26-8706_Bid_Schedule.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Immokalee Sports Complex Phase 2
Solicitation number
26-8706
Issued by
Collier County, Florida

About this file

This is a bid schedule for Collier County, Florida's construction of the Immokalee Sports Complex Phase 2 Project, Bid No. 26-8706. The project encompasses multiple divisions of work including procurement and contracting requirements, general requirements, concrete work, equipment installation, furnishings, special construction, earthworks, exterior improvements, and utilities. Key deliverables include construction of a 1,495-square-foot pool mechanical building with a below-slab surge tank, renovation of existing restroom facilities, installation of a feature pool with amenities (ADA lift, competition equipment, slide, basketball hoop), a splash pad with safety flooring, site clearing and grading, landscaping and irrigation installation (88,823 square feet of sod, 32 canopy trees, 43 palm trees, 2,072 shrubs and groundcovers), drainage systems, utility tie-ins, fencing (575 linear feet of chain link, 341 linear feet of decorative aluminum), and various site improvements. Sealed bids were due January 14, 2027, at 3:00 p.m. local time, with a non-mandatory pre-bid meeting held November 19, 2026, at 11:00 a.m. in Naples, Florida. Complete bid documents were available through the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl.

The bid schedule presents all line items with quantities and unit costs shown as zero dollars, indicating this is a blank template for contractor pricing submission rather than a completed bid evaluation. Collier County has allocated a $650,000 Owner's Allowance for unforeseen conditions and owner-directed work, to be expended through change orders with supporting documentation. A bid alternate (ALT-1) for an electric rolling gate with emergency vehicle accessibility is available for separate pricing. The contractor is responsible for determining all costs associated with bid items and ensuring bid completeness; failure to identify or include required work, materials, or services does not relieve the contractor of its obligation to perform all work for the contract price.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Vendor Name
BID SCHEDULE
CONSTRUCTION ITB: 26-8706
IMMOKALEE SPORTS COMPLEX PHASE 2
PHASE 2
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
1Survey - Layout and As-Built Survey1LS$ - 0$ - 0
2Mobilization/Demobilization1LS$ - 0$ - 0
3Payment and Performance Bond1LS$ - 0$ - 0
4Maintenance of Traffic1LS$ - 0$ - 0
5Record Drawings - Provide and Maintain record (as-built) drawings for Engineer's Certification1LS$ - 0$ - 0
SUBTOTAL DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS:$ - 0
DIVISION 01 - GENERAL REQUIREMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
6Temporary Tree and Plant Protection - Construction-phase tree and plant protection, trimming, protection - zone fencing, and pruning.1ALLOW$ - 0$ - 0
7Construction Waste Management and Disposal - Salvaging, recycling, and disposing of non-hazardous demolition and construction waste.1ALLOW$ - 0$ - 0
SUBTOTAL DIVISION 01 - GENERAL REQUIREMENTS:$ - 0
DIVISION 03 - CONCRETE
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
85" thick reinforced concrete sidewalk or slab w/ sub-base - Pool deck and sidewalks1938SY$ - 0$ - 0
96" thick reinforced concrete pavement with sub-base - Dumpster enclosure aprons, pads. Mechanical building pad and driveway385SY$ - 0$ - 0
SUBTOTAL DIVISION 03 - CONCRETE:$ - 0
DIVISION 11 - EQUIPMENT
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
10Galvanized Chain Link Fence - 8.0' height 6-gauge galvanized chain link fence, posts, footings, fasteners, etc.575LF$ - 0$ - 0
11Decorative Aluminum Fence - 4.0' height decorative aluminum picket fence, posts, footings, fasteners, etc.341LF$ - 0$ - 0
