The document is a detailed construction schedule for the 26059 Avon Road Crosswalk Improvements project, developed for the Town of Avon, Colorado. The schedule spans from April 9, 2025, to November 18, 2025, and outlines a comprehensive 54-day construction timeline divided into three primary phases: Phase 1 focuses on removals and curb ramps/sidewalk work, covering multiple locations including I-70 westbound and eastbound ramps, Beaver Creek Boulevard, Benchmark Road, Hurd Lane, and US 6. Phase 2 involves Rectangular Rapid Flashing Beacon (RRFB) installation, including pull boxes, conduit placement, and beacon positioning. Phase 3 concentrates on project finalization, including landscape restoration, punch list completion, final inspection, clean-up, and project acceptance.
The construction schedule details specific daily tasks with precise start and end dates, breaking down complex infrastructure improvements across various roadways and intersections. The project involves extensive infrastructure work including removal of existing concrete elements, sidewalks, curb ramps, and asphalt, followed by placement of new aggregate base course, concrete sidewalks, curb ramps, and other roadway components. The schedule indicates a methodical approach to the Highway Safety Improvement Project (HSIP), federally funded and focused on crosswalk improvements along Avon Road from the I-70 interchange to US6, with careful sequencing of construction activities to minimize disruption and ensure efficient project completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Avon RRFBs.kmz | KMZ file | |
| 32030 Avon Rd Crosswalk Improvements - Federal Funding - RFQ CM _ Materials Testing.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish
1 Advertisement 1 day Wed 4/9/25 Wed 4/9/25
2 Bid Phase Services 15 days Thu 4/10/25 Wed 4/30/25
3 Notice to Proceed 0 days Wed 5/21/25 Wed 5/21/25
4 Pre-Construction Meeting 0 days Mon 8/18/25 Mon 8/18/25
5 Shop Drawings & Submittals 10 days Tue 8/19/25 Tue 9/2/25
6 Construction 54 days Thu 9/4/25 Tue 11/18/25
7 Phase 1: Removals & Curb Ramps/Sidewalk45 days Thu 9/4/25 Wed 11/5/25
8 Utility Locates/Potholing 3 days Thu 9/4/25 Mon 9/8/25
9 Mobilization/Construction Signing 3 days Tue 9/9/25 Thu 9/11/25
10 Construction Surveying 3 days Fri 9/12/25 Tue 9/16/25
11 Erosion Control Initial Installation 2 days Wed 9/17/25 Thu 9/18/25
12 I-70 WB Ramps 5 days Fri 9/19/25 Thu 9/25/25
13 Removal of Concrete Curb Ramps 2 days Fri 9/19/25 Mon 9/22/25
14 Removal of Sidewalk 2 days Fri 9/19/25 Mon 9/22/25
15 Removal of Concrete Median Cover Material2 days Fri 9/19/25 Mon 9/22/25
16 Removal of Curb and Gutter 2 days Fri 9/19/25 Mon 9/22/25
17 Removal of Asphalt Mat 2 days Fri 9/19/25 Mon 9/22/25
18 Placement of Aggregate Base Course3 days Tue 9/23/25 Thu 9/25/25
19 Placement of Hot Mix Asphalt (Patching)3 days Tue 9/23/25 Thu 9/25/25
20 Placement of Concrete Sidewalk 3 days Tue 9/23/25 Thu 9/25/25
21 Placement of Concrete Curb Ramp 3 days Tue 9/23/25 Thu 9/25/25
22 Placement of Curb and Gutter 3 days Tue 9/23/25 Thu 9/25/25
23 I-70 EB Ramps 5 days Fri 9/26/25 Thu 10/2/25
24 Removal of Concrete Curb Ramps 2 days Fri 9/26/25 Mon 9/29/25
25 Removal of Sidewalk 2 days Fri 9/26/25 Mon 9/29/25
26 Removal of Concrete Median Cover Material2 days Fri 9/26/25 Mon 9/29/25
27 Removal of Curb and Gutter 2 days Fri 9/26/25 Mon 9/29/25
28 Removal of Asphalt Mat 2 days Fri 9/26/25 Mon 9/29/25
29 Placement of Aggregate Base Course3 days Tue 9/30/25 Thu 10/2/25
30 Placement of Concrete Sidewalk 3 days Tue 9/30/25 Thu 10/2/25
31 Placement of Concrete Curb Ramp 3 days Tue 9/30/25 Thu 10/2/25
32 Placement of Curb and Gutter 3 days Tue 9/30/25 Thu 10/2/25
33 Beaver Creek Blvd 6 days Fri 10/3/25 Fri 10/10/25
34 Removal of Concrete Curb Ramps 2 days Fri 10/3/25 Mon 10/6/25
35 Removal of Sidewalk 2 days Fri 10/3/25 Mon 10/6/25
36 Removal of Concrete Median Cover Material2 days Fri 10/3/25 Mon 10/6/25
37 Removal of Curb and Gutter 2 days Fri 10/3/25 Mon 10/6/25
38 Placement of Aggregate Base Course4 days Tue 10/7/25 Fri 10/10/25
39 Placement of Concrete Sidewalk 4 days Tue 10/7/25 Fri 10/10/25
40 Placement of Concrete Curb Ramp 4 days Tue 10/7/25 Fri 10/10/25
41 Placement of Curb and Gutter 4 days Tue 10/7/25 Fri 10/10/25
42 Benchmark Rd 6 days Mon 10/13/25Mon 10/20/25
43 Removal of Concrete Curb Ramps 2 days Mon 10/13/25Tue 10/14/25
44 Removal of Sidewalk 2 days Mon 10/13/25Tue 10/14/25
45 Removal of Concrete Median Cover Material2 days Mon 10/13/25Tue 10/14/25
46 Removal of Curb and Gutter 2 days Mon 10/13/25Tue 10/14/25
47 Placement of Aggregate Base Course4 days Wed 10/15/25Mon 10/20/25
48 Placement of Concrete Sidewalk 4 days Wed 10/15/25Mon 10/20/25
49 Placement of Concrete Curb Ramp 4 days Wed 10/15/25Mon 10/20/25
50 Placement of Curb and Gutter 4 days Wed 10/15/25Mon 10/20/25
51 Hurd Lane 4 days Tue 10/21/25 Fri 10/24/25
52 Removal of Concrete Curb Ramps 2 days Tue 10/21/25 Wed 10/22/25
53 Removal of Sidewalk 2 days Tue 10/21/25 Wed 10/22/25
54 Removal of Concrete Median Cover Material2 days Tue 10/21/25 Wed 10/22/25
55 Removal of Curb and Gutter 2 days Tue 10/21/25 Wed 10/22/25
56 Placement of Aggregate Base Course2 days Thu 10/23/25 Fri 10/24/25
57 Placement of Concrete Sidewalk 2 days Thu 10/23/25 Fri 10/24/25
58 Placement of Concrete Curb Ramp 2 days Thu 10/23/25 Fri 10/24/25
59 Placement of Curb and Gutter 2 days Thu 10/23/25 Fri 10/24/25
60 US 6 8 days Mon 10/27/25Wed 11/5/25
61 Removal of Concrete Curb Ramps 2 days Mon 10/27/25Tue 10/28/25
62 Removal of Sidewalk 2 days Mon 10/27/25Tue 10/28/25
63 Removal of Concrete Median Cover Material2 days Mon 10/27/25Tue 10/28/25
64 Removal of Curb and Gutter 2 days Mon 10/27/25Tue 10/28/25
65 Removal of Asphalt Mat 2 days Mon 10/27/25Tue 10/28/25
66 Placement of Aggregate Base Course6 days Mon 10/27/25Mon 11/3/25
67 Placement of Hot Mix Asphalt (Patching)6 days Wed 10/29/25Wed 11/5/25
68 Placement of Concrete Sidewalk 6 days Wed 10/29/25Wed 11/5/25
69 Placement of Concrete Curb Ramp 6 days Wed 10/29/25Wed 11/5/25
70 Placement of Curb and Gutter 6 days Wed 10/29/25Wed 11/5/25
71 Phase 2: RRFB Work 12 days Mon 10/27/25Tue 11/11/25
72 Placement of Type 2 Pull Boxes/Conduit6 days Mon 10/27/25Mon 11/3/25
73 Placement of Rectangular Rapid Flashing Beacons12 days Mon 10/27/25Tue 11/11/25
74 Striping 1 day Thu 11/6/25 Thu 11/6/25
75 Phase 3: Finalizing 5 days Wed 11/12/25Tue 11/18/25
76 Landscape Restoration 2 days Wed 11/12/25Thu 11/13/25
77 Punch List 3 days Wed 11/12/25Fri 11/14/25
78 Final Inspection 1 day Mon 11/17/25Mon 11/17/25
79 Final Clean-up 1 day Tue 11/18/25 Tue 11/18/25
80 Final Acceptance 1 day Tue 11/18/25 Tue 11/18/25
5/21
8/18
Mar 30, '25 Apr 6, '25 Apr 13, '25 Apr 20, '25 Apr 27, '25 May 4, '25 May 11, '25 May 18, '25 May 25, '25 Jun 1, '25 Jun 8, '25 Jun 15, '25 Jun 22, '25 Jun 29, '25 Jul 6, '25 Jul 13, '25 Jul 20, '25 Jul 27, '25 Aug 3, '25 Aug 10, '25 Aug 17, '25 Aug 24, '25 Aug 31, '25 Sep 7, '25 Sep 14, '25 Sep 21, '25 Sep 28, '25 Oct 5, '25 Oct 12, '25 Oct 19, '25 Oct 26, '25 Nov 2, '25 Nov 9, '25 Nov 16, '25 Nov 23, '25 Nov 30, '25
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
E. Alameda Pkwy & S. Buckley Road Construction Schedule
26059 Avon Rd
Crosswalk Improvements