24QB087 Salient Characteristics Concrete Forms.pdf
PDF 120 KB Posted
- Attached to
- Patrick Space Force Base - Concrete Forms Federal contract opportunity
- Solicitation number
- FA252124QB087
About this file
This document is a set of salient characteristics specifications for concrete forms required for a federal contract opportunity. The government requires the contractor to provide, installation not included, concrete forms for a K-SPAN building in a box complete kit foundation for a launch abort system hanger size: 40'H x 77.5"W x 104"L, in accordance with commercial industry standards. The salient characteristics provide specifications for one wall, with a requirement for two walls total. The document details the required formwork materials, accessories, installation, and tolerances.
The related federal contract opportunity is a sources sought notice for a small business set-aside requirement for the concrete forms. The government is conducting market research to determine interest, capability, and socio-economic status of potential sources. Interested parties are requested to submit a capabilities package with details on their business, any teaming arrangements, and relevant experience by August 8th. The government will use this information to determine the small business set-aside decision.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 24QB087 Sources Sought Concrete Forms.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Concrete Form Salient Characteristics Specifications
REF FA2452124QB087
1 | P a g e
1.1 Requirement: The government requires contractor to provide, installation not included, concrete forms for a K-SPAN building in a box complete kit foundation for a launch abort system hanger size:
40’H x 77.5”W x 104”L in accordance with commercial industries standards.
Salient Characteristics for Design/Specifications: Provides specifications for one (1) wall. Requirement is two (2) walls total.
2.1 FORMWORK MATERIALS
a. Design formwork to withstand pressure resulting from placement and vibration of concrete and to maintain specified tolerances.
b. Design formwork to accommodate waterstop materials in joints at locations indicated in Contract Documents.
c. Provide temporary openings in formwork if needed to facilitate cleaning and inspection.
d. Design formwork joints to inhibit leakage of mortar.
e. Limit deflection of facing materials for concrete surfaces exposed to view to 1/240 of center-to-center spacing of facing supports.
f. Do not use earth cuts as forms for vertical or sloping surfaces.
g. Submit product information on proposed form-facing materials if different from that specified herein.
h. Submit manufacturer's product data on form liner proposed for use with each formed surface.
2.1.1 Carton Forms
Moisture resistant treated paper faces, biodegradable, structurally sufficient to support weight of wet concrete until initial set.
2.1.2 Steel or Aluminum Forms
Provide form surfaces that do not contain irregularities, dents, or sags. Wood forms are not acceptable.
2.2 FORMWORK ACCESSORIES
a. Use commercially manufactured formwork accessories, including ties and hangers.
b. Form ties and accessories must not reduce the effective cover of the reinforcement.
2.2.1 Form Ties
a. Use form ties with ends or end fasteners that can be removed without damage to concrete.
b. Where indicated in Contract Documents, use form ties with integral water barrier plates or other acceptable positive water barriers in walls.
2.2.2 Waterstops
Submit manufacturer's data sheet on waterstop materials and splices.
2.2.2.1 PVC Waterstop
Polyvinylchloride waterstops must conform to Corps of Engineers (COE) CRD-C 572.
2.2.2.2 Rubber Waterstop
Rubber waterstops must conform to COE CRD-C 513.
2 | P a g e
2.2.2.3 Thermoplastic Elastomeric Rubber Waterstop
Thermoplastic elastomeric rubber waterstops must conform to ASTM D471.
2.2.2.4 Hydrophilic Waterstop
Swellable strip type compound of polymer modified chloroprene rubber that swells upon contact with water must conform to the following requirements when tested in accordance with American Society for Testing and Materials (ASTM) D412: Tensile strength 420 psi minimum; ultimate elongation 600 percent minimum. Hardness must be 50 minimum on the type A durometer and the volumetric expansion ratio in distilled water at 70 degrees F must be 3 to 1 minimum.
2.2.3 Biodegradable Form Release Agent
a. Provide form release agent that is colorless, biodegradable, and water-based, with a zero VOC content.
b. Provide product that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces.
c. Provide form release agent that reduces formwork moisture absorption, and does not contain diesel fuel, petroleum-based lubricating oils, waxes, or kerosene. Submit documentation indicating type of biobased material in product and biobased content. Indicate relative dollar value of biobased content products to total dollar value of products included in project.
d. Submit manufacturer's product data on formwork release agent for use on each form-facing material.
