240724 SSD AE Schools RFQP Final.pdf
PDF 348 KB Posted
- Attached to
- RFQ/P for Architectural & Engineering Services
- Solicitation number
- 2025.01
- Issued by
- Teller County, Colorado
About this file
The document is a Request for Qualifications and Proposal (RFQ/P) issued by Summit School District in Colorado for Architectural and Engineering (A/E) Professional Services for their 2024 Bond Program. The district is seeking up to three design firms to support a comprehensive school improvement program involving multiple school sites, with projects ranging from large-scale replacements to priority renovations. The total bond measure is approximately $195M, with projects including a replacement elementary school in Breckenridge, Career and Technical Education (CTE) improvements at Summit High School, campus renovations, and various maintenance projects at elementary and middle schools. Proposals are due on August 21, 2024, with interviews scheduled for September 11, 2024, and final candidate selection anticipated by September 13, 2024.
The RFQ/P outlines a detailed scope of work that emphasizes collaborative and transparent design processes, including engagement with Design Advisory Groups (DAGs) and community meetings. Respondents can apply for consideration of all projects, specific project groups, or priority projects only. The district will use a CM/GC (Construction Manager/General Contractor) delivery method and expects high-performance design standards. Firms must provide comprehensive team qualifications, project experience, and demonstrate ability to work within budget constraints. While fees are not submitted initially, short-listed firms will be invited to provide fee proposals, and the final selection will consider both technical qualifications and cost. The district also emphasizes local economic impact and will track local expenses throughout the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 240812 SSD AE RFQP Clarification 01.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATIONS
& PROPOSAL (RFQ/P)
FOR PROFESSIONAL SERVICES
Request for Qualifications & Proposal for Professional Services
ARCHITECTURAL & ENGINEERING
For the 2024 Bond Program – School Projects
Summit School District
Qualifications Due 08.21.2024 @ 5 PM
Provided by: DYNAMIC PROGRAM MANAGEMENT
SUMMIT SCHOOL DISTRICT
A/E RFQ/P 2 © DYNAMIC PROGRAM MANAGEMENT, LLC
Request for Qualifications & Proposal
A. Invitation & Procurement Schedule
Summit School District (Owner) would hereby invite interested firms and/or individuals (Professional Service Providers) to submit a response to this Request for Proposal (RFQ/P) for professional services in support of the 2024 Bond Program for School Projects.
QUALIFICATIONS SUBMITTAL INSTRUCTIONS
Proposals must be submitted via the electronic submission on BidNet (https://www.bidnetdirect.com/colorado ) no later than 5:00 PM prevailing time on August 21st, 2024, as specified on the solicitation notice. Please note that candidates must register on BidNet in order to submit proposals electronically. Late proposals will not be accepted. If you need assistance, please contact BidNet’s Vendor Support Department at 800-835-4603, Option 2.
No physical copy will be required, please address the Cover Letter to:
Ms. Kara Drake, CFO 150 School Road
PO Box 7 Frisco, CO 80443
Questions shall be submitted, in writing only, through bidnetdirect.com site for this solicitation no later than 5:00 PM prevailing time on August 8th, 2024. Responses to all questions shall be issued in the form of an addendum no later than 5:00 PM, August
12th, 2024.
Candidates should not rely on any other statements, either written or oral, that alter any specification or other term or condition of the RFQ/P during the open solicitation period.
Candidates should not contact any team members or any individual associated with the Owner or the Colorado Department of Education (CDE) regarding this RFQP or this project.
PROCUREMENT SCHEDULE
RFQ/P Available 7.24.2024
RFQ/P Clarification Deadline by 5 PM 8.08.2024
RFQ/P Clarification Responses 8.12.2024
RFQ/P Responses due by 3:00 PM 8.21.2024
Interview Invitations sent to Short-Listed Candidates 8.28.2024
Interviews 9.11.2024
Candidates Notified of Selection 9.13.2024
Contract Accepted by BOE Sept. 2024
C https://www.bidnetdirect.com/colorado
A/E RFQ/P 3 © DYNAMIC PROGRAM MANAGEMENT, LLC
SUBMISSION CHECK LIST
A complete submission includes the following:
1. Cover Letter
2. Firm Information
3. Qualifications
4. Similar Project Experience
5. Project Approach
6. References
Fees are not to be submitted at this time. A short list of candidates will be invited for interviews and fee proposals will be required as part of the interview process.
CONTRACT FORMAT
The contract format for this project will be a modified AIA B133. The shortlisted candidates invited for interviews will be provided with the proposed contract for comment prior to interviews.
B. Owner and Project Information
The Summit School District Board of Education has decided to include an approximately $195M bond measure on the November 2024 ballot. The projects included in this bond program are the following:
Location General Scope* Project
Category
Base Hard
Cost Budget
Breckenridge Elementary Replacement elementary school on site. 40,000 SF +/-.
Large Project
$30M
Summit HS – CTE & Snowy Peaks School
New 23,000 – 30,000 SF CTE + 30,000 +/- Snowy Peaks School Wing.
Possible 5000 SF CTE Renovation
Large Project
$40M
Summit HS Campus Track / Field / Stadium Renovation School Building Improvements / Renovation
Priority Project
$10M
Summit Middle School
Renovation, carpet, track improvements, HVAC, boilers, other maintenance projects, repurpose Snowy Peaks space
Priority Project
$4.3M
Upper Blue Elementary
Casework, paint/wallpaper, site work, playground, boilers, other maintenance projects
Priority Project
$2.2M
Frisco Elementary Playground, site work, carpet, siding, gym partition, food service equipment, other maintenance projects
Priority Project
$1.3M
A/E RFQ/P 4 © DYNAMIC PROGRAM MANAGEMENT, LLC
Silverthorne Elementary Site asphalt & concrete, playground, carpet, casework, food service, plumbing, other maintenance projects
Priority Project
$1.7M
Dillon Valley Elementary
Site asphalt & concrete, pk playground, carpet, gym partition, siding, storefront, painting, lighting, other maintenance projects
Priority Project
$1M
Summit Cove Elementary
Elementary & pk playground, site asphalt & concrete, storefront, elevator upgrade, wallpaper/paint, boilers, other maintenance projects
Priority Project
$2M
* A more detailed scope of work for each project will be provided to the short listed firms.
Please find the overall program schedule and facility master plan at this link: SSD Bond Schedule and Master Plan
The Owner intends to hire, or has already selected, the following professionals for the project team:
Owner’s Representative (Dynamic Program Management)
Surveyor
Architect / Engineering - Schools (Up to 3 Firms)
Architect / Engineering - Housing (Single Firm)
CM/GC – Schools (Up to 2 Contractors maximum)
CM/GC – Housing (Single Firm)
Commissioning Agent
Geotechnical Engineer & CMT
Environmental Consultant
Hazardous Materials Abatement Contractor
FF&E Vendor (Possibly through A/E team(s))
Moving Company
C. Scope of Work
Please note, SSD may choose up to three design firms for the scope of work in the 2024 bond program.
Respondents may choose to apply to be considered for the following:
1. All projects in the program
2. CTE / Snowy Peaks / Summit HS Renovation & Campus Improvements and all Priority Projects
3. Breck Elementary and all Priority Projects
4. Priority projects only (no large projects)
After interviews are conducted, the Owner will select the best fit team(s) for the various project groups.
As noted above, the design team for the housing projects will be a separate procurement.
https://drive.google.com/drive/folders/1yFSEZkQlb7UtL48YYB4vWm9dRuf23HDl?usp=drive_link https://drive.google.com/drive/folders/1yFSEZkQlb7UtL48YYB4vWm9dRuf23HDl?usp=drive_link
A/E RFQ/P 5 © DYNAMIC PROGRAM MANAGEMENT, LLC
The A/E Scope of Work will generally consist of the requirements in the AIA B-133 contract and the following:
TRANSPARENCY
All scope of work shall be completed in a collaborative and transparent manner. The Candidate should expect to attend Board of Education, Community and Design Advisory Group (DAG) in evenings outside of normal business hours. It is anticipated each large project will have a separate DAG (Breck Elementary, Snowy Peaks School & High School Campus / CTE Improvements). Each play yard project will have a separate
DAG.
PROGRAMMING/CONCEPTUAL DESIGN CONFIRMATION
The Candidate will assist the Owner in the development of a program that meets the needs of the school. The Candidate will develop a basic site plan, building footprint/ floor plan and exterior design concept format. The Candidate shall utilize the Master Plan already developed for this project and prepare schemes for the Owner and DAG to review. It is expected most, if not all, DAG meetings will take place in the evenings after normal business hours. The DAG for the new elementary school and CTE building may be interested in touring other newer k-12 facilities in Colorado and expect design team members to accompany them on these school tours. The Candidate shall provide an understanding that the options presented can be completed within the Owner’s budget and other parameters. The delivery method selected for the project is CM/GC. It is expected the A/E firm will have representatives at the CM/GC interviews. The Candidate will plan an informational meeting for the public with the Owner’s Representative.
Please note, the CTE/Snowy Peaks/High School renovation projects will need considerable amount of time to develop several conceptual programs for the owner to evaluate as programming has not been finalized. Time has been allowed in the proposed schedule to allow for this important work within Schematic Design.
SCHEMATIC DESIGN (SD)
Consisting of SD drawings, outline specifications and other documents illustrating the scale and relationship of Project components. Schematic Design should include the evaluation of systems for the project including the ability of the Owner and their staff to operate and maintain the new facility given the High-Performance Design components.
The project program and budget must be within the Owner’s budget for the program. The Candidate will present SD documents to the DAG and Owner’s Executive Committee for review and refinement. The Candidate will plan informational meetings for the public with the Owner’s Representative. The Candidate shall coordinate User Group meetings for various stakeholders who will utilize the building on a daily basis to refine the design. SD documents shall be provided to the CM/GC to prepare a construction cost estimate, and the Candidate shall assist the CM/GC in reviewing and verifying the construction cost estimate.
DESIGN DEVELOPMENT (DD)
Consisting of DD drawings, outline specifications, and other documents to fix and describe the size and character of the entire Project as to site, architectural, structural, mechanical, and electrical systems, materials and such other elements as may be appropriate.
Continuing review of High-Performance design ideas and operation and maintenance by the Owner.
A/E RFQ/P 6 © DYNAMIC PROGRAM MANAGEMENT, LLC
The Design Development Documents shall be developed in sequence replicating the proposed Bidding Packages. DD documents shall be provided to the CM/GC to update the construction cost estimate, and the Candidate shall assist the CM/GC in reviewing and verifying the construction cost estimate. The project must be within budget for the project to move into Construction Documents.
The Design Advisory Groups may still be meeting through the first half of Design Development. Please refer to project schedule regarding DAG meetings. The Candidate shall coordinate User Group meetings for various stakeholders who will utilize the building daily to refine the design during Design Development. At completion of Design Development, the Candidate shall lead a community meeting to provide a progress update.
Please note that although the permit authority is DFPC, it is expected that the large projects will need to go through a municipal review process such as a location & extent that will require the design team to lead and be the point of contact for the municipality. This may include presentations at planning & zoning commission and town council meetings. The design team, as their base scope of work, will be expected to respond to comments and design direction received from this process.
CONSTRUCTION DOCUMENTS (CD)
Consisting of CD drawings and specifications setting forth in detail the requirements for the construction of the Project. These shall include a complete set of architectural, civil, site development, structural, mechanical, electrical drawings including low voltage systems and I.T., kitchen design and specifications and any other information necessary for the design of the project.
The Candidate will assist the CM/GC in preparation of a written report summarizing the construction cost estimate through the completion of this phase of work. After working on the construction documents, the Candidate will prepare a presentation of the Final Design for the DAG, Executive Committee and Board of Education and plan an informational meeting for the public with the Owner’s Representative.
BIDDING PHASE AND CONSTRUCTION ADMINISTRATION
The Candidate will assist the CM/GC in obtaining bids by rendering interpretations and clarifications of the drawings and specifications in appropriate written form. The Candidate shall assist the Construction Manager in conducting mandatory pre-bidding conferences with all principal bidders.
The Candidate must attend construction meetings weekly and as needed based on the stage of construction and will assist the CM/GC in administration of the project by reviewing and timely return of submittal and shop drawings, providing observation during construction, and providing project documentation in the form of supplemental instructions, requests for information, change orders, etc.
ALTERNATE #1 – TRAFFIC ENGINEERING
Candidate shall provide as an alternate in the fee proposal (if short listed) traffic engineering for projects that will require CDOT coordination.
A/E RFQ/P 7 © DYNAMIC PROGRAM MANAGEMENT, LLC
ALTERNATE #2 – POOL CONSULTANT
Candidate shall provide as an alternate in the fee proposal (if short listed) a pool consultant to provide design for upgrades/repairs at the pool located at Summit High School.
SUBCONSULTANTS
It is expected the Candidate will provide the following subconsultants at a minimum for these projects – as required for the project scopes of work:
Civil Engineering Kitchen Designer
Structural Engineering Landscape Architecture
MEP Engineering Irrigation Design
Acoustical Consultant Fire Protection Design
IT / Low Voltage Design Interior Design
Envelope / Waterproofing/ Roofing Consultant Lighting Design
Traffic Engineer for CDOT requirements (Alternate) Playground Design
Aquatics Consultant (Alternate)
SUSTAINABILITY PROGRAM
At this time, it is expected the projects will be designed to be energy and water efficient.
While the Owner does not intend to pursue a sustainability program such as LEED, the Owner expects the schools to be designed to be within High Performance standards.
UTILITY COORDINATION
Candidates will be expected to assist in utility coordination with the various utility providers with assistance from the Owner’s Representative. Please note the coordination of utility design will be necessary for the new elementary site that currently does not have utility connections.
FF&E
General FF&E coordination with the selected vendor is required as the base scope of work. Attending design meetings to provide input for FF&E with the selected vendor is expected as a base scope of work.
DESIGN ALTERNATES
At all phases of design, the design team is expected to develop a list and design add alternates for the project for the owner to review and make decisions as to if the alternates will be incorporated into the program. This list will need to be identified early and submitted to the Owner during SD and DD.
LOCAL EXPENSES
Candidate should understand local economic impact is important to the Owner. The Candidate will be expected to track and report to the Owner’s Representative on each pay application a breakout of local expenses for any meals, lodging, subconsultants, gas, etc.
made within Summit School District boundaries for the duration of the project. These expenses are compiled each month and provided to the Board of Education as an estimate of expenses spent within the community as a result of the project.
A/E RFQ/P 8 © DYNAMIC PROGRAM MANAGEMENT, LLC
ADDITIONAL GRANT FUNDING
The Owner will pursue additional grant funding. These grants may include BEST, GOCO, DOLA, Colorado Health Foundation, etc. The Candidate will provide assessments, drawings and specifications as required to submit to various grant programs.
D. Submittal Requirements
Responses shall respond to each item noted below. Please limit response information to relevant information only.
1. COVER LETTER / LETTER OF INTEREST
Please indicate if your firm intends to apply to be considered for the following:
1. All projects in the program
2. CTE / Snowy Peaks / Summit HS Campus Improvements and all Priority
Projects
3. Breck Elementary and all Priority Projects
4. Priority projects only (no large projects)
2. FIRM INFORMATION
Provide a brief history of the firm including the following information:
- Number of years in business
- Location of office servicing this project and size of staff
- Location of main office, if different, and size of staff
- Location of any proposed associate architect and size of staff
- Information on any claims or lawsuits your firm has had in the past 10 years.
- Confirmation your firm will include all items outlined in the Scope of Work in
Section C.
- Indicate if your firm meets the insurance limits outlined below by providing an
ACORD format insurance certificate. Please note if your firm does not meet these limits, but if they could be provided if required by the Owner.
General Liability
General Aggregate $ 2,000,000
Products/Completed Operations Aggregate $ 2,000,000
Each Occurrence Limit $ 1,000,000
Personal/Advertising Injury $ 1,000,000
Fire Damage (Any One Fire) $ 50,000
Medical Payments (Any One Person) $ 5,000
Auto Liability
$1M Bodily Injury/Property Damage Each Accident Coverage applying to owned, hired and non-owned autos
Professional Liability
Per Loss $ 3,000,000
Aggregate $ 5,000,000
Policy is to be on a primary basis; if other professional coverage is carried.
A/E RFQ/P 9 © DYNAMIC PROGRAM MANAGEMENT, LLC
Workers; Compensation Per State minimums
3. QUALIFICATIONS OF PROPOSED TEAM
- Provide organizational chart for your proposed team, including subconsultants and, if applicable, associate architects
- Provide roles and responsibilities for each team member
- Provide resumes for all key team members including subconsultants and associate architects
- Please note proposed key team members are expected to be involved throughout the life of the project and may not be changed without written authorization from the Owner
- Given your current and planned workload - in a simple table - provide current availability and commitment to this project for each architectural team member proposed as a % of full time (40 hours per week) availability at each stage of design outlined in Section C
A sample table would look similar to the following:
4. SIMILAR PROJECT EXPERIENCE
- Provide project profiles for up to five similar projects in progress or completed by your firm. Please include the following:
o Project Description o Approximate Program Cost o Client Contact Information o General Contractor Contact Information o Information regarding if the project was delivered on time and on budget, and if not, why?
o A description of how this project is similar to the projects within the
Owner’s 2024 Bond Program
- The selection committee is interested in reviewing projects in which the proposed key team members have provided services and worked collaboratively together.
5. PROJECT APPROACH
- Provide your team’s design philosophy in approaching pk-12 educational projects.
- Describe how you integrate the Owner and community into the design process.
- How do you integrate flexibility for the future into your design?
- How do you approach challenges such as being over budget, over schedule and ensuring quality of the finished project?
- Indicate how your firm will handle the CA phase and if you will have local staff or a local associate architect available to respond quickly if needed during construction.
Team Member, Role Program/ Concept
SD DD CD CA
Jane Doe, Principal-in-Charge 25% 25% 10% 5% 0%
John Doe, Project Architect 30% 50% 50% 50% 25%
Etc. X% X% X% X% X%
A/E RFQ/P 10 © DYNAMIC PROGRAM MANAGEMENT, LLC
- Meeting design deliverable milestones is paramount to the success of this project. Please indicate you have reviewed the provided schedule and provide any proposed changes that could increase the probably of a successful project for the Owner. Provide alternate schedule if necessary.
If your firm is interested in the Breckenridge Elementary Replacement Project:
Please note, the baseline schedule shows the start of construction of Breckenridge Elementary to be the spring of 2026. If your firm feels the construction could commence in the spring/summer of 2025, please provide an alternative schedule for the Owner to evaluate to demonstrate how that could be feasible.
6. REFERENCES
Provide a comprehensive list of all school projects completed or begun within the past 8 years by your firm with contact information, along with a project description. Identify in the reference list which projects this A/E team has performed collectively. The Owner reserves the right to check additional references beyond those provided in the submittal.
SUBMITTAL SCORING MATRIX
Submittal Section Points
COVER LETTER 5
FIRM INFORMATION 10
QUALIFICATIONS OF PROPOSED TEAM 25
SIMILAR PROJECT EXPERIENCE 25
PROJECT APPROACH 20
REFERENCES 15
TOTAL 100 POINTS
E. Short List and Interviews
From the scoring results, the selection committee will short list firms to invite to an interactive interview. At the time of interviews, initial scoring will be discarded, and all firms will start from equal scoring positions.
The interview format will include an initial Design Review Group (DAG) meeting prepared by the Candidate with the selection committee and then time for Q&A. Fees and contract comments will be submitted in advance of the interviews. Fees will be reviewed for all short-listed firms and will be a portion of the scoring matrix for final selection.
The proposed contract and more detailed interview format information will be provided to the short-listed candidates.
F. Provisions
ACCEPTANCE AND REJECTION
The Owner reserves the right to request additional information which, in the Owner’s opinion, is necessary to ensure that the Owner has complete information with regard to the Professional Service Provider’s competence, business organization, and financial resources to assist in determining if the Professional Service Provider is qualified.
A/E RFQ/P 11 © DYNAMIC PROGRAM MANAGEMENT, LLC
The Owner reserves the right (a) to terminate the Request for Proposals process at any time; (b) to reject any or all proposals; and (c) to waive formalities and minor irregularities in the proposals received. The Owner reserves the right to reject any and all proposals in response to this Request for Proposal that are deemed not to be in the Owner’s best interests. The Owner further reserves the right to amend this Request for Proposal at any time and will notify all recipients accordingly.
RFQP SUBMISSION INFORMATION
Proposals due at the specified date and time must be received at Owner's location by that date and time to receive consideration. Proposals received after the specified date and time are considered late and are not opened. Owner is not responsible for any late proposals received by mail or any other method of delivery.
The Owner is not responsible for cost incurred in preparation of this proposal. Proposals will not be returned and become the property of the Owner once submitted. By submitting a proposal all Candidates agree to the terms and conditions of this RFQ/P and the RFQ/P will become part of the awarded Candidates contract. The Owner and the Owner’s legal council will review the agreement and negotiate terms prior to commencement of work.
Candidates acknowledge all submissions to this RFQP may be subject to the Colorado Open Records Act (CORA).
Addenda may be issued for this RFQP. All attendees of the mandatory site walk will be emailed any addenda information. It is assumed by the Owner any candidate providing a submission is responsible for receiving and reviewing all information provided by addenda.
INSURANCE
The Professional Service Provider shall provide insurance coverage for the Project which shall not be less than the amounts listed in the contract as set forth in the Request for Qualifications and Proposals; such insurance coverage shall include professional liability, general liability, automobile liability and workers' compensation.
The consultant and their insurance carrier(s) shall agree to a Waiver of Subrogation. At the time of award, consultant shall furnish to Owner a Certificate of Insurance for General Liability naming the Owner and Owner’s Representative as additional insured to provide evidence of insurance compliance. Consultant shall also furnish to Owner a Certificate of Insurance for Professional Liability to provide evidence of insurance compliance.
CONTRACT FEES
If the apparent winner’s fee exceeds the Owner’s budget and if subsequent negotiations with the apparent winner(s) are unsuccessful, the Owner reserves the right to negotiate with the next highest-scoring Candidate.