26-65 LNG Storage Tank Painting.pdf
PDF 1 MB Posted
- Attached to
- LNG Exterior Tank Painting
- Solicitation number
- 26-65R
- Issued by
- New London County, Connecticut
About this file
File Summary
This is a Request for Proposal (RFP) issued by the City of Norwich, Connecticut, acting on behalf of Norwich Public Utilities (NPU), for the repainting of NPU's 55,000-gallon liquefied natural gas (LNG) storage tank located at 10-12 Wisconsin Avenue in Norwich, Connecticut. The project encompasses complete removal and disposal of lead-based paint and polychlorinated biphenyl (PCB)-containing coatings from both steel and concrete tank surfaces, surface preparation to specified standards, application of a new three-coat paint system with stripe coat to steel surfaces, resurfacing and waterproofing of concrete supports, and application of the NPU logo. A mandatory pre-bid meeting is scheduled for May 18, 2026, at 1:00 PM at the LNG tank site. Proposals must be submitted electronically via the City of Norwich Procurement Portal by 2:00 PM prevailing time on June 1, 2026. All work must be completed by Friday, September 18, 2026. Respondents must demonstrate a minimum of three successfully completed similar projects on liquefied natural gas facilities within the last six years and possess specific AMPP/SSPC certifications including QP-1 and QP-2 designations, with a designated on-site Competent Person holding C3/C5 Supervisor, AMPP Coatings Inspector Level 1 or higher, AMPP Coating Application Specialist Level 2, OSHA 30-hour Construction Safety, and current First Aid/CPR/AED certifications.
Proposals must include a lump sum price with unit pricing for contingencies, detailed work plans and schedules, containment and environmental control approaches, waste management plans, coating system data sheets, and references for relevant project experience. A bid surety of five percent of the total bid amount in the form of a Bid Bond, Certified Check, or Bank Check is required at the time of bid submission. The contract award is not based solely on price; NPU will evaluate contractor qualifications and experience, project approach, time to completion, and overall value to the utility. The successful contractor must provide insurance certificates within five days of award and execute performance and payment bonds prior to contract signing. The project remains subject to Connecticut prevailing wage requirements, zero tolerance workplace violence policies, and compliance with all OSHA, EPA, and state/local environmental and safety regulations. All hazardous waste streams must be properly characterized through TCLP testing, managed according to TSCA and RCRA requirements, and disposed of at EPA-licensed treatment, storage, and disposal facilities, with the contractor responsible for all transportation, manifesting, and disposal costs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 26-65R_Jun_8_26_solicitation_doc.pdf | ||
| 26-65R_May_4_26_solicitation_doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Invitation for Bid/Proposal
RFP No. 26-65
The Purchasing Agent, City of Norwich, on behalf of Norwich Public Utilities, will receive proposals for the repainting of NPU’s 55,000-gallon LNG (liquefied natural gas) storage tank until 2:00 P.M. prevailing time on June 1, 2026, at which time they will be opened on the Procurement website and be available to view. All proposals are to be submitted via the City of Norwich Procurement Portal at the following website:
City of Norwich Procurement Portal
The RFP documents may be downloaded from the following website:
City of Norwich Procurement Portal
Addenda, if any, will be posted on the website listed above. Vendors/Contractors, prior to submitting their proposals, should check the websites to ensure they have received all issued addenda.
Norwich Public Utilities reserves the right to reject any proposal, in whole or in part, to waive minor irregularities if deemed in the best interest of the City of Norwich/NPU.
No Vendor may withdraw its proposal within sixty (60) days of the opening date. Should there be reason why the contract cannot be awarded within the specified time, the time may be extended by mutual agreement between Norwich Public Utilities and the selected Vendor.
All final awards of the bid shall follow the City of Norwich Code of Ordinances §7-46 – Delinquent Tax Setoff Against Money Due Bidder or Contractor.
By submitting a proposal, the vendor certifies they are not on a state or federal debarment or suspended list and are not prohibited from performing any state or federal work.
All Vendors must submit bids/proposals through the City Procurement Portal.
Responding bidders must ensure that employees and applicant for employment are not discriminated against because of their race, color, religious creed, age, marital status, national origin, ancestry, sex, gender identity or expression, intellectual disability, mental disability or physical disability, including, but not limited to blindness, unless it is shown by such bidder that such disability prevents performance of the work involved.
Robert R. Castronova Purchasing Agent
City of Norwich Department of Finance – Purchasing Agent Phone: (860)823-3706 100 Broadway, Room No. 105 Fax: (860)823-3812 Norwich, CT 06360 E-mail: rcastronova@cityofnorwich.org https://norwichct.bonfirehub.com/portal/?tab=openOpportunities
INSTRUCTIONS TO BIDDERS
CITY OF NORWICH, CT 06360
RFP: 26-65
LNG Exterior Tank Painting
The following instructions and specifications shall be observed by all Vendors/Contractors:
1. Time and Place of Proposal Opening Proposals will be received on June 1,2026 at 2:00 P.M. online at:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities No bids will be allowed after the time and date of bid opening.
2. Pre-Bid Meeting – 5/18/26 at 1 PM at the LNG Tank Site located at 10 Wisconsin Avenue in
Norwich, CT.
3. Availability of Documents Vendors are advised that all documents related to this project are only available online at the following web address:
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities
4. Addenda
If additional information becomes available or changes are made to the documents, an addendum will be issued not later than 3 days prior to the opening date. All addenda shall become part of the Contract Documents.
Notice of any addendum will be posted on the following website:
5. Bid Surety Requirements
A Bid Surety in the amount of five percent (5%) of the total amount bid is required at the time of bid. Bid Surety shall be in the form of a Bid Bond provided by a surety licensed to do business in the State of Connecticut, Certified Check or Bank Check.
FAILURE OF A BIDDER TO PROVIDE THE REQUIRED BID SURETY SHALL RESULT IN REJECTION OF
ITS BID.