2.2.4 Chamfer Materials
Use lumber materials with dimensions of 3/4 x 3/4 in.
2.2.5 Construction and movement joints
a. Submit details and locations of construction joints in accordance with the requirements herein.
b. Locate construction joints within middle one-third of spans of slabs, beams, and girders.
If a beam intersects a girder within the middle one-third of girder span, the distance between the construction joint in the girder and the edge of the beam must be at least twice the width of the larger member.
c. Locate construction joints in walls and columns at underside of slabs, beams, or girders and at tops of footings or slabs.
d. Make construction joints perpendicular to main reinforcement.
e. Provide movement joints where indicated in Contract Documents or in accepted alternate locations.
f. Submit location and detail of movement joints if different from those indicated in Contract
Documents.
g. Submit manufacturer's data sheet on expansion joint materials.
h. Provide keyways where indicated in Contract Documents.
Longitudinal keyways indicated in Contract Documents must be at least 1-1/2 in. deep, measured perpendicular to the plane of the joint.
2.2.6 Other Embedded Items
Use sleeves, inserts, anchors, and other embedded items of material and design indicated in Contract Documents.
3 | P a g e
3.1 WATERSTOP INSTALLATION AND SPLICES
a. Provide waterstops in construction joints as indicated.
b. Install formwork to accommodate waterstop materials. Locate waterstops in joints where indicated in Contract Documents. Minimize number of splices in waterstop. Splice waterstops in accordance with manufacturer's written instructions. Install factory-manufactured premolded mitered corners.
c. Install waterstops to form a continuous diaphragm in each joint. Make adequate provisions to support and protect waterstops during progress of work. Protect waterstops protruding from joints from damage.
3.2 FORMS
a. Provide forms, shoring, and scaffolding for concrete placement. Set forms mortar-tight and true to line and grade.
b. Chamfer above grade exposed joints, edges, and external corners of concrete 0.75 inch.
Place chamfer strips in corners of formwork to produce beveled edges on permanently exposed surfaces.
c. Provide formwork with clean-out openings to permit inspection and removal of debris.
d. Inspect formwork and remove foreign material before concrete is placed.
e. At construction joints, lap form-facing materials over the concrete of previous placement.
Ensure formwork is placed against hardened concrete so offsets at construction joints conform to specified tolerances.
f. Provide positive means of adjustment (such as wedges or jacks) of shores and struts.
Do not make adjustments in formwork after concrete has reached initial setting. Brace formwork to resist lateral deflection and lateral instability.
g. Fasten form wedges in place after final adjustment of forms and before concrete placement.
h. Provide anchoring and bracing to control upward and lateral movement of formwork system.
i. Construct formwork for openings to facilitate removal and to produce opening dimensions as specified and within tolerances.
j. Provide runways for moving equipment. Support runways directly on formwork or structural members. Do not support runways on reinforcement. Loading applied by runways must not exceed capacity of formwork or structural members.
k. Position and support expansion joint materials, waterstops, and other embedded items to prevent displacement. Fill voids in sleeves, inserts, and anchor slots temporarily with removable material to prevent concrete entry into voids.
l. Clean surfaces of formwork and embedded materials of mortar, grout, and foreign materials before concrete placement.
3.3.1 Coating
a. Cover formwork surfaces with an acceptable material that inhibits bond with concrete.
b. If formwork release agent is used, apply to formwork surfaces in accordance with manufacturer's recommendations before placing reinforcement. Remove excess release agent on formwork prior to concrete placement.
c. Do not allow formwork release agent to contact reinforcement or hardened concrete against which fresh concrete is to be placed.
3.3.2 Forms for Standard Rough Form Finish
4 | P a g e
Provide formwork in accordance with American Concrete Institute (ACI) 301 Section 5 with a surface finish, SF-1.0, for formed surfaces that are to be concealed by other construction.
3.3.3 Forms for Standard Smooth Form Finish
Provide formwork in accordance with ACI 301 Section 5 with a surface finish, SF-3.0, for formed surfaces that are exposed to view. Do not provide mockup of concrete surface appearance and texture.
3.3.4 Form Ties
After ends or end fasteners of form ties have been removed, repair tie holes in accordance with ACI 301 Section 5 requirements.
3.3.5 Tolerances for Form Construction
a. Construct formwork so concrete surfaces conform to tolerances in ACI 117.
b. Position and secure sleeves, inserts, anchors, and other embedded items such that embedded items are positioned within ACI 117 tolerances.
c. To maintain specified elevation and thickness within tolerances, install formwork to compensate for deflection and anticipated settlement in formwork during concrete placement.
Set formwork and intermediate screed strips for slabs to produce designated elevation, camber, and contour of finished surface before formwork removal.
If specified finish requires use of vibrating screeds or roller pipe screeds, ensure that edge forms and screed strips are strong enough to support such equipment.
3.4.1 PVC Waterstop
Make splices by heat sealing the adjacent waterstop edges together using a thermoplastic splicing iron utilizing a non-stick surface specifically designed for waterstop welding. Reform waterstops at splices with a remolding iron with ribs or corrugations to match the pattern of the waterstop. The spliced area, when cooled, must show no signs of separation, holes, or other imperfections when bent by hand in as sharp an angle as possible.
3.4.2 Rubber Waterstop
Rubber waterstops must be spliced using cold bond adhesive as recommended by the manufacturer.
3.4.3 Thermoplastic Elastomeric Rubber Waterstop
Fittings must be shop made using a machine specifically designed to mechanically weld the waterstop.
A portable power saw must be used to miter or straight cut the ends to be joined to ensure good alignment and contact between joined surfaces. Maintain continuity of the characteristic features of the cross section of the waterstop (for example ribs, tabular center axis, and protrusions) across the splice.
3.4.4 Hydrophilic Waterstop
Miter cut ends to be joined with sharp knife or shears. The ends must be adhered with adhesive.
Tolerances for Form Construction
a. Construct formwork so concrete surfaces conform to tolerances in ACI 117.
b. Position and secure sleeves, inserts, anchors, and other embedded items such that embedded items are positioned within ACI 117 tolerances.
c. To maintain specified elevation and thickness within tolerances, install formwork to compensate for deflection and anticipated settlement in formwork during concrete placement.
5 | P a g e
Set formwork and intermediate screed strips for slabs to produce designated elevation, camber, and contour of finished surface before formwork removal.
If specified finish requires use of vibrating screeds or roller pipe screeds, ensure that edge forms and screed strips are strong enough to support such equipment.
3.3 WATERSTOP INSTALLATION AND SPLICES
a. Provide waterstops in construction joints as indicated.
b. b. Install formwork to accommodate waterstop materials. Locate waterstops in joints where indicated in Contract Documents. Minimize number of splices in waterstop.
Splice waterstops in accordance with manufacturer's written instructions. Install factory-manufactured premolded mitered corners.
c. Install waterstops to form a continuous diaphragm in each joint. Make adequate provisions to support and protect waterstops during progress of work. Protect waterstops protruding from joints from damage.
3.4.5 PVC Waterstop
Make splices by heat sealing the adjacent waterstop edges together using a thermoplastic splicing iron utilizing a non-stick surface specifically designed for waterstop welding. Reform waterstops at splices with a remolding iron with ribs or corrugations to match the pattern of the waterstop. The spliced area, when cooled, must show no signs of separation, holes, or other imperfections when bent by hand in as sharp an angle as possible.
3.4.6 Rubber Waterstop
Rubber waterstops must be spliced using cold bond adhesive as recommended by the manufacturer.
3.4.7 Thermoplastic Elastomeric Rubber Waterstop
Fittings must be shop made using a machine specifically designed to mechanically weld the waterstop.
A portable power saw must be used to miter or straight cut the ends to be joined to ensure good alignment and contact between joined surfaces. Maintain continuity of the characteristic features of the cross section of the waterstop (for example ribs, tabular center axis, and protrusions) across the splice.
3.4.8 Hydrophilic Waterstop
Miter cut ends to be joined with sharp knife or shears. The ends must be adhered with adhesive.