24Z1A1B AST SOW.pdf
PDF 4 MB Posted
- Solicitation number
- 15BFA025Q00000195
About this file
This Statement of Work (SOW) details the requirements for supplying and installing a 12,000-gallon Disaster Proof Aboveground Storage Tank (AST) for diesel fuel at the Federal Correctional Institution (FCI) Cumberland in Maryland. The project scope includes providing a new AST with an integrated three-stage Polishing Unit, located at the end of building SB (Powerhouse), and involves comprehensive installation services such as site preparation, concrete pad construction, tank mounting, fuel system connections, monitoring equipment installation, and system testing.
Key contractor responsibilities include hooking up the AST to existing backup generators, transferring existing fuel, adhering to spill prevention plans, performing pressure tests, installing a new filtering/polishing system, running electrical wiring, powering up and testing the system, providing staff training, obtaining necessary permits, and ensuring proper cleanup and disposal of project-related debris. The contractor must comply with all federal, state, and local safety standards, provide personal protective equipment, submit required documentation, and furnish a written guarantee covering materials and workmanship. The project will be executed under strict security protocols at the correctional facility, with specific requirements for contractor access, background checks, and institutional work procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MR Questionnaire - FCI Cumberland.pdf | ||
| MR Questionnaire - FCI Cumberland.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Digitally signed by JOSEPH
JOSEPH FISHER �!:��02s.03.1ao1:oo:24 -04'00'
APPROVED
STATEMENT OF WORK
FCI CUMBERLAND B&F PROJECT
24Z1A1B SUPPLY AND INSTALL OF
DISASTER PROOF AST
8y J. Flshet, IIIXR Facllltles Admlnlstn,tor •t 7:00 am. Alar 11, 2025
I. SPECIFICATIONS:
A. INTRODUCTION
The Federal Bureau of Prisons (FBOP), Federal Correctional Institution (FCI) Cumberland, 14601 Burbridge Rd. SE
Cumberland, MD, intends to make a single award to a responsible entity that will provide the equipment and installation of a 12,000-gallon Disaster Proof Aboveground Storage Tank (AST) for diesel fuel.
B. SCOPE OF WORK
The successful contractor shall provide labor, equipment, parts, materials and supplies to provide the following:
1. Contractor shall provide and install a new 12,000-gallon Aboveground Storage Tank (AST) with an integrated three stage Polishing Unit at the end of building SB (Powerhouse).
2. Contractor shall hook up the AST to the existing back up generators
3. Contractor shall utilize the existing fuel transfer system.
4. Contractor shall be responsible for the transfer of existing fuel into the new AST.
5. Contractor shall be responsible for adhering to the owners Spill, Prevention, Countermeasure, and Containment plan and provide any spill containment devices.
6. Contractor provided AST system shall include site preparation, form and pour a new 40' x 12' x 9" concrete pad, properly vented 12,000-gallon Disaster proof AST stairs, 4" bollards, 10 gallon remote fill spill bucket, remote fill cabinet, tank monitor/leak detection control panel inside generator room/with a high level alarm, RA-1 mini alarm, tank monitor probes and sensors, vent riser and cap, primary and secondary emergency vent, fuel piping, mechanical interstitial gage, mechanical clock gauge with alarm to monitor inventory and piping that will be equipped with anti-siphon valve, fire valve and ball valve.
7. The contractor shall perform a pressure test on the tank.
8. The contractor shall install a new filtering/polishing system on the existing surface and connect it to the new
AST.
9. The contractor shall run wire from inside the Powerhouse to power the new AST system.
10. The contractor shall power up the system once the install is complete.
11. The contractor shall perform start up on the AST and filtering system.
12. The contractor shall test all systems and ensure proper operation prior to completion of the project.
13. The contractor shall provide training for all equipment pertaining to the install.
14. The contractor shall be responsible for obtaining all necessary permits and adhering to all regulations pertaining to AST's.
15. The contractor shall be responsible for cleanup and proper disposal of all debris generated by executing this work.
Notes:
• All equipment/manpower to install the AST system will be provided by the Contractor.
• The newly installed AST shall meet and/or exceed all technical specifications and guidelines
• Equipment, materials, and programming listed by manufacture.
• Contractor Field Technician: A contractor assigned worker, or contractor sponsored worker (sub-contractor) that has qualifying technical skills, expertise, and experience in a specific field of work or construction discipline.
May also be noted and used in this Statement of Work as a "Field Technician", "Worker", or "Contractor".
File details come from the government source that posted it. Updated .