751/24130. ABG; MISP - Visitor Center Redesign
Solicitation number
RFP 171 240000001087 2
Issued by
Luce County, Mcbride Village, Michigan

About this file

This is a Project Statement issued by the Michigan Department of Technology, Management and Budget (DTMB), Design and Construction Division, on behalf of the Department of Natural Resources – Mackinac Island State Park Commission, soliciting Professional Services Contract (PSC) proposals for the Mackinac Island Visitor Center Redesign located at 7200 Lake Shore Drive, Mackinac Island, Michigan. The project requires comprehensive architectural and engineering services including Phases 300 (Schematic Design) and 500 (Final Design) to renovate and upgrade the existing visitor center facility. Scope includes interior layout redesign to improve visitor flow, addition of ADA-compliant public toilet facilities, new electrical heating system, electrical distribution upgrades, information desk design, interactive interpretive display spaces, gift shop design with custom shelving and displays, and point-of-sales desk design. A mandatory pre-proposal meeting and site walk-through inspection will be held on Friday, February 23, 2024 at 11:00 a.m. at the visitor center, requiring attendees to take the 8:00 a.m. ferry from St. Ignace. Proposals are due on Thursday, March 7, 2024 at 2:00 p.m. ET, with questions accepted until February 29, 2024 at 3:00 p.m. ET. The desired project schedule includes design during Spring/Summer 2024, bidding in Fall 2024, and construction from October 2025 through April 2026.

Proposers must submit responses through Michigan's SIGMA VSS procurement website with a total cost for all phases as the bid amount, and must hold a valid Unique Entity Identifier (UEI) number. PSC responsibilities include permit application preparation and submission fees, site assessment and data collection, cost estimates at 50% and final stages, submittal of contract documents for owner review, bidding document posting, best value bid evaluation and award recommendation, construction administration, bi-weekly progress reports, and maintenance of complete project documentation. All projects are subject to prevailing wage requirements under the Governor's 2021 administrative rule, and Buy American preference provisions apply as appropriate. Individual proposal attachments cannot exceed 6 megabytes, and technical submissions must include personnel resumes and a proposed design and construction schedule. Key review meetings are required in-person format, while other meetings may be conducted electronically; all review materials must be submitted electronically and in hard copy format ten days prior to meetings.

View the file

Other files

File Type Posted
24130 Addendum 1 - Lobby Reno.pdf PDF
24130 Attachment B.pdf PDF
24130 Addendum 1.pdf PDF
24130 Attachment A.pdf PDF
SAMPLE Billable Rate Contract (Rev 221207).pdf PDF
24130 RFP Billable Rate.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0427 (R 02/22)

PROJECT STATEMENT

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration

Design and Construction Division 3111 West St. Joseph Street

Lansing, Michigan 48909

FILE NUMBER

751/24130.ABG

PROPOSAL DUE DATE

Thursday, March 7, 2024 at 2:00pm ET

CLIENT AGENCY

Department of Natural Resources – Mackinac Island State Park Commission

PROJECT NAME AND LOCATION

Mackinac Island Visitor Center Redesign PROJECT ADDRESS (if applicable) 7200 Lake Shore Drive, Mackinac Island, MI 49757

CLIENT AGENCY CONTACT

Myron Johnson johnsonm54@michigan.gov

TELEPHONE NUMBER

231-436-4100

DTMB - DCD PROJECT DIRECTOR

Alan Goschka, Project Director; goschkaa@michigan.gov

TELEPHONE NUMBER

517-388-3489

WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION:

A MANDATORY PRE-PROPOSAL MEETING will be conducted by the Issuing Office for this Request for Proposal On Site at the Mackinac Island State Park, Visitor Center at 7200 Lake Shore Drive, Mackinac Island, MI 49757at 11:00am on Friday, February 23, 2024.

Note: The ferry to the island only departs from St Ignace and will need to take the 8:00am ferry to the island to make the 11:00am meeting. A return ferry departs the island at 12:30pm.

It is requested that PSCs intending to attend the walkthrough RSVP to the DTMB-DCD Project Director prior to 5:00pm on February 21, so that any weather assessment on February 22 that results in a rescheduling of the date can result in notification to participants no later than noon on February 22.

MANDATORY (Check box if Mandatory)

COVID 19 Precautions:

1. Depending on project location, individuals may be required to wear masks to attend any meetings and for a firm to be eligible to submit proposals / quotations / bids. Bring and be prepared to wear a mask if required upon arrival. Requirements may change at any time and any updated guidance must be followed.

PROJECT DESCRIPTION/SERVICES REQUESTED

Provide a PSC Proposal (Technical and Cost) for all required Professional Architectural and Engineering Services in compliance with the State of Michigan, Department of Technology Management and Budget DTMB Project Statement Form (DMB427), DTMB ISID Billable Rate Professional Services Contract and the DTMB 430 RFP Billable Rate Form (DMB 430) and DTMB Facilities Administration, Design and Construction Division policies and procedures for the development of Contract Bid Documents and Construction Administration. The technical portion shall be concise, include personnel resumes. A proposed schedule for design, bidding and construction must be included.

Project Statement:

Mackinac State Historic Parks (MSHP) is looking to renovate and upgrade the existing Visitor Center for the Mackinac Island State Park. The existing facility is currently outdated, has limited public ADA toilet facilities and only has minimal heating capacity and no A/C. The project shall include redesign of the facility’s interior layout to address visitor flow and interaction through the facility, new visitor ADA toilets, new electrical heating system and new electrical distribution throughout. The interior layout of the facility shall include a new information desk, space for interactive interpretive displays (the design of the displays does not need to be included), a gift shop design including all custom merchandise shelving and displays, point of sales desk for the gift shop, toilets and required electrical system upgrades.

PSC proposals:

Interested bidders shall provide a complete PSC Proposal for all required Professional Services for the project. The consulting services shall be in compliance with the State of Michigan, Department of Management and Budget Contract for Professional Services and DMB Facilities Administration, Design and Construction Division policies and procedures (DMB 430) for the development of Contract Bid Documents and Construction Administration. Proposals shall include Phase 300 Schematic Design and Phase 500 Final Design services as required to produce selected improvement plans including advantages and disadvantages of options, option cost comparisons, and comparative life cycle considerations with a professional recommendation for consideration.

PSC services shall include but are not limited to:

Phases 300 and 500 services to develop complete schematic planning, design, contract document development, permitting and bidding.

Preparation and submission of all required permit applications and permit application fees including but not limited to LARA shall be included.

The PSC shall be responsible for gathering and verifying all base as-built information required for the proper design of the project.

• Providing 50% and Final (100%) estimates of construction costs for Phases 300 and 500 development plans.

Submittal of 50% and 90% contract documents for owner review for design Phases 300 and 500, posting of bidding documents on the State of Michigan procurement website (SIGMA-VSS), Best Value Bid Evaluation, PSC Recommendation of Contract Award and Contract Administration.

Provide a bi-weekly progress summary email to the project team briefly documenting the prior two week’s progress by the PSC and display the initial project schedule and current schedule status.

A graphic bar chart schedule (in weeks) indicating the PSC’s proposed timeline for services based on a proposed PSC contract start date. SSiittee aasssseessssmmeenntt aanndd ddaattaa ccoolllleeccttiioonn wwoorrkk ccaann bbeeggiinn aass ssoooonn aass ppoossssiibbllee aafftteerr ccoonnttrraacctt iiss aawwaarrddeedd aanndd aapppprroovveedd bbyy DDTTMMBB..,, aannttiicciippaattee mmiidd ttoo eenndd ooff MMaayy..

For scheduling purposes, assume fourteen (14) calendar days each of Owner review for 50% and 90% submissions.

Clear documentation of the number of meetings proposed during each Phase, indicating whether the meetings are proposed to be on-site, face to face, by telephone, or in specific electronic format.

While some project team meetings may be considered in the form of computer-based meetings (e.g., GoToMeetings, Teams, Zoom, etc.), key review meetings shall be in person. For all meetings being held for document review, all required review information shall be submitted electronically and in hard copy formats ten (10) days prior to the meetings. At a minimum, meetings will be required at key project intervals including the project planning kick off meeting, 50% reviews and 90% reviews.

Maintaining an inclusive, transparent, and informative relationship with DTMB and DNR-MSHP.

AAddddiittiioonnaall RReeqquuiirreemmeennttss

All vendors need to have a Unique Entity Identifier (UEI) number registered in SIGMA All projects are subject to prevailing wages under the Governor’s administrative rule in 2021.

Buy American Preference: As appropriate and consistent with the law, the non-federal entity should, to the greatest extent practicable under a federal award, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States (including but not limited to iron, aluminum, steel, cement, and other manufactured products).

The PSC shall be required to maintain a complete project file of all project documentation including, but not limited to, contract documents, all correspondence, all e-mails, and telephone communication logs. The project files shall be maintained in an electronic file format and delivered to the DTMB Design and Construction Division with the PSC’s final Payment Request.

ATTACHMENTS:

Attachment A - original floor plan of the facility toilet rooms (the facility has received minor renovations since then and an existing condition configuration will have to be documented by the

PSC).

Attachment B – 1987 renovation plans for the public space (an existing condition configuration will have to be documented by the PSC).

Please NOTE:

Proposal responses MUST be uploaded to SIGMA VSS. Please enter the total cost for all phases as bid amount.

Please remember that individual attachments can be no larger than 6mb.

If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance. They can be reached by telephone at 888.734.9749 or by email at sigma-procurement-helpdesk@michigan.gov

Please notify the Office of Design and Construction if you are having SIGMA VSS issues. Include your SIGMA ticket number in an email to our contract specialists, Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov ).

You may be asked to email your proposal. Emailed submissions will require DCD approval and will be handled on a case-by-case basis. Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.

NIGP CODES

90607, 90638, 90644, 90652, 90658, 92507, 92531, 92534, 92567, 92588, DESIRED SCHEDULE OF WORK

Design Spring/Summer 2024, bid Fall 2024, construction October 2025 through April 2026

ACCEPTING RFP QUESTIONS UNTIL:

Please do not submit online questions via VSS. ALL questions should be emailed to Alan Goschka, AIA at goschkaa@michgian.gov no later than Thursday, February 29, 2024 at 3:00pm Eastern Time (ET).

REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers' safety rules that are administered by federal agencies (EPA, OSHA, and DOT), state agencies (DCH, EGLE, DNR, and MIOSHA), and any other local regulations and standards that may apply.

This form is required to be a part of the professional service contract. (Authority: 1984 PA 431) Attachment(s)