25-024 ITB 23230205 - Engineering plans.pdf
PDF 7 MB Posted
- Attached to
- ITB 25-024
- Solicitation number
- 336-ITB 25-024
- Issued by
- Clinton County, Iowa
About this file
Project Summary
This is a Scope of Work and engineering construction document issued by the Iowa Communications Network (ICN) for the relocation of fiber optic cable infrastructure along N Bluff Boulevard in Clinton County, Iowa. The project encompasses the relocation of existing ICN cable that conflicts with a planned street improvement project. The scope requires the installation of approximately 970 feet of minimum 1.25-inch HDPE conduit, placement of two 24"x36"x30" Tier 15 polymer concrete handholes with grade-level lids, and installation of one new 48-strand armored OSP (Outdoor Splice Point) fiber optic cable. The total cable pull, including slack, is approximately 1,170 feet. The project involves horizontal directional drilling due to bedrock conditions in the area. Sealed bids were required by August 27, 2025, at 2:00 PM CDT, with all bid proposals remaining firm for 90 days. No vendor conferences or mandatory site visits are specified in the documentation. The contract term and award date are not explicitly stated in the provided documents.
The pricing structure includes authorization for right-of-way permit fees as extras above the quoted bid price, with all excavation permits to be obtained by the contractor. The contractor is responsible for providing all labor, supervision, and materials necessary for a fully functional system meeting ICN standards, including HDPE conduit, duct splices, grounding and tracer wires, crushed rock, and wire mesh. Specific material requirements include orange smooth wall SDR 13.5 HDPE conduit and single-mode, gel-free, loose tube OSP cable with 600-pound short-term tensile strength. No set-aside designations, incumbent contractors, or specific funding sources are identified in the available documentation. The contractor must submit construction redline as-built drawings with offsets, meter marks, and installation depths within two weeks of project completion, along with splicing redlines and final acceptance documentation before final payment is processed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
400 EAST 14TH STREET
GRIMES STATE OFFICE BUILDING
DES MOINES, IOWA 50319
ICN © 2021, COPY WITH PERMISSION
IOWA COMMUNICATIONS NETWORK
IOWA COMMUNICATIONS NETWORK
CONSTRUCTION DRAWINGS FOR:
RELOCATION OF ICN FIBER ALONG N BLUFF BLVD
BETWEEN N 6TH ST TO SPRINGDALE DR. (CLINTON CO.)
PROJECT LOCATION
PROJECT OVERVIEW:
EXISTING ICN CABLE IS IN CONFLICT ALONG N BLUFF BLVD BETWEEN N 6TH ST TO SPRINGDALE DR. FOR STREET IMPROVEMENT PROJECT IN CLINTON, IA. RELOCATE WILL CONSIST OF ONE NEW MIN. 1.25-IN CONDUIT PLACED FROM END TO END ROUGHLY 970-FT ALONG WITH ONE NEW 48 ARMORED CABLED PULLED FROM END TO END.
RELOCATION WILL REQUIRE:
· PLACEMENT OF TWO (2) 24"x36"x30" TIER 22 HANDHOLES, SET WITH LIDS AT OR JUST BELOW GRADE
· PLACEMENT OF 970-FT± OF NEW MIN OF 1.25-IN HDPE CONDUIT
· TOTAL CABLE PULL INCLUDING SLACK ROUGHLY 1170-FT
· AREA IS BEEN CONFIRMED OF BEDROCK THAT WILL REQUIRE ALL TERRAIN HORIZONTAL DIRECTIONAL DRILLING
MACHINE.
· COORDINATE WITH SPLICER TO MINIMIZE TIME TRENCHES ARE OPEN
·· SECURELY FENCE OFF ANY OPEN TRENCHES
· AFTER SPLICING CUT-OVER, BACKFILL AND TAMP ALL EXCAVATED AREAS
· RESTORE RIGHT-OF-WAY PER DOT REQUIREMENTS, INCLUDING RE-SEEDING WHERE NEEDED
· SET ICN WARNING MARKERS AT EDGE OF RIGHT-OF-WAY LINE, PERPENDICULAR TO HANDHOLES
*THIS CONTACT LIST IS NOT ALL-INCLUSIVE. CONTRACTOR IS RESPONSIBLE FOR REQUESTING LOCATES OF ALL UTILITIES.
AutoCAD SHX Text
CITY OF CLINTON
AutoCAD SHX Text
PROJECT LOCATION
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
SIZE:
AutoCAD SHX Text R:\OSP PROJECTS\HARRIS\Clinton County\23230205 - Possibly Conflict Along S Bluff Blvd In Clinton\ICN RELO PLANS\23230205 - TITLE PAGE.dwg
AutoCAD SHX Text
OF
AutoCAD SHX Text
PAGE
AutoCAD SHX Text
LINK NAME:
AutoCAD SHX Text
FILE:
AutoCAD SHX Text
OSP PROJECT LOG #:
AutoCAD SHX Text
TITLE PAGE
AutoCAD SHX Text 23230501
AutoCAD SHX Text
ICN CABLE RELOCATION
AutoCAD SHX Text
CLINTON - MANUFACTORING DR
AutoCAD SHX Text 903 (4F)
AutoCAD SHX Text
NONE
AutoCAD SHX Text 11 x 17
AutoCAD SHX Text
AutoCAD SHX Text
400 EAST 14TH STREET
DES MOINES, IOWA 50319
ICN © 2021, COPY WITH PERMISSION
IOWA COMMUNICATIONS NETWORK
STANDARD INSTALLATION REQUIREMENTS:
GENERAL REQUIREMENTS:
1. THE CONTRACTOR SHALL POTHOLE ALL EXISTING UTILITIES.
2. PROVIDE THE OWNERS OF ANY NATURAL GAS UTILITY 48 HOURS ADVANCE NOTICE THAT WORK IS
SCHEDULED IN THE VICINITY OF THEIR LINES/MAINS SO THAT THEY CAN PROVIDE STANDBY AND
PROTECT SERVICES.
3. MAINTAIN PROOF OF NOTIFICATION TO AND RECEIPT OF NOTIFICATION BY THE GAS UTILITY.
4. PERMITS AND COORDINATION
4.1. SECURE ALL NECESSARY STATE AND LOCAL (CITY, COUNTY, ETC.) PERMITS, PUBLIC OR PRIVATE
EASEMENTS, FACILITY PERMITS, USAGE PERMITS, AND ANY OTHER PERMIT REQUIRED BY AN
AUTHORITY HAVING JURISDICTION (AHJ).
4.2. ICN WILL OBTAIN AND PROVIDE COPIES OF IDOT PERMITS.
4.3. IF PERMITS ARE REQUIRED TO BE IN THE NAME OF THE OWNER RATHER THAN THE CONTRACTOR, THE
CONTRACTOR SHALL PREPARE THE PERMIT FOR THE OWNER'S SIGNATURE.
4.4. COORDINATE INSTALLATION WITH ALL OWNERS AND AHJ OVER THE ROUTE, THE FIBER,
RIGHT-OF-WAY AND BUILDINGS IN WHICH END POINTS WILL BE LOCATED.
4.5. FAILURE TO COORDINATE WITH THE AHJ AND TO OBTAIN ALL NECESSARY PERMITS IS AT THE PERIL
OF THE CONTRACTOR.
4.6. RIGHT-OF-WAY PERMIT FEES ARE AN AUTHORIZED EXTRA ABOVE THE QUOTED BID PRICE.
EXCAVATION PERMITS SHALL BE BY THE CONTRACTOR.
4.7. ENSURE ALL FACILITIES ARE PLACED WITHIN THE PUBLIC RIGHT-OF-WAY.
5. ENSURE THAT PERSONNEL WORKING IN THE ROW ARE EQUIPPED WITH AND USE PROPER SAFETY
EQUIPMENT AND ATTIRE.
6. ALL TOOLS AND TEST EQUIPMENT REQUIRED TO DO A PROJECT SHALL BE PROVIDED BY THE CONTRACTOR OR ITS SUBCONTRACTOR(S). SECURITY OF TOOLS AND TEST EQUIPMENT SHALL BE THE RESPONSIBILITY OF EACH WORKER. THE ICN SHALL NOT BE RESPONSIBLE FOR THE SECURITY OF ANY PROPERTY LEFT ON ICN'S PROPERTY OR ON PROPERTY CONTROLLED BY THE ICN OR THE STATE OF
IOWA.
7. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTRUCTING ITS EMPLOYEES IN SAFETY MEASURES
CONSIDERED APPROPRIATE FOR THE JOB. IN ADDITION, THE CONTRACTOR SHALL NOT PERMIT
PLACING OR USE OF TOOLS OR MATERIALS IN TRAFFIC LANES OR OTHER LOCATIONS. THE TOOLS OR MATERIALS SHALL NOT BE PLACED IN SUCH A MANNER SO AS TO CREATE SAFETY HAZARDS TO STATE
EMPLOYEES, CONTRACTING AGENCY EMPLOYEES, THE PUBLIC OR THEMSELVES.
8. EXCAVATIONS AND TRENCHES: THE ICN REQUIRES ALL OPEN EXCAVATIONS OR TRENCHES TO BE
MONITORED AND ATTENDED TO DURING CONSTRUCTION PER. THE ICN REQUIRES ALL OPEN
EXCAVATIONS AND TRENCHES BACKFILLED THE SAME DAY. IF THE CONTRACTOR IS REQUIRED TO LEAVE AN EXCAVATION OR TRENCH OPEN, THEN THE CONTRACTOR SHALL PROPERLY FENCE AND/OR COVER THE EXCAVATION FOR SAFETY. CONTRACTOR SHALL FOLLOW ALL OSHA REQUIREMENTS FOR
EXCAVATION AND TRENCH SAFETY.
9. CONTRACTOR AND ITS EMPLOYEES SHALL COMPLY WITH ALL OSHA REGULATIONS. THE CONTRACTOR
SHALL COMPLY WITH ALL APPLICABLE STATE AND FEDERAL LAWS.
10. CONTRACTOR SHALL COMPLY WITH ALL IOWA ONE CALL REQUIREMENTS AS PROVIDED BY IOWA CODE, CHAPTER 480.
11. PROVIDE ALL LABOR AND SUPERVISION FOR THE PROJECT.
12. PROVIDE AND INSTALL MATERIALS NEEDED TO RESULT IN A FULLY FUNCTIONAL SYSTEM MEETING ICN
STANDARDS, WHETHER OR NOT THE MATERIALS OR METHODS ARE SPECIFICALLY MENTIONED IN THIS
DOCUMENT. SEE THE LIST OF ICN-FURNISHED MATERIALS.
13. INSTALL CABLE ROUTE MARKERS FURNISHED BY ICN. WHERE POSSIBLE, INSTALL MARKERS ADJACENT
TO POLES, BUILDINGS OR IN OTHER PROTECTED AREAS.
14. A COPY OF THIS SCOPE OF WORK AND THE ENGINEERING PLAN FOR THIS PROJECT SHALL BE ON SITE AND AVAILABLE ANY TIME WORK IS BEING PERFORMED. FAILURE TO HAVE THE REQUIRED DOCUMENTS ON SITE MAY RESULT IN ICN REQUIRING THE CONTRACTOR TO STOP WORKING UNTIL THE REQUIRED
DOCUMENTS ARE ON-SITE.
15. SUBCONTRACTORS SHALL MEET THE SAME QUALIFICATIONS STATED FOR CONTRACTORS.
CONTRACTOR SHALL OBTAIN APPROVAL OF THE CONTRACTING AGENCY'S PROJECT MANAGER PRIOR
TO USING A SUBCONTRACTOR ON ANY PROJECT.
16. RESTORE ALL DAMAGE TO PRIVATE PROPERTY, RIGHT-OF-WAY, ICN PROPERTY, AND ANY OTHER
PROPERTY DAMAGED IN THE COURSE OF THE WORK.
16.1.ANY DISRUPTION OF GRASS IN AN INDIVIDUAL'S YARD OR IN A PRIVATE MAINTAINED AREA OF THE PUBLIC RIGHT OF WAY (THE AREA BETWEEN THE SIDEWALK AND THE STREET CURB) MUST BE
RESTORED THROUGH RE-SODDING. ANY DISRUPTION OF THE GRASS IN THE MEDIAN WAY OR AN
UNIMPROVED SHOULDER MUST BE RESTORED EITHER THROUGH RE-SODDING OR RE-SEEDING AS
REQUIRED BY THE ROW OWNER.
16.2.AREAS SHALL BE RESTORED TO ORIGINAL OR BETTER CONDITION.
16.3. DIRT SHALL BE MECHANICALLY COMPACTED AROUND HANDHOLES AND PITS.
16.4. LAWNS SHALL BE SODDED WITH LIKE GRASS.
16.5. CONTRACTOR IS RESPONSIBLE FOR WATERING THE SOD UNTIL IT HAS KNITTED TO THE
GROUND BENEATH.
DUCT INSTALLATION REQUIREMENTS
1. HDPE DUCT SHALL BE NO LESS THAN 48 INCHES DEEP.
2. DUCT SHALL BE INSTALLED IN THE PUBLIC RIGHT-OF-WAY.
3. WHEN CROSSING A HIGHWAY IN DOT RIGHT-OF-WAY, DUCT SHALL BE NO LESS THAN 48 INCHES BELOW
GRADE UNDER THE ROADWAY AND SHOULDERS. HDPE MAY BE USED UNDER THE ROADWAY AND
SHOULDERS IF INSTALLED AT A MINIMUM DEPTH OF 48”.
4. SHOULD IT BE NECESSARY TO CROSS PRIVATE PROPERTY, THE CONTRACTOR MAY APPLY TO THE ICN
FOR AN EXCEPTION, AND REQUEST PERMISSION TO SECURE AN EASEMENT. THE EASEMENT IS
REQUIRED TO BE IN THE NAME OF ICN AND THE CONTRACTOR SHALL HAVE THE EASEMENT PREPARED BY A LAND SURVEYOR LICENSED IN THE STATE OF IOWA. CONTRACTOR SHALL BE RESPONSIBLE FOR
ALL FEES UNLESS PREVIOUSLY AUTHORIZED BY THE ICN.
5. AT THE CONCLUSION OF THE PROJECT, PROVIDE AND LEAVE A PULL ROPE IN ALL DUCTS, CONDUITS
AND PATHWAYS, INCLUDING INDOOR, OUTDOOR, NEW AND EXISTING.
6. DIRT SHALL BE MECHANICALLY COMPACTED AT ALL DUCT SPLICES, BORE PITS AND AROUND
HANDHOLES.
7. GROUND SHALL BE RESTORED TO THE CONDITION FOUND PRIOR TO CONSTRUCTION AND DEBRIS
REMOVED PRIOR TO SODDING OR SEEDING.
8. ALL CONDUITS SHALL BE PLUGGED VIA DUCT SEAL OR OTHER METHOD UPON COMPLETION OF CABLE
INSTALLATION.
9. IF SCHEDULE 40 PVC CONDUIT IS UTILIZED, ALL ANGLES (45, 90 DEGREE OR OTHER) REQUIRE FITTINGS
TO LONG SWEEP TO ACCOMMODATE MINIMUM CABLE BEND RADIUSES.
10. THE ICN REQUIRES PICTURES BY THE CONTRACTOR AND/OR ON- SITE INSPECTION BY ICN STAFF PRIOR TO COMPLETION OF THE PROJECT WHERE PIPE AND FITTINGS ARE NOT EXPOSED; I.E. UNDERGROUND, BEHIND A WALL, ETC.
HANDHOLE REQUIREMENTS
1. INSTALL HANDHOLES SO THAT THE LID IS LEVEL AND FLUSH WITH THE SURROUNDING NATURAL GRADE.
THE LID SHALL NOT EXTEND ABOVE THE SURROUNDING NATURAL GRADE.
2. PROVIDE ¼” OPENING HARDWARE CLOTH TYPE SCREEN WIRE BELOW THE HANDHOLE.
3. PROVIDE 5-6 INCHES OF ¾” CRUSHED ROCK BELOW THE HANDHOLE. ROCK SHALL BE COMPACTED.
GRAVEL SHALL EXTEND A MINIMUM OF 6 INCHES BEYOND THE OUTSIDE WALLS OF THE HANDHOLE. DO
NOT USE PEA GRAVEL OR OTHER ROUND STONE.
4. DO NOT PLACE GRAVEL INSIDE HANDHOLE ABOVE THE HARDWARE CLOTH.
5. CONDUIT SHALL EXTEND A MINIMUM OF 6” ABOVE THE HARDWARE CLOTH/GRAVEL.
6. FAILURE OF THE CONTRACTOR TO INSTALL HANDHOLES AS SPECIFIED WILL CAUSE THE CONTRACTOR
TO RETURN AND RE-INSTALL THE HANDHOLE ACCORDING TO THIS SPECIFICATION BEFORE PAYMENT
FOR THE PROJECT IS MADE.
7. HANDHOLE INSTALLATIONS SHALL FOLLOW ICN STANDARD TYPICAL INSTALLATION; SEE TYPICAL
DRAWING.
FIBER INSTALLATION REQUIREMENTS
1. INSTALL FIBER ACCORDING TO INDUSTRY “BEST PRACTICES”.
2. THE CONTRACTOR SHALL NOT VIOLATE THE MANUFACTURER'S MINIMUM INSTALLATION BEND RADIUS
WHEN THE CABLE IS UNDER TENSION, OR THE MINIMUM INSTALLED BEND RADIUS.
3. TO PREVENT EXCEEDING THE MANUFACTURER'S MAXIMUM PULLING TENSION DURING INSTALLATION OF THE FIBER OPTIC CABLE, THE CONTRACTOR SHALL USE A “BREAK-AWAY” PULLING SWIVEL WHEN
INSTALLING CABLE.
4. THE “BREAK-AWAY” FUNCTION SHALL ACTIVATE AT OR BELOW THE MAXIMUM PULLING TENSION
SPECIFIED BY THE CABLE MANUFACTURER.
5. THE CONTRACTOR SHALL TEST ALL STRANDS OF THE FIBER, ON THE REEL, PRIOR TO BEGINNING FIBER
INSTALLATION. CONFIRM THAT ALL STRANDS MEET MANUFACTURER'S LOSS SPECIFICATIONS.
6. THE CONTRACTOR SHALL FIELD VERIFY ALL LENGTHS AND EXISTING CONDITIONS PRIOR TO STARTING
CONSTRUCTION.
7. SLACK LOOPS IN HANDHOLES SHALL BE COILED, INSTALLED, AND SECURED TO AVOID DAMAGE TO THE
COIL AND NOT INTERFERE WITH LIDS.
8. SLACK LOOPS AT SPLICES SHALL BE COILED TO MATCH THE EXISTING FIBER CABLE TAILS AND
ALLOWANCE FOR SPLICE PREPARATION.
9. ICN FIBER IN ALL HANDHOLES SHALL BE LABELED WITH ICN WRAP AROUND CABLE TAGS OR OTHER
LABELED CABLE TAGS.
BUILDING ENTRY REQUIREMENTS
1. WEATHER-SEAL ALL PENETRATIONS.
2. USE MORTAR OR SIMILAR CEMENT TO SEAL PENETRATION OF BRICK OR CEMENT BLOCK.
3. FIRESTOP PENETRATIONS OF ANY FIRE-RATED FLOOR, WALL OR CEILING.
4. REPLACE THE FIRESTOP MATERIAL IN ANY EXISTING FIRESTOPPED PENETRATION USED BY THE
CONTRACTOR.
5. ALL OUTDOOR CONDUITS, OF ANY LENGTH, SHALL BE GALVANIZED IRON PIPE (GIP). EMT, PVC AND
PLASTIC ARE PROHIBITED.
LOCATE FACILITY REQUIREMENTS
1. TRACER WIRE SHALL BE CONTINUOUS.
2. SPLICES IN THE TRACER WIRE ARE NOT ALLOWED. IF TRACER WIRE IS ACCIDENTALLY SEVERED, REQUEST PERMISSION FROM ICN TO SPLICE.
