25-8396_-_Bid_Schedule_R1.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Everglades Blvd. North Shoulder Improvements
Solicitation number
25-8396
Issued by
Collier County, Florida

About this file

The file is a Bid Schedule for Collier County, Florida's Everglades Blvd. North Shoulder Improvements Project (Bid No. 25-8396), outlining a comprehensive road infrastructure improvement initiative. The project involves north shoulder improvements with numerous construction elements, including mobilization, maintenance of traffic, clearing and grubbing, mailbox relocation, excavation, embankment, road stabilization, asphalt paving, culvert installation, driveway construction, fencing, landscaping, and traffic signage. The bid is scheduled for submission by June 30th, 2025, at 3:00 p.m. local time, with a non-mandatory pre-bid meeting set for May 22nd, 2025, at 10:00 a.m. in Naples, Florida. Prospective bidders are required to register on the county's procurement portal to obtain complete project documents.

The bid schedule includes an extensive list of line items with quantities but currently shows zero dollar amounts, indicating that actual pricing will be submitted by bidders. An owner's allowance of $100,000 is included for time and materials related to unforeseen conditions, which will be allocated through change orders with proper documentation. The project appears to be funded by Collier County and involves significant infrastructure improvements, including road widening, shoulder construction, drainage improvements, and landscaping. Bidders must complete the project using specified materials and construction methods, with detailed specifications for each component of the road improvement project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

EVERGLADES BLVD. NORTH SHOULDER IMPROVEMENTS
CONSTRUCTION ITB NO. 25-8396
BID SCHEDULE
ITEM NO.ITEM DESCRIPTIONUNITQTYUNIT COSTTOTAL COST
101-1MOBILIZATIONLS1$ - 0$ - 0
102-1MAINTENANCE OF TRAFFICLS1$ - 0$ - 0
104-10-3STAKED SILT FENCE TYPE IIILF37,616$ - 0$ - 0
110-1-1STANDARD CLEARING & GRUBBINGLS1$ - 0$ - 0
110-7-1MAILBOX, FURNISH & INSTALL, SINGLEEA2$ - 0$ - 0
110-7-2MAILBOX, RELOCATE, SINGLEEA130$ - 0$ - 0
120-1EXCAVATIONCY3,500$ - 0$ - 0
120-6EMBANKMENTCY4,200$ - 0$ - 0
121-70FLOWABLE FILLCY50$ - 0$ - 0
160-4TYPE B STABILIZATIONSY9,100$ - 0$ - 0
285-701-1OPTIONAL BASE GROUP 1 (4" THICK, BLACK BASE, SHOULDERS)SY20,020$ - 0$ - 0
285-715OPTIONAL BASE GROUP 15 (9" THICK, BLACK BASE ONLY)SY726$ - 0$ - 0
286-2TURNOUT CONSTRUCTION-ASPHALT, DRIVEWAY BASE-ASP. MAT.TN1,760$ - 0$ - 0
334-1-53-1SUPERPAVE ASPH. CONC. TYPE SP-9.5 (1", TRAF. B)(DRIVEWAYS)TN88$ - 0$ - 0
334-1-53-2SUPERPAVE ASPH. CONC. TYPE SP-12.5 (TRAF. C)(2" WIDENING)TN72.6$ - 0$ - 0
334-1-53-3SUPERPAVE ASPH. CONC. TYPE SP-12.5 (TRAF. C)(2" OVERLAY)TN5236$ - 0$ - 0
337-7-83ASPH. CONC. FRICTION COURSE TYPE FC-9.5 (1" THICK, TRAF. C)TN3,666$ - 0$ - 0
425-1-521DITCH BOTTOM INLET TYPE "C"EA1$ - 0$ - 0
430-174-115PIPE CULVERT, OP. MATERIAL, ROUND, 15" SD (DRIVEWAYS)LF456$ - 0$ - 0
430-174-118PIPE CULVERT, OP. MATERIAL, ROUND, 18" SD (DRIVEWAYS)LF136$ - 0$ - 0
430-174-224PIPE CULVERT, OP. MATERIAL, OTHER SHAPE, 14"X23" SDLF8$ - 0$ - 0
430-175-118PIPE CULVERT, OP. MATERIAL, ROUND, 18" CDLF1,760$ - 0$ - 0
430-175-224PIPE CULVERT, OP. MATERIAL, OTHER SHAPE, 19"X30" CDLF95$ - 0$ - 0
430-982-125MITERED END SECTION, OP., ROUND, 18" (CD)EA54$ - 0$ - 0
430-982-625MITERED END SECTION, OP., OTHER SHAPE, 18" (CD)EA1$ - 0$ - 0
430-984-123MITERED END SECTION, OP. ROUND, 15" (SD)EA116$ - 0$ - 0
430-984-125MITERED END SECTION, OP. ROUND, 18" (SD)EA80$ - 0$ - 0
430-984-629MITERED END SECTION, OP. OTHER SHAPE, 14"X23" (SD)EA2$ - 0$ - 0
522-2CONCRETE DRIVEWAYS, 6" THICKSY2200$ - 0$ - 0
526-1-1BRICK PAVERS (DRIVEWAYS)SY200$ - 0$ - 0
550-10-110FENCING, TYPE A STANDARD, RESET EXISTINGLF100$ - 0$ - 0
570-1-2PERFORMANCE TURF (SOD)SY83,600$ - 0$ - 0
580-1-2LANDSCAPE COMPLETE, RELOCATE EXISTINGLS1$ - 0$ - 0
700-1-50SIGNS, RELOCATEAS40$ - 0$ - 0
706-1-3PAVEMENT MARKERS, RETRO-REFLECTIVE (TYPE "B")EA2,764$ - 0$ - 0
711-11-125TRAFFIC STRIPE, SOLID, THERMO. (24" WHITE)LF514$ - 0$ - 0
711-11-141TRAFFIC STRIPE, SOLID, THERMO. (6" WHITE, 6'-10' SKIP)LF250$ - 0$ - 0
711-11-160PAVEMENT MESSSAGES (THERMOPLASTIC)EA3$ - 0$ - 0
711-11-170DIRECTIONAL ARROWS (THERMOPLASTIC)EA9$ - 0$ - 0
711-11-224TRAFFIC STRIPE, SOLID, THERMO. (18" YELLOW)LF152$ - 0$ - 0
711-15-101TRAFFIC STRIPE SOLID, THERMOPLASTIC-WHITE (6")GM7.900$ - 0$ - 0
711-15-201TRAFFIC STRIPE SOLID, THERMOPLASTIC-YELLOW (6")GM6.900$ - 0$ - 0
TOTAL BID:$0.00

Owner's Allowance - Owner has set up an amount of $100,000.00 (T&M) for Owner's Use. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.

File details come from the government source that posted it. Updated .