Sarasota County has issued a Request for Professional Services (RPS) for Construction, Engineering & Inspection (CEI) Services for the Central County Solid Waste Disposal Complex (CCSWDC) Stage II Roadway Improvements & Scale Installation project. The county is seeking a qualified consultant to provide comprehensive construction engineering and inspection services, including verification testing, materials sampling, and testing for the roadway improvements and scale installation construction project. The proposal will be submitted through OpenGov Procurement, with the evaluation and selection to be conducted by the Professional Services Review Committee (PSRC) using specific scoring criteria. Proposers must meet detailed qualifications, including having a registered Professional Engineer, demonstrating experience in roadway construction, and possessing various certifications from the Florida Department of Transportation and other agencies.
The scope of services includes extensive project oversight, on-site and off-site inspection, sampling and testing, and project close-out documentation. Proposers must maintain specific insurance coverages, including Workers' Compensation, Commercial General Liability (with Sarasota County as an additional insured), and Professional Liability, with minimum coverage limits specified. The contract will be awarded to the most qualified proposer based on the evaluation committee's ranking, with the intent to select a firm that can most effectively manage the technical and logistical aspects of the construction project. The successful consultant will be responsible for detailed documentation, daily reporting, meeting management, and ensuring compliance with all contract specifications and regulatory requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 252749MM_Project_Documents.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROFESSIONAL SERVICES (“RPS”) – PART I (ADDENDUM 1)
RPS Part I Rev. 02/10/25 Page 1 of 6
RPS #: 252749MM
RPS TITLE: CEI Services For CCSWDC Stage II Roadway Improvements & Scale Installation
PURPOSE
In accordance with Section 287.055, Florida Statutes, Sarasota County, a political subdivision of the State of Florida, will receive proposals on the date indicated in OpenGov Procurement (OpenGov), the County’s electronic procurement portal for the purpose of selecting a qualified Proposer to provide Construction, Engineering & Inspection (CEI) Services for Central County Solid Waste Disposal Complex (CCSWDC) Stage II Roadway Improvements & Scale Installation. Proposers are required to comply with Part II, Scope of Services.
OpenGov is located at https://procurement.opengov.com/portal/scgov
PROPOSER
2.1 For the purposes of this RPS, the term “Proposer” is defined as the legal entity submitting a proposal.
2.2 Proposers intending to submit a bid as a joint venture with another company must provide documentation attesting to the formation of that joint venture with their submittal. For purposes of this solicitation, all vendors who make up the joint venture will be considered together as the Proposer.
QUALIFICATIONS
3.1 The Proposer must be a business organization registered with the Florida Department of Business & Professional Regulation (DBPR) to provide engineering services in the State of Florida at the time of submittal.
3.2 At least one key personnel listed in the Proposal must be a registered Professional Engineer licensed by the Florida Board of Professional Engineers at the time of submittal.
3.3 Proposals should demonstrate experience providing engineering and inspection services in roadway construction and/or reconstruction.
3.4 Preferred Qualifications
3.4.1 At least one Key Personnel has experience performing complex technical assignments, making and checking engineering computations, inspecting and documenting construction work, and conducting testing in accordance with specifications and testing guide.
RPS Part I Rev. 02/10/25 Page 2 of 6
3.4.2 At least one Key Personnel possesses a minimum of 7 years of experience in roadway construction and/or reconstruction.
3.4.3 At least one Key Personnel possesses a minimum of 7 years of experience in transportation/commercial electrical engineering with experience performing complex electrical inspections.
3.4.4 The proposed Key Personnel as a team have current Florida Department of Transportation (FDOT) Construction Training Qualification Program (CTQP) certifications, and additional certifications as follows (all certifications must be active at the time of submittal):
a. Florida Department of Environmental Protection
(FDEP) (ADDENDUM 1)
b. CTQP Asphalt Paving Level I and II
c. CTQP Asphalt Plant I and II
d. CTQP Earthwork Construction Inspection Level I and II
e. CTQP Concrete Field Inspector Level II
f. CTQP Quality Control Manager
g. CTQP Final Estimates I and II
h. Florida Department of Environmental Protection (FDEP) Florida Stormwater, Erosion, and Sedimentation Control Training and Certification Program for Inspector and Contractors. (ADDENDUM 1)
i. FDOT Advanced Temporary Traffic Control (TTC)
(ADDENDUM 1)
MEETINGS & SCHEDULE
An anticipated schedule is provided in the Timeline posted in OpenGov. All meetings will take place at the time, date, and location specified in the solicitation Timeline. Short-listed Proposers should be prepared to attend presentations and/or interviews either in Sarasota, Florida or virtually, at the County’s discretion.
SUBMITTAL INSTRUCTIONS
Refer to the Submittal Instructions section in OpenGov for instructions on how to submit a proposal. Proposers are advised to review the General Terms and Conditions of Solicitations which are available in OpenGov.
RPS Part I Rev. 02/10/25 Page 3 of 6
VENDOR QUESTIONNAIRE
6.1 All proposers must complete the required forms and information included in the Vendor Questionnaire section of OpenGov. Completed forms and other requested documents must be uploaded with proposer’s submittal in OpenGov. Proposers who fail to complete and upload required forms and documents or fail to provide responses to questions in the Vendor Questionnaire section of OpenGov may be found non-responsive.
WRITTEN PROPOSALS
The information requested in each section below will be used by the evaluation committee to evaluate and score written proposals. All proposal documents must be submitted in the Vendor Questionnaire section in OpenGov in the format requested.
7.1 Ability of Professional Personnel
7.1.1 Single page letter of interest summarizing Proposer’s
qualifications.
7.1.2 Required and preferred licenses and certifications.
7.1.3 Resumes of key personnel, including subconsultants, demonstrating individual qualifications and experience.
7.2 Proposer’s Past Performance & Experience
7.2.1 Complete the Summary of Professional Experience &
Capabilities Form in the Vendor Questionnaire section of OpenGov). Projects submitted should demonstrate the experience of the Proposer, subcontractor(s), and current team members who may have worked for other firms on similar projects and provide detailed information regarding the Proposer’s capabilities, project management techniques, and project controls.
7.3 Approach
7.3.1 Project Approach – Provide a detailed project approach that includes, but is not limited to the following:
a. Project management techniques, controls, program and technologies to be employed to meet project schedule and budget requirements.
RPS Part I Rev. 02/10/25 Page 4 of 6
b. Assignment of personnel to provide the most efficient service.
c. Where elements of the work will be performed, and who in the organizational chart will oversee performance of the work to provide the most efficient services.
d. Anticipated impacts of the Proposer’s current and projected workload on the project.
e. Detailed information explaining how location of the firm, key personnel and sub-contractors will affect project, including how impact of any physical distance will be mitigated through the use of technology, processes or other means.
7.3.2 Workload
Complete the Current & Projected Workload Form (in the Vendor Questionnaire section of OpenGov) to identify active and awarded projects.
7.3.3 Organization
a. Provide an organizational chart delineating personnel assigned to the project (including subconsultants).
b. Provide an organizational chart showing the corporate management structure of the Proposer.
7.3.4 Schedule/Timeline
Provide a graphical representation of the proposed project schedule/timeline indicating major milestones and deliverables.
SELECTION PROCESS
8.1 Written Proposals
8.1.1 All timely responses meeting the criteria set forth in this RPS will be considered by the County.
8.1.2 Written proposals will be evaluated and scored by the
Professional Services Review Committee (PSRC) using the evaluation criteria in the Evaluation Criteria section of OpenGov.
8.1.3 When evaluating written proposals, the PSRC will use the scale below to score each criterion. Only whole numbers are to be
RPS Part I Rev. 02/10/25 Page 5 of 6 used when scoring. Scores will be given weight as indicated in the evaluation criteria in OpenGov.
Score Description
5 Excellent
4 Very Good
3 Good
2 Satisfactory
1 Unsatisfactory
0 N/A
8.2 Presentations
The PSRC will conduct discussions with, and may require public presentations by, no fewer than the three (3) highest scoring Proposer
8.3 Ranking
Following discussions or presentations, the PSRC will rank the short-listed Proposers. When ranking short-listed Proposers, the PSRC will consider information contained in the written proposals, clarifications (if any), and information provided during discussions or presentations.
Ranking shall be determined without regard to the score established as a result of the evaluation of written proposals.
8.4 Recommendation of Award
The Proposer ranked first by the PSRC will be recommended for award.
AWARD
9.1 It is the intent of the County to award a contract to the Proposer(s) who, in the sole opinion of the County, is most qualified to perform the scope of services required.
9.2 In the event of a tie the tie-breaking procedures identified in the Sarasota County Procurement Manual will apply.
9.3 Local preference as defined in the Procurement Code section 2-215 is not applicable to this solicitation.
9.4 Contract
A draft of the contract that the successful Proposer(s) will be expected to
RPS Part I Rev. 02/10/25 Page 6 of 6 sign (a CCNA Specific Project Agreement) is posted on the Procurement website, shown below. The County may, in its sole discretion, select a different contract type or make revisions to the one referenced above following the recommended award of this solicitation.
https://www.scgov.net/government/procurement/contract-templates
CONFLICT OF INTEREST
10.1 Any Proposer who has drafted any portion of a scope of work or specifications for a project, or any entity which provides material assistance to such Proposer in such work, shall be ineligible to compete for the contract for design or construction of that project.
10.2 Selected Proposers, either directly or through an affiliate, may not have a business relationship with any entity to perform work related to a work assignment issued under any resulting contract
CHANGES IN PROJECT TEAM
11.1 A change in the project team of a Proposer after the submission of a proposal could result in reconsideration of the scoring of applicable evaluation criteria, at the sole discretion of the County.
11.2 Any changes in the Proposer’s Key Personnel must be brought to the attention of Procurement as soon as possible after the change is made.
The changes, the reasons for the changes, and resumes for the individuals being substituted for an original project team member, must be submitted to the Procurement Analyst identified in the Solicitation Summary prior to the scheduled evaluation committee meeting.
11.3 Decreases in scoring may result from the reconsideration of changes in the project team of a Proposer. No increases in scoring will result from the reconsideration of changes in the project team of a Proposer.
11.4 After recommendation of award, the successful Proposer shall not be allowed to substitute project team members named in this proposal without the prior written permission of the County. Substitution may, in the sole opinion of the County, be grounds for cancellation of a recommended award, or termination of agreement.
REUSE OF EXISTING PLANS
12.1 The plans on this project are subject to reuse in accordance with Section
287.055 (10), Florida Statutes.
PART II
SCOPE OF SERVICES
RPS Rev. 01/31/20 Part II - Page 1 of 3 Prepared by Capital Projects Department
1. Description of Project
The County is requesting construction engineering and inspection (CEI) services, including verification testing services which are required for inspection, and materials sampling and testing for Central County Solid Waste Disposal Complex (CCSWDC) Stage II roadway improvements and scale installation construction project (“Project”).
2. Scope of Services
The Consultant shall provide the following CEI services which may include, but are not limited to:
A. Project Oversight and Management:
i. Provide inspection services and services deemed necessary for the successful completion and closure of the work performed by various contractors on the County Project.
ii. Maintain the required level of surveillance of contractor activities and observe the contractor’s work to determine the progress and quality of work.
iii. Identify discrepancies and note any significant omissions, substitutions, defects, or deficiencies in the work of the contractor.
Inform and consult with the County on the best course of action to resolve such omissions, substitutions, defects, or deficiencies. Direct and monitor the contractor to resolve the corrective actions.
Document and report all details of each corrective action and its associated resolution to the County.
iv. Maintain complete and accurate records of all activities and events relating to the Project and properly document all Project changes.
v. Maintain complete and accurate records of the contractor's daily operations and of significant events that affect the work for activities both on-site and at the asphalt plant.
vi. Lead all Project meetings including providing agenda and meeting minutes. Meeting minutes shall be distributed within 3 business days after the meeting.
vii. Interpret plans, specifications, and special provisions for each construction contract.
viii. Inspect materials (on site and at the asphalt plant) entering into the work in accordance with the plans, specifications, and special provisions for the construction contract to determine if the Project is constructed in conformity with those documents.
ix. Process and review shop-drawings for Project.
x. Process Requests for Information (RFI) or Requests for Modification
(RFM).
RPS Rev. 01/31/20 Part II - Page 2 of 3
xi. Process Claim Analysis and extra work cost-estimations.
xii. Conduct baseline project schedule analysis and provide written response within 15 calendar days of receipt.
xiii. Conduct monthly Project Schedule Update Analysis and provide written response within 7 calendar days of receipt.
xiv. Perform verification of contractor’s monthly pay estimates, resolve any disputed quantities, and provide final concurrence within three days after the monthly cut-off.
xv. Perform coordination with utility companies, and adjacent property owners.
xvi. Prepare one Daily Report of Construction for each inspector(s) assigned to the Project, for every calendar day of the Project. Each Daily Report shall have a minimum of three photographs attached showing construction operations of the work reported in the associated Daily Report.
B. On-site Inspection:
i. Monitor and inspect Contractor’s work zone traffic control plan and review modifications to the work zone traffic control plan, including alternate work zone traffic control plan, in accordance with the County’s procedures. Consultant employees performing such services shall be qualified in accordance with the Florida Department of Transportation’s (FDOT) procedures.
ii. Monitor and inspect Contractor’s installation of complex scale, scale system and electrical components in accordance with permitting authorities and Contractor’s Construction Contract.
C. Off-site Inspection:
i. Prepare asphalt documentation in accordance with the awarded contract, FDOT Specifications, FDOT Construction Project Administration Manual (CPAM) and the County provided Asphalt Documentation Preparation and Submittal Procedure.
ii. Perform the inspection and verification of Materials on Hand at the Contractor or fabricator yard. Consultant employee shall verify the quantities of stored materials to the quantities provided by the Contractor.
D. Sampling and Testing:
i. Perform sampling and testing of component materials and completed work in accordance with the contract documents listed in the Construction Contract. The minimum sampling frequencies set out in the FDOT's Materials Sampling, Testing and reporting guide shall
RPS Rev. 01/31/20 Part II - Page 3 of 3 be met. In complying with the aforementioned guide, provide daily surveillance of the contractor's quality control activities and perform the sampling and testing of materials and completed work items for verification and acceptance.
ii. Perform inspection and sampling of materials and components at the asphalt plant and of materials normally done in a laboratory remote from the project site.
iii. Determine the acceptability of all materials and completed work items on the basis of either test results or verification of a certification.
iv. The County may monitor the effectiveness of the Consultant's testing procedures through observation and independent assurance testing.
v. Sampling, testing and laboratory methods shall be as required by the County’s and FDOT's Standard Specifications, Supplemental Specifications or as modified by the Special Provisions of the Construction Contract.
E. Certifications
i. The Proposer must maintain the certifications they submit in their proposal among its team for the life of the resulting contract.
ii. The Consultant’s staff responsible for preparing the Certified Final
Estimate must hold a Final Estimates Level II Certification from the Construction Training Qualification Program (CTQP).
F. Close-out
i. Submit project documents electronically into the County’s document management system “E-Builder” and filed in accordance with County procedures and Consultant’s approved QA Plan.
ii. Project documents shall be uploaded on a continuous, “RealTime” basis, and shall be completed within 15 calendar days of Final Acceptance of the Construction Contract. Examples of closeout documents are: as-builts, project photographs, pipe video, field books, asphalt LOT packages, National Pollution Discharge Elimination System Inspections, Earthwork Density Logs, Change Orders/Interim Field Change Agreements, Plan sheet revisions, shop drawings, mix designs, claims, manual, warranties, and general correspondence.
PART III – INSURANCE REQUIREMENTS
Insurance Template Adopted 04/19/19 Page 1 of 2
CONTRACTOR’S INSURANCE
Contractor shall, on a primary basis and at its sole expense, maintain in full force and effect, at all times during the life of this Contract, insurance coverage (including endorsements) and limits as described herein. These requirements, as well as the County’s review or acceptance of insurance maintained by Contractor, are not intended to and shall not in any manner limit or qualify the liabilities or obligations assumed by Contractor under this Contract.
Insurance requirements itemized in this Contract and required of the Contractor shall extend to all subcontractors to cover their operations performed under this Contract.
The Contractor shall be responsible for any modifications, deviations, or omissions in these insurance requirements as they apply to subcontractors.
Insurance carriers providing coverage required herein must be licensed to conduct business in the State of Florida and must possess a current A.M. Best’s Financial Strength Rating of A- Class VII or better.
Each insurance policy required by this Contract shall apply separately to each insured against whom claim is made and suit is brought, except with respect to limits of the insurer’s liability.
The Contractor shall be solely responsible for payment of all premiums for insurance contributing to the satisfaction of this Contract and shall be solely responsible for the payment of all deductibles and retentions to which such policies are subject.
Contractor shall furnish Certificates of Insurance to the County Administrative Agent evidencing the types and amounts of coverage, including endorsements, required by this Contract prior to commencement of work and prior to expiration of the insurance contract, when applicable. Such Certificate(s) of Insurance shall, to the extent allowable by the insurer, include a minimum thirty (30) day notice of cancellation (10 days for non-payment of premium) or non-renewal of coverage. Notwithstanding these notification requirements, the Contractor will be required to provide County with 5-day prior written notice of any policy cancellation or non-renewal.
The County reserves the right to review, modify, reject, or accept any required policies of insurance, including limits, coverage, or endorsements, herein from time to time throughout the term of this Contract. County reserves the right, but not the obligation, to review and reject any insurer providing coverage due to its poor financial condition or failure to operate legally.
A. WORKERS’ COMPENSATION: Contractor agrees to maintain Workers’ Compensation insurance in accordance with Florida Statutes, Chapter 440.
Employers Liability to be included with a minimum limit of $500,000 per accident/per disease/per employee. If work is to be performed over or adjacent to navigable water and involves maritime exposure, applicable LHWCA, Jones Act, or other maritime law coverage shall be included.
In the event the Contractor has “leased” employees, the Contractor or the
PART III – INSURANCE REQUIREMENTS
Insurance Template Adopted 04/19/19 Page 2 of 2 employee leasing company must provide evidence of a Workers’ Compensation policy for all personnel on the worksite.
Contractors who are exempt from Florida’s Workers’ Compensation law must provide proof of such exemption issued by the Florida Department of Financial Services, Bureau of Workers’ Compensation.
B. COMMERCIAL GENERAL LIABILITY: Contractor shall maintain Commercial General Liability per ISO form CG0001 or its equivalent, including but not limited to coverage for premises and operations, personal injury, products & completed operations, liability assumed under an insured contract, and independent contractors with limits of not less than $1,000,000.00 each occurrence, $2,000,000.000 aggregate covering all work performed under this Contract.
Contractor agrees to endorse Sarasota County Government as an additional insured on the Commercial General Liability coverage.
C. PROFESSIONAL LIABILITY: Contractor shall maintain Professional Liability, or equivalent Errors & Omissions Liability, with limits not less than $1,000,000.00 per claim/occurrence for professional services rendered under this Contract. If coverage is written on a claims-made basis: a. Any retroactive date shall precede the effective date of this Contract; b. Contractor shall provide certificates of insurance evidencing the required coverage for a period of two years after final payment under this Contract is made, or provide evidence showing Contractor has obtained a two-year extended reporting period endorsement.
| Part 1 - Addendum 1 |