Pawnee IHC Roof Repair IHS SOW.1.doc

DOC document 3 MB Posted

Attached to
Roof Repairs, Pawnee Indian Health Center
Solicitation number
246-2012-Q-0025
Issued by

About this file

Scope of Work Project OK0CAS04H6

View the file

Other files

File Type Posted
PawneeRoofSF18.pdf PDF
52.213-4 Ts Cs--Simplified Acquisitions Other ThanCommercialItems (Aug2011).docx DOCX document
Insurance Requirements.docx DOCX document
PawneeCountyWageDecision.mht MHT file
Additional Provisions-Terms and Conditions-Non 8(a).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oklahoma City Area

Indian Health Service OEHE - Division of Facilities Management

701 Market Drive

Oklahoma City, Oklahoma 73114

Phone: (405) 951-3857 Fax: (405) 951-3932

SCOPE OF WORK

Indian Health Service (IHS)

Pawnee Indian Health Center

Pawnee, Oklahoma

Project # OK0CAS04H6 Pawnee Roof Repair

I.

GENERAL:

A. The contractor shall provide a 20 year water tight engineering roof design solution to repair and eliminate all potential roof leaks due to the architectural roofing and EIFS panel design. The roof areas which are suspected to be prone to roof leaks is the counter and receiving metal flashing, top metal parapet coping, metal guttering, EIFS panel roof transitions and wall seams, thermoplastic membrane, metal panel roof and metal cover on the topside of the skylights on the roof area..

B. It is highly recommended that the contractor perform an initial on-site visit. The contractor is responsible for reviewing verifying the scope of work.

C. The Pawnee Indian Health Center was placed in service after construction completion on March 1, 2004. The architectural roof was designed by JSRa (Johnson Smithipong & Rosmand Associates, Inc. Architect) and included both a metal roof system and a thermoplastic membrane liner flat roof. The metal roof and the membrane liner flat roof are joined by EIFS walls at the roof transition (see Pic1, Pic2, and Pic3).

Pic1: Pawnee Indian Health Center (IHC) – Roof Front and Top Overview

D. Contractor shall be qualified, reputable and certified in commercial roofing. Applicable certifications shall accompany contractor’s quote. Contractor shall perform all work so as not to void the existing warranties. (See appendix F)

Pic2: Pawnee IHC - Flat Roof and Roof Eave with EIFS Walls.

Pic3: Pawnee IHC - Roof Eave and Top Flat Roof with EIFS Walls.

E. The Pawnee Indian Health Center has had ongoing roof leaks since being placed in service on March 1, 2004. Temporary repairs have been done to patch the roof leaks during the one year warranty period. (see Pic4, Pic5, Pic6. Pic7 and Pic8).

Pic4: Pawnee IHC - Roof Eave Flashing seams transition with EIFS Walls.

Pic5: Pawnee IHC - Roof Eave Flashing seams transition with EIFS Walls.

Pic6: Pawnee IHC - Roof Eave Flashing seams transition with EIFS Walls.

Pic7: Pawnee IHC - Roof Flashing seams with Caulking Failing.

Pic8: Pawnee IHC – Flat Roof Flashing seams transition with EIFS Walls.

F. Other areas of leakage are the metal parapet coping over the parapet walls, the metal covering and the receiving flashing placed around the skylights roof transition with the EIFS walls. There are various size gaps in the opening around the metal covering of the main skylight which allow rain, dust, and pests to enter the inside of the building. (see Pic 9 and Pic10)

Pic9: Pawnee IHC – Flat Roof Coping seams with EIFS Walls.

Pic10: Pawnee IHC – Skylight Metal Cover and Coping seams with EIFS Walls.

G. The contractor shall replace the existing roof guttering system which is too small to adequately drain-off and support the heavy rains (see Pic11, Pic12).

Pic11: Pawnee IHC – Guttering Damage due to Melted Siding Ice Sheets.

Pic12: Pawnee IHC – Guttering Damage due to Melted Siding Ice Sheets.

H. The contractor shall add rain guttering to the loading dock area. The guttering/downspouts shall eliminate rain from draining off the flat dock canopy onto the docking area. (See Pic13).

Pic13: Two downspouts are required for the dock area.

I. Contractor shall inspect the current metal roofing panel system and provide quotes for required repairs based on potential roof leak areas. A water test is to be conducted on suspected metal roof areas for validation on roof leaks. Contractor shall provide a design solution for resolving gutter overflow during heavy rains. (See Pic16).

Pic16: Pawnee IHC – Guttering System with small downspout and drains

J. Contractor shall replace the roof downspouts with either lighter material downspouts, or, if the downspouts are salvageable, anchor and securely fasten the roof downspouts to the EIFS wall through the metal studs (See Pic17).

Pic17: Depiction of Downspouts Requiring Improved Fastening to EIFS Walls & Stud

II.

SERVICES TO BE PERFORMED BY THE CONTRACTOR:

A. Contractor shall provide all labor, material, and installation to provide a minimum 20 year water tight roof repair which eliminates all roof leaks.

B. Work shall be done while the health center is occupied and operational. Work may be required to be performed during and after normal working hours. Normal working hours are Monday-Friday from 8:00 a.m. to 5:00 p.m. Coordination and scheduling of work is critical in this health center environment and should be coordinated with the IHS COTR and Facility Manager.

C. The contractor is fully responsible for verifying and validating all information contained within this scope. Contractor must fully evaluate the condition of the existing conditions prior to the start of work.

D. Contractor shall abide by all Safety, Security and Infection Control Policies and Procedures of the Pawnee Indian Health Center. Before any work is to be performed a Start of Construction letter notice shall be provided to the assigned IHS COTR at least 7 days in advance for review and approval.

E. When egress corridors, fire alarm detection and suppression systems are impaired during construction, the Contractor shall inform the Facility Manager to ensure that an Interim Life Safety Measure is conducted in coordination with the IHS COTR, Pawnee Indian Health Center Safety Office and Facility Manage & Engineer.

F. The Pawnee Indian Health Center is a tobacco free campus. No smoking is permitted in the health center and grounds. The contractor is responsible for their subcontractors to obey and be in compliance of the IHS tobacco free campus.

G. Signing in/out and scheduling of contractors and sub-contractors must be coordinated with the Pawnee Indian Health Center Facilities Management Department in order to maintain traffic-flow, parking, access to building and locked areas.

H. All applicable documents shall be distributed as follows:

a. Project Officer / IHS COTR::

Hugo Gonzalez, P.E.

Senior Staff Engineer, Mechanical Engineer IHS - Oklahoma City Area Office

OEHE - Division of Facilities Management 701 Market Drive Oklahoma City, Oklahoma 73114 Phone: (405) 951-3857 Fax: (405) 951-3932

Hugo.Gonzalez@ihs.gov

b. Facility Manager:

Joe Jones, Facility Manager

Pawnee Indian Health Center 1201 Heritage Circle

Pawnee, OK 74058 Phone:

(918) 762-6715 Joseph.Jones@ihs.gov

c. Contract Specialist Joe Wallace Phone: 405-951-3929 Joseph.wallace@ihs.gov I. All work must conform to, and comply with, the latest edition/version of ALL applicable OSHE, federal, state, and local laws, rules, regulations, codes, and standards.

J. Contractor shall use Energy efficient equipment and material when replacing defective government equipment and materials.

K. Upon completion of work, Contractor shall provide training on the cleaning and maintenance of new equipment that is installed.

L. All new materials and equipment shall be furnished with an owner’s manual, parts list, local authorized dealer contact information, and warranty ending date.

M. All new materials and equipment shall meet specifications required by this solicitation and shall have approved certificates of installation if required by ALL applicable federal, state, and local codes, standards, or regulations.

N. All shipping containers shall be disposed of at an offsite suitable landfill or be recycled.

O. Contractor shall conduct a detailed roof leak on-site investigation and water test on the suspected roof areas that are causing current and potential future risk for roof leaks into the building. The entire roof for the Pawnee Indian Health Center is to be inspected and investigated to determine roof leak areas that have occurred.