12Single Swing Gate - 8.0' height x 4' wide 6-gauge galvanized chain link gate, latch hardware, posts, footings, fasteners, etc.1EA$ - 0$ - 0
13Single Swing Gate - Decorative Aluminum - 4.0' height decorative aluminum gate, latch hardware, posts, footings, fasteners, etc.1EA$ - 0$ - 0
14Double Swing Gate - Decorative Aluminum - 4.0' height decorative aluminum gates, latch hardware, posts, footings, fasteners, etc.4EA$ - 0$ - 0
15Manual Rolling Gate & Knox Box - 35' manual rolling gate atop v-track and concrete grade beam w/ Knox Box1EA$ - 0$ - 0
SUBTOTAL DIVISION 11 - EQUIPMENT:$ - 0
DIVISION 12 - FURNISHINGS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
16Trash Receptacle - Product selection by Collier County Parks and Recreation Department; Installed by Contractor2EA$ - 0$ - 0
17Recycle Receptacle - Product selection by Collier County Parks and Recreation Department; Installed by Contractor2EA$ - 0$ - 0
18Umbrella - Product selection by Collier County Parks and Recreation Department; Installed by Contractor3EA$ - 0$ - 0
SUBTOTAL DIVISION 12 - FURNISHINGS:$ - 0
DIVISION 13 - SPECIAL CONSTRUCTION
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
19Removable Bollards - Removable vehicular rated guard bollard painted yellow with reflective markings2EA$ - 0$ - 0
20Vehicular Rated Bollards - Vehicular rated guard bollard painted yellow with reflective markings4EA$ - 0$ - 0
21FPL Transformer, Raised Pad, Fence Raise/Repair - See civil drawings1EA$ - 0$ - 0
22Dumpster Enclosure Structures - CMU walls, stucco finish, paint, gates, hardware, and hose bib2EA$ - 0$ - 0
23Pool Showers - Accessible stainless steel shower by MDF (#565 SMSS)2EA$ - 0$ - 0
24Sports Lighting Painting - Includes all materials, equipment, and labor to remove mold, algae, and staining buildup; prepare the pole for paint, (1) coat primer per surface type (metal or concrete) and apply (2) coats high-quality Sherwin-Williams paint up to a height of 20'4EA$ - 0$ - 0
Pool Mechanical BuildingAssumes a 1,495 square foot CMU building on slab consisting of a conditioned office, a large pool equipment room, and a conditioned electrical/mechanical room. The building is assumed to include a standing seam metal roof, reinforced slab with an integral below-grade concrete surge tank, mechanical ventilation, electrical power distribution, and code-compliant LED lighting.
25Building Construction (1,495 SF) - CMU structure, structural slab, standing seam roof, interior partitions, ventilation, electrical rough-in, lighting1LS$ - 0$ - 0
26Surge Tank Structure (Below Slab – 215 SF equivalent) - Excavation, reinforced concrete tank, integration with slab system1LS$ - 0$ - 0
27Conditioned Spaces Premium (Office + Electrical Room) - HVAC systems, insulation, additional electrical scope1LS$ - 0$ - 0
28Electrical Systems / Power Distribution - Panels, distribution, conduit infrastructure for SCADA/IT/card access by County1LS$ - 0$ - 0
29Doors, Roll-Up Door, and Openings - Hollow metal doors, window, roll-up door, louvers, wall penetrations1LS$ - 0$ - 0
30Exterior Chemical Storage Enclosure - Chain link fencing, four gates, slabs, roof overhang structure and columns1LS$ - 0$ - 0
31Utility Tie-Ins - Electrical service, water connections, sanitary for wash sinks and floor drains, pipe connections for pool filter back wash1LS$ - 0$ - 0
32Site Preparation - Demolition, clearing, grading, building pad preparation1LS$ - 0$ - 0
33Signage - Wall mounted signage including ADA placards1LS$ - 0$ - 0
Existing Restroom RenovationAssumes four restroom areas (two women’s and two men’s), new hollow metal doors and hardware, plumbing walls, LED lighting to code, ventilation upgrades, and new restroom accessories including partitions, ceiling, wall, and floor materials/finishes, baby changing stations, hand dryers, sinks/urinals/toilets, and ADA-compliant countertops.
