The file's text, extracted by GovTribe without its formatting.
Audit
| Attachment #13 - RFP Number___________ Cost Worksheet | |
| Proposer Name: | |
| Key Staff Members Name and Title | Hourly Rate |
| Task 1: Audit Plan and Program | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 1: Detailed Audit Plan and Program in an electronic format e-mailed to the CPUC Contract Manager. | Per Plan | | 12 | |
| Task 2: Monthly Status Reports | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 2: Monthly Status Reports over the course of the agreement in an electronic format e-mailed to the CPUC Contract Manager. | Per Report | | 36 | |
| Task 3: Standing Meetings | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 2.a: Standing meetings over the course of the agreement to be conducted virtually using Microsoft Teams or WebEx platforms. | Per Meeting | | 12 | |
| Task 4: Draft Audit Reports | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 3: Draft Audit Reports over the course of the agreement in Microsoft Word in an electronic format e-mailed to the CPUC Contract Manager | Per Report | | 12 | |
| Task 5: Final Audit Reports | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 5: Final Audit Reports over the course of the agreement in Adobe PDF electronic format e-mailed to the CPUC Contract Manager. | Per Report | | 12 | |
SUBTOTAL TASKS 1-5 Total Cost Tasks 1-5
| Task 6: Additional Services After Final Reports | The cost for Task 5 must be 10% of the cost of Tasks 1 through 5. | Total Cost Task 5 |
| Refer to RFP Section 1, Scope of Work for potential services needed | | |
| TOTAL PROPOSAL COST | Total Cost |
Examination
| Attachment #__ - RFP Number___________ Cost Worksheet | |
| Proposer Name: | |
| Key Staff Members Name and Title | Hourly Rate |
| Task 1: Examination Plan and Program | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 1: Detailed Examination Plan and Program in an electronic format e-mailed to the CPUC Contract Manager. | Per Plan | | 12 | |
| Task 2: Monthly Status Reports | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 2: Monthly Status Reports over the course of the agreement in an electronic format e-mailed to the CPUC Contract Manager. | Per Report | | 36 | |
| Task 3: Standing Meetings | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 2.a: Standing meetings over the course of the agreement to be conducted virtually using Microsoft Teams or WebEx platforms. | Per Meeting | | 12 | |
| Task 4: Draft Examination Reports | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 3: Draft Examination Reports over the course of the agreement in Microsoft Word in an electronic format e-mailed to the CPUC Contract Manager | Per Report | | 12 | |
| Task 5: Final Examination Reports | Unit of Measure | Cost Per Unit | Amount Required | Total Task Cost |
| Deliverable 5: Final Examination Reports over the course of the agreement in Adobe PDF electronic format e-mailed to the CPUC Contract Manager. | Per Report | | 12 | |
SUBTOTAL TASKS 1-5 Total Cost Tasks 1-5
| Task 6: Additional Services After Final Reports | The cost for Task 5 must be 10% of the cost of Tasks 1 through 5. | Total Cost Task 5 |
| Refer to RFP Section 1, Scope of Work for potential services needed | | |
| TOTAL PROPOSAL COST | Total Cost |