This document is a Contract Data Requirements List (CDRL) that details the data requirements for a federal contract opportunity related to welding electrodes.

The CDRL identifies three data items required for the contract: an Inspection and Test Plan, Certification Data for Special Emphasis Materials, and a Certification/Data Report for Special Emphasis Certificates of Conformance. The data items outline specific requirements for material marking, certification, and submission procedures. The contract reference is TDP paragraph 3.9.3, 3.15.1, and 3.17.

The related federal contract opportunity is for the procurement of Level 1 Welding Electrodes for the Portsmouth Naval Shipyard, issued by the Defense Logistics Agency Land and Maritime. The solicitation number is SPMYM324Q8038. Qualified sources are being requested to provide the welding electrodes in accordance with the specified attachments.

View the file

Other files for this federal contract opportunity

Other files attached to LEVEL 1 WELDING ELECTRODES, newest first.
File Type Posted
SPMYM324Q8038 RFQ.pdf PDF
24Q8038 Attachment 1.pdf PDF
24Q8038 Exhibit B.pdf PDF
24Q8038 Attachment 2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP

D . SYSTEM/ITEM

WELDING ELECTRODE

E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

INSPECTION AND TEST PLAN

3. SUBTITLE

INSPECTION SYSTEM PROCEDURES

4. AUTHORITY (Data Acqisition Document No.)

DI-QCIC-81110 (SE)

5. CONTRACT REFERENCE

TDP: PARA 3.9.3

6. REQUIRING OFFICE

CODE 245

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

E

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

N/A

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

Draft Final

Reg Repro

16. REMARKS

Paragraph 10.4 of DI-QCIC-81110 does not apply.

For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.

Code 136.2 0 1 0

15. Total 0 1 0

G. PREPARED BY

Jason Laflamme

H. DATE

02/23/24

I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Page 1 of 3 Page(s)

S/N 0102-LF-010-5600

Steven W Harmon 05/07/2024

0002 A

24Q8038/4059E300

Form Approved OMB No. 0704-0188

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP

D. SYSTEM/ITEM

WELDING ELECTRODE

E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO.

A002

2. TITLE OF DATA ITEM

CERT DATA FOR SPECIAL EMPHASIS MATL

3. SUBTITLE

(QUALITY CONFORMANCE/REQUIRED TESTS

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-81020 (DD)

5. CONTRACT REFERENCE

TDP: PARA 3.15.1

6. REQUIRING OFFICE

CODE 245

7. DD 250 REQ

SD

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

N/A

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

Draft Final

Reg Repro

16. REMARKS

For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material.

Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.

133.2 0 1 0

15. Total 0 1 0

G. PREPARED BY

Jason Laflamme

H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Page 2 of 3 Page(s)

S/N 0102-LF-010-5600

The following paragraphs of DI-MISC-81020 shall be modified as shown below:

10.1.1 - Add: Material marking for spooled wire shall be as identified within the applicable commodity specification.

10.1.2 - Add: For Weld Materials, the weld material manufacturer is considered the original mill.

10.2 - Replace the entire paragraph with: For Weld Materials, Certification is required for each test performed under Quality Conformance listed in the applicable paragraph of the military specification. (or Table 5 of AWS specifications)

02/23/24 Steven W Harmon 05/07/2024

0003 A

Form Approved OMB No. 0704-0188

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP

D. SYSTEM/ITEM

WELDING ELECTRODE

E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO.

A003

2. TITLE OF DATA ITEM

CERTIFICATION/DATA REPORT

3. SUBTITLE

SPECIAL EMPHASIS C OF C

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-80678 (CCDD)

5. CONTRACT REFERENCE

TDP: PARA 3.17

6. REQUIRING OFFICE

CODE 245

7. DD 250 REQ

SD

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

N/A

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

Draft Final

Reg Repro

16. REMARKS

Block 4 - Paragraphs 10.2.1, 10.2.2, 10.2.3, 10.3, and 10.4 of DI-MISC-80678 do not apply.

For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material.

Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.

133.2 0 1 0

15. Total 0 1 0

G. PREPARED BY

Jason Laflamme

H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Page 3 of 3 Page(s)

S/N 0102-LF-010-5600

02/23/24 Steven W Harmon 05/07/2024

0004 A