25-04-87-02 Plans.pdf
PDF 4 MB Posted
- Solicitation number
- 25-04-87-02
- Issued by
- Taylor County, Iowa
About this file
This construction document set, prepared by the Iowa Department of Natural Resources Engineering Section, outlines accessibility improvements at Lake of Three Fires State Park in Taylor County. The project involves constructing ADA-compliant Portland Cement Concrete (PCC) sidewalks and parking infrastructure across two primary sites: sidewalk improvements at the pit latrine and parking stall enhancements at the CCC Shelter. Specific work includes removing and replacing existing sidewalks to meet ADA grade requirements (maximum 5% running slope and 2% cross slope), constructing one 11-foot ADA van accessible parking stall with proper signage and striping, installing expansion joints, and managing material excavation and placement. The bid closing date is May 28, 2026, at 3:00 PM, with electronic submission required. Contractors are strongly advised to visit the site and inspect actual conditions prior to bidding and must verify all dimensions and conditions shown on the plans. Work cannot commence until September 14, 2026, and all contractors are responsible for identifying and avoiding damage to existing utilities, protecting trees and desirable vegetation, and providing their own waste disposal areas for excess excavated material and broken concrete.
The project will be subject to the Iowa Department of Transportation Standard Specifications for Highway and Bridge Construction, Series 2023, with the contractor bearing full responsibility for compliance with all applicable ADA standards and local codes. Contractors must provide daily availability of materials, equipment, and labor for installation and maintenance of erosion control features throughout the project duration. The Iowa DNR Capital Manager and Project Manager is Zach Gunsolley, reachable at 515-250-3713 or zach.gunsolley@dnr.iowa.gov, who oversees all bid package documentation and contractor inquiries. No information regarding project funding sources, contract amounts, or award dates is provided in this construction document set.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25-04-87-02 Bid Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A.01
Zachary A. Gunsolley Date License Number: 18702 My license renewal date is December 31, 2027 Pages or sheets covered by this seal:
All
Capital Manager Authorization - Parks
This project includes constructing ADA-compliant PCC sidewalks and parking stall.
Iowa DNR
Zach Gunsolley
515-250-3713 zach.gunsolley@dnr.iowa.gov
1517 185th Ave
Diagonal, IA 50845
Iowa Department of Natural Resources Construction Documents for
Lake of Three Fires State Park Taylor County, Iowa
Accessibility Improvements Project No. 25-04-87-02
Project Location Map
N
Sheet Index A.01 A.02 A.03 B.01 B.02
C.01
Cover Sheet Location Map Project Overview Project Details Site 1 Sidewalk Improvements at Pit Latrine Quantities & General Information
Iowa DNR
Zach Gunsolley
515-250-3713 zach.gunsolley@dnr.iowa.gov
1517 185th Ave
Diagonal, IA 50845
Engineering Bureau Chief
Authorization to Bid
Date
Date
I hereby certify that this engineering document was prepared by me or under my direct personal supervision and that I am a duly licensed Professional Engineer under the laws of the State of Iowa.
Directory Project Manager
Organization
Contact
Phone
Address
City, State, Zip
District Engineer Organization
Contact
Phone
Address
City, State, Zip
Project Description
Project Number:
25-04-87-02
Bid Date:
05/28/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Accessibility Improvements Lake of Three Fires State Park, Taylor County
Sheet No:Drawn by: ZG
C:
\U se rs
\Z ac h Gu ns ol le y\
De sk to p\
-0
4-
-0
Lo 3F
A cc es sib ili ty
Im pr ov em en ts
\2 5-
-8
7-
P la ns .d w g
5/ 1/
1:
A
M Pl ot D at e:
Revision Date Cover Sheet
Project Area
AutoCAD SHX Text Zachary A. Gunsolley 18702
AutoCAD SHX Text A
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text W
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text P
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text L
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text G
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text L
AutoCAD SHX Text A
0' 200' 400'
N
Project Number:
25-04-87-02
Bid Date:
05/28/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Accessibility Improvements Lake of Three Fires State Park, Taylor County
Sheet No:Drawn by: ZG
C:
\U se rs
\Z ac h Gu ns ol le y\
De sk to p\
-0
4-
-0
Lo 3F
A cc es sib ili ty
Im pr ov em en ts
\2 5-
-8
7-
P la ns .d w g
5/ 1/
1:
A
M Pl ot D at e:
Revision Date A.02Location Map
Site 1 CCC Shelter
Park Office
Beach
Co . R d N4
Site 2 Beach Lodge
5'
5'
20'
5'
2'
50'
10'
5'
2' 11'
0' 20' 40'
N
Project Number:
25-04-87-02
Bid Date:
05/28/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Accessibility Improvements Lake of Three Fires State Park, Taylor County
Sheet No:Drawn by: ZG
C:
\U se rs
\Z ac h Gu ns ol le y\
De sk to p\
-0
4-
-0
Lo 3F
A cc es sib ili ty
Im pr ov em en ts
\2 5-
-8
7-
P la ns .d w g
5/ 1/
1:
A
M Pl ot D at e:
Revision Date A.03Project Overview
Site 1 CCC Shelter
CCC Shelter
Provide striping as shown, including stall boundary stripe.
Construct one 11' ADA van parking stall. Match existing pavement grade. Harvest excess topsoil and Class 10 material for fill at existing pit latrine. Expansion joint at sidewalk.
Place excess Class 10 and topsoil material on a 6:1 slope from edge of sidewalk.
Remove and replace PCC sidewalk
0' 20' 40'
N
Site 2 Beach Lodge
Beach Lodge
End sidewalk at joint at SW shelter post. Add expansion joint along edge of shelter floor and existing sidewalk.
Remove and replace PCC sidewalk. Harvest excess Class 10 material for fill at existing pit latrine.
Furnish and compact Special Backfill to maintain 4.5% maximum grade or less for sidewalk.
Protect existing grill.
Place sidewalk edge at edge of grill.
End sidewalk at existing sidewalk joint at south side of shelter entrance. Add expansion joint along edge of shelter floor and existing sidewalk. Remove existing sidewalk. Strip and stockpile existing topsoil. Furnish and compact Class 10 and Special Backfill to maintain 4.5% maximum grade or less for sidewalk to existing pit latrine.
Add expansion joint material at pit latrine.
Pit LatrineProvide striping as shown and add ADA van parking sign in front of stall.
Cut 6:1 slope from edge of sidewalk as necessary to maintain sidewalk slope
Perimeter Slope and Sediment Control Device
Note: Protect trees and avoid damage to roots.
Project Number:
25-04-87-02
Bid Date:
05/28/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Accessibility Improvements Lake of Three Fires State Park, Taylor County
Sheet No:Drawn by: ZG
C:
\U se rs
\Z ac h Gu ns ol le y\
De sk to p\
-0
4-
-0
Lo 3F
A cc es sib ili ty
Im pr ov em en ts
\2 5-
-8
7-
P la ns .d w g
5/ 1/
1:
A
M Pl ot D at e:
Revision Date B.01Project Details
Special Backfill
Sidewalk Detail Not to Scale
Per Plan 5"
4"
Three longitudinal #4 reinforcement bars evenly spaced with 6" minimum lap
MUTCD R7-8 and R7-8aP (van accessible) Solid green legend and border, reflective white background, white accessibility symbol on blue background.
ADA Accessible Parking Signs Detail Not To Scale
Notes:
1. 12"X18" accessibility sign shall be mounted 7' from finish grade to bottom edge of sign face.
Mounting height may be reduced to 5' if placed in a landscape area in which pedestrians are not expected to use.
2. Signage to be located at end of parking stall, 2' back from edge of pavement, centered on stall if possible.
3. All signage shall be high-intensity prismatic .080 aluminum reflective sign meeting the requirements of the MUTCD and
ADAAG.
4. Installation of square post and anchor base in accordance with IDOT SUDAS Section 8040.
Square Post 2-1/4"
Ground/Paving Surface
6"
1' -6
7'
3' 3'
Square Anchor Base 2-1/2" located at top of bollard or top of ground surface.
Use 6" Steel Pipe Bollard filled with concrete and painted traffic yellow.
Special Backfill
Parking Stall Not to Scale
6" 4"
#4 reinforcement bars @ 24" centers each way
Per Plan 1.5% target slope any direction
1.5% target cross slope
AutoCAD SHX Text
RESERVED PARKING
AutoCAD SHX Text
VAN
AutoCAD SHX Text
ACCESSIBLE
Project Number:
25-04-87-02
Bid Date:
05/28/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Accessibility Improvements Lake of Three Fires State Park, Taylor County
Sheet No:Drawn by: ZG
C:
\U se rs
\Z ac h Gu ns ol le y\
De sk to p\
-0
4-
-0
Lo 3F
A cc es sib ili ty
Im pr ov em en ts
\2 5-
-8
7-
P la ns .d w g
5/ 1/
1:
A
M Pl ot D at e:
Revision Date B.02Site 1 Sidewalk Improvements at Pit Latrine
Site 1 Sidewalk Improvements at Pit
Latrine (no scale)
See A.03 for location
Pit Latrine
Place excess Class 10 and topsoil material on a 6:1 slope from edge of sidewalk.
Remove existing sidewalk
Cut 6:1 slope from edge of sidewalk as necessary to maintain sidewalk slope
Strip and stockpile existing topsoil. Furnish and compact Class 10 and Special Backfill to maintain 4.5% maximum grade or less for sidewalk to existing pit latrine. Add expansion joint material at pit latrine.
C.01
Estimate Reference Information 1.
2.
3.
4,5.
6.
7.
8-11.
See referenced IDOT specification and Sheet B.01. In fill areas, place and compact after Class 10 placement.
See referenced IDOT specification. Place and compact in fill areas below special backfill and topsoil.
See referenced IDOT specification. Place in areas after Class 10 placement.
See referenced IDOT specification and Sheet A.03, B.01 and B.02. Class C mix, Class 2 durability coarse aggregate.
See referenced IDOT specification. This item includes all necessary survey and staking to complete work in accordance with the Contract Documents and 2010 ADA Standards. Non-compliant work shall be removed and replaced at the sole expense of the contractor. Noteworthy ADA requirements:
A. 2% maximum cross slope on sidewalks.
B. 5% maximum running slope on sidewalks.
C. 2% maximum slope in any direction on parking stalls, landing areas, access aisles.
See referenced IDOT specification and Sheet A.03 and B.01. Two locations, but Van Parking Sign only at CCC Shelter.
See referenced IDOT specification.
Project Number:
25-04-87-02
Bid Date:
05/28/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Accessibility Improvements Lake of Three Fires State Park, Taylor County
Sheet No:Drawn by: ZG
C:
\U se rs
\Z ac h Gu ns ol le y\
De sk to p\
-0
4-
-0
Lo 3F
A cc es sib ili ty
Im pr ov em en ts
\2 5-
-8
7-
P la ns .d w g
5/ 1/
1:
A
M Pl ot D at e:
Revision Date Quantities & General Information
General Information
1. Verify actual locations and elevations with DNR Engineer.
2. All work shall conform to and be performed in accordance with all applicable codes and ordinances.
3. The contractor shall visit the site and inspect the project area and thoroughly familiarize themselves with the actual job conditions prior to bidding and the start of work. Failure to visit the project site shall not relieve the contractor from performing the work in accordance to the plans, specification, special provisions and contract.
4. The contractor shall verify, at the site, all dimensions and conditions shown on the plans and shall notify the DNR Engineer of any discrepancies, omissions, and/or conflicts prior to proceeding with the work.
5. It shall be the contractor’s responsibility to provide waste areas or disposal sites for excess material (excavated material or broken concrete) which is not desirable to be incorporated into the work involved on this project. No payment for overhaul will be allowed for material hauled to these sites. No material shall be placed within the right-of-way, unless specifically stated in the plans or approved by the DNR Engineer.
6. The contractor shall not disturb desirable grass areas and desirable trees outside the construction limits. The contractor will not be permitted to park or service vehicles and equipment or use these areas for storage of materials. Storage, parking and service areas will be subject to the approval of the DNR Engineer.
7. Where utilities and fixtures are shown as Existing on the plans or encountered within the construction area, it shall be the responsibility of the contractor to notify the DNR Engineer of those utilities prior to the beginning of any construction. The contractor shall be afforded access to these facilities for necessary modification of services. Underground facilities, structures and utilities have been plotted from available surveys and records and therefore their locations must be considered approximate only. It is possible there may be others, the existence of which is presently not known or shown. It is the contractor’s responsibility to determine their existence and exact location and to avoid damage thereto. No claims for additional compensation will be allowed to the contractor for any interference or delay caused by such work.
8. The contractor shall shape graded area to maintain surface drainage. All elevations are to finish grade.
9. The contractor is expected to have materials, equipment, and labor available on a daily basis to install and maintain erosion control features on the project. This may involve seeding, silt fence, rock ditch checks, silt basins or silt dikes.
10. The Iowa DOT Standard Specifications for Highway and Bridge Construction, Series 2023, plus General Supplemental Specifications and Supplemental Specifications effective at the time of letting, shall apply to this project. The item's description includes applicable IDOT specification sections.
11. Work Restrictions: Work cannot begin until September 14, 2026. This includes mobilization.
| Sheets and Views |
| 25-04-87-02 Plans-A.01 |
| 25-04-87-02 Plans-A.02 |
| 25-04-87-02 Plans-A.03 |
| 25-04-87-02 Plans-B.01 |
| 25-04-87-02 Plans-B.02 |
| 25-04-87-02 Plans-C.01 |
| 2026-05-01T11:20:15-0500 | |
| Zach Gunsolley |
| 2026-05-01T11:38:17-0500 | |
| Andrew Place |
| 2026-05-01T12:18:38-0500 | |
| Travis Baker |
File details come from the government source that posted it. Updated .