SOW ATBM Ceiling Lighting and Drywall Repair.pdf
PDF 182 KB Posted
- Attached to
- Repair/Replace/Refurbish the Ceiling and Security Chain-Link Fencing at the Tafuna ATBM, American Samoa
- Solicitation number
- 24958
About this file
SOW ATBM Ceiling Lighting and Drywall Repair (pdf)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Fence SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TUT NDB-ATBM CELEING REPAIRS
PR #WP-16-01877
FEDERAL AVIATION ADMINSTRATION
WESTERN SERVICE AREA
ENGINEERING SERVICES
AWP
S T A T E M E N T OF W OR K
FOR
REPAIR/RESURFACE DAMAGED CELEINGS
TUT NDB/ATBM/
SOMOA TAFUNA, AMERICAN SAMOA
July 5, 2016
PR #WP-16-01882
AMERICAN SAMOA
CEILING REPAIRS REPLACEMENT
PROJECT LOCATION:
TAFUNA ATBM
100 Tafuna Road Pago Pago, AS 96799
FACILITY MANAGER:
Smith Lutu FAA Pago Pago SSC Pago Pago International Airport 100 Tafuna Road Pago Pago, AS 96799 648 699 9485 X222 Cell 684 733 3888
PROJECT ENGINEER:
Ira Farnoush FAA AWP Regional Office 15000 Aviation Blvd.
Hawthorne, CA 90250
(310) 725-7294 Office
(310) 880-0462 Cell
SITE CONTACT:
Smith Lutu FAA Pago Pago SSC Pago Pago International Airport 100 Tafuna Road Pago Pago, AS 96799 648 699 9485 X222
Cell 684 733 3888
Bidders/Vendors shall furnish all labors, equipment, tools, services and materials (some materials to be furnished by FAA and identified herein) necessary to accomplish the following Scope of Work; in compliance with this Request and the 2015 International Building Code:
1.0 SCOPE
All rooms in building, remove the existing surface mounted light fixtures, exit signs, etc.
Furnish and install ½” Green Board (Water-Resistance) drywall over existing drywall ceilings or over existing wood ceiling trusses.
Fasten green-board to roof trusses with code compliant fasteners.
Provide Level V smooth drywall finish on all ceilings throughout.
Prime and paint as necessary to completely seal all walls and ceilings throughout building. Repair any and all blemishes, damaged areas, touch-up areas, patches, etc., prior to priming and painting.
Install Government Furnished (GF) ceiling mounted light fixtures in all rooms to replace all light fixtures as described below.
Scope of work for each room shall include but not limited the following:
Manager Room (16’x12’):
Replace and paint ceilings, paint walls and install 3 new GF light fixtures.
Conference Room (20’x22’):
Replace and paint ceilings, paint walls and install 6 new GF light fixtures.
Kitchen (14’x15’)
Equipment Room Office Wing (20’x22’):
Replace using 5/8” green-board and paint ceilings, paint walls and install 4 new GF light fixtures.
Room 106 (17’x12’):
Replace and paint ceilings, paint walls and install 2 new GF light fixtures.
Room 107 (9’x11’):
Replace and paint ceilings, paint walls and install 2 new GF light fixtures.
Room 108 (11’x10’):
Replace using 5/8” green-board and paint ceilings, paint walls and install 2 new GF light fixtures.
Room 109 (18’x12’):
2.0 REQUIREMENTS:
The contractor shall verify in the field all dimension conditions, and comply with any and all local construction safety codes including compliance with IBC & NEC requirements.
In addition, electrical work shall comply with requirement of the FAA Electrical Specifications Standard FAA –C-1217e.
The prime and paints shall be from known manufacturer. The color of the paint must be coordinated and approved by the FAA.
3.0 SUBMITTAL WITH BIDS PACKAGE:
Not applicable
4.0 EXECUTION OF WORK : The Contractor shall assume full responsibility for the protection and safekeeping of products stored on the site. The Contractor, Contractors employees, and Subcontractors shall maintain the jobsite in a neat and orderly condition at all times, including the daily removal of rubbish, waste and tools, equipment, and materials not required for the work in progress. All persons on site shall maintain safe working conditions and provide adequate protection safeguards for all workers and equipment.
5.0 DELIVERIES OR PERFORMANCE: The Contractor shall be required to (a) Commence work under this contract within fifteen (15) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than twenty one (21) Calendar days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.
6.0 SECURITY REQUIREMENTS: The job site is located within the Samoa International airport in secure area. The Contractor shall comply with all instructions, rules, security, safety, environmental, health requirements of the Federal, State, local and airport authorities at all time.
7.0 GOVERNMENT FURNISHED MATERIALS
LED CEILING LIGHT FIXTURE 2’x4’ Flat 25
8.0 ATTACHEMENT
FAA Electrical Specification FAA-C-1217e.
END OF DOCUMENT