3. WIRE SPLICES ONLY IN HANDHOLES.
4. USE EITHER AN EPOXY SPLICE KIT, SCOTCH 3M 3832 OR A MOLEX PERMASEAL BUTT SPLICE. 10-12 GA.
SPLICE MATERIALS SHALL BE DESIGNED FOR UNDERGROUND APPLICATIONS.
5. LEAVE THE WIRE SPLICE VISIBLE IN THE HANDHOLE.
6. ROUTE A GROUND WIRE FROM THE GROUND INSIDE THE BUILDING, THROUGH THE ENTRY TO THE TII 163
TERMINAL.
7. SECURE ALL RISER CONDUITS WITH 3 EACH TWO-HOLE CONDUIT STRAPS.
8. WIRE THE PEDESTAL/TERMINAL SO THAT LOCATES MAY BE PERFORMED IN ANY DIRECTION AND FROM
THE FAR END.
9. DO NOT LEAVE ANY EXPOSED TRACER WIRE OR GROUND WIRE.
10. PERMANENTLY GROUND THE TRACER WIRE AT THE HANDHOLE ON THE FURNISHED GROUND ROD.
11. AT THE CONCLUSION OF THE PROJECT LEAVE THE TRACER WIRE SHIELD SHORTED TO GROUND IN THE
LOCATE TERMINAL.
12. USE TRACER WIRE THAT IS RATED FOR DIRECT BURIAL WHERE REQUIRED. TRACER WIRE SHALL BE #12 AWG, SOLID HF CCS 30 MIL HDPE HIGH FLEX TRACER WIRE: EITHER SOLID COPPER OR COPPER CLAD
STEEL.
13. LABEL ALL WIRES IN THE LOCATE TERMINAL/PEDESTAL/TRIVIEW. (I.E. “GROUND”, “FACING DMACC”, “FACING NORTH” ETC.)
14. FAILURE TO LABEL THE LOCATE WIRES WILL CAUSE THE CONTRACTOR TO RETURN AND PROPERLY
LABEL THE WIRES BEFORE PAYMENT FOR THE PROJECT IS MADE.
15. BOND TRACER WIRE(S) WITHIN SPLICE ENCLOSURES UTILIZING A 3M 4460-D\FO SHIELD BONDING KIT.
16. ROUTE TRACER WIRE(S) OUT OF SPLICE ENCLOSURE THROUGH A SINGLE PORT UTILIZING A FOSC
CLOSURE SEALING KIT.
17. AT SPLICE LOCATIONS WITH NO LOCATE PEDESTAL, TRACER WIRES SHALL BE BONDED TOGETHER, WITHIN THE SPLICE ENCLOSURE.
18. AT EACH END OF ANY TRACER WIRE, USE APPROPRIATE-SIZED RING TERMINAL (CRIMP) CONNECTORS USING APPROPRIATE CRIMP TOOL; OR CREATE A WIRE EYELET AS PER TYPICAL INSTALLATION OF
TRI-VIEW LOCATE PEDESTAL DETAIL.
DELIVERABLES/ACCEPTANCE:
1. CONTRACTOR SHALL PROVIDE CONSTRUCTION REDLINE AS-BUILTS WITH:
1.1. OFFSETS TO FIXED OBJECTS TO THE CABLE/CONDUIT RUNNING LINE, HANDHOLES AND NEW
FACILITIES.
1.2. METER MARKS OF CABLE INSTALLATIONS AT HANDHOLE ENTRY/EXIT, SPLICE LOCATIONS, BUILDING
ENTRIES, ETC.
1.3. DEPTHS OF CABLE AND/OR CONDUIT INSTALLATION.
1.4. ONE ORIGINAL SET OF AS-BUILT DRAWINGS MUST BE PROVIDED WITHIN TWO (2) WEEKS AFTER COMPLETION OF CONSTRUCTION FOR THE ICN MANAGEMENT RECORDS. REDLINE AS-BUILT DRAWINGS
MUST BE COMPLETE.
2. CONTRACTOR SHALL PROVIDE SPLICING REDLINE OF ALL SPLICING COMPLETED AND VALIDATION THAT
THE SPLICE PLAN WAS FOLLOWED.
3. CONTRACTOR IS RESPONSIBLE TO LOCATE FIBER UNTIL ACCEPTANCE BY THE ICN. ACCEPTANCE
INCLUDES:
3.1. SUBMISSION OF CONSTRUCTION AND SPLICING RED LINE DRAWINGS BY CONTRACTOR.
3.2. ASSIGNMENT OF LINK NUMBER BY THE ICN (IF APPLICABLE).
3.3. SUBMISSION OF FINAL AS BUILT DRAWING BY THE ICN TO THE ICN NETWORK MAINTENANCE
PROVIDER.
3.4. SUBMISSION TO IOWA ONE CALL AND THE ICN NETWORK MAINTENANCE PROVIDER'S CONTRACT
LOCATER.
3.5. THE MEASUREMENTS IN THE STATEMENT OF WORK ARE ESTIMATES AND NEED TO BE VERIFIED BY
THE CONTRACTOR.
4. ONLY WRITTEN MODIFICATIONS TO THIS SCOPE OF WORK ARE BINDING - VERBAL CHANGES TO THIS SCOPE OF WORK BY ANY PERSON OR PERSONS ARE NOT BINDING, UNLESS CONFIRMED IN WRITING.
5. FINAL PAYMENT WILL NOT BE PROCESSED UNTIL ALL DELIVERABLES ARE RECEIVED AND ACCEPTED.
16.6.ALL DEBRIS SHALL BE REMOVED FROM THE CONSTRUCTION AREAS INCLUDING BUT NOT 6. IMMEDIATELY UPON INSTALLATION, SEAL THE ENDS OF ALL DUCTS WITH DUCT SEAL OR EXPANSION LIMITED TO: CONSTRUCTION MATERIALS, TRASH, LARGE OBJECTS OR STONES WITHIN BACKFILLED FOAM TO PREVENT SILTATION OR FILLING WITH MOISTURE. THIS APPLIES TO BOTH NEW AND EXISTING
AREAS, ETC. DUCTS.
7. AT THE CONCLUSION OF THE PROJECT, ENSURE THAT A PULL ROPE IS LEFT IN ALL PATHWAYS, BOTH
INSIDE AND OUTSIDE, NEW AND EXISTING.
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
SIZE:
AutoCAD SHX Text R:\OSP PROJECTS\HARRIS\Clinton County\23230205 - Possibly Conflict Along S Bluff Blvd In Clinton\ICN RELO PLANS\23230205 - TITLE PAGE.dwg
AutoCAD SHX Text
OF
AutoCAD SHX Text
PAGE
AutoCAD SHX Text
LINK NAME:
AutoCAD SHX Text
FILE:
AutoCAD SHX Text
OSP PROJECT LOG #:
AutoCAD SHX Text
ICN GENERAL NOTES
AutoCAD SHX Text 23230501
AutoCAD SHX Text
ICN CABLE RELOCATION
AutoCAD SHX Text
CLINTON - MANUFACTORING DR
AutoCAD SHX Text 903 (4F)
AutoCAD SHX Text
NONE
AutoCAD SHX Text 11 x 17
AutoCAD SHX Text
DES MOINES, IOWA 50319
ICN © 2021, COPY WITH PERMISSION
IOWA COMMUNICATIONS NETWORK
400 EAST 14TH STREET
NOTE ON HDPE CONDUIT AND SPLICES:
1. HDPE SHALL BE ORANGE SMOOTH WALL SDR 13.5
2. DUCT SPLICES SHALL BE MADE OF THE FOLLOWING (IN ORDER OF PREFERENCE.)
-ELECTROFUSION
-CRIMP ON
-CLAMP ON / BOLT ON (SPLIT COUPLINGS)
-PUSH ON
3. ALL SPLICES SHALL BE AIR AND WATER TIGHT
4. DUCT SPLICES SHALL BE OF A TYPE MADE SPECIFICALLY FOR JOINING HDPE CONDUIT
5. ALL DUCT SPLICES SHALL BE MADE IN SUCH MANNER AS TO ALLOW CONTINUOUS PULLING OF
CABLE THROUGH DUCT.
NOTE ON OSP FIBER CABLE
Single Mode, Single Armor, Gel Free, Loose Tube OSP cable (12-strand minimum, refer to Materials) Tensile Strength: 600 lb short term Attenuation: 0.35/0.25 dB at 1310/1440 nm
NOTE ON HANDHOLE(S):
Polymer Concrete (Quazite, New Basis, Martin, e.g.) 24"x36"x30" Tier 15 Hybrid Polymer Concrete - Fiberglass (Oldcastle FRP, e.g.) 24"x36"x30" Tier 15
*NOTE ON CONTRACTOR PROVIDED MATERIAL(S):
Contractor shall supply all other materials required for proper installation, including but not limited to: HDPE, Duct Splices, Grounding and Tracer Wires, Rock, Wire Mesh, etc.
ANY EXCEPTIONS MUST BE AGREED UPON IN WRITING PRIOR TO CONSTRUCTION.
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
SIZE:
AutoCAD SHX Text R:\OSP PROJECTS\HARRIS\Clinton County\23230205 - Possibly Conflict Along S Bluff Blvd In Clinton\ICN RELO PLANS\23230205 - TITLE PAGE.dwg
AutoCAD SHX Text
OF
AutoCAD SHX Text
PAGE
AutoCAD SHX Text
LINK NAME:
AutoCAD SHX Text
FILE:
AutoCAD SHX Text
OSP PROJECT LOG #:
AutoCAD SHX Text
MATERIALS
AutoCAD SHX Text 23230501
AutoCAD SHX Text
ICN CABLE RELOCATION
AutoCAD SHX Text
CLINTON - MANUFACTORING DR
AutoCAD SHX Text 903 (4F)
AutoCAD SHX Text
NONE
AutoCAD SHX Text 11 x 17
AutoCAD SHX Text
AutoCAD SHX Text https://0.35/0.25
NEW HDPE W/ 48F
NEW
HDPE
W / 4
8F
2+
SE
C. L
INE
CLINTON CO. CLINTON CO.
CLINTON TOWNSHIP CLINTON TOWNSHIP
T81N-R07E SEC. 1 T81N-R07E SEC. 6
CONSTRUCTION DOCUMENT
IOWA COMMUNICATIONS NETWORK
400 EAST 14TH STREET
GRIMES STATE OFFICE BUILDING
DES MOINES, IOWA 50319
ICN © 2023, COPY WITH PERMISSION
AutoCAD SHX Text 50'
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
SCALE IN FEET
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
EXISTING ICN DUCT
AutoCAD SHX Text
PROPOSED ICN DUCT
AutoCAD SHX Text
PROPOSED ICN HANDHOLE
AutoCAD SHX Text
EXISTING ALLIANT POLE
AutoCAD SHX Text
EXISTING ICN (AERIAL)
AutoCAD SHX Text A
AutoCAD SHX Text
EXISTING ICN HANDHOLE
AutoCAD SHX Text
RIGHT-OF-WAY
AutoCAD SHX Text
ROW
AutoCAD SHX Text
TO BE ABANDONED
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
SIZE:
AutoCAD SHX Text R:\OSP PROJECTS\HARRIS\Clinton County\23230205 - Possibly Conflict Along S Bluff Blvd In Clinton\ICN RELO PLANS\Proposed Relocation Options.dwg
AutoCAD SHX Text
OF
AutoCAD SHX Text
PAGE
AutoCAD SHX Text
LINK NAME:
AutoCAD SHX Text
FILE:
AutoCAD SHX Text
OSP PROJECT LOG #:
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
CABLE RELO
AutoCAD SHX Text 7-10-25
AutoCAD SHX Text
CABLE RELO
AutoCAD SHX Text
N BLUFF BLVD FROM N 6TH ST TO SPRINGDALE DR
AutoCAD SHX Text 1" = 40'
AutoCAD SHX Text 11 x 17
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 0903 (4F)
AutoCAD SHX Text 23230205
NOTES: 1. STA. 222+00: PLACE 24X36X30 HANDHOLE WITH LID AT GRADE SET MARKER - STA. 222+00: PLACE 24X36X30 HANDHOLE WITH LID AT GRADE SET MARKER - (SPLICE) 4. STA. 222+00 TO 221+50: EXPOSE 50-FT OF EXISTING, LIVE ICN CABLE FOR SPLICE STA. 222+00 TO 221+50: EXPOSE 50-FT OF EXISTING, LIVE ICN CABLE FOR SPLICE TAIL. 3. STA. 222+00 TO 3102+20: PLACE APPROX. 970-FT OF HDPE CONDUIT WITH NEW 48F STA. 222+00 TO 3102+20: PLACE APPROX. 970-FT OF HDPE CONDUIT WITH NEW 48F CONDUIT NOTES: HDPE SHALL BE ORANGE SMOOTH WALL SDR 13.5, MINIMUM 1.25-IN SEE ENGINEERING PLANS FOR SPECIAL DEPTH REQUIREMENTS AND ALL OTHER AREAS PLACE 48-TO-60 INCHES DEEP. PULL HDPE INTO HANDHOLE PER TYPICAL DRAWING CABLE NOTES: PULL THROUGH ONE NEW 48 ARMORED CABLE FROM END TO END. LEAVE 100-FT COILS IN HANDHOLE
NEW HDPE W/ 48F
CLINTON CO.
CLINTON TOWNSHIP
T81N-R07E SEC. 6
CONSTRUCTION DOCUMENT
· IOWA COMMUNICATIONS NETWORK
400 EAST 14TH STREET
GRIMES STATE OFFICE BUILDING
DES MOINES, IOWA 50319
ICN © 2023, COPY WITH PERMISSION
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
SCALE IN FEET
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
EXISTING ICN DUCT
AutoCAD SHX Text
PROPOSED ICN DUCT
AutoCAD SHX Text
PROPOSED ICN HANDHOLE
AutoCAD SHX Text
EXISTING ALLIANT POLE
AutoCAD SHX Text
EXISTING ICN (AERIAL)
AutoCAD SHX Text A
AutoCAD SHX Text
EXISTING ICN HANDHOLE
AutoCAD SHX Text
RIGHT-OF-WAY
AutoCAD SHX Text
ROW
AutoCAD SHX Text
TO BE ABANDONED
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
SIZE:
AutoCAD SHX Text R:\OSP PROJECTS\HARRIS\Clinton County\23230205 - Possibly Conflict Along S Bluff Blvd In Clinton\ICN RELO PLANS\Proposed Relocation Options.dwg
AutoCAD SHX Text
OF
AutoCAD SHX Text
PAGE
AutoCAD SHX Text
LINK NAME:
AutoCAD SHX Text
FILE:
AutoCAD SHX Text
OSP PROJECT LOG #:
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
CABLE RELO
AutoCAD SHX Text 1-7-19
AutoCAD SHX Text
CABLE RELO
AutoCAD SHX Text
N BLUFF BLVD FROM N 6TH ST TO SPRINGDALE DR
AutoCAD SHX Text 1" = 100'
AutoCAD SHX Text 11 x 17
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 0903 (4F)
AutoCAD SHX Text 23230205
NOTES: 3. STA. 222+00 TO 3102+20: CONTINUE CABLE PLACEMENT STA. 222+00 TO 3102+20: CONTINUE CABLE PLACEMENT 4. STA. 222+00: PLACE 24X36X30 HANDHOLE WITH LID AT GRADE BESIDE POLE - END STA. 222+00: PLACE 24X36X30 HANDHOLE WITH LID AT GRADE BESIDE POLE - END HDPE/CABLE - STUB OUT TWO DUCTS INTO HH (LOCATE POINT/SPLICE POINT) 5. STA. 3101+90: EXISTING ICN HH/SPLICE. IRHTP 36F & SEGRA 24F TO BE CUT FROM STA. 3101+90: EXISTING ICN HH/SPLICE. IRHTP 36F & SEGRA 24F TO BE CUT FROM SPLICE CASE NIGHT OF SPLICE AND PULLED BACK THROUGH EXIST. CONDUIT TO NEW HH FOR 3-WAY SPLICE. HANDHOLE TO BE REMOVED AFTER SPLICE. SEE DIAGRAM A. CONDUIT NOTES: HDPE SHALL BE ORANGE SMOOTH WALL SDR 13.5, MINIMUM 1.25-IN SEE ENGINEERING PLANS FOR SPECIAL DEPTH REQUIREMENTS AND ALL OTHER AREAS PLACE 48-TO-60 INCHES DEEP. PULL HDPE INTO HANDHOLE PER TYPICAL DRAWING CABLE NOTES: PULL THROUGH ONE NEW 48 ARMORED CABLE FROM END TO END. LEAVE 100-FT COILS IN HANDHOLE.
DIAGRAM A
SWING EXIST. IRHTP 36F INTO TO NEW
HH/MAINT SPLICE THE NIGHT OF THE
SPLICE. SEGRA WILL NEED TO DO THE
SAME. NEW PIECE OF CONDUIT
INSTALLED FROM NEW HH TO RISER &
FOR SEGRA
EMPTY DUCT FOR SEGRA
CUT IRHTP 36F & PULL BACK TO NEW
HH/MAINT SPLICE THE NIGHT OF THE
SPLICE. SEGRA WILL NEED TO DO THE
SAME. HH TO BE REMOVED AFTER SPLICE
CONSTRUCTION DOCUMENT
IOWA COMMUNICATIONS NETWORK
400 EAST 14TH STREET
GRIMES STATE OFFICE BUILDING
DES MOINES, IOWA 50319
ICN © 2023, COPY WITH PERMISSION
AutoCAD SHX Text
LS439 (EXIST. SPLICE)
AutoCAD SHX Text
LINK 903A -4FLINK 903A -4F
AutoCAD SHX Text
EXISTING 1.25-IN IRHTP LINK 7036 -36F & SEGRA 24FSEGRA 24F
AutoCAD SHX Text
NEW HH/MAINT SPLICE
AutoCAD SHX Text
IRHTP LINK 36F
AutoCAD SHX Text
IRHTP LINK 36F
AutoCAD SHX Text
NEW 1.25-IN HDPE W/ 48FNEW 1.25-IN HDPE W/ 48F
AutoCAD SHX Text
EXISTING 1.25-IN TO BE ABANDONED AFTER SPLICE
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
EXISTING ICN DUCT
AutoCAD SHX Text
PROPOSED ICN DUCT
AutoCAD SHX Text
PROPOSED ICN HANDHOLE
AutoCAD SHX Text
EXISTING ALLIANT POLE
AutoCAD SHX Text
EXISTING ICN (AERIAL)
AutoCAD SHX Text A
AutoCAD SHX Text
EXISTING ICN HANDHOLE
AutoCAD SHX Text
RIGHT-OF-WAY
AutoCAD SHX Text
ROW
AutoCAD SHX Text
TO BE ABANDONED
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
SIZE:
AutoCAD SHX Text R:\OSP PROJECTS\HARRIS\Clinton County\23230205 - Possibly Conflict Along S Bluff Blvd In Clinton\ICN RELO PLANS\Proposed Relocation Options.dwg
AutoCAD SHX Text
OF
AutoCAD SHX Text
PAGE
AutoCAD SHX Text
LINK NAME:
AutoCAD SHX Text
FILE:
AutoCAD SHX Text
OSP PROJECT LOG #:
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
CABLE RELO
AutoCAD SHX Text 7-10-25
AutoCAD SHX Text
CABLE RELO
AutoCAD SHX Text
N BLUFF BLVD FROM N 6TH ST TO SPRINGDALE DR
AutoCAD SHX Text 1" = 40'
AutoCAD SHX Text 11 x 17
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 0903 (4F)
23230205
| Sheets and Views |
| 23230205 - TITLE PAGE-TITLE PAGE |
| 23230205 - TITLE PAGE-ICN GENERAL NOTES |
| 23230205 - TITLE PAGE-MATERIALS |
| Proposed relocation options-1 |
| Proposed relocation options-2 |
| Proposed relocation options-DIAGRAM A |
File details come from the government source that posted it. Updated .