6. Instructions
Proposals should be submitted to the City of Norwich Procurement portal at:
Proposals will not be accepted by mail, in person or by email.
All forms and associated documents must be uploaded through the procurement portal.
7. Examination of Site Conditions
Vendors must satisfy themselves by personal examination of the site and location of the proposed work as to the actual conditions and requirements of the work and inform themselves fully of the conditions relating to the construction and labor under which the work will be performed. No claim because of lack of knowledge by the contractor regarding the site, the proposed wok or content of the specifications and drawings will be allowed. At the date established for the opening of proposals, it will be presumed that each vendor has made an examination of the location and site of the work to be done under this contract and has satisfied itself as to the actual conditions and requirements.
https://norwichct.bonfirehub.com/portal/?tab=openOpportunities
8. Sales and Use Tax
Vendors are reminded that the Connecticut State Sales and Use Tax and associated Federal taxes are not applicable under this contract, and therefore these taxes are not to be included in the bid price(s).
Under the terms of Connecticut Agencies Regulations §12-426-18, Contractors and Subcontractors, the contractor may purchase materials and supplies as are to be installed or placed in projects being performed under these contracts and will remain in such projects after completion, including tangible personal property that remains tangible personal property after its installation or placement, without payment of the tax and shall not charge any such exempt organization or agency any sales or use tax thereon.
9. Definitions
For the purposes of these documents:
The word “City” means the City of Norwich, CT.
The words “NPU” means Norwich Public Utilities.
The word “Bidder” refers to the party or parties submitting a bid or proposal to perform the work to be done or materials to be furnished.
The word “Vendor” or Contractor” refers to the party or parties contracting to perform the work to be done or materials to be furnished under the Contract; the legal representatives of such party or parties.
10. Intent
The intent of these specifications is to obtain a Vendor/Contractor that will furnish all labor, supervision, tools, materials and equipment necessary to meet all the requirement of this Request for Proposal.
11. Contractor Qualifications
Contractors, if required, must be able to present satisfactory evidence that they are capable and fully prepared with necessary capital, personnel, materials and equipment to do the work to be contracted under this proposal.
12. Certificate in Good Standing
Any corporation whose proposal is being considered for acceptance by the NPU may be required, if requested, to provide a “Certificate of Good Standing” from the Office of the Secretary of State for Connecticut.
13. Award/Contract Execution
The firm whose proposal is accepted by the NPU will be required to furnish all insurance certificates in the amounts specified, within 5 days from the date of the award notice. The firm(s) will also be required to furnish, if required. all performance and payment bonds to NPU prior to contract signing.
The firm(s) whose proposal is accepted will be required to execute a contract, in substantially the form included in the RFP documents. Once the contract is completed, the contractor will be issued a Purchase Order and/or a Notice to Proceed.
Please note that this is a Request for Proposals, and as such, price is not the sole determinant of the project award. NPU will evaluate the relevant experience of respondents, project approach, time to completion, and price when determining which proposal presents the greatest overall value to NPU.
14. Contractor’s and Subcontractors’ Insurance
See section 8 of The Contract for Services
15. Safety All work done and all equipment used shall comply with all pertinent OSHA, Federal, State and local regulations, laws and ordinances affecting those employed and any affecting the conduct of the work.
Bidders are required to verify they have read NPU’s safety guidelines.
The State of Connecticut and all political subdivisions have adopted a zero tolerance policy for workplace violence. In accordance with Executive Order No. 16 issued by Governor John G.
Rowland, all contractors, subcontractors and vendors must comply with this policy.
16. Personnel Requirements
All work under this contract hall be performed by competent and proficient tradesmen employed by the contractor and under its supervision. Apprentices and helpers may be used, but only under the direct supervision of the job foreman.
This project may be subject to CT prevailing wages.
17. Subcontractors
The Contractor shall not sublet any portion of the work without written permission from NPU.
In no case may it be more than forty-nine percent (49%) of the monetary value of the contract.
The major units of the work shall be performed by the Contractor. If the Contractor sublets any part of the work, this does not relieve it or the bonding company of their liabilities and obligations to NPU. There is no contractual relationship between any subcontractor and NPU.
The City/NPU deals only with the Contractor; subcontractors are recognized as employees of the Contractor.
The Contractor must not assign or dispose of its contract in any way without the consent of
NPU.
18. Freedom of Information
All bids will be made available for public inspection. in accordance with the provisions of Connecticut General Statutes § 1-210, Freedom of Information. Copies of any information resulting from any bid opening are generally not available until a contract has been formally awarded.
19. Non-Collusion
The individual signing this bid hereby declares that no person or persons other than members of its organization are interested in this bid or in the contract proposed to be taken; that it is made without any connection to any other person or persons submitting a bid for the same work and is in all respects fair and without collusion or fraud; that no person acting on behalf of or employed by the City of Norwich is directly or indirectly interested in the supplies or work to which they relate or will receive any part of the profit or any commission therefrom in any manner which is unethical or contrary to the best interests of the City of Norwich.
Request for Proposal
LNG Tank Exterior Painting
Norwich Public Utilities (NPU) is requesting proposals from qualified contractors to repaint NPU’s 55,000 gallon LNG (liquified natural gas) storage tank located at 10-12 Wisconsin Avenue, Norwich, CT. Included in the work is the proper removal and disposal of lead and PCB’s, as described in the attached Remediation Specifications.
The NPU LNG storage tank is cryogenically designed to store LNG inside at -260 degrees F and at 60-65 psig. The tank is a double containment tank, with one tank inside another.
The inner tank, constructed of aluminum, is a pressure vessel, designed to hold LNG at a maximum pressure of 90 psig. The outer tank is a carbon steel support tank. Between the two tanks is an annular space which varies in width from 8 ½” around the outside to 12” at the tank ends. The annular space is filled with perlite granular insulation and then highly evacuated.
