This Statement of Work details crane rental requirements for Western Area Power Administration (WAPA) to erect two steel monopole transmission structures and demolish one steel lattice tower in southeastern Hand County, South Dakota. The work requires a rental crane and certified operator for a minimum of 4 days between April 14-23, 2025, with work to be performed during normal hours of 6:30 AM - 5:00 PM including weekends as needed.
The project involves installing two 105-foot monopoles (structures 37/5 and 37/4) with 7'9" slip joints, with the heaviest sections weighing 22,671 lbs, and removing one 70-foot steel lattice tower. The contractor must provide a crane capable of these lifts, along with certified operators, and submit various documentation including crane specifications, operator certifications, annual inspection reports, load charts, and proof of insurance ($500,000/$1,000,000 liability limits). WAPA will provide project drawings, rigging, and coordinate the work plan with the contractor. The contractor's quote must include all costs including mobilization/demobilization, weather delays, and additional equipment like jibs and counterweights, with onsite work priced at an hourly rate based on actual costs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (Attachment 1)
Crane Rental for Setting Transmission Structures In SE Hand County, South Dakota
Description of Project
Western Area Power Administration (WAPA) requires the service of a rental crane and operator for erection of two (2) steel monopole and demolition of one (1) steel lattice electrical transmission towers located in southeastern Hand County, South Dakota, along 372nd Ave 14 miles West of Hwy 281. The projected duration for the crane rental requirement is a minimum of 4 days. Dates are subject to change but anticipated during the timeframe April 14th – April 23rd, 2025.
Work to be Performed by Contractor and Contractor Requirements
Please review site conditions as this is an active construction site. WAPA may provide matting for site access and setup but cannot guarantee. The Contractor shall furnish mobile crane/cranes with operators to perform the work as described below. Both the crane and operator must be certified per applicable industry standards. An inspection of the boom assembly shall be performed by the Contractor and by WAPA personnel before any work is performed. The crane shall be load tested at the site before any work is performed and documented on WAPA’s Crane Inspection and Test Record form. The crane must be capable of lifting and positioning the required loads to the required height as outlined below.
Work Description and Sequence
Upon request, a project review at the work site may be provided and is recommended prior to bid submittal. Project drawings may also be provided upon request.
Following is an overview of the work. Other tasks by the Contractor may be required, as deemed necessary to accomplish the project. Contractor shall coordinate the work plan and equipment setup with WAPA, including the Contractor crane, as well as WAPA’s manlift, crane and other equipment as required. WAPA will provide and rig each tower section to be lifted and guide the tower sections onto the base plate foundations and onto the slip joint of adjoining sections as they are lowered in place by the Contractor.
Structures:
Structure Number Action Max height
(Assembled) Heaviest Section
Weight of Heaviest Section (lb)
Weight of Top Section (lb)
37/5 NEW Installing 105’ (+7’9” slip) Pole base 22,671 6,000
37/4 NEW Installing 105’ (+7’9” slip) Pole base 22,671 6,000 37/4 Existing Removing 70’ Steel Lattice
The work shall be completed within WAPA’s normal working hours: 6:30 A.M – 5:00 P.M, federal holidays excluded, unless otherwise approved by WAPA. Work will continue through the weekend as needed.
Payment
Offeror’s quote shall include all applicable costs, including mobilization and demobilization, weather delay rates, and potential charges involving jibs, counterweights, etc. Onsite work shall be priced at an hourly rate and include all associated charges. Payment will be based on actual costs.
Submittals
The contractor shall provide the following submittals prior to work:
1. Type and capacity of crane to be utilized.
2. Signed Crane Rental Provisions Document (attachment A) provided within this statement of work.
3. Load chart, per ‘Crane Rental Provisions: Load Charts’.
4. Current crane operator certification.
5. Current annual crane inspection report, per ‘Crane Rental Provisions: Crane Inspections.
6. Proof of insurance.
The Contractor shall provide the following submittal upon completion at the job site.
1. Crane Inspection and Test Record (attachment B).
WAPA-Provided Documents
1. Project drawings will be provided to Contractor and may be provided prior to award upon request.
2. WAPA’s Power System Safety Manual (PSSM) will be provided to the Contractor and may be provided prior to award upon request.
Attachment A
CRANE RENTAL PROVISIONS
This form must be signed and returned before any work is performed by the Contractor.
Operation of Equipment.
No work shall be performed for WAPA without WAPA representatives approving the work and being present at the jobsite while the work is being performed. This is to ensure that clearances, hot line orders, and other documentation required is understood and adhered to in order to provide for a safe jobsite.
All equipment to be furnished by the contractor shall be in safe operating conditions and meet all applicable ANSI and OSHA standards for the type of equipment to be used. The contractor shall provide fully trained, experienced, and qualified personnel as is necessary for the proper and efficient operation and maintenance of the equipment, and all fuel, lubricants and other operating supplies necessary for the operation of the unit. Results of the latest physical examination of the equipment operator shall be submitted to WAPA before work is performed. All expenses incurred by the contractor for this job, including the wages of operating personnel, shall be paid by the contractor and the cost thereof included in the rental unit price. The equipment operator shall be fully qualified and competent in the type of equipment he/she is operating, knowledgeable in the operating capabilities and limitations, and is expected to prevent or stop any lift which endangers equipment or personnel.
Indemnity.
The contractor hereby releases and agrees to indemnify and hold harmless the United States, its officers, agents, and employees on account of all damages or claims for damage by whomsoever made, of any nature whatsoever arising out of or in any manner connected with the operation by the contractor's employees or representatives of the contractor's equipment under this purchase order. The contractor shall provide written certification from the company's insurance carrier that liability, care, and handling insurance is in effect for the duration of the contract.
Insurance.
The contractor shall provide insurance as follows:
1. General liability limits of $500,000/$1,000,000.
2. Proof of insurance must be provided prior to starting the project.
References.
WAPA’s Power System Safety Manual (PSSM) is attached. It is the responsibility of the contractor to become familiar with this reference and the American National Standards Institute (ANSI) manual B30.5 and to ensure that all employees comply with them. The equipment furnished under this purchase order must have been tested and certified as per the stated references. The contractor is expected to conform to all applicable OSHA regulations for the type of work to be performed under this purchase order.
Lattice Boom Cranes.
The contractor shall not allow any employee to attempt to disassemble or assemble a lattice boom crane by removing the bottom boom pins with the boom not properly supported or supported by pendant lines. No one shall be allowed under the boom when the boom is in a horizontal position unless the boom is fully supported by some form of blocking other than the pendant lines.
Crane Inspections.
Any crane used under this purchase order shall have had a thorough crane inspection performed within the last 12 months. The inspection shall have been conducted by a firm specializing in crane inspection and repair, or by the crane manufacturer. A written record of the crane inspection shall be submitted to WAPA one working day prior to the use of the crane on the site. The record may be on forms utilized by the crane inspection service or the crane manufacturer. It shall, however, be detailed to show the critical components of the unit by item and their individual condition.
If a crane has been subjected to the following conditions, a thorough inspection shall be performed in addition to the inspections performed on a twelve-month interval:
- Contact with energized conductors.
- Crane has been subjected to a tipping condition.
- Crane has been overloaded above 110% of capacity at any given radius or boom angle.
- Welding has been performed on the boom, outriggers, or other critical crane components.
- One year has elapsed since the last inspection has been performed.
Load Charts.
The contractor shall submit a reproduction of the load rating chart for the crane to be used under this purchase order to WAPA at least five working days prior to commencement of work. At the worksite, the operator shall discuss the load rating chart, crane placement, and rigging associated with the lift with WAPA supervisory personnel present at the site prior to any lift being performed. Only slings or chain of adequate capacities shall be used to rig the loads.
Crane Operation Near High-Voltage Lines.
Equipment shall not be operated where it is possible to bring such equipment or any part of the equipment within 10 feet of any high voltage line or installation unless at least one of the following safety precautions has been taken:
The utility company or owner of the line has been notified, the line de-energized and grounded, and control measures have been taken to prevent energization of the line during the progress of the work.
Adequate guards or barriers have been erected or exist to prevent the equipment or any part thereof from approaching closer than the clearances listed in OSHA
1926.950 Table V-1 to an energized conductor. These guard or barriers must provide prevention of contact and not rely on visual observation.
NOTE: A notice of the 10-foot limitation shall be posted in the operator's cab of cranes, shovels, backhoes, and related equipment.
On-Site Safety Meeting.
A safety meeting including the crane operator and WAPA employees shall be held prior to commencement of work at the jobsite.
I have read and understand all of the above provisions.
Contractor Name
Contractor Address
Signature Date
Attachment B Western Area Power Administration
CRANE INSPECTION AND TEST RECORD
Cranes, Hoists, “A” Frames, Aerial Man-Lifts, Hoisting Equipment
Government Office:
Name of Contractor & Specifications No.:
Make: Model: Serial No.:
Rated Capacity:
Counterweight Lbs:
Length of Boom (if hydraulic, open and closed):
Condition of Boom:
Length of Jib: Condition of Jib: Rated Capacity:
Boom Hoist Line Size:
No. Parts: Pendant Line Size:
Load Line Size: No. Parts: Jib Line Size:
Condition of all cable, sheaves, fittings, connectors, etc. Satisfactory Operators: exp. date Signalman: exp.
date Deficient Riggers : exp. date Annual Inspection :
Equipped with Power-Down On: Load Line Jib Line Type of Boom Stops: Condition of Stops:
Guards Installed:
Type of Mounting: Long Wide Crawler Standard Truck Performance Test – Main Boom Load in Pounds:
Boom Radius:
Degree of Swing:
Outriggers:
Satisfactory: Lifting Swinging Lowering Braking Travel Under Load Test (If crane is going to travel under load on actual work) Load in Pounds:
Boom Radius:
Performance Test – Jib or Boom Extension Load in Pounds: Boom Radius: Jib Used:
Degree of Swing:
Outriggers:
Satisfactory: Lifting Swinging Lowering Braking Remarks:
Tested By:
Contractor’s Representative – Signature, Title)
Date:
Witnessed By:
(Government Representative – Signature, Title)
Date: