The document is an Invitation for Bid (IFB) from the Unified Government of Athens-Clarke County, Georgia for the purchase and installation of a cascade system for the Fire Training Center. The project consists of providing a 6000 psi compressor, storage cylinders, and related equipment. Bids are due by 3:00 PM ET on Monday, August 5, 2024, and the Unified Government expects to award the contract within 7 days of the bid opening. The successful contractor will be required to commence work within 10 calendar days of receiving the notice to proceed and complete the project within the number of calendar days proposed in the bid.
The IFB specifies that the bid price must include the cost for installation and training, and that payment and performance bonds in the amount of 100% of the contract total will be required. Bidders must provide information on their qualifications and experience, and the Unified Government reserves the right to reject any and all bids. The project is funded by the Unified Government, and there are no set-asides or specific funding amounts disclosed.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE: July 2, 2024
TO: GENERAL CONSTRUCTION CONTRACTORS
SUBJECT: BID #25015 Fire Training Center Cascade System
You are invited to submit a bid for BID #25015 Fire Training Center Cascade System for the Unified Government of Athens-Clarke County (ACCUG).
The project consists of purchasing and installing a cascade system for the Fire Training Center.
The estimated cost of this project is $65,000.00.
Inquiries regarding Bids should be made to Rena Durie, Senior Buyer, (762) 772-1483 or rena.durie@accgov.com. Technical questions may be directed to Battalion Chief of Support Services Jonathan Pou, at 706-614-1565 or email: Jonathan.Pou@accgov.com.
Attached hereto are the bid form, bid specifications, and general instructions.
The written specifications contained in this bid shall not be changed or superseded except by written addendum from the Unified Government of Athens-Clarke County Purchasing Division of the Finance Department. Failure to comply with the written specifications for this bid may result in rejection of the bid by the Unified Government of Athens-Clarke County.
Bids are to be sealed, marked with the bidder's name and address and labeled: "Bid #25015 Fire Training Center Cascade System” and delivered to:
The Unified Government of Athens-Clarke County Finance Department, Purchasing Division 375 Satula Avenue Athens, GA. 30601
Not later than 3:00 P.M. ET, Monday, August 5, 2024.
The Bidder shall affix to the outside of its sealed bid envelope, its Unified Government of Athens-Clarke County Vendor Number, its Georgia Contractor License Number, Bidder’s name, Bidder’s address, and project title.
A qualified interpreter for the hearing impaired is available upon request at least 10 (ten) days in advance of the bid opening date. Please call (706) 613-3088 for more information for the hearing impaired. This service is in compliance with the Americans with Disabilities Act (ADA).
It is the policy of the Athens-Clarke County government that no person or business shall be excluded from participation, denied the benefits of, or otherwise discriminated against in relation to the award and performance of any contract or subcontract on the grounds of race, color, creed, national origin, age, or sex.
The Unified Government of Athens-Clarke County reserves the right to reject any and all bids, to waive any technicalities or irregularities and to award the bid based on the highest and best interest of the Unified Government of Athens-Clarke County.
NEW
SUBMISSION FORMAT FOR
ACCUG BID DOCUMENTS
Jessica Beri Purchasing Administrator
THE UNIFIED GOVERNMENT OF ATHENS-CLARKE COUNTY
BID #25015
FIRE TRAINING CENTER CASCADE SYSTEM
For
ATHENS-CLARKE COUNTY FIRE DEPARTMENT
SUBMISSIONS ARE DUE AT THE ADDRESS SHOWN BELOW NO LATER THAN
3:00 P.M. ET, Monday August 5, 2024
FINANCE DEPARTMENT, PURCHASING DIVISION
375 SATULA AVENUE
ATHENS, GA. 30601
THE RESPONSIBILITY FOR SUBMITTING A RESPONSE TO THIS BID TO THE
PURCHASING DIVISION OF THE UNIFIED GOVERNMENT OF ATHENS-CLARKE
COUNTY ON OR BEFORE THE STATED DATE AND TIME WILL BE SOLELY AND
STRICTLY THE RESPONSIBILITY OF THE BIDDER.
ISSUE DATE: July 8, 2024
TABLE OF CONTENTS
SECTION I ................ BID SUBMISSION INSTRUCTIONS
SECTION II .............. INVITATION FOR BID OVERVIEW AND PROCEDURES
SECTION III ............. INSURANCE REQUIREMENTS FOR CONTRACTORS
SECTION IV ............. GENERAL CONDITIONS
SECTION V .............. SCOPE OF WORK
SPECIFICATON INDEX
00100 00200 00300 etc…..
SECTION VI ............. BID FORMS
SECTION VII ........... BID SCHEDULE
SECTION I – BID SUBMISSION INSTRUCTIONS
ALL BIDS RECEIVED WILL BECOME A PART OF THE OFFICIAL CONTRACT FILE AND MAY BE
SUBJECT TO DISCLOSURE UNDER THE OPEN RECORDS ACT.
A complete signed BID must include the documents listed below:
BID FORMAT: Bidders are expected to examine the specifications, price schedule, and all instructions. Failure to do so will be at the bidders’ risk. Each offeror shall furnish the information required by the solicitation. The BID SUBMITTAL must be signed by an officer of the company, who is legally authorized to enter into a contractual relationship in the name of the offeror.
MANDATORY DOCUMENTS CHECKLIST: Bidder must complete, execute and include with the bid the following Mandatory documents. BIDS RECEIVED WITHOUT THE MANDATORY DOCUMENTS MAY
BE REJECTED:
Section VI-A BID BOND Section VI-B BID FORM AND STATEMENT OF BIDDERS QUALIFICATIONS Section VI-C ACKNOWLEDGEMENT OF ADDENDA Section VI-D GEORGIA SECURITY & IMMIGRATION COMPLIANCE (GSIC) ACT AFFIDAVIT Section VI-E BID SCHEDULE Section VI-F AFFIDAVIT VERIFYING RESIDENCY STATUS OF AN APPLICANT (SAVE) Section VI-G CORPORATE CERTIFICATE Section VI-H PARTNERSHIP CERTIFICATE Section VI-I NONCOLUSSION AFFIDAVIT OF PRIME BIDDER Section VI-F SUBCONTRACTOR LISTING Section VI-G NONCOLLUSION AFFIDAVIT OF SUBCONTRACTOR
DUE WITHIN 24 HOUR OF THE BID OPENING BY THE APPARENT LOW BIDDER:
Section VI-I NON-COLLUSION AFFIDAVIT OF PRIME BIDDER Section VI-J SUBCONTRACTOR LISTING
Section VI-K NON-COLLUSION AFFIDAVIT OF SUBCONTRACTOR
BID SUBMISSION AND DELIVERY INSTRUCTION: ALL bid copies must be submitted in a sealed envelope or container with the OUTER MOST Container stating the Unified Government of Athens-Clarke County Vendor Number (ACCUG Vendor number), address, telephone number, the BID number and title (BID #25015 “Fire Training Center Cascade System”). If you do not know your vendor number, please call 706- 613-3088 or email: accpurchasing@athensclarkecounty.com If you do not have a vendor number, please fill out a bid list application found at http://www.athensclarkecounty.com/DocumentView.aspx?DID=256 so one may be issued to your company.
One (1) unbound marked original of the complete signed bid One (1) copy of the bid without pricing are to be delivered to:
The Unified Government of Athens-Clarke County Finance Department, Purchasing Division 375 Satula Avenue Athens, GA. 30601
Not later than 3:00 P.M. ET, Monday August 5, 2024
Hand delivered copies may be delivered to the above address only between the hours of 8:00 a.m. and 5:00 p.m.
ET, Monday through Friday, excluding holidays observed by the Unified Athens-Clarke County.
Bidders are responsible for informing any commercial delivery service, if used, of all delivery requirements and for ensuring that the required address information appears on the outer wrapper or envelope used by such service.
ALL ORIGINAL BIDS MUST BE UNBOUND: NO
STAPLES, PAPERCLIPS OR ANY TYPE OF BINDING
mailto:accpurchasing@athensclarkecounty.com http://www.athensclarkecounty.com/DocumentView.aspx?DID=256
INVITATION FOR BID #25015
FOR
FIRE TRAINING CENTER CASCADE SYSTEM
SECTION II – INVITATION FOR BID OVERVIEW AND PROCEDURES
A. PURPOSE
The Unified Government of Athens-Clarke County is soliciting Bids for 25015 Fire Training Center Cascade System from responsible contractors.
B. INFORMATION TO BIDDERS
1. BID TIMETABLE:
The anticipated schedule for the bid process is as follows:
Bid Documents Available………………………Monday, July 8, 2024 Deadline for submission of questions…………. 3:00 P.M. ET, Monday, July 22, 2024 Bid Opening…………………………………....3:00 P.M. ET, Monday August 5, 2024 Bids Valid Until ………………………………120 days after submission
2. CONTACT PERSON: The contact person for this BID is Rena Durie, Senior Buyer. Explanation(s) desired by offeror(s) regarding the meaning or interpretation of this BID must be requested from the contact person, in writing via rena.durie@accgov.com. Technical questions may be directed to Battalion Chief of Support Services Jonathan Pou, at 706-614-1565 or email:
Jonathan.Pou@accgov.com.
3. ADDITIONAL INFORMATION/ADDENDA: The Unified Government of Athens-Clarke County will issue responses to inquiries and any other corrections or amendments it deems necessary in written addenda issued prior to the bid opening date. Bidders should not rely on any representations, statements or explanations other than those made in this Invitation for Bid or in any addendum to this Invitation for Bid. Where there appears to be a conflict between the Invitation for Bid and any addenda issued, the last addendum issued will prevail.
Bidders must acknowledge any issued addenda. Bids which fail to acknowledge the bidder’s receipt of any addendum will result in the rejection of the bid if the addendum contains information which substantively changes the Owner’s requirements
Bidders who obtain this BID document from Georgia Procurement Registry or Athens Clarke County or from any source other than the Unified Government of Athens-Clarke County Purchasing are advised to re-visit the Georgia Procurement Registry site to obtain any addenda which may be issued. The Unified Government of Athens-Clarke County assumes no responsibility for Bidders’ failure to acknowledge any addenda issued.
4. LATE SUBMITTAL, LATE MODIFICATIONS AND LATE WITHDRAWALS
Bid submittals received after the bid opening date and time will not be considered. Modifications received after the bid opening date will not be considered. The Unified Government of Athens-Clarke County assumes no responsibility for the premature opening of a bid not properly addressed and identified, and/or delivered to the proper designation.
http://ssl.doas.state.ga.us/PRSapp/PR_index.jsp http://www.athensclarkecounty.com/index.aspx?NID=375 http://ssl.doas.state.ga.us/PRSapp/PR_index.jsp
5. WITHDRAWAL OF BID: A bidder may withdraw his bid before the expiration of the time during which bids may be submitted without prejudice to the bidder, by submitting a written request of withdrawal to the Purchasing Administrator.
6. REJECTION OF BIDS: The Unified Government of Athens-Clarke County may reject any and all bids and reserves the right to waive any irregularities or informalities in any bid or in the bid submittal procedure.
Bid submittals received after said time or at any place other than the time and place as stated in the notice will not be considered.
7. UNBALANCED BIDS: The Unified Government of Athens-Clarke County may reject a bid as non-responsive if the prices bid are materially unbalanced between line items or sub line items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Unified Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
8. DISCREPANCY IN UNIT PRICE: In case of discrepancy between a unit price and an extended price and total amount, the unit price will be presumed to be correct, subject, however, to correction to the same extent and in the same manner as any other mistake.
9. ACCEPTANCE OF BID (AWARD): It is the intent of the Owner to award a contract to the lowest responsible bidder provided the bid has been submitted in accordance with the requirements of the bidding documents and does not exceed the funds available. The Owner shall have the right to waive informalities and irregularities in a bid received and to accept the bid which, in the Owner’s judgment, is in the Owner’s own best interests.
The Owner shall have the right to accept Alternates in any order or combination, and to determine the low bidder on the basis of the sum of the base bid.
10. STATEMENT OF EXPERIENCE AND QUALIFICATIONS: The bidder may be required, upon request, to prove to the satisfaction of the Unified Government of Athens-Clarke County that he/she has the skill and experience and the necessary facilities and ample financial resources to perform the contract(s) in a satisfactory manner and within the required time. If the available evidence of competency of any bidder is not satisfactory, the Bid of such bidder may be rejected.
11. MINIMUM BID ACCEPTANCE PERIOD
Bids shall be valid and may not be withdrawn for a period of 60 days from the date specified for receipt of bids.
12. NON-COLLUSION AFFIDAVIT
By submitting a bid, the bidder represents and warrants that such bid is genuine and not a sham or collusive or made in the interest or in behalf of any person not therein named and that the bidder has not directly or indirectly induced or solicited any other bidder to put in a sham bid, or any other person, firm or corporation to refrain from submitting and that the bidder has not in any manner sought by collusion to secure to that bidder any advantage over any other bidder.
By submitting a bid, the bidder represents and warrants that no official or employee of the Unified
Government of Athens-Clarke has, in any manner, an interest, directly or indirectly in the bid or in the contract which may be made under it, or in any expected profits to arise there from.
13. GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT
By submitting a proposal and executing the attached affidavits, the offeror verifies its compliance with O.C.G.A. §13-10-91. The offeror further agrees to maintain records of such compliance and shall provide a copy of each such verification to Unified Government of Athens-Clarke County, at the time the subcontractor(s) is retained to perform such services.
14. COST INCURRED BY BIDDERS
All expenses involved with the preparation and submission of the bid to the Unified Government of Athens-Clarke County, or any work performed in connection therewith is the responsibility of the bidder(s).
15. AMERICANS WITH DISABILITIES ACT (ADA)
A qualified interpreter for the hearing impaired is available upon request at least 10 (ten) days in advance of the bid opening date. Please call (706) 613-3088 for more information for the hearing impaired. This service is in compliance with the Americans with Disabilities Act (ADA).
16. MINORITY BUSINESS ENTERPRISE POLICY STATEMENT: It is the policy of the Athens-Clarke County government that no person or business shall be excluded from participation, denied the benefits of, or otherwise discriminated against in relation to the award and performance of any contract or subcontract on the grounds of race, color, creed, national origin, age, or sex.
17. HOLD HARMLESS AND INDEMNIFICATION
The Bidder agrees, insofar as it legally may, to indemnify and hold harmless the Unified Government of Athens-Clarke County, its officers, employees and agents from and against all loss, costs, expenses, including attorneys' fees, claims, suits and judgments, whatsoever in connection with injury to or death of any person or persons or loss of or damage to property resulting from any and all operations performed by Bidder, its officers, employees, and agents under any of the terms of this contract.
18. ON SITE VISIT: Point of Contact for the On-Site Visit is Chief Jonathan Pou who can be reached by phone (706)614-1565 or email: Jonathan.Pou@accgov.com. Each bidder is responsible for inspecting the site and for reading and being thoroughly familiar with the contract documents. The failure or omission of any bidder to inspect the site shall in no way relieve any bidder from any obligation in respect to his bid.
19. BID OPENING: All bids will be opened in public and read aloud at the time and place of the bid opening.
20. COMMENCEMENT OF WORK AND WORK PERIOD: The Unified Government of Athens-Clarke
County expects to award the contract within 7 days of the bid opening date for work to commence (on exact date, if known, or within 60 workdays of award of contract).
21. INDEPENDENT CONTRACTOR: The contractor shall not be an employee of the Unified Government of Athens-Clarke County, but shall be an independent contractor. Nothing in this agreement shall be construed as authority for the contractor to make commitments which shall bind the Unified Government or to otherwise act on behalf of the Unified Government, except as the Unified Government may expressly authorize in writing.
22. BID SECURITY: Bid security shall be made payable to the owner in the amount of 5% of the bid sum. Security shall be an original bid bond issued by a surety licensed to conduct business in the State of Georgia, and be included on the Federal Approved Surety's List. The successful bidder's security will be retained until he has signed the Contract and furnished the required payment and performance bonds. The Owner reserves the right to retain the security of the other bidders until the successful bidder enters into contract or until 60 days after bids are received. If awarded bidder refuses to enter into a contract, the Owner will retain his bid security as liquidated damages, but not as a penalty. The bid security must be submitted with the Bid. Payment and Performance bonds in the amount of 100% of the contract total will be required if the contract is awarded.
23. EXECUTION OF CONTRACT: Each bidder shall be prepared, if so requested by the Owner, to present evidence of his experience, qualifications, and financial ability to carry out the terms of the Contract. Notwithstanding any delay in the preparation and execution of the formal Contract Agreement, each bidder shall be prepared, upon written notice of bid acceptance, to commence work within 10 days following receipt of official written order of the Owner to proceed, or on date stipulated in such order.
The awarded bidder shall assist and cooperate with the Owner in preparing the formal Contract Agreement, and within 10 days following its presentation shall execute same and return it to the Owner.
24. BRAND NAMES: Unit price bids are requested on products that equal or exceed the quality and performance of the brands and model numbers listed. References to brand names, trade names, model numbers or other descriptions peculiar to specific brand products are made to establish a required level of quality and functional capabilities, and are not intended to exclude other products of that level.
Comparable products of other manufacturers will be considered if proof of comparability is contained in the bid. It shall be the responsibility of the bidders, including bidders whose product is referenced;
to furnish with the bid such specifications, catalog pages, brochures or other data as will provide an adequate basis for determining the quality and functional capabilities of the product offered. Failure to provide this data may be considered valid justification for rejection of a bid.
SECTION III - INSURANCE REQUIRED FOR CONTRACTORS
UNIFIED GOVERNMENT OF ATHENS-CLARKE COUNTY
Before commencing work under the contract, the Contractor shall provide to the Unified Government of Athens- Clarke County, Attn: Purchasing Administrator, a Certificate of Insurance evidencing the required kinds and amounts of insurance. The insurance company will only be accepted if it is in good standing within the state of Georgia through the Insurance Commissioner’s office. It must also be rated “A-” or better and have a financial rating of VII or better with AM Best Company. The contractor shall procure at his own expense the following insurance coverage as listed below:
i. Workers’ Compensation/Employers Liability – Contractors are required to comply with applicable Federal and Georgia State workers’ compensation statutes. Policies covering Workers’ Compensation liability shall provide coverage of statutory benefits and employers liability of at least $1,000,000 each accident; at least $1,000,000 each employee for disease and $1,000,000 policy limit for disease.
ii. General Liability - $2,000,000 aggregate; $1,000,000 per occurrence. Coverage should be on a per-occurrence basis.
iii. Automobile Liability – Automobile liability insurance shall be written on the comprehensive form of policy – Combined single limit of at least $1,000,000 to include Hired Autos and Non-owned Autos. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract.
iv. Excess Liability - $2,000,000 aggregate; $1,000,000 per occurrence. Excess coverage shall follow form of General Liability and Auto policies.
The Contractor shall insert the substance of this requirement, including this paragraph, in subcontracts under the contract that require work on The Unified Government of Athens-Clarke County property and shall require subcontractors to provide and maintain a copy of all subcontractors’ proofs of required insurance, and shall make copies available to the Purchasing Administrator upon request.”
The Contractor shall provide the following endorsements with the certificate of insurance. Contractor shall list the Unified Government of Athens-Clarke County as an additional insured on their General Liability and Auto Liability coverages. A waiver of subrogation is to be provided in favor of the Unified Government of Athens- Clarke County for all policies including Workers’ Compensation. A primary and non-contributory endorsement shall be provided on their General Liability and Auto Liability coverages. The Contractor’s carrier(s) shall provide an endorsement requiring carrier(s) to provide the Unified Government of Athens Clarke County written notice of any cancellation or substantial change of insurance coverage prior to cancellation for all policies.
SECTION IV - GENERAL CONDITIONS
A. Contractor shall furnish all service, personnel, material, tools and equipment as necessary for completion of
Fire Training Center Cascade System in accordance with specifications.
B. CONTRACTOR'S INVOICE:
a. The Contractor shall prepare and submit invoices to the Finance Office address specified on individual orders. If the invoice does not comply with these requirements, the Finance Office will return it with the reasons why it is not a proper invoice. A proper invoice must include the items listed below.
(i) Name and address of the Contractor.
(ii) Invoice date and invoice number. (The Contractor should date invoices as close as possible to the date of the mailing or transmission.)
(iii) Purchase order number for supplies delivered or services performed.
(iv) Description, quantity, unit of measure, unit price, and extended price of supplies delivered or services performed.
(v) Shipping and payment terms (e.g., shipment number and date of shipment, discount for prompt payment terms).
(vi) Name and address to which payment is to be sent.
(vii) Name (where practicable), title, phone number, and mailing address of person to notify in the event of a defective invoice.
(viii) Any other information or documentation required by the contract (e.g., evidence of shipment).
C. TERMINATION FOR CAUSE: The Unified Government of Athens-Clarke County reserves the right to terminate the resulting contract, in whole or in part, for failure to comply with any provisions of the contract as outlined by providing a written notice to the contractor at least ten (10) days before the effective date of termination. The contractor will not be relieved of any outstanding responsibilities or unfinished obligations under this contract. The contractor has the right to terminate this contract for cause by providing a written notice of intent to the Purchasing Administrator to terminate at least ten (10) days prior to the effective date of the contract termination.
D. REPORTING DISPUTES: The contractor shall report any contract disputes and/or problems to the
Purchasing Administrator, both verbally and in writing, within 48 hours of their occurrence.
E. SAFETY: The contractor shall take every precaution at all times for the protection of persons and property, including the Unified Government's employees and property and its own. The contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the work under this contract.
The contractor shall maintain an adequate safety program to insure the safety of contractor employees, subcontractor employees, and all other individuals working under this contract. In addition, the contractor must also provide the Unified Government of Athens-Clarke County with a written safety program that he intends to follow in pursuing work under this contract. No work under this contract will be permitted until the Unified Government is assured that the contractor has an adequate safety program in effect.
F. SUBCONTRACTS: No portion of the work shall be subcontracted without prior written consent of the
Unified Government of Athens-Clarke County Purchasing Office. If a portion of the work is approved for subcontracting, the contractor shall remain fully liable and responsible for the work to be done by the subcontractor(s) and shall assure compliance with all requirements of this contract.
G. DIFFERING SITE CONDITIONS:
(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Unified Government’s (ACCUG) Project Manager of (1) Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract; or (2) Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract. (b) The ACCUG Project Manager shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly. (c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required. (d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.
H. MATERIAL AND WORKMANSHIP:
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract.
References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the ACCUG Project Manager, is equal to that named in the specifications, unless otherwise specifically provided in this contract. (b) The Contractor shall obtain the ACCUG Project Manager’s approval of the machinery and mechanical and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the ACCUG Project Manager the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery and mechanical and other equipment. When required by this contract or by the ACCUG Project Manager, the Contractor shall also obtain the ACCUG Project Manager’s approval of the material or articles which the Contractor contemplates incorporating into the work. When requesting approval, the Contractor shall provide full information concerning the material or articles. When directed to do so, the Contractor shall submit samples for approval at the Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection. (c) All work under this contract shall be performed in a skillful and workmanlike manner. The ACCUG Project Officer may require, in writing, that the Contractor remove from the work any employee the ACCUG Project Officer deems incompetent, careless, or otherwise objectionable.
I. SUPERINTENDENCE BY THE CONTRACTOR:
At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the ACCUG Project Manager and has authority to act for the Contractor.
J. PERMITS AND RESPONSIBILITIES:
The Contractor shall, without additional expense to the Unified Government of Athens-Clarke County, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occurs as a result of the Contractor's fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
K. OTHER CONTRACTS:
The Unified Government of Athens-Clarke County may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Unified Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the ACCUG Project Manager. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Unified Government employees.
L. PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS:
(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the ACCUG Project Manager. (b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site, and (2) on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work.
If the Contractor fails or refuses to repair the damage promptly, the ACCUG Project Manager may have the necessary work performed and charge the cost to the Contractor.
M. OPERATIONS AND STORAGE AREAS:
(a) The Contractor shall confine all operations (including storage of materials) on the Unified Government of Athens-Clarke County premises to areas authorized or approved by the ACCUG Project Manager. The Contractor shall hold and save the Unified Government of Athens-Clarke County, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance. (b) Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the ACCUG Project Manager and shall be built with labor and materials furnished by the Contractor without expense to the Unified Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the ACCUG Project Manager, the buildings and utilities may be abandoned and need not be removed. (c) The Contractor shall, under regulations prescribed by the ACCUG Project Manager, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the ACCUG Project Manager. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
N. CLEANING UP:
The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Unified Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the ACCUG Project Manager.
O. ACCIDENT PREVENTION:
(a) The Contractor shall provide and maintain work environments and procedures which will- (1) Safeguard the public and the Unified Government of Athens-Clarke County personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities; (2) Avoid interruptions of Unified Government operations and delays in project completion dates; and (3) Control costs in the performance of this contract.
(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall- (1) Provide appropriate safety barricades, signs, and signal lights; (2) Comply with the standards issued by the Secretary of Labor at 29 CFR part 1926 and 29 CFR part 1910; and (3) Ensure that any additional measures the ACCUG Project Manager determines to be reasonably necessary for the purposes are taken; (d) Whenever the ACCUG Project Manager becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or the Unified Government personnel, the ACCUG Project Manager shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the ACCUG Project Manager may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause. (e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.
P. JOINT VENTURES:
a. Each co-venturer (hereinafter “partner”) in a JV must meet the minimum experience requirement as outlined in the Bid. If a JV is presented, then the JV shall submit a statement specifying the distribution of ownership in the JV (i.e.: Firm A = 60%, Firm B = 40%).
b. The JV shall designate a Partner in Charge who shall act as the point of contact for both the present and future should ACCUG need to contact them. Also, the JV Partner in Charge shall complete at least 50% of the work as defined in the Bid.
c. Both named partners must have been engaged in similar projects of scope and magnitude of mass grading on airports under FAA guidelines and regulations for at least two cumulative years each. Bidder shall submit evidence of such experience.
d. The designated Project Manager must have and show evidence of at least two cumulative years of prior airport mass grading supervisory experience.
e. Each partner within the JV must be properly licensed for the scope of work on the project.
Q. NON-DISCRIMINATION ORDINANCE
Contractor agrees to abide by and be bound by Chapter 6-21 of the Code of Athens-Clarke County, Georgia, regarding Unlawful Discrimination and agrees to ensure that any and all subcontractors operating pursuant to this solicitation also agree to abide by and be bound by Chapter 6-21 of the Code of Athens-Clarke County, Georgia.”
SECTION V – BID SPECIFICATIONS or SCOPE OF WORK
Project Title: Cascade System Installation Location: Athens-Clarke County Fire Training Center
1. Introduction This document outlines the requirements and scope of work for the installation of a cascade system at the Athens-Clarke County Fire Training Center. The system will be used to provide high-pressure air for SCBA refilling operations.
2. Objectives The primary objective of this project is to install a fully functional and compliant cascade system to support the training needs of the Athens-Clarke County Fire Training Center.
3. Scope of Work
3.1 Equipment Supply
The supplier shall provide the following equipment as specified along with any equipment required to complete the project but is not listed below:
| Qty | Description | | 1 | 6000 psi Compressor Motor including magnetic starter, hour meter, auto drain, auto pressure switch, gauge panel and filter to process 24,000 cu ft of air, in an enclosed sound suppressing cabinet with electronic co monitor.
| 1 | Compressor TRPL FILL W/CONTROLS 5500 PSI | | 4 | Compressor 6000 PSI UN Storage Cylinder | | 1 | Compressor Unistrut & Clamps 1/per 4 Cyl | | 4 | Compressor CGA-702 N&N W/JIC Elbow | | 1 | Compressor Hose 120" (10ft) 7000 PSI w/ends | | 4 | Compressor Hose 72" (6FT) 7000 PSI w/ends | | 1 | Installation Setup and Training
3.2 Installation
- Site Preparation:
- Ensure the installation area is clean and ready.
- Verify electrical supply and other utilities are in place and compliant with the equipment requirements.
- Installation of Equipment:
- Install the compressor and associated components according to the manufacturer’s specifications.
- Ensure all connections (electrical, air, etc.) are secure and properly configured.
3.3 Testing and Commissioning
- Conduct initial tests to verify the system operates correctly.
- Perform safety checks and ensure all safety features (e.g., low oil pressure shutdown, high oil temperature shutdown) are functional.
- Demonstrate system operation to designated fire department personnel.
3.4 Training
- Provide training for fire department personnel on the operation and maintenance of the cascade system.
- Supply operation manuals and maintenance documentation.
3.5 Maintenance and Inspection
1. System Installation (when requested):
- Install the cascade system as per the specifications and site requirements.
2. System Maintenance (after installation):
- Perform regular maintenance on the installed system to ensure optimal performance.
3. System Inspection (minimum annually):
- Conduct annual inspections of the installed cascade system to ensure compliance with safety and operational standards.
4. System Repair (when necessary):
- Repair the cascade system promptly as needed to maintain functionality and safety.
3.6 Additional Responsibilities
a. Ensure cleanliness and order at the installation site.
b. Purchase and maintain required insurance.
4. Deliverables
- Fully installed and operational cascade system.
- Training sessions for fire department personnel.
- Documentation including operation manuals and maintenance guides.
- Regular maintenance and inspection reports.
SECTION VI BID FORMS
SECTION VI-A: BID BOND
STATE OF GEORGIA
COUNTY OF CLARKE
KNOW ALL MEN BY THESE PRESENTS, that we, , as Principal, and , as Surety, are held and firmly bound unto the Unified Government of Athens-Clarke County, Georgia in the sum of Dollars ($ ) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, personal representatives, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, the Principal has submitted to the Owner a Bid for construction of BID #______ SPLOST 2005, Project No. ___, _______________________________________________.
NOW THEREFORE, the conditions of this obligation are such that if the Bid be accepted, the Principal shall, within ten days after receipt of conformed Contract Documents, execute a Contract in accordance with the Bid upon the terms, conditions and prices set forth therein, and in the form and manner required by the Contract Documents and execute sufficient and satisfactory separate Performance and Payment Bonds payable to the Owner, each in an amount of 100 percent of the total Contract Price, in form satisfactory to the Owner, then this obligation shall be void;
otherwise, it shall be and remain in full force and effect in law; and the Surety shall, upon failure of the Principal to comply with any or all of the foregoing requirements within the time specified above, immediately pay to the aforesaid Owner, upon demand, the amount hereof in good and lawful money of the United States of America, not as a penalty, but as liquidated damages.
This bond is given pursuant to and in accordance with O.C.G.A. §36-91-1 et.seq. and all the provisions of the law referring to this character of bond as set forth in said Sections or as may be hereinafter enacted and these are hereby made a part hereof to the same extent as if set out herein in full.
IN WITNESS WHEREOF, the said Principal has hereunder affixed its signature and seal, and said Surety has hereunto caused to be affixed its corporate signature and seal, by its duly authorized officers, on this day of , 20___.
MANDATORY SUBMITTAL
CONTRACTOR – PRINCIPAL:
By:
(name signed)
(name printed or typed)
Title:
Address:
Attest:
(SEAL)
Note: Attest for a corporation must be by the corporate secretary; for a partnership by another partner; for an individual by a notary.
SURETY:
By:
Attest:
(SEAL)
Note: Surety companies executing Bond must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the state where the Project is located.
Surety and Insurers must have an A.M. Best Financial Strength Rating of A or higher, with a Financial Size Category of VII or higher.
END OF SECTION
SECTION VI-B: BID FORM AND STATEMENT OF BIDDERS QUALIFICATION
NAME AND ADDRESS OF BIDDER:
Company Name/Contact Name:
Phone: Fax:
Email:
The Unified Government of Athens-Clarke County Finance Department/Purchasing Division 375 Satula Avenue Athens, Georgia 30601
PROJECT: Bid #25015 Fire Training Center Cascade System
GENTLEMEN/LADIES:
1. Having carefully examined the Bidding Documents of the TITLE Bid # 25015 Fire Training Center Cascade
System dated ______________and Addendum (a) _________________, as well as the premises and conditions affecting the Work, the Undersigned proposes to furnish all services, labor and materials required by them in accord with said documents, for the sum of ___________________________________ Dollars ($___________________), which sum is hereinafter called the "Base Bid ."
2. The Undersigned agrees that this Bid may not be revoked or withdrawn after the time set for the opening of bids but shall remain open for acceptance for a period of sixty days following such time.
3. In case he is notified in writing by mail, telegraph, facsimile or delivery of the acceptance of this Bid within sixty days after the time set for the opening of bids, the Undersigned agrees to execute within ten days a contract for the Work for the Above-stated compensation.
4. Time for completion: The Undersigned agrees to commence actual physical work on the site with adequate force and equipment within ten calendar days of the date of the Proceed Order and complete the work ready for use not later than the number of calendar days after the Contractor receives the Proceed Order as set forth below:
NUMBER OF CALENDAR DAYS REQUIRED TO COMPLETE PROJECT:_____________
The time stated for completion shall include final cleanup of the premises.
5. The Bidder shall deliver to the Owner, a list of all Subcontractors proposed for the work whose subcontracts will be
$50,000.000 or more, with this Solicitation, as outlined in Section II – Bid Submittal Instructions.
Authorized Representative/Title (print or type) Authorized Representative (Signature) Date
COMPANY NAME:
SECTION VI-B1: BID FORM AND STATEMENT OF BIDDERS QUALIFICATION
The Bidder submits the following statement of Bidders qualifications for consideration of the Owner.
1. Have you ever failed to complete any work awarded to you? If so, where and why?
2. Have you ever defaulted on a Contract? If so, where and why?
3. List the most important projects recently completed by your company, stating the approximate cost for each, and the month and year completed
4. Experience in specific work similar in importance to this project:
5. Background and experience of the principal members of your organization, including officers.
(To be subscribed and sworn to before a Notary)
All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized.
If necessary, questions may be answered on separate attached sheets. The Bidder may submit any additional information he desires. Attach all additional sheets to this Solicitation for Sealed Bid.
6. Legal Name of Bidder:
7. Permanent Main Office Address:
SECTION VI-B2: BID FORM AND STATEMENT OF BIDDERS QUALIFICATION
8. When organized
9. If a Corporation, where incorporated?
10. Number of years engaged in the contracting business under your present firm or trade name?
11. Credit Available for this contract?
12. Contracts now in hand (Gross Amount)
13. General character of work performed by your company:
14. Have you ever refused to sign a Contract at the original bid? If so, where and why?
15. Provide a bank reference:
The undersigned hereby authorizes and requests any person, firm, or corporation to furnish any information requested by the Local Public Agency in verification of the recitals comprising this Statement of Bidder's Qualifications.
Authorized Representative/Title (print or type) Authorized Representative (Signature) Date
SECTION VI-B3: BID FORM AND STATEMENT OF BIDDERS QUALIFICATION
The foregoing statement of qualifications is submitted under oath.
Under oath, I certify that I am a principal or other representative of the firm of _______________________________ and that I am authorized by it to execute the foregoing bid on its behalf. I am a principal person of the foregoing with management responsibility for the foregoing subject matter and as such I am personally knowledgeable of all its pertinent matters. The foregoing statements of acts in the foregoing bid are true.
I certify that this Bid is made without prior understanding, agreement or connection with any corporation, firm or person submitting a bid for the same materials, labor, supplies or equipment and is in all respects fair and without collusion or fraud. We understand collusive bidding is a violation of state and federal law and can result in fines, prison sentences, and civil damage awards. We agree to abide by all conditions of this bid.
The full names and addresses of persons and firms interested in the foregoing bid as principals are as follows:
NAME TITLE ADDRESS
Dated this ___________ day of ______________________________, 20_____.
Company Name:
Contact Person:
Phone: Fax:
Email:
By: Title:
State of: County of:
________________________________ being duly sworn exposes and says that he or she is __________________of
____________________ and that the answers to the foregoing questions and all statements therein contained are true and correct.
Subscribed and sworn to before me this _______ day of ________________________, 20______.
Notary Public
My Commission Expires: _________________________, 20_______.
Notary Seal
F:\Purchasing\BIDS25\25015 RFP Fire Training Center Cascade System\25015 Fire Training Center Cascade System.docx Page 24 of 35
SECTION VI-C: ADDENDA ACKNOWLEDGEMENT
The Offeror has examined and carefully studied the Specifications and the following Addenda, Receipt of all of which is hereby acknowledged:
Addendum No.
dated
Acknowledgement
Initial
Offerors must acknowledge any issued addenda. Proposals which fail to acknowledge the offeror’s receipt of any addendum will result in the rejection of the proposal if the addendum contained information which substantively changes the Owner’s requirements.
F:\Purchasing\BIDS25\25015 RFP Fire Training Center Cascade System\25015 Fire Training Center Cascade System.docx Page 25 of 35
SECTION VI-D GEORGIA SECURITY & IMMIGRATION COMPLIANCE (GSIC) AFFIDAVIT
The Unified Government of Athens-Clarke County and Contractor agree that compliance with the requirements of O.C.G.A.
§ 13-10-91, as amended, and Rule 300-10-1-.02 of the Rules of the Georgia Department of Labor are conditions of this Agreement for the physical performance of services.
The Contractor further agrees that its compliance with the requirements of O.C.G.A. § 13-10-91, as amended, and DOL Rule 300-10-1-.02 is attested to on the executed Contractor Affidavit and Agreement attached hereto.
If employing or contracting with any subcontractor(s) in connection with this Agreement, Contractor further agrees:
(1) To secure from the subcontractor(s) an affidavit attesting to the subcontractor’s compliance with O.C.G.A. § 13-10-91, as amended, and DOL Rule 300-10-1-.02; such affidavit being in the form attached hereto; and
The failure of Contractor to supply the affidavit of compliance at the time of execution of this Agreement and/or the failure of Contractor to continue to satisfy the obligations of O.C.G.A.