessary to determine the responsibility of any bidder or to determine the ability of any bidder to perform the Work.

The Owner reserves the right to disqualify any prospective bidder or to reject any bid if evidence required by the Owner or Architect from the bidder is not submitted or if the evidence submitted or investigation of any such bidder fails to satisfy the Owner or Architect that any such bidder is responsible, able, or qualified to carry out the obligations of the Contract or to complete the work as contemplated therein.

5. DOCUMENTS

Bidders may obtain complete sets of the electronic Bidding Documents from the contact designated in the Advertisement for Bids.

6. EXAMINATION

Bidders shall carefully examine the Bidding Documents and the existing building to obtain first-hand knowledge of existing conditions and to verify conditions under which work will be performed. Failure to do so will not relieve a successful Bidder of the obligation to furnish all material and labor necessary to carry out the provisions of the Bidding Documents and to complete the contemplated work for the amount set forth in his bid. Submission of a Bid will be considered conclusive evidence that a Bidder has visited the site and is conversant with local facilities and difficulties, the requirements of the Bidding Documents, applicable laws and codes, the state of labor and material markets, and has made due allowance in his bid for all contingencies that may arise, whether or not stated.

The Contractor will not be given extra payments for conditions that can be determined by examining the Bidding Documents and existing building.

7. INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS

Should a Bidder find discrepancies in, or omissions from the Drawings, Specifications, or any Contract Documents, or should they be in doubt as to their meaning, or should they find provisions of any law or applicable code conflicting with provisions of the Bidding Documents, they shall at once notify the Architect.

Interpretations, corrections, and changes of the Bidding Documents will be made by Addendum. Such Addendum, as part of the Bidding Documents, shall be binding on all bidders. Interpretations, corrections, and changes of the Bidding Documents made in any other manner will not be binding, and bidders shall not rely upon them.

INSTRUCTIONS TO BIDDERS 000112 - 3

If a Bidder, prior to submitting a Bid, fails to give notification to the Architect of the existence of any such discrepancies, omissions, ambiguities, errors, or conflicts, they shall comply with the interpretations or directions given by the Architect in resolving same, without claiming extra costs.

8. ADDENDA

Addenda will be issued to all who are known by the issuing office to have received a complete set of Bidding Documents.

Addenda will be issued no later than two business days prior to the date for receipt of Bids.

Each Bidder shall ascertain prior to submitting a Bid that the Bidder has received all Addenda issued, and the Bidder shall acknowledge their receipt in the Bid.

9. PRE-BID MEETING

Pre-bid walk-through is scheduled for Thursday, November 19, at 10:00 A.M. at the Project site.

10. PREPARATION OF BIDS

Bids shall be submitted, in duplicate, on the forms included with the Bidding Documents. All blanks on the bid form shall be legibly executed in a non-erasable medium. Sums shall be expressed in both words and figures. In case of discrepancy, the amount written in words shall govern.

Interlineations, alterations, and erasures must be initialed by the signer of the Bid.

11. SUBMISSION OF BIDS

All copies of the Bid and any other documents required to be submitted with the Bid shall be enclosed in a sealed, opaque envelope. The envelope shall be addressed to the party receiving the Bids and shall be identified with the Project name, the Bidder's name and address and, if applicable, the designated portion of the Work for which the Bid is submitted. If the Bid is sent by mail, the sealed envelope shall be enclosed in a separate mailing envelope with the notation "SEALED BID ENCLOSED" on the face thereof.

Bids received after the time and date for receipt of Bids will be returned unopened. The Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids. Oral, telephonic, telegraphic, facsimile, or other electronically transmitted bids will not be considered.

12. MODIFICATION OR WITHDRAWAL OF BIDS

A Bid may not be modified, withdrawn, or canceled by the Bidder during the stipulated time period following the time and date designated for the receipt of Bids, and each Bidder so agrees in submitting a Bid.

Prior to the time and date designated for receipt of Bids, a Bid submitted may be modified or withdrawn by notice to the party receiving Bids at the place designated for receipt of Bids. Such notice shall be in writing over the signature of the Bidder. Written confirmation over the signature of the Bidder shall be received, and date- and time-stamped by the receiving part on or before the date and time set for receipt of Bids. A change shall be so worded as not to reveal the amount of the original Bid.

INSTRUCTIONS TO BIDDERS 000112 - 4

Bids may be modified at a time prior to bid opening by submitting to the Owner a written modification, enclosed in a sealed opaque envelope, signed by the Bidder, or an officer thereof if the Bidder is a corporation, clearly setting forth in what respects the Bid is to be modified. Bids may be withdrawn on written or telegraphic request received from bidders prior to the time fixed for bid opening. Negligence on the part of the Bidder in preparing his Bid confers no right for the withdrawal of the Bid after it has been opened. No Bidder may withdraw his Bid within forty-five (45) days after the opening thereof.

13. OPENING AND AWARD

Bids will be opened as stated in the Advertisement for Bids. The Owner will award the Contract, if at all, as soon as possible following the opening of Bids. If at the time the Contract is to be awarded, the amount of the lowest bid submitted by a qualified Bidder does not exceed the amount of funds and estimate by the Owner, as available to finance the Contract, the Contract will be awarded.

The Owner shall have the right to waive informalities and irregularities in a Bid received and to accept the Bid which, in the Owner’s judgment, is in the Owner’s own best interests.

14. REJECTION OF BIDS

The Owner reserves the right to reject any or all Bids when such rejection is in his interest and to reject any Bid for one or more of the following:

The Bidder fails to furnish any of the information required pursuant to the Instructions to Bidders.

1. The Bidder misstates or conceals any material fact.

2. The Bid does not strictly conform to law or to requirements of the Contract Documents.

3. The Bid is conditional.

4. The Bid is incomplete (by reason of, for example, failure to fill in an alternate price or failure to submit required documentation described herein).

5. The Bidder, or any of his Subcontractors, are deemed unqualified to undertake the work.

15. SUBMITTALS

The Bidder shall, as soon as practicable or as stipulated in the Bidding documents within three (3) business days, after notification of selection for the award of a Contract, furnish to the Owner through the Architect in writing:

1. A designation or the Work to be performed with the Bidder’s own forces;

2. Names of persons or entities proposed for the principal portions of the Work.

All Subcontractors must be acceptable to the Owner and Architect. The Contractor shall provide all information concerning its Subcontractors as requested.

16. QUALIFICATIONS FOR HISTORIC RESTORATION WORK

In order to ensure that only the best workmanship representing the highest standards of current historic restoration practice are used in the Work and that the building is not damaged, the Specifications require previous experience in historic treatment work meeting the requirements of federal and/or state historic preservation agencies as outlined in the "Quality Assurance" paragraph of individual Specification Sections.

INSTRUCTIONS TO BIDDERS 000112 - 5

The Contractor shall submit the Bidder Qualification Form for Restoration Work with its bid, documenting that they and/or their proposed Subcontractors meet the requirements of the Specifications in this specialty. Failure to submit Bidder Qualification Form for Restoration Work, lack of required qualifications in documentation submitted, or submission of incomplete form shall be cause for rejection of the bid.

17. HISTORIC SIGNIFICANCE ACKNOWLEDGMENT

This property has been determined to possess historic and architectural significance and is listed in the National Register of Historic Places The Contractor shall recognize that all aspects of the property may potentially contribute to this significance, and the Contractor shall not judge the relative significance of any features nor the impact of any or all proposed work. This responsibility shall rest solely with the Architect on behalf of the Owner.

Consequently no deviations from the Contract Documents shall be performed, and no features or materials shall be altered, removed, reused or taken from the premises, without the written approval of the Architect as being consistent with the requirements of the Contract Documents. All historic treatment work shall be consistent with The Secretary of the Interior’s Standards for the Treatment of Historic Properties.

18. SALES AND COMPENSATING USE TAXES

The Owner is exempt from paying sales and compensating use taxes of the State of Connecticut and of cities, counties, and other subdivisions of the State of Connecticut on all materials sold to it pursuant to the provisions of this Contract. These taxes are not to be included in bids. This exemption shall apply to supplies and materials which are incorporated in such project. This exemption does not, however, apply to equipment rentals, small tools, and supplies for equipment such as supplies of gasoline used in operating trucks. The term "materials" as used in this article shall include supplies incorporated in this Project. It is the Contractor’s responsibility to be fully aware of rules and regulations of the State of Connecticut that may or may not apply to sales and compensation.

19. LAWS AND REGULATIONS

All applicable State Laws, municipal ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the Project shall apply to the Contract throughout, and they will be deemed to be included in the Contract the same as though herein written out in full.

20. FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR

After the Owner has ascertained the successful Bidder, they shall send a Notice of Award of Contract to the Bidder to whom a Contract has been awarded.

In case of failure or refusal of an accepted Bidder to enter into a Contract within ten days after the issue date of the Notice of Award, the Bidder will be considered as having abandoned the Contract. In such event, the Bidder shall be liable for and agrees to pay to the Owner, on demand, damages for such failure or refusal. Such damages shall be the difference between the price bid by them and the price for which such contract shall subsequently be relet, plus the cost of such reletting, plus any other consequential expenses and damages.

INSTRUCTIONS TO BIDDERS 000112 - 6

The Contract used for this project shall be the Standard Abbreviated Form of Agreement between Owner and Contractor (AIA Document A104), 2017 Edition published by the American Institute of Architects. The retainage under the Contract shall be five percent (5%) of the amount of the work completed. Return contracts within seven (7) calendar days from Notice of Award.

22. BONDING REQUIREMENTS

Each bid must be accompanied by a performance bond and payment bond. The performance bond must be for 100 percent (100%) of the contract price.

The payment bond must be for 100 percent (100%) of the contract price.

23. INSURANCE REQUIREMENTS

The Contractor shall purchase and maintain insurance of the following types of coverage and limits of liability:

Contractor shall, at its own expense and cost, obtain and keep in force during the entire duration of the Project or Work the following insurance coverages covering the Contractor and all of its agents, employees, and subcontractors and other providers of services and shall name the Town of Thompson and the Board of Education its employees and agents as an Additional Insured on a primary and non-contributory basis to the Contractor's Commercial General Liability and Automobile Liability policies. These requirements shall be clearly stated in the remarks section on the Contractor's Certificate of Insurance. Insurance shall be written with insurance carriers approved in the State of Connecticut and with a minimum Best's Rating of A-VIII with all policies written on an occurrence form basis. In addition, all carriers are subject to approval by the Town. Minimum Limits and requirements are stated below:

Worker's Compensation Insurance:

Statutory Coverage Employer's Liability $500,000 each accident/$500,000 disease-policy limit/$500,000 disease each employee A Waiver of Subrogation shall be provided in favor of the Town of Thompson and its employees and agents.

Commercial General Liability:

Including Premises & Operations, Products and Completed Operations, Personal and Advertising Injury, Contractual Liability and Independent Contractors.

Limits of Liability for Bodily Injury and Building Damage

Each Occurrence $1,000,000 Aggregate $2,000,000 (The Aggregate Limit shall apply separately to each job.)

A Waiver of Subrogation shall be provided in favor of the Town of Thompson and its employees and agents.

Automobile Insurance:

Including all owned, hired, borrowed, and non-owned vehicles.

Evidence of Combined Single Limit of Liability for Bodily Injury and Building Damage: Per Accident $1,000,000 A Waiver of Subrogation shall be provided in favor of the Town of Thompson and its employees and agents.

INSTRUCTIONS TO BIDDERS 000112 - 7

The Contractor shall provide a Certificate of Insurance as "evidence" of General Liability, Auto Liability including all owned, hired, borrowed and non-owned vehicles, statutory Worker's Compensation and Employer's Liability coverage.

The Contractor shall direct its Insurer to provide a Certificate of Insurance to the Town before any work is performed. The Contractor will be responsible to provide written notice to the Owner 60 days prior to cancellation or non-renewal of any insurance policy. The Certificate shall evidence all required coverages including the Additional Insured on the General Liability and Auto Liability policies and Waiver of Subrogation on the General Liability policy.

The Contractor shall provide the Town copies of any such insurance policies upon request.

END OF INSTRUCTIONS TO BIDDERS

BID FORM 000113 - 1

BID FORM

Tourtellotte Memorial High School Roof Restoration 785 Riverside Drive, North Grosvenordale, CT 06255

Thompson Public Schools 785 Riverside Drive, North Grosvenordale, CT 06255

We (I) have received the Contract Documents (Contract Drawings and the Project Manual) for the Work. We have also received Addenda Nos._______________ (if applicable) and have included their provisions in this Bid. We have examined both the Contract Documents and the site and submit the following Bid:

In submitting this Bid, We (I) agree:

1. To hold our Bid open until forty-five (45) days after Bid Opening.

2. To accept the provisions of the Instructions to Bidders.

3. To enter into and execute a Contract within ten (10) days of the Notice of Award issue date, and to furnish Performance and Labor and Material Bonds.

4. To accomplish the Work in accordance with the Contract Documents and the Contract.

5. To complete the Work on schedule as noted in the Instructions to Bidders.

The Undersigned acknowledges the receipt of the following addenda, but agrees that it is bound by all addenda whether or not listed herein:

Addendum No. Date of Addendum

BASE BID

All labor, material, services and equipment necessary for completion of the Work shown on the Drawings and the Technical Specifications for General Work.

We (I) will perform the Work of this Contract for the lump-sum of:

_________________________________________________________ Dollars ($___________)

BID FORM 000113 - 2

ALTERNATES

Provide all work in accordance with the requirements of the Drawings and Specifications for the following:

ALTERNATE NO. 1: Replace Slate Roofing.

Add/Deduct ________________________________________________ Dollars ($___________)

UNIT PRICES

We (I) agree to perform all work in accordance with the requirements of the Drawings and Specifications for the following items at the unit prices given:

We (I) will perform all work required for Unit Price No. 1 for the unit price PER square foot:

_________________________________________________________ Dollars ($___________)

We (I) have attached the following documents to this Bid.

1. Statement of Bidder Qualifications

2. Contractor's proposed construction schedule

3. Proof of insurance and relevant licenses

4. Bidder Qualification Form for Restoration Work

5. Performance bonding and payment bonding

We (I) understand that the Owner reserves the right to reject any or all Bids and to waive any informalities in the bidding.

Legal name of firm (please type)

Address (please type)

Name and title of signer (please type) Seal (if firm is a corporation)

Signature Date

STATEMENT OF BIDDER QUALIFICATIONS 004400 - 1

STATEMENT OF BIDDER'S QUALIFICATIONS: PROOF OF COMPETENCY

The submission of this signed and notarized form is a requirement of the Bidding Documents.

All items must be answered and the data given must be clear and comprehensive. Failure to answer these questions in a complete and satisfactory manner will result in the rejection of the bid. The Owner reserves the right to reject any bidder who in the judgment of the Owner, and based on a review of the Qualifications forms, is not qualified to perform the work of the Contract as specified. The Owner's decisions regarding rejection of the bids based on a bidder's qualifications shall be final.

If necessary, questions may be answered on separate attached sheets. The bidder may submit any additional information he desires.

1. Name of Bidder.

2. Permanent main office address.

3. When organized.

4. If a corporation, where incorporated.

5. Number of years engaged in the contracting business under your present firm or trade name.

6. Contracts on hand: (Schedule these; show amount of each contract and the appropriate anticipated dates of completion.)

7. General character of work performed by your company.

STATEMENT OF BIDDER QUALIFICATIONS 004400 - 2

8. Have you ever failed to complete any work awarded to you?

If so, where and why?

9. Have you ever defaulted on a contract?

If so, where and why?

10. List the more important projects recently completed by your company, stating the approximate cost for each and the month and year completed.

11. List your major equipment available for this contract.

STATEMENT OF BIDDER QUALIFICATIONS 004400 - 3

12. List your experience in construction work similar in importance to this project.

13. List the background and experience of the principal members of your organization, including the officers.

14. Amount of credit available:

15. Give bank references:

STATEMENT OF BIDDER QUALIFICATIONS 004400 - 4

16. Bidder will be required to furnish evidence satisfactory to the Owner that he has sufficient means and experiences in the types of work called for to assure completion of the contract in a satisfactory manner.

_________________________________________________ Seal: (If firm is a corporation) Legal name of firm (please type)

Address (please type)

Name and title of signer (please type)

Notary Public Date

BIDDER QUALIFICATION FORM FOR HISTORIC TREATMENT WORK 000115 - 1

BIDDER QUALIFICATION FORM FOR HISTORIC TREATMENT WORK

Tourtellotte Memorial High School Roof Restoration 785 Riverside Drive, North Grosvenordale, CT 06255

Tourtellotte Memorial High School is a significant historic structure eligible to be listed in the National Register of Historic Places. The Bidder must demonstrate to the satisfaction of the Owner that its firm, and the personnel to be employed in the execution of the work, possess requisite experience in the successful completion of comparable work on other buildings listed in the National Register of Historic Places.

All items of this Bidder Qualification Form must be answered, and the data given must be clear and comprehensive. Failure to answer these questions in a complete and satisfactory manner will result in rejection of the Bid. The Owner reserves the right to reject any Bidder who, in the judgment of the Owner and based on a review of the Bidder Qualification Form, is not qualified to perform the work required for this Project. The Owner's decision regarding rejection of any Bidder Qualification Form shall be final.

Questions No. 1 through 5 refer specifically to the General Contractor's firm and will be used to determine the ability of the General Contractor to manage and perform the quality of work required for this Project. Questions 6 through 14 refer to the Specialists that would be performing the indicated work. If needed, answers may be on separate attached sheets. Submit photographic data as required.

“Specialist” shall mean an individual or firm of established reputation (or, if newly organized, whose personnel have previously established a reputation in the same field), which is regularly engaged in, and which maintains a regular force of workers skilled in either (as applicable) manufacturing or fabricating items required for the Project, installing items required for the Project, or otherwise performing work required for the Project. Bidder Qualification shall be required for the following:

General Contractor Masonry Cleaning Historic Treatment Specialist Stone Masonry Repointing Historic Treatment Specialist Sheet Metal Historic Treatment Specialist Cast Plaster Historic Treatment Specialist

If necessary, questions may be answered on separate attached sheets. The bidder may submit any additional information he desires. In submitting the names of the persons and firms below, the Bidder represents that he has investigated the qualifications of the submitted persons and firms and has found them to have performed the work stated.

GENERAL CONTRACTOR

1. How many years has your organization been in business under its present name?

2. How many years under previous business names (if any)?

3. List previous names.

BIDDER QUALIFICATION FORM FOR HISTORIC TREATMENT WORK 000115 - 2

4. List projects on which historic preservation/restoration/renovation work was performed within the past five (5) years on buildings listed in the National Register of Historic Places.

A minimum of three (3) projects successfully completed in the past five (5) years is required to be acceptable. A contractor need not have performed all of the above types of construction on a single project. Provide a brief description and at least 5 photographs of each of the listed projects, clearly depicting the scope of work of the project. Two of the following projects should be similar in size, nature, and scope to the Tourtellotte Memorial High School Roof Restoration.

Project Name & Address Year Cost Owner (Tel.#) Architect (Tel.#)

A.

B.

C.

D.

5. Provide the names of proposed supervisors and foremen to be employed on this job.

Indicate on which job, of the ones listed above, they have worked. On a separate sheet, give brief resume of each describing their specific qualifications and past experience in supervising, directing and executing work comparable to that required in this project.

