This document is Addendum #2 for Gaston College's Invitation for Bid (IFB) #25-021, related to the procurement of Welding TIG Machines for the college's Welding Technology Program. The addendum updates the bid's response timeline, pushing the due date to 7/14/2025 at 4:00 PM, and provides clarifying responses to five vendor questions regarding electrical requirements, torch specifications, training expectations, and machine configuration. The addendum emphasizes that vendors must configure machines for single-phase power, provide a specific torch type (CKC-150, 2-piece, 12.5ft, Rigid Head style), and include mandatory on-site training costs within their total extended item cost.

The addendum includes technical details such as electrical supply specifications, with a photo of a PWA-12 wall plug illustrating the power connection type. Vendors are instructed to review Section 2.7 and include this addendum in their bid response, with a warning that failure to provide all required items may result in bid rejection. The document clarifies that quotes for additional items like water coolers or machine carts are not currently requested, and on-site training is compulsory. Vendors must provide comprehensive electrical supply details in their response and ensure their machines meet the specified single-phase power configuration requirements.

View the file

Other files

File Type Posted
25-021 - IFB Welding Tig Machines.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gaston College IFB #25-021 Addendum # 2 (to be submitted with Bid) Vendors are strongly encouraged to review Section 2.7 and include this addendum in their response to the bid. Failure to provide all required items may result in the rejection of the bid.

Due to an error in posting Addendum #1, the new due date is 7/14/2025 at 4:00 PM

This addendum updates the questions and answers for the IFB 25-021.

Question 1: Can you please provide us with the Manufacture and part number of wall plug needed?

Response 1: The main power supply to the shop panels is three-phase. However, the current machines are wired for single-phase power, using a three-prong connection. Vendors should have machines configured for single-phase operation.

Vendors must include electrical supply details in their response (See Section 4.8).

Question 2: Do you require a cooler?

Response 2: We are requesting bids for the power unit or head machine as outlined in Section 5. Please note that quotes for water coolers or machine carts are not requested at this time.

Question 3: Will you be needing set up and training for the machines?

Response 3: Please refer to Section 4.4 for delivery and setup details, and Section 5.1, Item 2 for training information.

Question 4: Which torch type were you looking for Response 4: The required torch needs to be a CKC-150 (2- piece) 12.5ft, Rigid Head style, Standard torch or similar; Item # CKC1512N or similar

Question 5: If we mark no on training, will this disqualify us from the bid? Where do we include training cost?

Response 5: On-site training is required. Vendors must include all costs as a total extended cost of the item.