In compliance with Occupational Safety and Health Administration (OSHA) requirements, an environmental assessment of the existing tank was performed and the presence of hazardous Polychlorinated Biphenyl (PCB) and Lead levels were detected on the tank surface. Using lead-based paint chip sampling, the paint on the LNG tank and cradle was identified to have greater than 0.50% lead content by weight and is therefore classified as Lead-Based Paint (LBP). Additionally, all painted metal surfaces returned >50 PPM on PCB-containing materials.
Below is brief summary of the project specifications, personnel certifications, and qualifications required to be considered for the project. Respondents MUST refer to the documents titled “SECTION 09 91 00 – LNG TANK PAINTING” and “SECTION 028433 – PCB REMEDIATION” for full project requirements, which are attached at the end of this RFP.
CONTRACTOR QUALIFICATIONS
All responding contractors must meet the following minimum requirements:
Organizational Certifications
• AMPP/SSPC QP-1 certification (field application to complex industrial structures)
• AMPP/SSPC QP-2 certification (hazardous paint removal)
Required On-Site Personnel Certifications
A designated Competent Person/Supervisor must be present on-site at all times and hold:
• AMPP C3/C5 Supervisor/Competent Person for De-leading & Hazardous Coatings Removal
• AMPP Coatings Inspector (CIP) Level 1 or higher
• AMPP Coating Application Specialist (CAS) Level 2
• OSHA 30-hour Construction Safety
• Current First Aid/CPR/AED
PCB/HAZWOPER Training Requirements
All personnel engaged in PCB abatement must have:
• OSHA 40-hour HAZWOPER (29 CFR 1910.120)
• OSHA 8-hour HAZWOPER Supervisor (for site Health & Safety Officer)
• OSHA 29 CFR 1910.1000 (Air Contaminants)
• OSHA 29 CFR 1910.1200 (Hazard Communication)
SCOPE OF WORK
The selected contractor shall furnish all labor, materials, equipment, containment, environmental controls, and waste management necessary to complete the following:
PCB and Lead Paint Removal
• Remove all PCB-containing and lead-based coatings from steel and concrete tank surfaces.
• Metal surfaces: Strip to SSPC-SP 10/NACE 2 Near-White Metal using wet abrasive blasting.
• Concrete surfaces: Prepare to ICRI CSP 3–5 per SSPC-SP13/NACE 6.
• Perform HEPA vacuuming and solvent/PCB-agent cleaning after blasting.
Coating System Installation – Steel Tank Surfaces
Apply a complete 3-coat system including stripe coat:
• Primer: Corothane 1 MIO-Zinc (3–4 mils DFT)
• Intermediate: Macropoxy 646 (5–10 mils DFT)
• Stripe Coat: Macropoxy 646 (3–6 mils DFT)
• Finish: Sherloxane 800 (4–6 mils DFT)
Concrete Supports – Resurfacing and Waterproofing
• Apply Duraplate 2300 resurfacer.
• Apply 3-coat waterproofing system (Loxon XP or approved equal).
Operational Constraints
• Tank remains in service throughout the project.
• All work inside tank berm must use intrinsically safe tools; area is Class I, Division
1. Use of any motorized equipment in the containment berm area requires a hot work permit.
• Contractor must build throughway that will enable travel over the containment berm. The throughway must anchor into the ground so as not to compromise the integrity of the berm.
CONTAINMENT AND ENVIRONMENTAL CONTROLS
Containment must comply with SSPC Guide 6 and meet the following minimum classifications:
• Wet/Dry Abrasive Blasting: Class 1A
• Power Washing: Class 1W
• Power Tool Cleaning: Class 1P
• Coating Application: Class 3A
Containment Requirements
• Fully sealed, fire-retardant, air- and water-impermeable materials.
• No welding, drilling, or bolting into tank structure.
• Contractor must submit engineered containment drawings and load calculations.
Ventilation Requirements
• Maintain –0.03 in. w.c. negative pressure.
• Maintain airflow of:
o 100 ft/min cross-draft o 60 ft/min downdraft
Air Quality Monitoring
• Pre-project baseline monitoring.
• TSP-Lead monitoring for first 5 days of removal.
• Visible emissions limited to 5 minutes.
WASTE MANAGEMENT AND DISPOSAL
All waste streams must be managed in accordance with TSCA (40 CFR 761) and RCRA.
Waste Characterization
Contractor shall perform TCLP testing for:
• RCRA metals
• PCBs
• pH, ignitability, reactivity, corrosivity
Waste Streams
• PCB Bulk Product Waste (>50 ppm)
• PCB/Lead Hazardous Waste (TSCA/RCRA)
• PCB Remediation Waste
• Decontamination residues and wash fluids
• PPE and containment materials
Storage and Handling
• Use DOT-approved containers.
• Label per TSCA/RCRA requirements.
• Maximum on-site storage: 90 days, except for flammable hazardous materials which must be removed from the site prior to the close of the workday as per NPU’s LNG Manual and 49 CFR 192.
Transportation and Disposal
• Only DEEP-licensed haulers may transport waste.
• Only EPA-licensed TSDFs may receive waste.
• Contractor must provide:
o Waste profiles o Manifests o Certificates of disposal
SURFACE PREPARATION AND CLEANLINESS TESTING
Steel Surface Profile
• Achieve 2–3 mil profile (ASTM D4417 Method C).
Chloride Testing
• Minimum 5 tests per 1,000 ft² until 3 consecutive days pass.
• Acceptable chloride level: ≤7 µg/cm².
SUBMITTALS
Pre-Construction Submittals
• Site-Specific Health & Safety Plan (HASP)
• Environmental Monitoring Plan
• Containment Plan with engineering calculations
• Waste Handling & Disposal Plan including chain of custody
• Coating System Product Data Sheets and SDS
• Work schedule
During Construction
• Daily sign-in logs
• Air monitoring results
• Waste container inspection logs
Closeout Submittals
• PCB wipe sampling results
• Concrete substrate clearance testing
• Waste manifests and certificates of disposal
• Final inspection reports
WARRANTY
The contractor shall provide a minimum 3-year warranty covering, at a minimum:
• Materials
• Workmanship
• Coating adhesion and performance
Any deviations or manufacturer specifications from the 3-year warranty period must be submitted in writing and approved by NPU. Respondents offering longer and/or stronger warranties may be evaluated higher than respondents offering a shorter and/or less comprehensive warranty.
