PDF 2 MB Posted

Attached to
Northeast Water Reclamation Facility Deep Injection Well Equipping and Conveyance
Solicitation number
26-8627
Issued by
Collier County, Florida

About this file

This is an exhibit document submitted by Collier County, Florida, for Bid No. 26-8627 concerning the Northeast Water Reclamation Facility Deep Injection Well Equipping and Conveyance project. The exhibit contains site and electrical room panel pictures documenting the physical infrastructure for the project, specifically showing Panel DP1 and Panel DP2 (Plant PLC Control Panels), two deep injection wells (DIW 1 and DIW 2), monitoring well equipment, annulus pressure tanks, and nitrogen cylinders. The project requires furnishing all labor, materials, equipment, and incidentals necessary to construct a comprehensive deep injection well system including two deep injection wells, one dual-zone monitoring well, approximately 3,800 linear feet of 36-inch and 24-inch diameter piping, sump pumps, sample pumps, pressure tanks, and a complete instrumentation and control system. A non-mandatory pre-bid meeting is scheduled for January 13, 2026, at 2:00 p.m. at Collier County Procurement Services Division, with sealed bids due electronically by February 12, 2026, at 3:00 p.m. local time. The successful bidder must substantially complete all work within 425 calendar days from the Notice to Proceed.

The anticipated project budget is $7,184,000 with a $600,000 Owner's Allowance reserved for unforeseen conditions or additional work through formal Change Orders. Bidders must submit a certified bid bond equal to five percent of the total bid amount and provide Payment and Performance Bonds covering 100 percent of the contract value through a licensed surety authorized to do business in Florida. Liquidated damages of $2,535.53 per calendar day apply if substantial completion is not achieved within the specified timeframe. No specific set-aside designations for disadvantaged enterprises are mentioned. Work hours are limited to 7:00 a.m. to 7:00 p.m., Monday through Friday, unless otherwise specified in contract documents. Bidders must demonstrate qualification through five project references completed within the last five years, current Florida contractor's licenses, E-Verify enrollment, and appropriate insurance certifications.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Panel DP1

Panel DP1

Plant PLC Control Panel

Plant PLC Control Panel

Panel DP2

Panel DP2

DIW 2

DIW 2

Annulus Pressure Tank & Nitrogen Cylinders

Monitoring Well

DIW 1 & Annulus Pressure Tank & Nitrogen Cylinders