P. The photos provided are for reference only. An investigation and verification of all the existing and potential roof leak areas are to be verified and validated by the contractor.

Q. Contractor shall conduct periodic project meeting with the Contract Specialist, Facility Engineer, and IHS COTR. Contractor shall provide approved engineering designs, documents and specifications of all.

R. Contractor shall provide manufacture warranties on the manufacturer’s standard form.

S. Contractor shall provide a written quality assurance reports to the IHS COTR for review and approval by the COTR. The reports shall address all work in progress during construction.

T. Contractor shall provide technical roofing care training to the Pawnee Indian Health Center facility technician staff and engineering for maintenance and preventive maintenance.

WORK PLAN

SERVICES TO BE PERFORMED BY THE CONTRACTOR:

1) Provide all technical service, labor, material, and installation to provide a complete roof repair.

1. Highly recommended: Verify scope of work via site visit.

2. Contractor will provide shop drawings for the following:

(a) Cap flashing at all parapet walls (shall be seam less design) (for details reference Appendix A1)

(b) Flashing at gable ends (for details reference Appendix A2)

(c) Flashing at TPO roof to the EIFS (for details reference Appendix B1)

(d) Flashing at Metal roofing to EIFS (for details reference Appendix B2)

(e) Gutter system for the entire building (for details reference Appendix D1)

1. Include Ice and snow stop and match existing color (for details reference Appendix D1)

2. Include commercial grade material and match existing color

3. Include (8 inch) commercial Box gutter design and match existing color

4. Include gutter hangers approved by roofing manufacturer

5. Include gutter design for area over loading dock and match existing color

3. Before any work may begin, all submittals must be approved by HIS COTR.

(4) Contractor shall provide a sample board detailing flashing and EIFS samples as well as gutters and support system to include down spouts.

2) Contractor shall perform the following demolition

(1) Remove (950 Linear Feet) of gutter entire building (for details reference Appendix D)

(2) Remove cap flashing (for details reference Appendix A1)

(4) Remove and repair corner metal flashing per Berridge Manufacturing Detail Flashing Specifications

(5) Repair flashing at skylights (2) (for details reference Appendix B4)

(6) Remove TPO roof at 3rd level roof (as required)

(7) Remove and salvage lightening protection system for later re-installation.

3) Contractor shall install/repair

(1) Level 3 Roof

(a) Replace and install new fully adhered 60 mil TPO membrane roof to match existing TPO to go up and over parapet wall terminating at top of wall (for details reference Appendix C1)

(b) Use sealant as recommended by TPO manufacturer

(c) Install new Cap Flashing around perimeter of level 3 Roof (for details reference Appendix A1)

(d) Re-install Lightening Protection system previously removed

(e) Install new flashing at level 4 sky light (for details reference Appendix B4)

(f) Repair EIFS opening at level 4 (for details reference Appendix B4)

(g) Caulk using Non‐Corrosive, Low Modulus Silicone Joint Sealant as required

2) Level 2 Roof (Metal )

(a) Repair or install new flashing clips at gables (for details reference Appendix A2)

(b) Repair any damaged existing TPO membrane roofing (for details reference Appendix A3)

(c) Install 2 part flashing at EIFS walls (for details reference Appendix B2)

(d) Repair fascia flashing (for details reference Appendix A2)

(e) Install new box style gutters (seamless aluminum) (for details reference Appendix D1)

(f) Furnish and install backer rod and caulk inside at skylight wall cap (for details reference Appendix B4)

(g) Install new gutter supports 1/8” gutter brackets for support of the 8” gutter in lieu of strap. Include the straps as gutter spacers and have both brackets and spacers as recommended by roofing manufacturer (for details reference Appendix D1)

(3) Level 1 Roof (TPO)

(a) Install 1 piece flashing at EIFS (for details reference Appendix B1)

(b) Install EIFS stop bead

(c) Patch Back EIFS

(d) Paint EIFS as Required

(e) Reinstall gutter down spouts (for details reference Appendix D1)

(f) Power wash all roofs as required to clean debris

(4) Loading Dock Level (TPO)

(a) Install 1 piece flashing at EIFES (for details reference Appendix B1)

(b) Install EIFS stop bead

(c) Patch Back EIFS

(d) Paint EIFS as Required

(e) Install gutter down spouts (for details reference Appendix D1)

(f) Power wash all roofs as required to clean debris

(g) Contractor shall perform all tests as required to include flooding of the TPO roofs and a spray test of the metal roof.

(5) Performance Standards.

(a) International Building Code (2006)

(b) ASCE 7-10 (2010) Minimum Design Loads for Buildings and Other Structures.

(c) FM 4435 (2004) Approval Standard for Roof Perimeter Flashing.

(d) FM 4470 (2010) Approval Standard for Single-Ply, Polymer-Modified Bitumen Sheet, Built-Up Roof (BUR) and Liquid Applied Roof Assemblies for Use in Class 1 and Noncombustible Roof Deck Construction.

(e) SMACNA 6th Edition Manual for Architectural Sheet Metal for Guttering System and Roof Perimeter Flashing.

(f) Manufacturer’s written instructions.

(g) Documents provided in Appendices A thru D.

(5) Quality Assurance

(a) Manufacturer’s Inspection. Manufacturer’s technical representative must visit the site during the installation for purposes of reviewing the materials installation practices and adequacy of work in place. Inspection(s) must occur at the start of new roof installation and at substantial completion. After each inspection, submit a report signed by the manufacturer’s technical representative to the Contracting Officer within 3 working days. Note submitted report to include the overall quality of work, deficiencies and any other concerns, and recommended corrective action.

(b) Contractor shall provide all manufacturers and contractor approved, signed and dated warranty cards for a watertight roof. The warranty is to be on the manufacture standard form, without monetary limitation in which manufacture or contractor agrees to repair or replace any components under the provided and installation watertight engineering roof design solution that fails in material or workmanship within the metal and TPO manufacture warranty period of 15-20 years. Failure includes roof leaks from the watertight engineering roof design solution provided and installed by the contractor at the Pawnee Indian Health Center).

Building Reference Location Information Locations for Flashing, Gutters, Downspout, Snow Guard Installation

The photograph located below, provides approximate location and length information for the different sections of the flashing, gutters, downspout, snow guard installations snow guard system. Included for reference are the CADD drawings.

Appendix A:

Parapet Wall Coping (Cap Flashing) and Flashing at Gable Ends

A1. Parapet Wall Coping (Cap Flashing)

1. At parapet wall coping on the 1st level roof area and loading dock area, an 8 inch wide top cover metal cap plate is to be added over seams to keep moisture from entering.

1st Level Parapet Wall Coping Seams:

1. 1st Level North Side:

Seams QTY = 7

2. 1st Level South Side:

Seams QTY = 10

3. Loading Dock:

Seams QTY = 8

Total = 25

Requirement for Installer:

A. Submittals and fabricated samples required for review and approval by IHS COTR

B. Material - 24 gauge and matching existing coping color

C. Sealant - Non-corrosive, low modulus silicon joint sealant (Tremco TremPro 646 ) D. Fabricated to contour and interlock over existing coping A. Remove heavy caulking and re-seal seams for moisture protection

E. Minimum 5 inch gasket fastener with neoprene washer F. Fasten to metal wall stud behind the hollow EFIS wall.

G. For uniform gasket us butyl tape behind the face of the metal when fasteners are installed as opposed to beads of sealant

Pic A1-1: Examples of Open and Heavily Caulked Seams at Parapet Wall Coping (Cap Flashing)

Pic A1-2: Examples of 1st Level South Side Removed Parapet Wall Coping (Cap Flashing)

Pic A1-5: Examples of Top Covered Seams on Parapet Wall Coping

2. At parapet wall coping on the 3rd level roof area, the metal coping is to be removed and replaced with new to Meet ANSI/SPRI ES-1 Wind Design for Roof Edge Systems.

3rd Level Parapet Wall Coping:

1. 3rd Level Flat Roof

Coping QTY = 345 Linear-Ft

Pic A1-3: Examples of 3rd Level Pre-Coping Construction & Current Removed Parapet Wall Coping (Cap Flashing)

Below for Reference Only on Correct Typical Parapet Wall Coping

SHAPE \* MERGEFORMAT

Pic A1-4a: Examples of Tested to Meet ANSI/SPRI ES-1 Wind Design for Roof Edge Systems for Parapet Wall Copings

Pic A1-4b: Examples of Tested to Meet ANSI/SPRI ES-1 Wind Design for Roof Edge Systems for Parapet Wall Copings A2. Flashing at Gable Ends

1. At the metal roof gable ends, the end metal panels have unfastened during high winds due to faulty crimping. The southeast gable end metal panel is under warranty for repair with Berridge Manufacturing still open warranty.

· Inspect and re-crimp all gable ends per Berridge Manufacturing Crimping Specifications

· Seal open gaps at facial metal flashing per Berridge Manufacturing Detail Flashing Specifications

Pic A2-1: Example of Metal Roof Gable End on the North and South Sides

Pic A2-2: Example of Metal Roof Gable End Panel Which has Un-Crimped

Pic A2-3: Example of Metal Roof Gable End with Facial Flashing Unsealed and Open Underneath

A3. Repair Damaged TPO Areas

1. Repair or replace any damaged existing 60 mil TPO membrane roofing areas per the manufacture specifications. The original 2004 Carlisle 60-mil TPO flat roof system at the 1st level, mechanically fastened over 2.5” of ISO into a steel deck, seem to be in good watertight condition according to a Carlisle technical onsite investigation conducted on 01/24/2011 and based on a second technical investigation conducted on 07/18/2011 by H&H Certified Roof Consultant. Based on recent inspections, the 1st level TPO flat roof has only one (1) area to be investigated and repaired per the Carlisle manufacture specification requirements.

Pic A3-1: North Side is the location of 1st level TPO flat roof damaged area to be investigated and repaired

Appendix B:

Flashing at TPO Roof to the EIFS Flashing at Metal Roofing to EIFS Flashing at Skylights B1. Flashing at TPO Roof to the EIFS

1. A one piece metal cover flashing is to be installed over existing L-shape metal flashing located at the bottom of the EFIS Walls (refer to detail drawings). A section of the metal cover flashing was removed on the 3rd level parapet EFIS wall for re-fabrication reference.

Locations for adding Top Metal Cover Flashing:

1. 1st Level Flat TPO Roof North Side:

Flashing QTY = 18 Linear-Ft

2. 1st Level Skylight North Side:

Flashing QTY = 43 Linear-Ft

3. 1st Level Flat TPO Roof South Side:

Flashing QTY = 45 Linear-Ft

4. Loading Dock Rear Side:

Flashing QTY = 123 Linear-Ft

5. 4th Level Skylight Bottom Front East Side:

Flashing QTY = 10 Linear-Ft

6. 3rd Level Flat TPO Roof East Side:

Flashing QTY = 10 Linear-Ft Total = 249 Linear-Ft

Requirement for Installer:

A. Submittals and fabricated samples required for review and approval by IHS COTR

B. Material - 24 gauge and color match to Berridge MFG Forest Green C. Sealant - Non-corrosive, low modulus silicon joint sealant (Tremco TremPro 646) D. Remove heavy caulking and re-seal seams for moisture protection

E. Minimum 5 inch gasket fastener with neoprene washer B. Fasten to metal wall stud behind the hollow EFIS wall. DO NOT FASTEN RANDOMLY TO HOLLOW EIFS WALL- Conduct QA Checks Typical Reference Drawing for Installation of Top Cover Flashing

Pic B1-1: 1st Level North Side Flat TPO Roof & Skylight with Incorrect L-shape Flashing & Heavy Caulked Seams

Pic B1-2: 1st Level North Side Flat TPO Roof & Skylight with Incorrect L-shape Flashing & Heavy Caulked Seams

Pic B1-3: 1st Level South Side Flat TPO Roof with Incorrect L-shape Flashing & Heavy Caulked Seams

Pic B1-4: Loading Dock Rear Side with Incorrect L-shape Flashing & Heavy Caulked Seams

Pic B1-5: 3rd Level Flat TPO Roof East Side with Incorrect L-shape Flashing & Heavy Caulked Seams

Next Photos of 2004 Installed EFIS Existing L-shape Flashing Added 1 Piece Metal Cover Flashing

Pic B1-2: 3rd Level Flat TPO Roof with added top metal cap flashing installed in 2004

Pic B1-3: 3rd Level Flat TPO Roof removed top metal cap flashing done in 2004

Pic B1-4: 3rd Level Flat TPO Roof measurements of top metal cap flashing for review and sample removed.

Pic B1-5: 3rd Level Flat TPO Roof measurements of top metal cap flashing for review and sample removed.

Pic B1-6: 3rd Level Flat TPO Roof removed top metal cap flashing done for review and refab sample.

Pic B1-7: 3rd Level Flat TPO Roof removed top metal cap flashing done for review and refab sample.

B2. Flashing at Metal Roofing to EIFS

1. A two piece reglet metal flashing with a top cut-in reglet and bottom counter flashing is to be installed over existing L-shape metal flashing located underneath the transitional area between the EFIS Wall connecting to the Berridge Manufacturing metal roofing system (refer to detail drawings). A section of the two piece reglet type metal flashing was removed from the southeast EFIS wall for re-fabrication reference.

Two Piece Reglet Metal Flashing for 2nd Level Metal Roof:

1. Northeast Rear Skylight Front Side:

Flashing QTY = 16 Linear-Ft

2. Southeast Rear Skylight Front Side:

Flashing QTY = 16 Linear-Ft

3. Northeast Flat Roof Side:

Flashing QTY = 48 Linear-Ft

4. Southeast Flat Roof Side:

Flashing QTY = 48 Linear-Ft

5. Northwest Rear Loading Dock Side:

Flashing QTY = 33 Linear-Ft

6. Southwest Rear Loading Dock Side:

Flashing QTY = 33 Linear-Ft

7. Northwest Flat Roof Side:

8. Southwest Flat Roof Side:

Total = 260 Linear-Ft Requirement for Installer:

A. Submittals and fabricated samples required for review and approval by IHS COTR

B. Material - 24 gauge and color match to Berridge MFG Forest Green C. Sealant - Non-corrosive, low modulus silicon joint sealant (Tremco TremPro 646) D. Remove heavy caulking and re-seal seams for moisture protection

E. Minimum 5 inch gasket fastener with neoprene washer F. Fasten to metal wall stud behind the hollow EFIS wall. DO NOT FASTEN RANDOMLY TO HOLLOW EIFS WALL- Conduct QA Checks Typical Reference Drawing for Installation of Two Piece Reglet Metal Flashing

Pic B2-1: Metal Roof EFIS Transitions Existing L-shape Flashing 2 Piece Reglet Metal Flashing

Pic B2-2: Detail of removed existing 2 piece reglet metal flashing sample for review and re-fabrication

Pic B2-3: Detail of removed existing 2 piece reglet metal flashing sample – top has a 1/8”EIFS Reglet Groove Cut

Pic B2-4: Detail Measurements of existing metal roof flashing to bottom of EFIS Wall

Pic B2-5: New Location for top reglet cutting. Install a new 1/8” EIFS Reglet Groove at 1-½” above bottom of EFFIS Wall and extend bottom of reglet 5 inches to cover new counter flashing.

Pic B2-6: Removed sample of top reglet flashing piece to be re-fabricated

Pic B2-7: Removed sample of bottom counter flashing piece to be re-fabricated

Pic B2-8: Detail measurements of existing metal roof flashing to bottom of EFIS wall

Pic B2-9: Detail of existing bottom of EFIS wall 3in w/ 2-1/2 in foam, ¼” EFIS front & back, 2in gap counter flashing

Pic B2-10: Removal of incorrect 2in x 2in L-shape metal flashing existing at bottom of EFIS wall to metal roof panel

B3. Flashing at Skylights

1. For the two skylights located at the 4th and 1st level, the metal capping and flashing unless deemed required for proper watertight seal may not be required to be removed. The 4th level skylight metal cap was not correctly fastened through the hollow EFIS wall to fasten into a metal stud. The 4th level skylight has uneven gap openings underneath the metal capping that ranges from ½” to 2” that allows dirt and pests to enter these gap areas. The loose metal capping and gaps is to be professionally sealed and fastened hitting the metal stud behind the hollow EFIS wall.

B3-1: Construction top opening and front of 4th level skylight with loose metal capping

Pic B3-1: 4th level skylight with loose metal capping and gaps due to incorrect fastening.

Pic B3-2: 4th level skylight with loose metal capping and gaps due to incorrect fastening.

Appendix C:

Level 3 Roof - New 60 mil TPO Membrane C1. Level 3 Roof – New Fully Adhered 60 mil TPO Membrane on 3 Level Up and Over EFIS Parapet Wall

1. The 3rd level was verified that NO TPO was wrapped over the top of the parapet wall for a water tight cover instead only a felt paper was used under the copping. A new Carlisle 60 mil fully adhered TPO membrane is to be tied into the original 2004 Carlisle 60-mil TPO flat roof system at the 3rd level, which was mechanically fastened over 2.5” of ISO into a steel deck. The existing parapet wall coping is to be removed and a new 60 mils TPO is to be wrap over the existing parapet EFIS wall terminating at least 4 inches at the backside of the parapet EFIS wall. The new coping is to cover the 4 inch backside wall terminate TPO. If the original 2004 Carlisle 60-mil mechanically fastened TPO membrane is deemed to be a risk for possible further uplifting and wrinkling that could cause potential roof leaks, then the Level3 TPO is to be replaced and a new fully adhered Carlisle 60 mil should be installed 60 mils TPO Membrane – Covering Parapet Wall:

1. Parapet Wall Height:

TPO QTY = 3.5 Ft Height

2. Coping Wrap Around w/ 4”Backside:

Wrap Over QTY = 1.5 Ft Wrap Over

3. Parapet Wall Parameter Length:

Parapet QTY = 315 Linear-Ft

Calculation of Square-Ft Above = (3.5 + 1.5) x 315 Total = 1,575 Square-Feet of TPO Material Typical Reference Drawing for Carlisle Installation of Cap Flashing Termination

Pic C1-3: 3rd Level Parapet Wall Parapet Wall Under Parapet Wall Copping Appendix D:

Commercial Guttering System D1. Commercial Box Guttering System

Objectives:

The objective is to provide a 5-20 year solution for a long-lasting and durable commercial metal guttering system that will transfer the heavy rain water off the metal roof system without spilling over the edges and being deforming due to a light gauged gutter fabrication and light hanger system. The guttering system was incorrectly installed with a shallow residential 4-1/2” guttering system that had an 8 inch metal accent cover. The 4 inch round down spout has, and is, pulling away from the EIFS walls due to the down spout be made out of heavy galvanized piping instead of light 24 gauge aluminum.

1. All of the existing 4-1/2” shallow residential gutter and 8 inch accent metal cover is to be removed. An 8 inch box style gutter system is to be installed with commercial approved hanger supports. Behind the guttering system, the EFIS wall is to be re-enforced with a metal backing plate securely fastened to the metal studs behind the hollow EFIS wall. All of the existing 4 inch round heavy galvanized down spouts are to be removed and replaced with 6 inch round down spouts.

Guttering System:

1. Drive Through North Side:

Gutter QTY = 52 Linear-Ft

2. Drive Through South Side:

Gutter QTY = 52 Linear-Ft

3. Front Building North Side:

Gutter QTY = 83 Linear-Ft

4. Front Building South Side:

Gutter QTY = 87 Linear-Ft

5. 1st Level Flat TPO Roof Northeast Side:

Gutter QTY = 149 Linear-Ft

6. 1st Level Flat TPO Roof Northwest Side:

Gutter QTY = 109 Linear-Ft

7. 1st Level Flat TPO Roof Southeast Side:

Gutter QTY = 119 Linear-Ft

8. 1st Level Flat TPO Roof Southwest Side:

Gutter QTY = 119 Linear-Ft

9. Rear Building North Side:

Gutter QTY = 78 Linear-Ft

10. Rear Building South Side:

Gutter QTY = 96 Linear-Ft

11. Loading Dock:

Gutter QTY = 96 Linear-Ft

Total = 1,040 Linear-Ft

Down Spout System:

1. Front Building Side:

Down Spout QTY = 12 x 19 Linear-Ft = 228 Linear-Ft

2. Rear Building Side:

Down Spout QTY = 6 x 38 Linear-Ft = 228 Linear-Ft

3. Top Loading Dock:

Down Spout QTY = 4 x 23 Linear-Ft = 152 Linear-Ft

4. Loading Dock:

Down Spout QTY = 3 x 15 Linear-Ft = 45 Linear-Ft

Total = 653 Linear-Ft Requirement for Installer:

A. Submittals and fabricated samples required for review and approval by IHS COTR

B. Material - 24 gauge and color match to Berridge MFG Forest Green seamless aluminum C. Sealant - Non-corrosive, low modulus silicon joint sealant (Tremco TremPro 646) D. Remove heavy caulking and re-seal seams for moisture protection

E. Minimum 5 inch gasket fastener with neoprene washer for stud fastening

A. Fasten to metal wall stud behind the hollow EFIS wall. . DO NOT FASTEN RANDOMLY TO HOLLOW EIFS WALL- Conduct QA Checks Typical Reference of Box Style Gutter:

Reference Photos for Review

Pic D1-1: Construction installation of existing 4-1/2” shallow gutter system with added 8 inch accent cover.

Pic D1-2: Installation of metal back plate used to fasten existing 4-1/2” gutters system

Pic D1-3: Installation of metal back plate used to fasten existing 4-1/2” gutters systems

Pic D1-4: Example of state of existing 4-1/2” shallow gutter system which is deforming and pulling apart.

Pic D1-5: Flat roof and rear of building depicting location of existing 4-1/2” shallow gutter.

Pic D1-6: Depiction of front of building showing flow over existing 4-1/2” shallow gutter and loading dock scuppers

Pic D1-7: Measurement of the existing 4-1/2” shallow gutter system

Pic D1-8: Removal of 8 inch accent cover to view the existing 4-1/2” shallow gutter and metal back plate

Pic D1-9: Removal of 8 inch accent cover to view the existing 4-1/2” shallow gutter and metal back plate

Pic D1-10: Rear building location & loading dock depicting location of existing 4” downspout

Pic D1-11: Example of existing partial 8” box gutter at loading dock.

Pic D1-12: Above Measurement of the added partial 8” box gutter at loading dock.

Pic D1-13: Example of down spout pulled loose due to incorrect fastening to metal stud behind hollow EFIS wall.

Appendix F:

Current Pawnee IHC Warranties

Metal Roof System

20 Year Watertight Warranty (reference Appendix F)

Berridge Manufacturing Company

1720 Maury Street

Houston, TX 77026

(800) 231-8127

Contact: Louis Heppner – Warranty Manager

Beck Wynne - Region Representative

TPO System

10 Year Warranty

Carlisle SynTec, Inc.

900 Hensley Lane

Wyle, TX 75098

(469) 549-1886

Contact: Brandon Dawson – Region Representative

EFIS System

10 Year Moisture Drainage Warranty (reference Appendix F)

Dryvit Systems, Inc.

One Energy Way West Warwick, RI 02893

(800) 556-7752