MINIMUM CONTRACTOR QUALIFICATIONS
In order to be considered qualified to respond to this Request for Proposal, respondents must have successfully completed at least three (3) similar projects on liquified natural gas facilities within the last six (6) years. Respondents with relevant project experience not meeting these requirements may submit a proposal, however NPU will be the sole determiner if sufficient minimum qualifications exist to be considered for the project.
PROPOSAL REQUIREMENTS
Proposals must include:
• Company qualifications and certifications
• Resumes of key personnel
• Detailed work plan and schedule
• Containment and environmental control approach
• Waste management plan
• Coating system data sheets
• Lump sum price and unit pricing for contingencies
• Listing of relevant similar project experience stated in the Minimum Contractor Qualifications section, including providing references for the completed projects.
EVALUATION CRITERIA
Proposals will be evaluated based on:
• Compliance with technical specifications
• Contractor qualifications and experience, particularly with LNG and cryogenic tanks
• Cost competitiveness
• Schedule feasibility
SITE ACCESS AND INSPECTION
The contractor shall provide safe access for Owner/Engineer inspections throughout the project, including, but not limited to:
• Scaffolding
• Fall protection
• Lighting (minimum 30 foot-candles)
Contractor personnel shall not be allowed on-site without NPU personnel being present.
NPU personnel will be made available to work Monday-Friday from 6:00 AM to 5:00 PM, excluding NPU holidays. Respondents requesting to work on Saturdays must include such request in their proposals and at the pre-bid meeting. Work on Sundays and holidays will not be permitted except in emergency conditions.
PROJECT SCHEDULE
Contractor shall submit a detailed schedule including:
• Mobilization
• Containment installation
• PCB/lead abatement
• Surface preparation
• Coating application
• Demobilization
• All work must be 100% completed by Friday, September 18th, 2026.
GENERAL CONDITIONS
• Contractor must comply with all Federal, State, and local regulations.
• More stringent regulation prevails in case of conflict.
• Contractor is responsible for protecting adjacent structures, utilities, and environment.
• Contractor is responsible for all cleanup and restoration of work areas.
• The earthen containment dike must be protected from compaction and other damage resulting from moving equipment, materials, and personnel into the tank area. Any damage to the dike resulting from this work must be restored to pre-project conditions, as determined by NPU, at the sole cost of the contractor.
NORWICH PUBLIC UTILITIES
10-12 WISCONSIN AVE, NORWICH, CT
LNG TANK PAINTING
SECTION 09 91 00
SECTION 09 91 00 – LNG TANK PAINTING
PART 1 – GENERAL
1.1 RELATED DOCUMENTS
A. Attention is directed to the drawings and general provisions of the Contract, including all General Bid Specifications and other Division 1 specification sections, which are hereby made a part of this Section of the Specifications.
B. Lead and Polychlorinated Biphenyl (PCB) Paint Sampling – NPU LNG Tank 10-12
Wisconsin Avenue, Norwich, prepared by BL Companies, Inc., dated December 16, 2025.
C. Section 02 84 33 – PCB Remediation, which is hereby made a part of this Section of the
Specifications
1.2 GENERAL REǪUIREMENTS
A. The LNG Tank Painting Contractor shall furnish all labor, materials, facilities, equipment, installation services, employee training, notifications, permits, licenses, certifications, agreements, and incidentals necessary to perform the specified work.
B. Work shall be performed in accordance with the contract documents, the latest regulations from the Occupational Safety and Health Administration (OSHA), the United
States Environmental Protection Agency (USEPA), and all other applicable federal, state, and local agencies. The Contractor shall comply with all applicable regulations even if the regulation is not specifically referenced herein. If a Federal, State or local regulation is more restrictive than the regulation of this specification, follow the more restrictive requirements.
C. Sampling has determined that polychlorinated biphenyls (PCBs) and Lead (Pb) are present in the existing paint. Reference testing report from Section 1.1-B above for locations, concentrations, and additional information. Reference specification section
02 84 33 – PCB Remediation for all specification requirements related to PCBs C PCB
Remediation. This specification section only covers the specific requirements for painting, lead-based paint removal/abatement, and its associated tasks.
D. All Contractors and Subcontractors performing lead-based paint removal, containment and collection, surface preparation, and coating of the LNG Tank Steel C Structure must hold current AMPP/SSPC ǪP-1 C ǪP-2 certifications and must be pre-approved by the Owner C Engineer prior to performing any work.
E. The LNG Tank Painting Contractor shall have on-site at all times a designated
Competent Person (CP)/ Supervisor with current C valid certifications for AMPP
C3/C5
LNG TANK PAINTING
“Supervisor/Competent Person Training for Deleading and Hazardous Coatings
Removal,” AMPP Coatings Inspector CIP Level 1 (or higher), AMPP Coating
Application Specialist (CAS) Level 2, OSHA 30, and First Aid/CPR/AED. A designated Competent Person (CP)/ Supervisor meeting these requirements must be on-site at all times why any work is being performed.
F. The LNG Tank must remain in service during the full course of work performance.
Taking the tank out of service is not feasible. All work performed on the tank, including surface preparation and painting, must be performed utilizing non-sparking tools, means
C methods. All work area inside the LNG tank berm should be considered Class 1 Div.
1, including the area within any containments erected around the tank during the performance of the work. All tools and equipment used within the LNG Tank berm area must be intrinsically safe, unless specifically submitted to and approved by the Owner
C Engineer prior to use.
G. Operating hours for field work are limited to 7:00am to 3:00pm daily
H. The company who performed the original logo painting has the electronic file and color standards and will print out a decal for use on this project. The awarded respondent will be granted open communication with this company for the duration of the project.
I. Disturbance or removal of lead (Pb) and/or PCB containing materials may cause a health hazard to workers and facility occupants. The LNG Tank Painting Contractor shall disclose to their workers, supervisory personnel, subcontractors, and consultants who will be at the jobsite the seriousness of the hazard and of the proper work procedures which must be followed.
1.3 SCOPE OF WORK
A. The work of this Section consists of the surface preparation and painting of all LNG
Tank Steel and Concrete Supports at the Norwich Public Utility (NPU) LNG Facility located at 10-12 Wisconsin Avenue in Norwich, Connecticut. All attached appurtenances that are currently painted are included in the LNG Tank Painting Scope.
The work includes full removal, abatement, and remediation of all existing coatings, lead (Pb), and PCB containing materials from the LNG Tank Steel and Concrete
Supports. The work also includes all associated environmental protection and waste disposal. Upon completion of all cleaning, surface preparation, abatement, and painting work, the scope also includes application of a new logo to the tank matching the currently existing logo.
B. The Contractor shall implement and maintain programs and procedures that comply with the requirements of this specification and all applicable standards and regulations.
The Contractor shall comply with all applicable regulations even if the regulation is not specifically referenced herein. If a Federal, State or local regulation is more restrictive than the regulation of this specification, follow the more restrictive requirements.
LNG TANK PAINTING
C. The Contractor shall provide the Owner C Engineer safe access and support to all parts of the structure for interim and final inspection during all cleaning and painting operations. This support shall include all necessary scaffolding, fall protection, and lighting as required.
D. The base bid for LNG Tank Painting includes, but is not limited to, the following:
E. Surface preparation and painting of the LNG Tank Steel C Concrete Supports. Including but not limited to:
a. Surface Pre-Cleaning of all work substrates via pressure washing per SSPC-
SP1
b. Surface Preparation of LNG Tank Steel via SSPC SP-10 (WAB)/NACE
WAB-2 “Near-White Metal Wet Abrasive Blast Cleaning.”
c. Surface Preparation of LNG Tank Concrete Supports per SSPC-
SP13/NACE 6 to ICRI No. 310.2R, CSP 3-5 via abrasive blasting or other suitable means and methods.
d. Post Surface Preparation Cleaning via blowing down, HEPA vacuuming, or use of solvent / PCB cleaning agent (such as Capsur) as needed for visual inspections C PCB clearance testing. See Section 02 84 33 for PCB inspections, clearance testing C disposal requirements
e. Containment, Collection, Storage, Testing, Classification, Transportation, and Disposal of all debris generated
f. Application of 3 Coat Paint System with stripe coat to LNG Tank Steel
g. Application of NPU Logo over completed LNG Tank paint system
h. Application of Concrete Resurfacer to the LNG Tank Concrete Supports
i. Application of 3 Coat Waterproofing System to LNG Tank Concrete Supports
j. Decontamination, Clearance Testing, and Disposal of all tools, equipment and materials. For PCB decontamination, clearance testing, and disposal requirements, see Section 02 84 33 – PCB Remediation
k. Interim G Final Inspections, including inspection/verification of finish coating system thicknesses per AMPP SSPC-PA2
LNG TANK PAINTING
1.4 ENVIROMENTAL HEALTH AND SAFETY
1.4.1 WORKER PROTECTION
A. DEEP and EPA regulate coatings containing toxic metals and the debris generated from the removal process as a hazardous waste. The Contractor shall comply with all
Federal, State and municipal laws, regulations and ordinances that require the
Contractor to provide for a safe and healthful work environment for work to be performed by the Contractor under this Contract.
B. The Federal Occupational Safety and Health Administration (OSHA) regulate the exposure to paint and debris containing toxic metals by workers involved in the removal of coatings. Coatings removed from structures that contain toxic metals, have been shown to have serious health effects on workers if regulations and caution are not observed.
C. The development of a “Compliance Program” to protect workers from lead and toxic metals is required by Federal and State regulations. The remaining portion of this specification focuses on lead but requires the Contractor and the Certified Industrial
Hygienist (CIH) to address other toxic metals and hazardous substances. On this specific project, the LNG Tank Painting Contractor and CIH must also address PCBs.
For requirements related to PCBs, please see specification Section 02 84 33 – PCB
Remediation.
D. The Contractor shall also comply with all registration, license, and permit requirements.
1.4.2 COMPLIANCE PROGRAM
A. The Contractor shall develop a written program under the direction and approval of a
Certified Industrial Hygienist (CIH) to establish and implement practices and procedures for protecting the health of those employees exposed to lead and other toxic metals and hazardous substances. The Compliance Program shall establish methods for complying with any applicable Federal, State or local regulations.
1.4.3 SIGNS AND DAILY LOGBOOK
A. Signs warning that lead paint removal operations are being conducted shall be posted at all approaches to the work areas and in areas where workers will be exposed to concentrations above the PEL. At a minimum, such signs shall include the words:
WARNING
LEAD WORK
AREA
POISON
NO EATING OR SMOKING
AUTHORIZED PERSONNEL
ONLY
RESPIRATORS REǪUIRED IN THIS AREA
LNG TANK PAINTING
B. The lettering shall be black block, no smaller than 3 in. tall, and on a white, yellow, or orange background. Caution ribbons shall also be used where appropriate.
C. A daily sign in/out log which identifies persons by name, address, and affiliation, or work classification for all employees with the project, and the times of arrival and departure must be maintained at the work site, and submitted to the Engineer on a weekly basis when lead paint removal operations are being performed.
1.5 ENVIRONMENTAL PROTECTION AND MONITORING
A. The Contractor shall comply with all Federal, State and municipal laws, regulations and ordinances that require protection of the environment, including laws and regulations whose purpose is to prevent contamination and pollution of the air, water and soil in and surrounding the work site, where lead paint being removed from a structure under this contract is subject to abatement, containment, transportation and disposal.
1.5.1 AIR ǪUALITY
1.5.1.1 BASELINE MONITORING
A. Pre-project monitoring shall be performed for a minimum of one day while no paint removal work is underway in order to establish baseline levels. Emissions from the project site will not be penalized by existing baseline levels. If the baseline levels are highly variable, the Engineer may require that periodic or full-time upwind monitoring be conducted. Include provisions for such monitoring in the required Environmental
Protection and Monitoring Program submittal.
1.5.1.2 HIGH VOLUME AMBIENT AIR MONITORING
A. High volume ambient air monitoring shall be conducted in strict accordance with the requirements of 40 CFR 50 and the equipment manufacturer's instructions.
B. The Contractor shall submit methods and procedures for locating the monitors, calibrating and conducting baseline and project monitoring, and completion of chain of custody forms. Include the name and qualifications of the State-certified laboratory proposed for use, and the test methods that will be utilized for the analysis of the sample filter/media.
C. Conduct the following monitoring activities under the observation of the Engineer:
locating and calibration of the monitors, daily removal and replacement of the filters, and completion of the chain of custody forms.
D. A continuous “Real-Time” PM10 monitoring plan may be acceptable for use in lieu of using high volume ambient air monitoring via TSP lead. The plan must be of sufficient and acceptable detail and include adequate backup, quality assurance, and site-
LNG TANK PAINTING
specific operational procedures to ensure accurate compliance monitoring aligning with the requirements for alternative air quality measurement methods. This alternate air monitoring methodology must be submitted and approved through the project submittal process.
1.5.1.3 TSP LEAD MONITORING
A. The monitoring shall be in accordance with 40 CFR 50 for the first 5 days while paint removal and cleanup activities are underway. Monitoring during paint application is not required, and if performed, will not be counted as one of the 5 days of project monitoring.
B. The monitors shall be placed at the point of maximum environmental impact (usually downwind of the cleaning operation) and other locations of potential public or environmental exposure. Monitors shall be moved to maintain this condition due to shifting wind patterns.
C. For TSP-lead monitoring, emissions in excess of the value attained by the following formula or exceeding 150% of background levels shall be cause to shut down the project until the work activities and/or containment are modified to provide better control of emissions.
D. The above calculation provides an allowance criteria for a 24-hour period. In order to convert this value to an allowance corresponding to the hours worked, do the following:
E. If the emissions are unacceptable at the end of the 5 days of monitoring, or a trend of exceedances is apparent from the 5 days of monitoring, the monitoring shall continue at the contractor’s expense until 5 days of acceptable monitoring limits have been obtained.
F. After the initial 5 days of monitoring, if visible emissions are in excess of the stated duration for 2 days, additional monitoring shall be required for a period of 2 consecutive days of TSP monitoring.
LNG TANK PAINTING
G. If the emissions are unacceptable after the 2 days of monitoring, the monitoring shall continue at the contractor’s expense until 2 days of acceptable monitoring limits have been obtained.
H. The Contractor shall conduct additional ambient air monitoring after periods of prolonged shutdown or following any significant changes in work practices.
1.5.1.4 LABORATORY ANALYSIS AND REPORT
A. The Contractor shall have all filters analyzed for lead using a State-certified laboratory.
The analysis shall be conducted in accordance with 40 CFR 50. The Contractor shall provide the Engineer with verbal results of the laboratory analysis within 5 days after the monitoring was performed, with a written summary report within 10 days.
1.5.1.5 VISIBLE EMISSIONS
A. The Contractor shall conduct visible emissions assessments in accordance with 40
CFR 60, Appendix A, Method 22. This assessment is based on total visible emissions regardless of the opacity of the emission.
B. Visible emissions are permitted at the following duration provided they do not extend beyond the established regulated areas. Random airborne emissions of a cumulative duration of no more than 1% of the workday are permitted. This amounts to a duration of 5 minutes in an 8-hour workday. Visible emissions in excess of this criterion are cause for immediate project shut down until the cause of the emissions is corrected.
C. The visible emissions assessment will account for all locations where emissions of lead dust might be generated, including but not limited to, the containment or work area, dust collection and waste recovery equipment as applicable and waste containerizing areas.
Observations and corrections of visible emissions and releases of dust debris are an ongoing daily requirement.
1.5.2 GROUND G SOIL PROTECTION
A. The Contractor shall not contaminate the ground or soil. An approved impervious covering must be placed on the ground under the work and decontamination areas and under waste containers.
B. Prior to the start of any work, the Contractor and the Engineer shall make a site inspection to determine the cleanliness of the area. Clean-up procedures that are required as a result of ground or soil contamination caused by the Contractor shall be the responsibility of the Contractor.
1.5.3 WATER ǪUALITY
A. The Contractor shall take all necessary precautions to prevent debris due to paint
LNG TANK PAINTING
related activities from entering the water. Any notification and clean-up procedures required to abate lead contamination in sediments or water shall be the responsibility of the Contractor. The Contractor shall protect all drains to prevent debris from entering the storm sewer system.
1.5.4 CONTAINMENT
A. The Contractor shall design, install, and maintain a containment to retain water, debris, dust, and paint used during cleaning, surface preparation, and coating operations. The containment shall be designed to reduce worker exposure to lead, toxic metals, hazardous substances, and PCBs as well as protect vehicular traffic, pedestrians, equipment, and the surrounding environment.
B. Table 1.5.4 outlines the minimum requirements for containment design for various activities, such as: cleaning, surface preparation, and paint application. Containment classifications and descriptions are based on SSPC – Guide 6, Guide for Containing
Debris Generated During Paint Removal Operations.
Table 1.5.4: Minimum Requirements for Containment Design Wet G
Dry
Abrasive
Blasting
, Class
1A
Power
Washing
Class 1W
Power Tool
Cleaning
(including vacuum-assisted), Class 1P
Coating
Application
, Class 3A
Containment
Materials
A1 Rigid or A2 Flexible
Penetrability B1 Air
Impenetrable
C B3 Water
Impenetrable
B1 Air
Impenetrable and B3 Water
Impenetrable
B1 Air
ImpenetrableC
B3 Water
Impenetrable
B1 Air
Impenetrable
Support
Structur e
D1 Fully Sealed D1 Fully Sealed D1 Fully Sealed D2 Partially Sealed
Entryway E2 Re-sealable
Door
E2 Re-sealable
Door
E2 Re-sealable
Door
E3 Overlapping
Door
Air Make-Up F1 Controlled Air F2 Open Air Supply F1 Controlled Air F2 Open Air Supply
Input Air Flow G2 Natural Input Air
Air Pressure H1
Instrumentation and H2 Visual
Verification
H3 Not Required H1
Instrumentation and H2 Visual
Verification
H3 Not Required
Air Movement I1 Minimum
Specified
I2 Not Specified I1 Minimum
Specified
I2 Not Specified
Exhaust
Dust
Filtration
J1 Air Infiltration J2 Not Required J1 Air Infiltration J1 Air Infiltration
LNG TANK PAINTING
1.5.4.1 ENGINEERING
A. The Contractor shall provide plans and calculations detailing the proposed method of containment and ventilation. The plans shall include an elevation view of the containment enclosure clearly showing any encroachments on the surroundings.
B. The plans shall contain details of the method of sealing joints, the entrance/exit openings, air intake points (including filters, louvers, and baffles), type/placement of lighting systems, and connections to the structure. Methods of attachment that require welding, drilling, bolting, or any methods requiring alteration of the structure or part of it, are not allowed.
C. If the containment will be attached or connected to the LNG Tank structure in anyways, the Contractor shall analyze the Structure to determine its ability to safely support the proposed containment system and equipment. The following calculations are required:
a. The maximum dead and live load imposed on the LNG structure by the containment system.
b. The maximum allowable load for any floors/platforms.
c. The calculations shall include an analysis of the stresses in all affected members and applicable load rating capacities.
D. Any containment system attached or connected to the LNG Tank Structure shall be analyzed to determine the amount of stress applied to the structure as a result of wind loads on the containment. The Contractor shall calculate an “allowable wind speed” which will be used, in the field, to determine the threshold for dismantling the containment system.
1.5.4.2 MATERIAL REǪUIREMENTS
A. All tarps, drapes and plastic sheeting materials used for containment or ground cover shall be fire-retardant and impermeable to air and water. All materials shall be in good condition.
1.5.4.3 LIGHTING
A. Light at the work substrates within the containment enclosure shall be maintained by the
Contractor at a minimum of 30 fc as measured by a light meter. Such lighting shall be maintained throughout the surface preparation, painting, and inspection activities. The use of explosion-proof lighting is mandatory.
B. The Contractor shall maintain, as fully operational and functional, all existing lighting systems including navigation lights, aerial lighting, and roadway or parking lot lighting and signage.
LNG TANK PAINTING
C. If existing lighting will be concealed, the Contractor shall install temporary lighting and a temporary lighting plan shall be required to be included in the Contractor’s submittals for review and approval by the Owner C Engineer in advance of the work.
1.5.5 FIELD OPERATIONS
A. All debris and abrasive, which have accumulated, as the result of surface preparation shall be vacuum cleaned at a frequency specified in the Contractor’s containment submittal, or more frequently if directed by the Engineer. Prior to removal or relocation to another point along the structure, all debris must be removed from the containment materials and equipment. The level of cleanliness shall be such that wind or physical contact during handling and transportation does not dislodge debris or dust.
1.5.6 VENTILATION
A. When negative pressure is required within a containment system, the designed system shall maintain a minimum negative pressure as measured by 0.76 mm (0.03 in.) of water column relative to external ambient air. Air velocity within the enclosure shall meet the minimum requirements of 30 m/min (100 ft/min) cross draft and 18 m/min (60 ft/min) downdraft. Submittals shall include a description of the dust collection and filtration equipment, including the equipment data sheets and airflow capacity.
1.5.7 HANDLING OF HAZARDOUS WASTE AND REPORTING RELEASE PROGRAMS
A. The Contractor shall submit a plan to the Engineer detailing all aspects of waste management including an Emergency Response Contingency Plan. The plan shall detail the methods for the collection, handling, sampling, testing, site storage, and disposal of wastewater, lead paint, and related debris. The Contractor and the Owner are the co-generators of the waste. The Owner will provide the EPA identification number and the
Contractor is responsible for all other waste management.
1.5.7.1 WASTE SAMPLING, TESTING AND CLASSIFICATION
A. All waste streams generated as part of the work shall be tested by TCLP for all eight
RCRA metals, PCBs, pH, flash point, ignitability, reactivity, corrosivity, and percent solids to determine proper disposal. The Engineer shall be the final authority on what shall be tested for possible contamination. Four samples representative of each waste stream shall be collected and tested in accordance with EPA SW846 Method 1311.
B. The Engineer must be notified of the date and time of sample collection prior to sampling activities. The Contractor, in the presence of the Engineer, shall perform sampling for testing and a State certified laboratory shall perform testing. Chain of custody must be adhered to for sample removal. TCLP test results certified by the testing laboratory shall be provided to the Engineer. The following information must be contained in the laboratory report as a minimum:
LNG TANK PAINTING
a. Job name, location, and Contract number
b. Identification of the waste stream analyzed
c. Number of samples collected and tested
d. Dates of sampling and testing
e. Defined laboratory test procedures
f. The names and signatures of sampling technicians and laboratory technicians
g. Summary of test results
C. The Contractor shall provide the Engineer with an original signed copy of the report no later than 14 days after the samples have been collected.
D. Non-hazardous waste shall not be mixed with hazardous waste. DEEP requires that a mixture of non-hazardous waste with hazardous waste must be treated as hazardous.
E. All debris cleaned and collected from abutments and other areas of collection shall be disposed of properly. Debris which include, but not limited to, sand, gravel, bituminous materials and bird excrement shall be packaged and stored separately from waste generated as a result of surface preparation. A representative sample of the debris shall be analyzed to determine its classification prior to disposal.
1.5.7.2 WASTE HANDLING, PACKAGING, AND STORAGE
A. Lead paint and related debris must be collected daily and placed in DOT approved containers of good integrity (i.e., no dents, holes, missing lids or locking mechanisms, etc.)
B. The Contractor shall inspect drums weekly and the results recorded in an on-site logbook accessible to the Engineer. Containers shall be closed and clearly labeled to identify the contents. Hazardous wastes must be labeled with the words “HAZARDOUS
WASTE,” the name of the waste, the hazards associated with the waste, and the date when accumulation began in the container. The hazardous waste label shall also include the generators’ name, address, and EPA identification number.
C. Containers shall be stored in a safe and suitable location at the job site. Storage shall be in a manner that protects the public and the environment, i.e., on a level impervious base, away from waterways, etc. Storage area(s) shall be approved by the Owner C Engineer prior to generating wastes.
D. Storage areas shall be labeled with the words “HAZARDOUS WASTE” Appropriate security (i.e., fencing, locked gated, etc.) must be maintained at the site to avoid injury, theft or vandalism with regards to hazardous waste. Once a container in the work area is full, it shall be moved to the secure storage area within 3 days. If a suitable location for hazardous waste storage does not exist on-site, the Contractor shall find an alternate storage site. The alternate storage site shall only be allowed with documented permission by the Engineer and DEEP. Evidence of improper storage and handling
LNG TANK PAINTING
shall be cause for immediate shutdown until corrective action is taken.
E. Storage of hazardous waste on site is limited to 90 days with the start date of initial accumulation in each container. The Engineer is to be informed one week in advance of the planned date(s) when hazardous waste is to be removed from the job site.
1.5.7.3 WASTE TRANSPORTATION AND DISPOSAL
A. Hazardous waste shall only be removed from the site by DEEP licensed haulers in the presence of the Owner or Engineer. Only EPA licensed Treatment Storage
Disposal Facilities (TSDF) shall accept the hazardous waste.
B. The Contractor shall submit the name, address, phone number, name of contact person and the EPA identification number of the TSDF. Before the start of work, the
Contractor shall provide the Engineer with a letter of intent from the TSDF stating that they agree to accept and treat said waste in accordance with all state and federal regulations.
C. All hazardous waste manifests must be signed by the Owner or Engineer upon removal of the waste. The Contractor shall provide the Engineer with a Certificate of Disposal upon receipt from the TSDF. The Owner must receive a signed manifest copy directly from the TSDF.
1.5.7.4 REPORTABLE RELEASES TO THE ENVIRONMENT
A. The Contractor’s on-site emergency response contingency plan shall outline steps to take in the event of a hazardous waste spill or release including procedures for notification to DEEP.
B. The Contractor is advised that a discharge of one or more pounds of lead with a particle size of 0.1 mm (4 mils) or less to the atmosphere, water or soil, within a 24-hour period, is considered to be a reportable release in accordance with 40 CFR 300 and 40 CFR
302.
1.6 REFERENCES
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referred to within the text by the basic designation only. In the event of conflicting requirements between this specification and the references cited, the most stringent requirement will apply. Current standards at time of bid govern this specification:
LNG TANK PAINTING
ASTM INTERNATIONAL (ASTM)
• ASTM D-3276
o Painting Inspectors (Metal Substrates)
THE ASSOCIATION FOR MATERIAL PROTECTION AND PERFORMANCE
(AMPP)/ NATIONAL ASSOCIATION OF CORROSION ENGINEERS (NACE)/
THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)
• SSPC Guide 6 o Guide for containing Debris Generated During Paint Removal Operations
• SSPC PA-1
o Shop, Field, and Maintenance Painting
• SSPC PA-2
o Measuring of Dry Film Thickness with Magnetic Gages
• SSPC ǪP-1
o Standard Procedure for Evaluating painting Contractors (Field Application to Complex Industrial Structures)
• SSPC ǪP-2
o Standard Procedure for Evaluating the Ǫualifications of Painting Contractors to Remove Hazardous Paint
• SSPC SP-15
o Commercial Grade Power Tool Cleaning
• SSPC SP-13/ Nace No. 6 o Surface Preparation of Concrete
• SSPC SP-10/NACE No. 2 o Near-White Metal Blast Cleaning
• SSPC SP-10 (WAB)/NACE WAB-2
o Near-White Metal Wet Abrasive Blast Cleaning
• SSPC SP-3
o Power Tool Cleaning
• SSPC SP-2
o Hand Tool Cleaning
• SSPC SP-1
o Solvent Cleaning
• SSPC VIS-5/NACE VIS-9
o Guide and Reference Photographs for Steel Surfaces Prepared by Wet Abrasive Blast Cleaning
• SSPC VIS 3
o Guide and Reference Photographs for Steel Power Tool Cleaning o SSPC VIS 1
Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast
Cleaning
• SSPC Guide 18 o Specifier’s Guide For Determining Containment Class and Environmental Monitoring Strategies for lead Paint Removal Projects
• SSPC Guide 16
LNG TANK PAINTING
o Guide to Specifying and Selecting Dust Collectors
• SSPC Guide 12 o Guide to Illumination of Industrial Coating Projects
• SSPC Guide 7 o Guide to the Disposal of Lead-Contaminated Surface Preparation Debris
• SSPC Guide 6 o Guide for Containment Surface Preparation Debris Generated During Paint Removal Operations
• SSPC
o Guide for Planning Coatings Inspection
• SSPC
o Development and use of Ǫuality Control Forms in Coatings Contracting
• SSPC TU 7
o Conducting Ambient Air, Soil, and Water Sampling During Surface Preparation and Paint Disturbance Activities
INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)
• ICRI No. 310.2R o Selecting and Specifying Concrete Surface Preparation For Sealers, Coatings, Polymer Overlays, and Concrete Repair
• ICRI Concrete Surface Profile (CSP) Chips
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
• 29 CFR 1910 – Subpart Z o Toxic and Hazardous Substances
•…
This is the start of the file's text. The full file is on GovTribe.