26-8633_Bid_Schedule.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Wiggins Pass Dredge 2026 - Grant Funded
- Solicitation number
- 26-8633
- Issued by
- Collier County, Florida
About this file
This is a bid schedule for Collier County, Florida's Wiggins Pass Dredge 2026 project, a grant-funded construction initiative advertised under ITB #26-8633. The project encompasses dredging operations in Wiggins Pass Channel with nearshore disposal of approximately 75,000 cubic yards of material, installation of 15 navigational channel markers and one manatee marker, environmental control and turbidity testing, construction surveys (pre, post, and interim), final tilling and grading, and restoration of construction access. Sealed bids are due by January 19, 2026, at 3:00 p.m. local time. A non-mandatory pre-bid meeting is scheduled for January 5, 2026, at 10:00 a.m. at Procurement Services located at 3295 Tamiami Trail East, Building C-2, Conference Room A in Naples, Florida. Prospective bidders must register through the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl to access the complete bid documents.
The bid schedule lists seven line items with estimated quantities and unit costs, with all pricing fields currently marked at zero pending contractor submission. The dredge quantity of 75,000 cubic yards is noted as estimated, with final quantity to be determined following pre-construction survey results. Collier County has allocated $139,575 in owner's allowance for unforeseen conditions and work directed by the owner, though this allocation does not guarantee contractor payment and any expenditures require change orders with supporting documentation. The owner will provide navigational channel marker materials, while the contractor is responsible for manatee marker material procurement. The project is subject to specific technical requirements including turbidity curtain installation, sand size restrictions on beach placement, and contractor-determined screening and grading methods.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule
| WIGGINS PASS DREDGE 2026 - GRANT FUNDED PROJECT |
| CONSTRUCTION ITB: #26-8633 |
| BID SCHEDULE |
Item Item Description Estimated Quantity Unit Unit Cost Total Cost
1 Mobilization and Demobilization 1 Lump Sum $ - 0 $ - 0
2 Dredge Wiggins Pass Channel with Nearshore Disposal (See Note I) 75,000 CY $ - 0 $ - 0
3a Navagational Channel Marker Install (See Note II) 15 Each $ - 0 $ - 0
3b Manatee Marker Installation (See Note III) 1 Each $ - 0 $ - 0
4 Environmental Control including Turbidity Testing 1 Lump Sum $ - 0 $ - 0
5 Construction Surveys (Pre, Post and Interim) 1 Lump Sum $ - 0 $ - 0
6 Final Tilling and Grading 1 Lump Sum $ - 0 $ - 0
7 Restoration of Construction Access 1 Lump Sum $ - 0 $ - 0
Total Bid $ - 0
* Staff has allocated $139,575 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.
| Notes: |
| I. Quantity is estimated; final quantity based on results of the pre-construction survey. |
| II. Includes replacement of removed markers or installation of new makers (OWNER to provide materials). |
| III. Includes replacement of removed manatee markers or installation of new makers (CONTRACTOR to provide materials). |
| IV. Includes the installation of turbidity curtain as described in the plans and specifications. |
| V. Pre & Post-construction surveys of the dredge and disposal area for Wiggins Pass. |
VI. Includes measures to ensure sand placed on the beach greater than 0.5" diameter does not exceed 5% through the use of screen boxes, raking, and/or other means as determined by the contractor. (Ref. Technical Spec. 11.4)
File details come from the government source that posted it. Updated .