This is Addendum #1 for the 25-2571 Wastewater Plant Improvements - White Road Construction project, issued by the Muskegon County Board of Public Works on March 10, 2025. The addendum provides key bidding information for the White Road Crush and Shape project, specifically noting that bids are due no later than Thursday, March 13, 2025, at 2:00 PM through the electronic Bidnet system. The document clarifies two critical points for potential contractors: first, water from the outlet ditch (which contains effluent from the wastewater treatment process) may be used for dust and moisture control, subject to local, state, and federal requirements; and second, work may not commence earlier than June 16, 2025.
The addendum does not include specific pricing details but emphasizes procedural requirements for bid submission. Contractors are warned that failure to acknowledge this addendum on the Addenda Summary could result in bid rejection, and no late bid responses will be accepted. The project appears to be a road reconstruction effort involving approximately 1.7 miles of roadway within the Muskegon County Resource Recovery Center, with work including crush and shape, trenching, road-widening, paving, and restoration. The document is signed by Angela Gasiewski, CPA, Director of Finance, and includes a technical clarification from Steve Taplin, P.E.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25-2571 White Road Crush and Shape.pdf | ||
| W9 BLANK.pdf | ||
| 25-2571 White Road Crush and Shape Bid Sheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Monday, March 10, 2025
ADDENDUM #1
25-2571 Wastewater Plant Improvements - White Road Construction
IFB 25-2571
This is addendum #1 to the above-mentioned solicitation for Muskegon County Board of Public Works. Please indicate this addendum on the Addenda Summary of the bid package; failure to acknowledge all addenda may be cause for rejection of the bid.
Bids are due in no later than Thursday, March 13, 2025 at 2:00 PM. Submittal Instructions are located in the Bid Conditions/Instructions for Responders in the IFB.
The time of receipt shall be determined by the time clock stamp in the electronic Bidnet system.
Respondents are responsible for ensuring that their bid response is submitted by the deadline indicated.
No late bid responses will be accepted.
Sincerely, Angela Gasiewski
Angela Gasiewski, CPA Director of Finance
BOARD OF
PUBLIC WORKS
Darrell Paige
Chair, District 7
Kim Cyr
Vice Chair, District 1
Stephanie Barrett
Water Resources
Commissioner
Secretary
Brett Herman
District 2
Michelle Hazekamp
District 3
Charles Nash
District 5
Jessica Cook
District 6
Jennifer Hodges
Ex-Officio Member
Scott Huebler Ex-Officio Member
DEPARTMENT OF FINANCE & MANAGEMENT- PROCUREMENT • 1903 MARQUETTE AVENUE, SUITE A106 •
MUSKEGON, MI 49442
(231) 724-6281 • FAX (231) 724-3337 • bids@co.muskegon.mi.us • www.co.muskegon.mi.us
3355 Evergreen Drive, NE Grand Rapids, MI 49525 t. 616-364-8491 f. 616-364-6955 www.preinnewhof.com page 1 of 1 S:\2024\2240709 Muskegon County RRC\CDS\Addendum\addendum no. 1.docx
Addendum No. 1 Owner: Muskegon County Resource Recovery Center, Muskegon County, Michigan
Project Title: White Road Crush and Shape
Project #: 2240709 Date of Addendum: March 10, 2025
Notice to Prospective Bidders
In accordance with Article 1 of the General Conditions, this Addendum is hereby issued as part of the
Contract Documents.
QUESTIONS AND ANSWERS
Below are questions that were received by Muskegon County or otherwise submitted during bidding, and the answers to those questions.
1. Will the contractor be able to use water from the outlet ditch for dust control and moisture control of the base?
The outlet ditch (north of White Road) contains effluent from the MCRRC wastewater treatment process. Contractor may use water from this ditch subject to compliance with all local, State and
Federal requirements.
2. Can the contractor start earlier than June 16th?
No. Work may not commence earlier than June 16, 2025.
Steve Taplin, P.E.