24N0007 ATCH 1_SOW COD Quick Change.pdf

PDF 89 KB Posted

Attached to
Color On Demand Quick Change System Federal contract opportunity
Solicitation number
47QSWC24N0007
Issued by
GSA Federal Acquisition Service

About this file

This document includes a statement of work and federal contract opportunity notice regarding a color on demand quick change system. The Marine Corps Logistics Base in Albany, Georgia seeks to acquire and install a new color on demand quick color change powder coating system to replace an existing system. The scope of work involves purchasing, delivering, installing, configuring, testing and training government personnel on a complete color on demand quick change powder coating system with controllers to manage up to 28 colors, 10 powder feed hoppers with 50-pound capacities, and two manual spray guns. Interested parties must respond by the date specified in SAM.gov to understand potential vendor capabilities and solutions for this requirement. The government may use responses for planning purposes only and does not guarantee issuing a request for quote.

View the file

Other files for this federal contract opportunity

Other files attached to Color On Demand Quick Change System, newest first.
File Type Posted
Sources Sought_MDMC COD Quick Change Sys.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Production Plant Albany

MARINE CORPS LOGISTIC BASE

ALBANY, GEORGIA

Purchase & Install COD (Color On Demand) Quick Change System

1.0 STATEMENT OF WORK

1.1 This document provides the description that shall be used to acquire ONE (1)

Color On Demand Quick Color Change System. The system as noted is a complete replacement for the existing Color on Demand. It will include the referenced controller, powder guns, and hoppers. The controllers will manage up to 28 colors, however we will set up the system to handle 10 colors. The “Hopper Farm” will contain all of the fluidizing air, powder tubing, pneumatic tubing and like for the hoppers. Each hopper will have a place on the “Color Pallet” touch screen representing a specific color. The system will automatically purge the current color, load the new one, and be ready to spray said color in, typically, less than 30 seconds.

1.2 Contractor shall verify all measurements prior to ordering materials. All work shall be accomplished in strict accordance with prevailing industry standards, manufacturer’s written instructions and all applicable codes.

1.3 All work requiring energy shall be done in compliance with OSHA 29 CFR

1910.147 and 1910.333 lock out tag out procedure. All electrical work shall comply with current NEC as well as local codes.

2.0 SCOPE OF WORK

2.1 The contractor shall provide all labor, tools, materials, equipment, safety measures, supervision and all associated permits and services to complete the work to furnish, install, and start-up of fully functional COD Quick Change System at Building

2211, MCLB Albany, GA. Contractor is responsible for the purchase of the system and all miscellaneous materials needed to install a fully functional system.

i. Contractor shall be responsible for due diligence. Customer will provide basic building/shop layouts, site visits, other information as necessary upon request. For point of contact, reference paragraph 4.5.

ii. Contractor will be responsible for connecting system to base power. (Customer will provide utilities (electrical power, gas and plant air) within 50' of equipment)

iii. Contractor will be responsible for System start-up and functions check.

iv. A minimum of 48 hours (8 hours per day) of In-plant operator/maintenance training for government operators and safety personnel for the conveyorized and batch powder systems.

v. Final inspection per government end user acceptance. Commissioning and testing of parts to be required before acceptance (Training end users from start to finish on all aspects of the conveyorized powder paint, batch powder paint and oven equipment).

3.0 EQUIPMENT DESCRIPTION

3.1 COD (Color On Demand) quick color change system

Powder Spray System combines the Color-on-Demand instant color selector* with the new HD manual gun and controller to provide an integrated solution for precision dispensing and ultra-fast, contamination-free color change in less than 20 seconds

Touch screen display-User-configurable buttons that can be set for size and color identification at the touch of a button

COD can accommodate up to 28 colors-More color changes per shift, higher throughput, and just-in time manufacturing for zero inventory and improved production efficiency.

HD manual Spray System (2ea)

Lightweight gun for reduced Operator fatigue and comfortable coating

All-digital gun control interface eliminates inconsistencies in powder output and resultant film build High efficiency pump that provides more powder with less compressed air.

Patented Select Charge® technology provides pre-programmed electrostatic settings for re-coating, metallic's or cavities.

AFC (automatic feedback current) control – automatically controls optimum electrostatic charging voltage based upon gun-to-part distance.

Auxiliary Power Purge trigger – cleans the powder path from the base of the handle through the nozzle, preventing internal powder build-up to ensure optimum spraying performance with a wide variety of powder materials.

10ea Powder feed Hoppers/50lb Capacities

1ea Hopper Farm/50lb Hoppers

Installation, Start up, Training

3.2 EXECUTION

3.3 Shipment, installation and training to be completed by the contractor and coordinated with the customer.

3.4 Place of Performance: Marine Depot Maintenance Command, B2211, Marine

Corps Base, Albany, GA.

3.5 Security Requirements: Contractor shall adhere to current installation security policies. For security policies and access to the base, contractors shall contact:

Visitor Control Center

Building 3010, Room 33

Marine Corps Logistics Base, Albany GA.

Ph: 229-639-5118 https://www.albany.marines.mil/Resources/MCLB-Offices-Staff/Pass-and-ID/

3.6 Government Furnished Property (GFP) and Services: The US Government will not provide any equipment, fuel, personnel, utilities or facilities to the contractor for the execution of this contract. Should an emergency arise, only the necessary basic lifesaving and life support measures will be provided if an emergency occurs.

3.7 Government Point of Contact (POC): Government POC is:

3.8 GENERAL REQUIREMENTS

3.9 Contractor shall cleanup work sites daily and properly dispose of debris off

Government property.

4.0 The work shall be performed in such a manner as to cause the least interference with the normal functions of the Government activity. Work areas will be cleared/vacated for the period of time necessary for the Contractor to perform work.

4.1 Prior to beginning any work, the Contractor shall meet with the designated

Government representative to discuss and develop mutual understandings relative to scheduling and administering work. All work shall be accomplished within 180 calendar days after date of award. This completion time includes 14-day period for checking background of the contractor’s personnel prior to arrival to start work on Base. All asbestos abatement and removal shall be accomplished on weekends and holidays (only if asbestos is found during the project). All other work shall be accomplished between the hours of 8:00 a.m. and 5:00 p.m., Monday thru Friday (excluding federal holidays) unless otherwise specified in the requirements section and specifically pre-arranged with the

Contracting Officer. This requires a written request two (2) days prior to proposed work.

https://www.albany.marines.mil/Resources/MCLB-Offices-Staff/Pass-and-ID/

4.2 Work shall be accomplished by personnel experienced in their respective trades.

The Contractor shall perform all work in accordance with acceptable industry standards and all federal, state, and local codes.

4.3 All work requiring energy (electrical, mechanical, hydraulic, pneumatic, chemical, thermal or other) removal shall be done in compliance with OSHA 29 CFR

1910.147 and 1910.333 lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist. NFPA 70E (current edition), Standard for Electrical Safety in the Workplace, shall also be utilized for worker safety compliance.

4.4 Except where specifically specified otherwise herein, all salvable materials and equipment disconnected or removed during the course of the work and not indicated or specified for reuse on the new work shall remain the property of the Government. All recyclable materials such as metals, pipes, pumps, engines, motors, and certain electrical components, to include switch gear, MCCs, conduit, copper wire, distribution and control panels, nuts, bolts, washers, old motor starters, obsolete breakers, cable lugs, conduit, conduit fittings, connection boxes, etc. will be recycled in accordance with MCO

5090.2A through the base Qualified Recycling Program (QRP). Remaining material shall be removed from the Government property. Contractor will disassemble or cut recyclable material to fit into roll-off containers or on flat bed trailers. With no part of the items hanging off the trailers or protruding out of the top of the containers.

4.5 Prior to performing "Hot Work" (welding, cutting, etc.) or operating other flame-producing/spark producing devices, a written permit shall be requested from the Fire

Division. CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE A

PERMIT IS ISSUED. The Contractor will provide at least two (2) ten (10) pound 4A:80

BC rated extinguishers for normal "Hot Work". All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire

Watch shall be trained in accordance with NFPA 51B and remain on-site for a minimum of 1 Hour after completion of the task or as specified on the hot work permit. When starting work in the facility, Contractors shall require their personnel to familiarize themselves with the location of the nearest fire alarm boxes and place in memory the

EMERGENCY FIRE phone number 229-639-5911. ANY FIRE, NO MATTER HOW

SMALL, SHALL BE REPORTED TO 229-639-5911 IMMEDIATELY.