This is a Request for Quote (RFQ) issued by the USDA Forest Service for the Las Dispensas Reforestation project in the Santa Fe National Forest, New Mexico. The 100% small business set-aside solicitation seeks a contractor to perform tree planting and protection tube installation on approximately 1,025 acres, with tree quantities potentially varying by +/-20%. The contract is classified under NAICS code 115310 with a small business size standard of $11.5 million.

Key details include a solicitation number of 127EAV25Q0020, with questions due by May 27, 2025, and quotes due by June 5, 2025. The period of performance is from August 15, 2025, to October 31, 2025. The contract will be a firm-fixed-price (FFP) award, with selection based on the best value offer that meets technical acceptability standards. The project involves reforesting lands burned during the 2022 Hermit Peak Calf Canyon wildfire, with an estimated 185,000 seedlings to be planted using mesh vexar or protex solid tube tree protectors for protection from animal damage and environmental conditions.

View the file

Other files

File Type Posted
Sec_J_Exhbt_3_ispct_sheet.docx DOCX document
Section_J_Exhibit_2_maps.docx DOCX document
Sec_J Exhbt_1_detailed_Unit_chrt_LasDispensas.pdf PDF
Section J_Exhibit_4_FS_handbook.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Ques�ons: All ques�ons regarding this solicita�on must be submitted no later than 1700 Mountain Time on May 27, 2025.

Ques�ons will only be accepted via email. Emails should be addressed to the aten�on of the Contrac�ng Specialist, Shavera Leveille at shavera.leveille@usda.gov.

2. Deadline for Responses: 1700 Mountain Time on June 5, 2025.

3. Period of Performance: 08/15/2025-10/31/2025

4. Basis for Award: Offers will be reviewed for conformance to the requirements of the RFQ. Award will be made based on the Best Value offer that meets or exceeds the acceptability standards for technical factors listed in section M. Failure to provide adequate information for technical sub-factors a & b, will result in the offer not being placed in the eligibility group of technically acceptable, which will remove the offer from further consideration.

Introduc�on. This is a combined synopsis/solicita�on for commercial products prepared in accordance with the format prescribed in FAR Subpart 12.6, as supplemented with addi�onal informa�on included in this no�ce. This announcement cons�tutes the only solicita�on; quotes are being requested and a writen solicita�on will not be issued.

Solicita�on 127EAV25Q0020: Las Dispensas Reforestation Santa Fe National Forest is issued as a request for quote (RFQ). This procurement is being issued as a 100% SMALL BUSINESS SET-ASIDE. The Santa Fe Na�onal Forest New Mexico has a requirement for tree planting and protection tube installation on 1025 acres. The applicable NAICS is 115310-Support Activities for Forestry, for which the small business size standard is $11.5 million (PSC: F005-Natural Resources/Conservation—Forest Tree Planting).

This solicita�on document incorporates provisions and clauses of those in effect through Federal Acquisi�on Circular (FAC) 2025-03 dated January 17, 2025. The result of this requirement will be a Firm Fixed Priced (FFP) contract. The right to make mul�ple or no award is reserved in the event it is advantageous to the Government to do so. The contractor shall provide pricing in accordance with the Schedule of Items and specifications/salient characteristics.

mailto:shavera.leveille@usda.gov ShaveraLeveille Cross-Out

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

8385 CODE 16. ADMINISTERED BYCODE

X

X

X

115310

SIZE STANDARD:

100.00 % FOR:SET ASIDE:UNRESTRICTED OR7EAV

REQUEST FOR

PROPOSAL

(RFP)

INVITATION

FOR BID (IFB)

10. THIS ACQUISITION ISCODE

REQUEST FOR

QUOTE (RFQ)

14. METHOD OF SOLICITATION

13b. RATING

NORTH AMERICAN INDUSTRY

CLASSIFICATION STANDARD

(NAICS):

SMALL BUSINESS

05/22/2025

912-463-3328SHAVERA LEVEILLE

(No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIME

06/05/2025 1700 MT

b. TELEPHONE NUMBERa. NAME

4. ORDER NUMBER3. AWARD/

127EAV25Q0020

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 4 1148426OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

LAS VEGAS NM 87701

LAS VEGAS RANGER DIST 1926 7TH ST

FOREST DISTRICT RANGER

USDA FOREST SERVICE SANTA FE NATL

15. DELIVER TO

ALBUQUERQUE NM 87102-3498

333 BROADWAY BLVD SE

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$11.5

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

6. SOLICITATION

ISSUE DATE

DELIVERY FOR FREE ON BOARD

(FOB) DESTINATION UNLESS

BLOCK IS MARKED

11.

SEE SCHEDULEX

12. DISCOUNT TERMS THIS CONTRACT IS A RATED

ORDER UNDER THE DEFENSE

PRIORITIES AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

8(A)

USDA-FS CSA SOUTHWEST 5

WOMEN-OWNED SMALL

BUSINESS (WOSB)

ECONOMICALLY DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

127EAV25Q0020 (1148426) Las Dispensas Reforestation Santa Fe National Forest

The Government intends to award a firm-fixed price contract. This requirement is a Small Business Set Aside. Offers will be reviewed for conformance to the requirements of the RFQ. Award will be made based on the Best Value offer that meets or exceeds the acceptability standards for technical factors listed in section M, and shall be fair market value for materials, labor and

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

X

DATED

ELLENA C. SILVA

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Government Use Only)

OFFER

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT: REFERENCE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 11/2021) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

incidentals represented in the specifications listed in the attached Statement of Work titled

"Las Dispensas Reforestation 2025". Contractors must be registered in SAM.gov on RFQ due date/time.

PRE- AWARD QUESTIONS AND PROPOSAL DATES: Quotes shall be emailed to The Contract Specialist

Shavera Leveille at shavera.leveille@usda.gov by

1700 Mountain Time on June 5, 2025, or sooner.

Facsimile proposals will not be accepted. If you have questions regarding this requirement, please email shavera.leveille@usda.gov by 1700 Mountain

Time May 27, 2025, and any questions submitted after this date will not be accepted. All answers will be posted to SAM.gov by May 30, 2025.

Background: The Pecos/Las Vegas Ranger District of the Santa Fe National Forest in northern New

Mexico needs tree planting services to reforest lands burned after the 2022 Hermit Peak Calf

Canyon wildfire. Tree survival and growth are dependent on the initial health of the tree seedlings, the way trees are handled and planted, environmental conditions such as soil moisture and weather, and influences of animal damage to the seedlings. The services secured with this contract will focus on the need to provide appropriate tree handling and planting techniques

Continued ...

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

4 2 of

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

127EAV25Q0020

during a period when environmental conditions are most favorable to ensure tree survival.

Description: This solicitation is for tree handling, tree planting, and tree protection installation services on the Pecos/Las Vegas

Ranger District of the Santa Fe National Forest.

The Forest expects to plant 185,000 seedlings on approximately 1025 acres. These quantities may vary by +/-20% depending on the number of seedlings delivered and plantability of the project area. Mesh vexar seedling protection tubes, protex solid tube tree protectors or similar products will be used for tree protection from animal damage and harsh environmental conditions.

The Contractor shall furnish all labor, equipment, quality control inspections, supervision, transportation, seedling and supply transport, supplies (except those designated as

Government furnished), and incidentals to perform all work necessary on the areas specified in the contract. All aspects of the work program shall be performed in an organized, systematic manner to assure services shall be performed over the entire unit.

The period of performance will begin from approximately mid-August to early September.

This date is weather and site dependent. If monsoonal moisture is determined to be inadequate for good tree survival at that time, the start date of the contract could be moved to mid-September or later.

Description, Location and Access:

All items were burned in a 2022 wildfire. Safety

Alert: Contractor needs to be aware that there are snags and burned trees at all planting sites that have the risk of falling or falling debris, especially during windy conditions. Not all of the acreage is plantable, portions of units may be too rocky for planting. Units may have 15-35 percent brush and grass/forb cover (See Section

J, Exhibit 1 for additional information on bid items).

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

4 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

127EAV25Q0020

Access Routes and Delivery Point:

The Delivery Point is the Las Vegas Ranger

Station at 1926 N. 7th Street, Las Vegas, New

Mexico (See Vicinity Map). The planting area has several access points to each of the five project locations (See section J).

District Point of Contact: Kenneth Reese, (505)438-5451, kenneth.reese@usda.gov

Delivery: 30 Days After Notice to Proceed

Period of Performance: 08/15/2025 to 10/31/2025

0001 Services for tree planting and tree protection 1025 AC tube installation on approximately 1025 acres.

Product/Service Code: F005

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- FOREST TREE PLANTING

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice

Processing Platform (IPP), https://www.ipp.gov.

If the contractor lacks an IPP account, USDA will automatically initiate the enrollment process with Treasury using the contractor's SAM.gov

Accounts Receivable POC as the IPP account holder. Once the enrollment process is complete, the IPP account holder will receive notification and can be invoiced. More information about IPP can be found at: https://www.ipp.gov

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Las Dispensas Reforestation 2025

THE SCHEDULE OF ITEMS

SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

BID

ITEM

UNIT

NAME DESCRIPTION

QUANTITY

ESTIMATED

(ACRES)*

BID

$/ACRE

AMOUNT ($)

($/ACRE x ACRES)

1.1 All Units Planting and install

mesh vexar or solid protection tubes

TOTAL FOR

BID ITEM $

Note: The Bid item will be awarded to the acceptable bidder with the best value to the Government. *Due to site variability (plantability) and seedling availability, quantity (acres) may vary +/-20 percent. Payment will be made on actual acres planted.

****Please include all applicable taxes in your quote****

POINT OF CONTACT: Shavera Leveille; email address: shavera.leveille@usda.gov

CONTRACTOR NAME, PHONE, EMAIL, & SAM Unique ID# _____________________________________

CONTRACTOR AUTHORIZED SIGNATURE:___________________________________________________

DEADLINE FOR RESPONSE TO THIS FAIR OPPORTUNITY OFFER: 1700 Mountain Time June 5, 2025 COMPLETED OFFERS (this form) WILL BE PROVIDED TO THE CONTRACTING SPECIALIST, Shavera Leveille BY EMAIL NO LATER THAN DEADLINE DATE ABOVE TO:

shavera.leveille@usda.gov

DELIVER GOODS TO: Las Vegas Ranger Station, 1926 N. 7th Street, Las Vegas, NM 87701

DISTRICT CONTACT: Kenneth Reese, (505)438-5451, kenneth.reese@usda.gov

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

Las Dispensas Reforestation 2025

C.1 - INTRODUCTION

C.1.1 Background

The Pecos/Las Vegas Ranger District of the Santa Fe National Forest in northern New Mexico needs tree planting services to reforest lands burned after the 2022 Hermit Peak Calf Canyon wildfire. Tree survival and growth is dependent on the initial health of the tree seedlings, the way trees are handled and planted, environmental conditions such as soil moisture and weather, and influences of animal damage to the seedlings. The services secured with this contract will focus on the need to provide appropriate tree handling and planting techniques during a period when environmental conditions are most favorable to ensure tree survival.

C.1.2 Scope of Contract

The solicitation is for tree handling, tree planting, and tree protection installation services on the Pecos/Las Vegas Ranger District of the Santa Fe National Forest. The Forest expects to plant 185,000 seedlings on approximately 1025 acres. These quantities may vary by +/-20% depending on the number of seedlings delivered and plantability of the project area. Mesh vexar seedling protection tubes, protex solid tube tree protectors or similar products will be used for tree protection from animal damage and harsh environmental conditions.

The Contractor shall furnish all labor, equipment, quality control inspections, supervision, transportation, seedling and supply transport, supplies (except those designated as Government furnished), and incidentals to perform all work necessary on the areas specified in the contract. All aspects of the work program shall be performed in an organized, systematic manner to assure services shall be performed over the entire unit.

C.1.2.1 This contract is a performance based, firm-fixed price contract.

C.1.2.2 The performance period will begin approximately mid-August to early September. This date is weather and site dependent. If monsoonal moisture is determined to be inadequate for good tree survival at that time, the start date of the contract could be moved to mid-September or later.

C.1.3 Description, Location and Access.

All items were burned in a 2022 wildfire. Safety Alert: Contractor needs to be aware that there are snags and burned trees at all planting sites that have the risk of falling or falling debris, especially during windy conditions.

Not all of the acreage is plantable, portions of units may be too rocky for planting. Units may have 15-35 percent brush and grass/forb cover. See Section J, Exhibit 1 for additional information on bid items.

C.1.3.1 Access Routes and Delivery Point

The Delivery Point is the Las Vegas Ranger Station at 1926 N. 7th Street, Las Vegas, New Mexico. See Vicinity Map.

The planting area has several access points to each of the five project locations.

Unit A is approximately 22 miles (about 35 minutes from Las Vegas Ranger Station (delivery point, see maps in Section J). Directions to the planting area are as follows. From the Las Vegas Ranger Station head north (turn right) onto 7th street/NM-518 N for 11.5 miles. Turn left onto NM-94 for 0.7 miles. Turn left onto NM-266 for 5.9 miles.

Turn right onto CO RD A3A for 3.1 miles. Turn left onto Forest RD 634 for 0.2 miles to planting unit.

Unit B (southern access) is approximately 20 miles (about 40 minutes) from Las Vegas Ranger Station (delivery point, see maps in Section J). Directions to the planting area are as follows. From the Las Vegas Ranger Station head north (turn right) on 7th street/NM-518 for 8.6 miles. Turn left onto CO RD A3 for 6.7 miles. Turn left onto Country RD A2 for 1.1 miles. Continue straight onto Forest RD 637 for 1.3 miles. At intersection turn north (right) on Forest RD 637 for 1.8 miles to Forest RD 637F. Travel north on Forest RD 637F for 0.4 miles to planting unit.

Unit B (northern access) is approximately 22 miles (about 40 minutes from Las Vegas Ranger Station (delivery point, see maps in Section J). Directions to the planting area are as follows. From the Las Vegas Ranger Station head north (turn right) onto 7th street/NM-518 N for 11.5 miles. Turn left onto NM-94 for 0.7 miles. Turn left onto NM-266 for 5.9 miles. Turn right onto CO RD A3A for 1.1 miles. Turn left onto Forest RD 634 for 2.35 miles. Turn left onto Forest RD 634CA for 0.5 miles to planting unit.

Units C is approximately 18 miles (about 35 minutes) from Las Vegas Ranger Station (delivery point, see maps in Section J). Directions to the planting area are as follows. From the Las Vegas Ranger Station head north (turn right) on 7th street/NM-518 for 8.6 miles. Turn left onto CO RD A3 for 6.7 miles. Turn left onto Country RD A2 for 1.1 miles. Continue straight onto Forest RD 637 for 1.3 miles. At intersection turn north (right) on Forest RD 637 for 0.3 miles to planting unit.

Units D, E, and H are approximately 22 miles (about 45 minutes) from Las Vegas Ranger Station (delivery point, see maps in Section J). Directions to the planting area are as follows. From the Las Vegas Ranger Station head north (turn right) on 7th street/NM-518 for 8.6 miles. Turn left onto CO RD A3 for 6.7 miles. Turn left onto Country RD A2 for 1.1 miles. Continue straight onto Forest RD 637 for 1.3 miles. At intersection turn south (left) on Forest RD 637A for 3.0 miles to 4x4 high clearance road. Travel south on 4x4 high clearance road for 1.4 miles to planting units.

Units I, J, and K are approximately 17 miles (about 40 minutes) from the Las Vegas Ranger Station (delivery point, see maps in Section J). Directions to the planting area are as follows: From the Las Vegas Ranger Station head south (turn left) on 7th Street for 0.5 miles. Turn right on Mills Ave. In 0.8 miles turn right onto State Route 65/Hot Springs Blvd. Continue for 15.1 miles to FSRD 156. Turn left, the planting project is 0.6 miles ahead.

Units F and G are approximately 18 miles (about 45 minutes) from the Las Vegas Ranger Station (delivery point, see maps in Section J). Directions to the planting area are as follows: From the Las Vegas Ranger Station head south (turn left) on 7th Street for 0.5 miles. Turn right on Mills Ave. In 0.8 miles turn right onto State Route 65/Hot Springs Blvd. Continue for 12.9 miles to NM HWY 65. Turn right onto NM HWY 65 for 2.7 miles and go to El Porvenir campground. Travel on 4x4 high clearance road for 0.9 miles to the planting project.

SECTION C2 – DEFINITIONS

Acceptable established tree: An existing conifer of seedling and/or sapling size that is of good form, color, free of damage, has 50% or greater crown ratio, and is the species and size specified in the Detailed Information Chart, Exhibit 1.

Acceptable Service: A job performed to the standard and within the acceptable quality level. The Contractor must do the specific job, and meet the standard, and meet the acceptable quality level before one can say that performance is acceptable for payment.

Acceptable Quality Level (AQL): The maximum allowable deviation from perfect performance that may occur before the Government will invoke payment deduction. An AQL does not allow a contractor knowingly to offer defective service, but limits reduced payment to circumstances in which defective performance results in a measurable reduction in the value of services rendered.

Access Point: The point identified for access to planting areas.

Animal Damage Control: Methods for protecting the seedlings from animal damage, particularly big game. May include tree protection shelters.

Best Value: One criterion used for selecting a service contractor for award, based on comparison of the service price offered, with the quality of service offered.

Calendar Days: Every day shown on the calendar, Sundays and holidays included.

Clearing: Removal of surface debris around the planting hole to avoid debris from falling into the hole. Debris includes duff, litter, rotten or charred wood, moss, loose rock, ashes, snow, and surface frost.

Contracting Officer (CO): A Government employee with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer acting within the limits of their authority as delegated by the Contracting Officer.

Contract Time: See Period of Performance.

Container plug: Seedling grown in a receptacle containing soil and nutrients. When the container seedlings are extracted from the receptacle, the soil stays intact around the roots. The soil and roots together are referred to as the container plug; the soil is the container media.

Contracting Officer’s Representative (COR). A Government person appointed by the contracting officer (CO) to help the CO with the contract administration and surveillance. The duties and responsibilities of a COR are defined in the letter of designation by the CO.

Delivery Point: The point identified for delivery of trees and other supplies. If there are multiple points of delivery of various items, it will be so noted.

Defective Service. A unit of service that contains one or more defects, or nonconformance with specified requirements.

Drip line: The line extending vertically from the exterior edge of a tree’s live crown to the ground.

Foreign material (in the planting hole): Large rocks, sticks, litter or similar material not part of the surrounding soil substrate that is in the planting hole after the tree is planted.

Ground line of tree before planting: The original ground line of the tree before planting is the soil surface level in the nursery beds or in the container receptacle. It is between the cotyledon scar and the root collar.

Group planting: Create patchy tree arrangements with tight tree groups between unplanted areas, to provide seed source and more closely mimic natural regeneration patterns in certain forest types. The unplanted acres are expected to randomly fill in with natural tree regeneration over time, and/or be planted some years later, for an uneven-aged forest structure with a grouped arrangement across the unit.

Inbox temperature: The temperature near the center of the box of trees measured with a probe thermometer or similar instrument. This is the temperature of the seedlings while in the shipping box.

Lateral roots: The horizontal roots extending from the main vertical (tap) root.

Microsite: A plantable spot favorable to seedling survival and growth. Examples of favorable microsites are stumps, down logs, large slash, snags, and standing cull trees that provide protection from sun, wind, animals, and other damaging agents. Priority for microsite selection, from highest to lowest, is fallen log, stump, and standing dead (as the latter may uproot and lift the seedling out of the ground). Seedlings shall be planted on the north and east sides of the shade structure.

Period of Performance (also Performance Period or Contract Time): The number of calendar days allowed in the contract for completion of the contract work. Includes all days of the week including weekends and holidays.

Plantable spot: An area where a tree can be planted in accordance with all specifications in the contract. In the Planting Inspection method, a plantable spot is also any area where the contractor has planted a tree.

Planting Inspection: The standard planting inspection procedure as described in Forest Service Handbook, R3 Supplement 2409.17 (effective 5/31/2002), 2.82 part 2 (refer to Section C.5.1 for internet access) and provided in Exhibit 3.

Protection: Natural and artificial materials that act as an obstacle protecting the tree from animal or other injurious agents. The protection material and effort required by the planter to protect the tree varies depending on the site conditions of each unit.

Quality Assurance: Those actions taken by the Government to assess the Contractor’s results to determine that they meet contract requirements. The methods for quality assurance are described in the Quality Assurance Surveillance Plan (QASP).

Quality Assurance Surveillance Plan (QASP): An organized written document used for quality assurance surveillance. The document contains specific methods the Government will use to perform surveillance of the contractor.

Quality Control. Those actions taken by a contractor to control the performance of services so that they meet the requirements of the PWS. The methods for inspecting for quality control are described in the Contractor’s Quality Control Plan (QCP).

Residual Tree: Live trees remaining in the unit after the harvest or fire activity.

Root Length: The length of root measured from the original ground line to the end of the main vertical tap root.

Satisfactorily Planted Tree: A tree that is planted in accordance with C.4.4.1.

Scalping: The removal of live vegetation, including roots, to reduce competition from existing vegetation and to expose mineral soil. The diameter of the scalp and the maximum depth of the scalp are specified in the Detailed Information Chart, Exhibit 1.

Shade: Natural and artificial materials that protect the trees from the sun’s heat and wind. See Microsite.

Stationary Material: Natural material used to shade or protect the tree that is not movable by the planter. Natural stationary material includes items such as stumps, logs, dead brush, rocks, or terrain features used to provide the required protection to the tree. Stationary material generally offers the most shade and protection for seedlings from the sun and animal trampling.

Seedling Protection Tube: A mesh or solid plastic or plastic-like material formed into a tube that is placed over a seedling to provide protection from animal browse or desiccation. It may be secured with a stick to the ground or have staking legs attached to the base. Assembly may be required.

Top Height: The length from the original ground line to the top of the terminal leader; does not include needles extending above the leader.

Transportable Shade: Natural material such as wood debris that can be moved to the planting spot to shade the tree from the sun.

Trees in Possession of the Contractor: The time after trees have been issued to the Contractor. During this time, the Contractor is responsible for all aspects of tree care and accountable for tree quantities.

Unplantable Spot: An area where a tree cannot be planted satisfactorily, and no tree has been planted. An allowance is given in the standard R-3 Planting Inspection for unplantable spots within the plot. In hoe planting, a spot is considered unplantable if a suitable spot for planting a tree cannot be found after three attempts of throwing the hoe, and if the hole cannot be opened at the spot with five swings or less.

Unsatisfactory Planted Tree: A planted tree which fails to meet one or more of the specifications of a satisfactorily planted tree (see C4.4.1). Refer to definitions for planting violations described by R-3 Planting Inspection. Refer to planting violations as described in FSH 2409.17, 2.82 provided in Exhibit 5, Reference E.2.2.

Walk-in Unit: A unit that is not directly accessible by an open road, where the distance between an open road and the nearest point of the unit exceeds ¼ miles. Distances are measured using GIS, they are a straight line and measured as a horizontal distance.

Wasted Material: Material provided to the Contractor to conduct a task such as installing tree shelters that are lost, dropped, or damaged by the Contractor, or which are installed on trees not in accordance with the requirements of the contract.

Wasted Tree: A tree which is lost, damaged, destroyed or handled contrary to the standards for care of trees.

Planted trees that exceed the maximum number of trees in the R-3 Planting Inspection plot procedure are also considered wasted trees.

C.3 – GOVERNMENT FURNISHED PROPERTY and SERVICES

The Government will provide the following items of Government property and services to the Contractor for use in in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract.

The property and services that will be provided by the Government are as follows:

Item Description Where, When, How

3.1 Detailed Information Chart Chart with unit specifics Provided in Solicitation, also provided in Exhibit 1.

3.2 Project Maps Maps of planting units with

access roads, access point(s) identified, and vicinity map

Provided in solicitation, also provided in Exhibit 2A-2B

3.3 Access Roads The Government will provide

access to the access point(s).

The Government will initially clear down trees from the

At least one Forest Service Road to access each unit.

access roads. Access roads are accessible by 4-wheel drive vehicle equipped for mountain driving.

3.4 Access behind locked gates Some units may be behind

locked gates. The Government will provide access through locked gates unless walk-in is required. Refer to C.4.1.4.

A key will be issued

3.5 Trees – planting stock Container Grown Trees: Length

of container plug will range from 5 to 9 inches. Top heights range from 3 to 12 inches. At least 90% of the trees will meet these specifications.

Provided on written order with sufficient advanced notice.

Available at delivery point.

Contractor is responsible for transport to planting units.

3.6 Seedling racks and seedling

cells

Some container stock will be in plastic racks and cell container.

These must be undamaged and returned to the delivery point.

Mora Nursery Delivery Point

3.7 Seedling protection tubes

and accessories

Protection tubes, bamboo sticks, or any other item necessary for installation.

Available at Las Vegas delivery point. Contractor is responsible for transport to planting units.

3.8 Electronic files of all unit

boundaries

Files for use in tablets and phones

Will send .pdf files for use in Avenza

3.9 Planting Inspection Sheet Form R3-2470-9. Quantity

necessary to inspect the contract. [OR one copy provided, to be duplicated by contractor]

Provided at Pre-work meeting.

Sample provided in Exhibit 3.

3.10 Campsite, if requested. See Section C.4.3.1.1 and

Section H

Permit issued by District within 5 working days of advanced request.

C.4 – CONTRACTOR WORK REQUIREMENTS and STANDARDS

C.4.1. General.

C.4.1.1 Road Access. The Contractor may access the units from forest roads indicated on project maps. After initial clearing of the access roads by the Government, the Contractor shall clear any subsequent falling of trees that block roads needed to access units. Four-wheel drive vehicles are highly recommended. The COR will approve the use, and conditions of use, of any road not shown on the project or unit map.

C.4.1.2 The Contractor may transport trees off-road to or within a planting unit consistent with any restrictions on motorized vehicles and with COR approval. Any motorized vehicle approved for off-road use must be cleaned, free of soil, vegetative matter, or other debris that could contain or hold seeds and free of leakage. No off-road use will be approved during periods where soil damage may occur or in stream protection zones.

C.4.1.3 Walk-in Units. The unit cannot be accessed from open forest roads. The Contractor shall transport trees to the unit using the method of his/her choice consistent with any restrictions on motorized vehicle and with COR approval.

C.4.1.4 Locked Gate. In cases where units are behind locked gates, the Contractor shall close and lock gates after entering or exiting each gate and will be subject to all other restrictions of administrative use. The Contractor is permitted to drive from the locked gate to the unit access point with only the minimum number of vehicles necessary for efficient transport of the crew.

C.4.1.5 Cultural and Historic Sites. All cultural and historic sites will be protected, no tree planting will occur within protected sites. Site boundaries will be identified and flagged (white flagging) by the Forest Service prior to operations.

C.4.1.6 Tree Orders and Delivery. The Contractor shall order in advance of desired delivery according to agreement with COR. The Contractor is responsible for transporting of all government issued supplies and seedlings to and from the delivery point and planting sites.

C.4.1.6.1 Returned Trees. The Contractor shall plant all trees ordered and delivered to the planting unit within 24 hours of delivery unless otherwise approved by the COR. Trees shall not be returned to the Government for cooler storage unless approved by the COR. When the COR determines that conditions are unsuitable for planting, the Contractor shall return all unplanted trees to the delivery point with no penalty for delay in planting the delivered trees.

C.4.1.7 Return Government Equipment. The Contractor shall return unused Government supplies, unplanted trees, all packaging materials, and wrapping materials to the delivery point daily.

C.4.1.8 Disposal of Trash. The Contractor is responsible for the proper disposal of their trash.

C.4.1.9 Invasive Plant Control. Contractors shall ensure that prior to bringing any tools and gear to a work site, they are free of all soil, vegetative matter or other debris that could contain or hold seeds. Tools and gear include, but not limited to, the following: augers, shovels, hoedads, clothing and boots.

C.4.2 Tree Handling and Care

C.4.2.1 The Contractor shall be responsible for the care of trees from the delivery point and throughout the time that the trees are in possession of the Contractor to assure they are properly cared for and not damaged or exposed to damaging conditions consistent with FSH2409.17, 2.53 parts 6 and 7, provided in Exhibit 4 Reference.

C.4.2.2 Trees not properly cared for may be considered wasted trees.

C.4.2.3 While in the possession of the Contractor, tree boxes SHALL NEVER be stacked greater than 4 boxes high to prevent crushing and damage, especially during transport. Boxes shall be placed and/or staked horizontally as to maintain the same orientations as delivery point. Boxes shall not be thrown or dropped.

C.4.2.4 Contractor shall not alter the trees (includes no root or top pruning).

C.4.2.5 Contractor shall take protections to keep roots moist during the planting operation.

C.4.2.6 The Contractor shall be aware of environmental hazards which affect tree survival; he/she shall alter crew work schedules and tree handling practices to allow planting whenever possible. Environmental hazards are described in FSH 2409.17, 2.53 part 8 and 2.82 part 1c and provided in Exhibit 4.

C.4.2.7 The Contractor shall maintain the internal box temperature of tree boxes that are in possession of the Contractor at or below 40 degrees Fahrenheit.

C.4.3 Tree Planting

C.4.3.1 Satisfactorily Planted Tree. Trees shall be planted satisfactorily both above and below ground as defined in FSH 2409.17, 2.67. Trees shall be planted in moist soil, free of foreign debris, and in a hole deep enough to accommodate the fully extended tree roots and shall meet all requirements of the contract. The open-hole method shall be used as described in FSH 2409.17, 2.63, and provided in Exhibit 4.

C.4.3.2 Clearing and Scalping. Each planting spot shall be free of surface debris and competing vegetation consistent with FSH 2409.17, 2.62, parts 1 and 2. The minimum clearing and scalping diameters and the maximum clearing and scalping depths are stated in the Detained Information Chart, Section J, Exhibit 1. After the tree has been planted, surface material must be pushed back over the cleared surface to serve as mulch. The sizes may differ from those stated in FSH 2409.17, 2.62.

C.4.3.3 Shade. Trees shall be planted in the best microsite available to mitigate problems associated with hot, dry aspects, consistent with FSH 2409.17, 2.61, parts 2 and 3a, and unit specific shade requirements as identified in Detailed Information Chart, Exhibit 1 and Shade Requirements, Exhibit 1A. Each tree shall be as close to the shade material as possible or within a distance that is less than ½ the height of the shade.

C.4.3.3.1 Planted trees shall be shaded consistent with the shade requirement identified in the Detailed Information Chart, Section J, Exhibit 1.

C.4.4.3.2 When shade is required, each tree shall be shaded at the ground level from the afternoon sun (approximately 2-4 pm), except on east facing slopes when the tree shall be shaded from the morning sun.

C.4.4.3.3 When transportable (shade) material is required, it must be at least 3 inches in diameter, and be within 100% of the spacing distance to the planted tree. Do not place shade on the uphill side of a planted tree where it can roll on to the tree.

C.4.3.4 When seedling protection shelters are required, shelters should be installed vertically (+/- 15 degrees) with the base of the shelter flush with the ground. Shelters shall be installed so as not to damage the seedling, including skinning the bark, breaking the leader, damaging roots, or needle stripping. The terminal bud of the seedling must be unattached to the shelter. The shelters shall be installed during the same day the trees are planted.

C.4.3.4.1 Tree shelters manufactured of plastic mesh or solid plastic sheet will be secured with a single bamboo stake. Bamboo stake is to be woven on one side at least three times to ensure vertical support. The tube shall be placed around the planted seedling with the bamboo stake on the uphill side of seedling. A landscape staple will be placed in the ground opposite the bamboo stick to further secure the protection tube to the ground. Both the bamboo stick and staple must be installed as to not cause root damage and be deep and firm in the ground. The bamboo stick must be at least 8 inches deep, and the staple at least 4 inched deep into the ground.

C.4.3.5 Trees shall be planted to achieve the average spacing specified in the Detailed Information Chart, Section J, Exhibit 1. It is expected that an irregular distribution will result as planters avoid acceptable established trees, rock or shallow soils and seek planting spots in the best microsites and soil conditions. For individual trees, the spacing may be varied as much as 50 percent in any direction to attain the best plantable spot. The number of trees planted shall not be materially changed by the method of selecting planting spots.

C.4.3.6 Acceptable Established Trees. A tree shall not be planted in direct competition with an acceptable established tree. Refer to the Detailed Information Chart, Exhibit 1 for species and size of acceptable trees. Do not plant a tree closer than 50% of the established spacing to an acceptable established tree.

C.4.3.7 Residual Trees. Trees shall not be planted within the immediate influence of established larger trees in the unit. Do not plant within the dripline plus the distance of the spacing of a live residual conifer tree with at least 20% live crown.

C.4.3.8 Species Mix. Where a mixture of species is required, the Contractor shall distribute the variety of species over the entire unit except where otherwise noted on the Detailed Information Chart, Section J, Exhibit 1. The COR may also dictate or alter specific species mix for varying site conditions.

C.4.3.9 Trees Not Meeting Specifications. The Contractor is not obligated to plant trees that do not meet the specifications in C.3.4, and they shall be returned to the Government. If trees not meeting specifications are planted, they shall be planted satisfactorily.

C.4.3.10 Quality Control. Those actions taken by a contractor to control the performance of services so that they meet the requirements of the PWS. The Contractor shall prepare a Quality Control Plan as described in Section E.

The Contractor shall inspect the work in accordance with the accepted Quality Control Plan.

C.4.3.11 The Contractor shall prepare a work plan and schedule that demonstrates that work will be completed within the performance period described in Section F. The Contractor shall provide a general plan with the technical proposal. A supplementary plan and schedule shall be provided after contract award, but at least 5 days before start work.

The Contractor shall update the work plan as work is in progress to account for changes; and the updated work plan may be accepted by the Contracting Officer.

C.4.3.12 Camping and Worksite Conditions. The Contractor shall prepare a Camping and/or Worksite Plan and operate in a manner that will protect the environmental resources and the public facilities. The conditions will be consistent with the requirements of Section H, Section I.

C.4.3.13 Communications. The Contractor shall keep the Contracting Officer advised as to where the Contractor can be reached prior to start of Contract Time. Further, the Contractor shall maintain contact with the Contracting Officer during periods of work suspension to reduce any delay in resuming planting and to determine the best suitable time and conditions to resume planting.

C.4.3.14 On-site Representative. The Contractor’s on-site representative shall be fully conversant and literate in the English language and shall be in the work area whenever work is in progress. Refer to F.3 Superintendence by the Contractor. The Contractor’s Inspector shall also be conversant and literate in the English language.

C.4.3.15 Crew Safety. The Contractor shall consider and address crew safety and provide a Safety Plan consistent with FAR 52.236.13 Accident Prevention Alt. I, recognizing that all subitems may be in areas of snags and fire burned trees.

C.4.3.16 Special Restrictions. Along boundaries adjacent to cliffs: shouting, creating loud noises, loitering or taking rest breaks is prohibited. Do not move large rocks or logs. Do not plant trees on roads, hiking trails, or animal trails.

C.5 STANDARDS

C.5.1. Mandatory Standard. The following sections from the Forest Service Handbook, R3-Supplement 2409.17- 2002-1 (effective 4/29/2002), Chapter 2 – Reforestation, are mandatory for execution of this contract.

Sections: 2.53 parts 6-8, 2.61, 2.62 parts 1 and 2, 2.63, 2.66, 2.67, and 2.82 parts 1.c and 2.

Sections mandatory for contract execution are provided as guidelines; the complete handbook is available at:

http://www.fs.fed.us/im/directives/field/r3/fsh/2409.17/2409.17_2.01_2.5.doc http://www.fs.fed.us/im/directives/field/r3/fsh/2409.17/2409.17_2.6_2.9.doc

C.5.2. Non-Mandatory Standard. The following references do not supersede direction given in C.5.1 or requirements set forth in this contract but provide background and supporting information that may be useful to a prospective offeror.

C.5.2.1. The Forest Service Handbook, R3-Supplement 2409.17-2002-1 (effective 5/31/2002), Chapter 2 – Reforestation exclusive of the sections listed in C.5.1. The handbook is available at the website specified in C.5.1.

C.5.2.2. Tree handling and planting procedures that are acceptable are like those generally accepted for planting seedlings in forested conditions. There are a number of references describing the care and planting procedures.

One reference is Reforestation Practices in Southwestern Oregon and Northern California (eds. Stephen D. Hobbs, Steven D. Tesch, Peyton W. Owston, Ronald E. Steward, John C. Tappeiner II, Gail E. Wells), Oregon State University Corvallis, Oregon. Specifically refer to Chapter 14, Seedling Handling and Planting by Robin Rose, pp. 330, 334-343.

C.6 PERFORMANCE REQUIREMENTS SUMMARY (PRS)

The following describes the major items in the contract with the consequences for meeting or not meeting the performance standard for the work described. Items below are included here as described.

Work Statement

Performance Standard Government Method of Assessment

Consequences for Meeting or not Meeting Performance Standard

C.4.2 Tree Handling and Care

Trees are properly handled and cared for as outlined under C.4.2 Tree Handling and Care and consistent with FSH 2409.17, 2.54 parts 4 through 7.

When violations occur, Contractor takes corrective action immediately.

COR and Inspector will monitor operations and conduct random samples.

-The Contractor’s care and handling of trees will affect the performance assessment as either a positive or negative incentive.

-If contractor does not meet the standard and/or take corrective action, the Government may collect damages (Section G.4) and provide adverse performance assessment.

C.4.3 Tree Planting

-Planting quality meets or exceeds performance standard of 92% quality.

COR or inspector will conduct periodic inspections consisting of plots consistent with R-3 Planting Inspection (FSH 2409.17, 2.82, part 2).

-The Contractor’s care and handling of trees will affect the performance assessment as either a positive or negative incentive.

-If Contractor achieves 93% planting quality or greater, full unit price is paid G.3.2.1.

If Contractor does not achieve at least 90% quality, is as per Section G.3. May result in adverse performance assessment.

http://www.fs.fed.us/im/directives/field/r3/fsh/2409.17/2409.17_2.01_2.5.doc http://www.fs.fed.us/im/directives/field/r3/fsh/2409.17/2409.17_2.6_2.9.doc https://www.fs.usda.gov/cgi-bin/Directives/get_dirs/fsh?2409.17!r3_ALL https://www.fs.usda.gov/cgi-bin/Directives/get_dirs/fsh?2409.17!r3_ALL

C.4.3.4 Shelter installation

- Shelters shall be installed properly, without damaging the seedling, and in concurrence with planting.

COR or inspector shall perform visual inspections and recorded on inspection sheet.

-Improper shade installation, seedling damage or untimely shade installation will result in shade violations recorded during inspection plots.

-If Contractor does not meet 93% quality or greater, reduced payment shall be made in accordance with Section G. May result in adverse performance assessment.

C.4.3.10 Quality Control

-Contractor maintains good quality control on all aspects of operation including tree handling, planting and shelter installation. Actions not consistent with contract specifications are corrected as per the Quality Control Plan.

COR or inspector randomly sample and observe operations.

-The quality of Quality Control provided by the Contractor will be reflected in the performance assessment as either a positive or negative incentive.

-If the Contractor fails to meet standards, work may be suspended, or the Contractor put in Default for failure to take corrective action immediately and result in adverse performance assessment.

C.4.3.10 Quality Control

-Contractor’s plot inspections are +/- 5% of Government’s quality.

Inspection completed to meet timeframes. Inspection records are complete and accurate.

COR or inspector randomly sample and observe Contractor inspections. Reviews Contractor inspection sheets daily.

-The ability of the Contractor to meet the standard will be reflected in the performance assessment as either a positive or negative incentive.

-When Contractor’s plot inspections meet standards, no deduction.

-If quality does not meet standard, deduction (Section G.3 & G.4) and/or damages will be assessed.

Work Plan and Schedule C.4.3.11

Work meets schedule as per the accepted Work Plan.

COR and Inspector conduct periodic monitoring.

-The Contractor’s ability to maintain the work schedule and complete work on schedule will be reflected in the performance assessment as either a positive or negative incentive.

Work not completed on schedule is subject to Default and may result in assessment of actual costs.

SECTION E--INSPECTION AND ACCEPTANCE

E.1. CONTRACTOR QUALITY CONTROL

E.1.1. Quality Control Plan. The Contractor shall provide a Quality Control Plan (QCP) with the technical proposal.

The Contractor shall supplement the QCP within 5 days of contract award based on items awarded to the Contractor and Government comments.

The general Quality Control plan must demonstrate how the Contractor will assure quality meets the requirements and specifications of the contract. It shall specify how quality will be monitored to assure the performance standards are met; the supervision of crew and work; and the personnel that will be performing the quality control. Quality control includes the monitoring of quality while work is in progress and an unbiased sample of planting, artificial shade, and protection shelters for determining actual quality percentage. The Contractor shall have at least one experienced, fluent in English, inspector whose duties do not include supervision or planting duties.

E.2.2. Plot Inspections- Tree Planting. The Contractor shall maintain a plot system that provides an unbiased sample of planting quality, and which represents the entire area planted. The plot system shall be consistent with the Planting Inspection Methods, specified in FSH 2409.17, 2.82, part 2, provided. The Contractor shall sample at least 1-percent of the planted area, with a minimum of 5 plots per unit.

The Government may observe or re-examine the Contractor’s plots at any time. Tree Shelter installation shall be included in the inspection of planting.

E.2.2.1. The Contractor shall mark and identify each inspection plot on the ground.

E.2.2.2. The Contractor shall provide written inspection data by unit using the Planting Inspection Sheet (R3-2470- 9), Exhibit 3, and shall provide a sketch map of the unit with plot locations. The Contractor may also provide a GPS waypoint file of the plot location. Planting inspection sheets and maps shall be provided to the Government by 8 a.m. the day after inspection or end of workday and shall be signed and dated by the person who conducted the inspection, certifying that the inspection records are complete and accurate.

E.2.2.3. The planting quality percent shall be based on the following calculation (reference columns of Planting Inspection…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .