26-8657_Bid_Schedule.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Goodlette-Frank Rd Sidewalks LAP Grant Funded
Solicitation number
26-8657
Issued by
Collier County, Florida

About this file

This is a Bid Schedule for Collier County, Florida's Goodlette-Frank Road Sidewalks LAP Grant-Funded Project (Bid No. 26-8657, FPID 448126-1-58-01). The project encompasses sidewalk construction and related improvements along Goodlette-Frank Road in Collier County, Florida. The bid schedule itemizes 28 line items across multiple categories including mobilization, traffic maintenance, sediment and inlet protection, clearing and grubbing, excavation and embankment work, concrete sidewalk and driveway installation (3,795 square yards), architectural pavers (237 square yards), detectable warnings, turf sodding (9,224 square yards), signage installation and removal, pavement markers, thermoplastic markings, and utility fixture adjustments. Sealed bids were to be received no later than January 14, 2027, at 3:00 p.m. local time. A non-mandatory pre-bid meeting was scheduled for November 12, 2026, at 10:00 a.m. at Procurement Services Division in Naples, Florida. Prospective bidders were directed to register on the Collier County procurement portal to obtain complete project documents.

The bid schedule contains 28 pay items with quantities specified for each work element; however, all unit prices and costs display as zero, indicating this is a blank template for vendor completion. Vendors who submit incomplete bid schedules may be deemed non-responsive or non-responsible. The project includes an Owner's Allowance of $100,000 allocated for unforeseen conditions and work directed by the Owner, though expenditure of this allowance is not guaranteed and requires change order documentation with supporting time and materials records. The project is grant-funded through the Local Agency Program (LAP), though specific funding amounts and sources are not detailed in this bid schedule document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Vendor Name:
Bid Schedule
26-8657 Goodlette-Frank Rd Sidewalks LAP - Grant Funded
FPID: 448126-1-58-01
*Vendor may be deemed non-responsive/non-responsible if an incomplete bid schedule is submitted.
Pay Item #DescriptionUnitQuantityUnit PriceCost
101-1MOBILIZATIONLS1$ - 0
102-1MAINTENANCE OF TRAFFICLS1$ - 0
104-10-3SEDIMENT BARRIERLF253$ - 0
104-18INLET PROTECTION SYSTEMEA129$ - 0
110-1-1CLEARING & GRUBBINGLS1$ - 0
110-7-1MAILBOX FURNISH & INSTALL (SINGLE)EA100$ - 0
120-1REGULAR EXCAVATIONCY230$ - 0
120-6EMBANKMENTCY516$ - 0
425-1-529INLETS, DT BOT, TYPE C, MODIFYEA18$ - 0
425-1-549INLETS, DT BOT, TYPE D, MODIFYEA16$ - 0
425-5MANHOLE, ADJUSTEA1$ - 0
425-10YARD DRAIN (ADJUST)EA38$ - 0
522-2SIDEWALK / DRIVEWAY CONCRETE, 6" THICKSY3795$ - 0
526-1-2PAVERS, ARCHITECTURAL, SIDEWALKSY237$ - 0
527-2DETECTABLE WARNINGSSF238$ - 0
570-1-2PERFORMANCE TURF - SODSY9224$ - 0
700-1-111SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, LESS THAN 12 SFEA13$ - 0
700-1-600SINGLE COLUMN GROUND SIGN ASSEMBLY, REMOVEEA13$ - 0
706-1-3RAISED PAVEMENT MARKER, TYPE BEA64$ - 0
710-90PAINTED PAVEMENT MARKINGS FINAL SURFACELS1$ - 0
711-11-123THERMOPLASTIC, STANDARD, WHITE, SOLID, 12" FOR CROSSWALK AND ROUNDABOUTLF501$ - 0
711-11-125THERMOPLASTIC, STANDARD, WHITE, SOLID, 24" FOR STOP LINE AND CROSSWALKLF126$ - 0
711-16-201THERMOPLASTIC, STANDARD, OTHER SURFACES, YELLOW, SOLID, 6"GM0.208$ - 0
711-17-1THERMOPLASTIC, REMOVE EXISTING THERMOPLASTIC PAVEMENT MARKINGS-SURFACE TO REMAINSF1980$ - 0
1080-24-500UTILITY FIXTURE, VALVE ASSEMBLY, ADJUST/MODIFYLS32$ - 0
ASB-1AS-BUILTSLS1$ - 0
TOTAL BID$ - 0
Owner's Allowance - Staff has allocated $100,000 in Owner's Allowance for the Owner's Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of the Owner's Allowance will be made through a Change Order with proper documentation of Time and Materials supporting the change.

File details come from the government source that posted it. Updated .