Name Number of years Jobs on which they have worked assoc. with firm (selected from above)

BIDDER QUALIFICATION FORM FOR HISTORIC TREATMENT WORK 000115 - 3

SPECIALISTS

6. Will you subcontract any part of the work? If so, list subcontractors and their trade:

7. List at least three (3) jobs involving Masonry Cleaning work that your firm (or subcontractor) has executed in the past five (5) years on buildings listed in the National Register of Historic Places.

8. Provide the names of skilled personnel proposed for Masonry Cleaning work. Indicate on which job, of the ones listed above, they have worked. On separate sheet, give brief resume of each describing their specific qualifications and past experience in performing Masonry Cleaning work.

BIDDER QUALIFICATION FORM FOR HISTORIC TREATMENT WORK 000115 - 4

9. List at least three (3) jobs involving Historic Stone Masonry Repointing work that your firm (or subcontractor) has executed in the past five (5) years in buildings listed in the National Register of Historic Places.

10. Provide the names of skilled personnel proposed for Historic Stone Masonry Repointing work. Indicate on which job, of the ones listed above, they have worked. On separate sheet, give brief resume of each describing their specific qualifications and past experience in performing Historic Stone Masonry Repointing work.

11. List at least three (3) jobs involving Historic Sheet Metal Repair work that your firm (or

BIDDER QUALIFICATION FORM FOR HISTORIC TREATMENT WORK 000115 - 5

12. Provide the names of skilled journeyman personnel proposed for Historic Sheet Metal

Repair work. Indicate on which job, of the ones listed above, they have worked. On separate sheet, give brief resume of each describing their specific qualifications and past experience in performing Historic Sheet Metal Repair work.

13. List at least three (3) jobs involving Historic Cast Plaster Repair work that your firm (or

14. Provide the names of skilled journeyman personnel proposed for Historic Cast Plaster

Repair work. Indicate on which job, of the ones listed above, they have worked. On separate sheet, give brief resume of each describing their specific qualifications and past experience in performing Historic Cast Plaster Repair work.

BIDDER QUALIFICATION FORM FOR HISTORIC TREATMENT WORK 000115 - 6

Submitted by:

_________________________________________________ Seal: (If firm is a corporation) Legal name of firm (please type)

Address (please type)

Name and title of signer (please type)

Notary Public Date

AIA

Document A104™ – 2017

Standard Abbreviated Form of Agreement Between Owner and

Contractor

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract

Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 15:55:24 ET on 02/01/2021 under Order No.4090953478 which expires on 12/28/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.

User Notes: (830034266)

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an attorney is encouraged with respect to its completion or modification.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

AGREEMENT made as of the « » day of « » in the year « »

(In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address and other information) and the Contractor:

for the following Project:

(Name, location and detailed description)

The Architect:

The Owner and Contractor agree as follows.

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract

Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 15:55:24 ET on 02/01/2021 under Order No.4090953478 which expires on 12/28/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.

TABLE OF ARTICLES

1 THE WORK OF THIS CONTRACT

2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

3 CONTRACT SUM

4 PAYMENT

5 DISPUTE RESOLUTION

6 ENUMERATION OF CONTRACT DOCUMENTS

7 GENERAL PROVISIONS

8 OWNER

9 CONTRACTOR

10 ARCHITECT

11 SUBCONTRACTORS

12 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS

13 CHANGES IN THE WORK

14 TIME

15 PAYMENTS AND COMPLETION

16 PROTECTION OF PERSONS AND PROPERTY

17 INSURANCE AND BONDS

18 CORRECTION OF WORK

19 MISCELLANEOUS PROVISIONS

20 TERMINATION OF THE CONTRACT

21 CLAIMS AND DISPUTES

EXHIBIT A DETERMINATION OF THE COST OF THE WORK

ARTICLE 1 THE WORK OF THIS CONTRACT

The Contractor shall execute the Work described in the Contract Documents, except as specifically indicated in the

Contract Documents to be the responsibility of others.

ARTICLE 2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 2.1 The date of commencement of the Work shall be:

(Check one of the following boxes.)

[ « » ] The date of this Agreement.

[ « » ] A date set forth in a notice to proceed issued by the Owner.

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract

Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 15:55:24 ET on 02/01/2021 under Order No.4090953478 which expires on 12/28/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.

[ « » ] Established as follows:

(Insert a date or a means to determine the date of commencement of the Work.)

If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this

Agreement.

§ 2.2 The Contract Time shall be measured from the date of commencement.

§ 2.3 Substantial Completion § 2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:

(Check the appropriate box and complete the necessary information.)

[ « » ] Not later than « » ( « » ) calendar days from the date of commencement of the Work.

[ « » ] By the following date: « »

§ 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial

Completion of such portions by the following dates:

Portion of Work Substantial Completion Date

§ 2.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 2.3, liquidated damages, if any, shall be assessed as set forth in Section 3.5.

ARTICLE 3 CONTRACT SUM

§ 3.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the

Contract. The Contract Sum shall be one of the following:

(Check the appropriate box.)

[ « » ] Stipulated Sum, in accordance with Section 3.2 below

[ « » ] Cost of the Work plus the Contractor’s Fee, in accordance with Section 3.3 below

[ « » ] Cost of the Work plus the Contractor’s Fee with a Guaranteed Maximum Price, in accordance with

Section 3.4 below

(Based on the selection above, complete Section 3.2, 3.3 or 3.4 below.)

§ 3.2 The Stipulated Sum shall be « » ($ « » ), subject to additions and deductions as provided in the Contract

Documents.

§ 3.2.1 The Stipulated Sum is based upon the following alternates, if any, which are described in the Contract

Documents and are hereby accepted by the Owner:

(State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the

Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)

§ 3.2.2 Unit prices, if any:

(Identify the item and state the unit price and the quantity limitations, if any, to which the unit price will be applicable.)

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract

Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 15:55:24 ET on 02/01/2021 under Order No.4090953478 which expires on 12/28/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.

Item Units and Limitations Price per Unit ($0.00)

§ 3.2.3 Allowances, if any, included in the stipulated sum:

(Identify each allowance.)

Item Price

§ 3.3 Cost of the Work Plus Contractor’s Fee § 3.3.1 The Cost of the Work is as defined in Exhibit A, Determination of the Cost of the Work.

§ 3.3.2 The Contractor’s Fee:

(State a lump sum, percentage of Cost of the Work or other provision for determining the Contractor’s Fee and the method of adjustment to the Fee for changes in the Work.)

§ 3.4 Cost of the Work Plus Contractor’s Fee With a Guaranteed Maximum Price § 3.4.1 The Cost of the Work is as defined in Exhibit A, Determination of the Cost of the Work.

§ 3.4.2 The Contractor’s Fee:

(State a lump sum, percentage of Cost of the Work or other provision for determining the Contractor’s Fee and the method of adjustment to the Fee for changes in the Work.)

§ 3.4.3 Guaranteed Maximum Price § 3.4.3.1 The sum of the Cost of the Work and the Contractor’s Fee is guaranteed by the Contractor not to exceed « »

($ « » ), subject to additions and deductions by changes in the Work as provided in the Contract Documents. This maximum sum is referred to in the Contract Documents as the Guaranteed Maximum Price. Costs which would cause the Guaranteed Maximum Price to be exceeded shall be paid by the Contractor without reimbursement by the Owner.

(Insert specific provisions if the Contractor is to participate in any savings.)

§ 3.4.3.2 The Guaranteed Maximum Price is based on the following alternates, if any, which are described in the

Contract Documents and are hereby accepted by the Owner:

(State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the

Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)

§ 3.4.3.3 Unit Prices, if any:

(Identify the item and state the unit price and the quantity limitations, if any, to which the unit price will be applicable.)

Item Units and Limitations Price per Unit ($0.00)

§ 3.4.3.4 Allowances, if any, included in the Guaranteed Maximum Price:

(Identify each allowance.)

Item Price

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract

Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 15:55:24 ET on 02/01/2021 under Order No.4090953478 which expires on 12/28/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.

§ 3.4.3.5 Assumptions, if any, on which the Guaranteed Maximum Price is based:

§ 3.4.3.6 To the extent that the Contract Documents are anticipated to require further development, the Guaranteed

Maximum Price includes the costs attributable to such further development consistent with the Contract Documents and reasonably inferable therefrom. Such further development does not include changes in scope, systems, kinds and quality of materials, finishes or equipment, all of which, if required, shall be incorporated by Change Order.

§ 3.4.3.7 The Owner shall authorize preparation of revisions to the Contract Documents that incorporate the agreed-upon assumptions contained in Section 3.4.3.5. The Owner shall promptly furnish such revised Contract

Documents to the Contractor. The Contractor shall notify the Owner and Architect of any inconsistencies between the agreed-upon assumptions contained in Section 3.4.3.5 and the revised Contract Documents.

§ 3.5 Liquidated damages, if any:

(Insert terms and conditions for liquidated damages, if any.)

ARTICLE 4 PAYMENT

§ 4.1 Progress Payments § 4.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for

Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the

Contractor as provided below and elsewhere in the Contract Documents.

§ 4.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:

§ 4.1.3 Provided that an Application for Payment is received by the Architect not later than the « » day of a month, the

Owner shall make payment of the certified amount to the Contractor not later than the « » day of the « » month. If an

Application for Payment is received by the Architect after the date fixed above, payment shall be made by the Owner not later than « » ( « » ) days after the Architect receives the Application for Payment.

(Federal, state or local laws may require payment within a certain period of time.)

§ 4.1.4 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold retainage from the payment otherwise due as follows:

(Insert a percentage or amount to be withheld as retainage from each Application for Payment and any terms for reduction of retainage during the course of the Work. The amount of retainage may be limited by governing law.)

§ 4.1.5 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.

(Insert rate of interest agreed upon, if any.)

§ 4.2 Final Payment § 4.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the

Contractor when

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct

Work as provided in Section 18.2, and to satisfy other requirements, if any, which extend beyond final payment;

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract

Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 15:55:24 ET on 02/01/2021 under Order No.4090953478 which expires on 12/28/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.

.2 the Contractor has submitted a final accounting for the Cost of the Work, where payment is on the basis of the Cost of the Work with or without a Guaranteed Maximum Price; and

.3 a final Certificate for Payment has been issued by the Architect in accordance with Section 15.7.1.

§ 4.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the

Architect’s final Certificate for Payment, or as follows:

ARTICLE 5 DISPUTE RESOLUTION

§ 5.1 Binding Dispute Resolution For any claim subject to, but not resolved by, mediation pursuant to Section 21.5, the method of binding dispute resolution shall be as follows:

(Check the appropriate box.)

[ « » ] Arbitration pursuant to Section 21.6 of this Agreement

[ « » ] Litigation in a court of competent jurisdiction

[ « » ] Other (Specify)

If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, claims will be resolved in a court of competent jurisdiction.

ARTICLE 6 ENUMERATION OF CONTRACT DOCUMENTS

§ 6.1 The Contract Documents are defined in Article 7 and, except for Modifications issued after execution of this

Agreement, are enumerated in the sections below.

§ 6.1.1 The Agreement is this executed AIA Document A104™–2017, Standard Abbreviated Form of Agreement

Between Owner and Contractor.

§ 6.1.2 AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, dated as indicated below:

(Insert the date of the E203–2013 incorporated into this Agreement.)

§ 6.1.3 The Supplementary and other Conditions of the Contract:

Document Title Date Pages

§ 6.1.4 The Specifications:

(Either list the Specifications here or refer to an exhibit attached to this Agreement.)

Section Title Date Pages

§ 6.1.5 The Drawings:

(Either list the Drawings here or refer to an exhibit attached to this Agreement.)

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract

Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 15:55:24 ET on 02/01/2021 under Order No.4090953478 which expires on 12/28/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.

Number Title Date

§ 6.1.6 The Addenda, if any:

Number Date Pages

Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are enumerated in this Article 6.

§ 6.1.7 Additional documents, if any, forming part of the Contract Documents:

.1 Other Exhibits:

(Check all boxes that…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .