This is an addendum to RFB #2504 issued by Kenosha County for the Kemper Center Roof Replacement project, dated January 29, 2025. The addendum addresses a single question regarding gas piping, clarifying that the removal and re-installation of gas piping is the responsibility of the awarded contractor. The document includes a series of project site photos showing various aspects of the existing roof conditions.

The site photos document the current state of the roof, showing a flat roof surface with EPDM membrane, various penetrations including gas piping, chimneys, and vents, flashing details, gutters, and the overall building structure which appears to be a historic brick building located near a waterfront. The photos provide detailed views of the roofing membrane condition, parapet walls, drainage systems, and architectural features that will need to be addressed during the roof replacement project. The building consists of both tan/cream colored brick portions and white-painted sections with a mix of flat and sloped roof areas.

View the file

Other files

File Type Posted
Vendor Responsibility Form Construction.pdf PDF
2504 Drawings.pdf PDF
2504 Bid Documents.pdf PDF
2504 Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFB #2504 Addendum One Page 1 of 1

Yes.

Questions and Answers:

Q. Would the County consider removing and re-installing the gas piping?

A. No, removing and re-installing the gas piping is the responsibility of the awarded Contractor.

Attachments:

Project Site Photos

End Addendum 1