34Interior Demolition and Preparation - Removal of existing fixtures, partitions, finishes, selective wall/demo work1LS$ - 0$ - 0
35Plumbing Systems and Fixtures - 10 sinks, 18 toilets, 5 urinals, supply/drain modifications, ADA compliance1LS$ - 0$ - 0
36Electrical and Lighting Upgrades - LED lighting to code, wiring, panel adjustments, device replacement1LS$ - 0$ - 0
37Ventilation Improvements - Exhaust fans, duct modifications, roof penetrations as required1LS$ - 0$ - 0
38Interior Construction and Finishes - Plumbing walls, patching, paint, minor wall reconstruction, floor and wall tiles1LS$ - 0$ - 0
39Doors and Hardware - Four hollow metal doors, frames, ADA hardware1LS$ - 0$ - 0
40Restroom Accessories and Specialties - Partitions with doors, hand dryers, baby changing tables, grab bars, mirrors, accessories1LS$ - 0$ - 0
41Utility Tie-Ins - Electrical service, water connections, sanitary for wash sinks and floor drains, pipe connections for pool filter back wash1LS$ - 0$ - 0
42Site Preparation - Demolition, clearing, grading, building pad preparation1LS$ - 0$ - 0
43Signage - Wall mounted signage including ADA placards1LS$ - 0$ - 0
Feature PoolFeature Pool and Amenities
44Pool1EA$ - 0$ - 0
45ADA Lift1EA$ - 0$ - 0
46Competition Equipment1EA$ - 0$ - 0
47Slide1EA$ - 0$ - 0
48Basketball Hoop Amenity1EA$ - 0$ - 0
49Mechanical Equipment1EA$ - 0$ - 0
50Miscellaneous Equipment1EA$ - 0$ - 0
Splash PadSplash Pad Amenity and Features
51Splash Pad1EA$ - 0$ - 0
52Features1EA$ - 0$ - 0
53Safety Floor1EA$ - 0$ - 0
54Mechanical Equipment1EA$ - 0$ - 0
SUBTOTAL DIVISION 13 - SPECIAL CONSTRUCTION:$ - 0
DIVISION 31 - EARTHWORKS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
55Site Clearing - Clearing, grubbing, vegetation protection, stumping, stripping and stockpiling topsoil and rock, and disconnecting utilities. Includes removal of existing hardscape, irrigation and fencing.1LS$ - 0$ - 0
56Erosion Control and NPDES - Includes silt fencing1LS$ - 0$ - 0
57Embankment - Includes miscellaneous fill as needed for construction and berm restoration at pool backwash area10CY$ - 0$ - 0
SUBTOTAL DIVISION 31 - EARTHWORKS:$ - 0
DIVISION 32 - EXTERIOR IMPROVEMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
581.5" thick asphaltic concrete type SP-12.5 - structural course - Balance of Emergency and Maintenance Access Road (Not Incl Repairs Existing Phase 1A)467SY$ - 0$ - 0
591" thick asphaltic concrete type SP-9.5 - friction course - Balance of Emergency and Maintenance Access Road (Not Incl Repairs Existing Phase 1A) and Dumpster Area560SY$ - 0$ - 0
6010" Limerock Base - Balance of Emergency and Maintenance Access Road (Not Incl Repairs Existing Phase 1A)467SY$ - 0$ - 0
61Painted pavement Markings STD1LS$ - 0$ - 0
626" PVC Conduits - Irrigation Sleeves248LF$ - 0$ - 0
634" PVC Conduits - Irrigation and pool heater sleeves354LF$ - 0$ - 0
64Planting Irrigation New Installation - Includes irrigation control system, piping, valves, drip, bubbler, and sprinkler distribution100851SF$ - 0$ - 0
65Soil Preparation (Performance Specification) - 6" depth in shrub beds for planting soils specified according to tesed performance requirements (particle size, organic matter percentage, pH, CEC, fertility, etc.), layered soil assemblies.1,867CY$ - 0$ - 0
66Sod Areas - Seeded, sodded, plugged, and sprigged turf; pesticides, erosion-control materials, turf renovation, and grass paving. (includes sod replacement of Field #1 upon completion of construction)88,823SF$ - 0$ - 0
67Plants - Canopy Tree - Nursery-grown trees and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates.32EA$ - 0$ - 0
68Plants - Palm Tree - Nursery-grown trees and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates.43EA$ - 0$ - 0
69Plants - Shrub / Groundcovers (Large) - Nursery-grown shrubs and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates.452EA$ - 0$ - 0
70Plants - Shrub / Groundcovers (Small) - Nursery-grown shrubs and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates.1620EA$ - 0$ - 0
71Plants - Mulch Rings - 4' dia mulch ring x 3" depth typical6CY$ - 0$ - 0
72Plants - Root Barrier - Deeproot UB24-2: 24" deep rigid panel root barrier608LF$ - 0$ - 0
73Mulch - 3" depth typical112CY$ - 0$ - 0
74River Rock Flats - 3" to 5" - 6" depth typical atop geotextile fabric - see landscape drawings1340SF$ - 0$ - 0
SUBTOTAL DIVISION 32 - EXTERIOR IMPROVEMENTS:$ - 0
DIVISION 33 - UTILITIES
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
75Connect/modifications to existing drainage structures - (1) 15-inch drainage pipe connection; (2) 12-inch drainage pipe connection; (1) 18-inch drainage pipe connection5EA$ - 0$ - 0
76Clean out existing Drainage Structures and flush pipe - 9 structures. Flush all pipes.1LS$ - 0$ - 0
7715" HPStorm PE Pipe81LF$ - 0$ - 0
7818" HPStorm PE Pipe175LF$ - 0$ - 0
794" PVC Drainage Pipe and Fittings - Serving pool deck shower drains105LF$ - 0$ - 0
806" PVC Drainage Pipe and Fittings - Serving building roof drainage250LF$ - 0$ - 0
818" PVC Drainage Pipe and Fittings675LF$ - 0$ - 0
8210" PVC Drainage Pipe and Fittings12LF$ - 0$ - 0
8312" PVC Drainage Pipe and Cap32LF$ - 0$ - 0
8415" PVC Drainage Pipe and Cap10LF$ - 0$ - 0
8512" PVC Drainage Pipe (C900 PVC, Class 305, DR 14)40LF$ - 0$ - 0
861 1/2" Potable water tie-in and stub out - Serving mechanical building16LF$ - 0$ - 0
871" Polytube Water Service w/ Valves and Fittings - Serving pool deck showers, hose bibbs380LF$ - 0$ - 0
88FDOT Mitered End Section w/ Grate1EA$ - 0$ - 0
89Proposed Catch Basin - Type C - CB #15, 14, 14A, 14B, 14C (all others installed under Phase 1A)5EA$ - 0$ - 0
90Pool Deck Drain - 12" Square4EA$ - 0$ - 0
91Pool Deck Drain - Trench Drain - Zurn Model No. 8606N - Each Channel Length is 81-1/4"270LF$ - 0$ - 0
92Risers, 6" No-Hub End/Bottom Outlets - Trench Drain20EA$ - 0$ - 0
93Pool Deck Drain - 8" ADS Basin w/ Riser7EA$ - 0$ - 0
94Pool Deck Drain - 8" ADS Basin w/ Riser and Dome Grate13EA$ - 0$ - 0
95Pool Deck (Yard) Drain - 18" ADS Basin2EA$ - 0$ - 0
96Pool Backwash Rip Rap - 12" depth typical atop geotextile fabric5227CY$ - 0$ - 0
97Pool Backwash Geotextile Fabric - Tencate Mirafi 160N geotextile fabric1891SF$ - 0$ - 0
98Hose Bibs - Freestanding tamper-proof anti-siphon hose bib on a painted concrete post3EA$ - 0$ - 0
SUBTOTAL DIVISION 33 - UTILITIES:$ - 0
BID ALTERNATES
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
ALT-1Electric Rolling Gate & Knox Box - 35' electric motor w/ emergency vehicle accessibility rolling gate atop v-track and concrete grade beam w/ Knox Box. Contractor to provide add alt pricing as part of bidding.1EA$ - 0$ - 0
SUBTOTAL BID ALTERNATES:$ - 0
PHASE 2 BASE BID:$ - 0
PHASE 2 BASE BID + ALT-1:$ - 0

*Staff has allocated $650,000 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.

The Contractor is responsible for determining and including all costs associated with each bid item and ensuring that its bid is complete and sufficient to perform all required work. Failure to identify, quantify, or include any required work, material, service, or associated cost shall not relieve the Contractor of its obligation to perform the Work required by the Contract Documents for the Contract Price.

File details come from the government source that posted it. Updated .