This is an Instructions to Bidders document for the Indiana County/Jimmy Stewart Airport in Indiana, Pennsylvania, soliciting bids to rehabilitate Runway 11-29 (Delta Project Number 24039-IDI). The project involves removal of existing asphalt pavement, preparation of the base course, adjustments to fillet geometry for connector taxiways, installation of a P-401 bituminous surface course, grooving the runway pavement, shoulder grading, underdrain cleanout adjustments, pavement marking, and incidental work on a runway measuring approximately 5,500 feet by 100 feet. A non-mandatory pre-bid conference is scheduled for Tuesday, June 23, 2026, at 1:00 PM in-person at the Airport Terminal Conference Room, 398 Airport Road, Indiana, Pennsylvania 15701. Bidders may submit written questions regarding project requirements to David W. Jones, P.E. and Brooke K. Taylor via email (djones@deltaairport.com; btaylor@deltaairport.com) until 4:00 PM local time on Tuesday, July 7, 2026. All bidders must provide evidence of competency and financial responsibility with their submission.
The bidding documents include the Invitation for Bids, Instructions to Bidders, Bid Forms and Supplements, Bid security, Contract Documents, and issued Addenda. Bidders must submit completed Prime Contractor Data Collection Forms and Subcontractor Data Collection Forms for every firm with which they intend to subcontract, regardless of Disadvantaged Business Enterprise (DBE) status, in compliance with 49 CFR Part 26 Subpart A. The project is subject to federal contract provisions and related regulations, and all federal clauses flow down to subcontractors and lower-tier agreements. The Owner is subject to public records laws and may release bid submissions accordingly; bidders may request confidential designation for sensitive documents by clearly marking them and providing written justification. Award and contract execution procedures are outlined in Section 30 of Part 1 - General Contract Provisions, with additional contract conditions and insurance requirements specified in Sections 10 and 40-90.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions To Bidders 1
Rehabilitate Runway 11-29 | 24039 - IDI
Instructions to Bidders
DEFINITIONS
Bid – The Bidder’s formal offer, written and submitted on the prescribed forms, to perform the Work for the Project at a specified cost based on the terms and conditions outlined in the Bidding Documents.
Bidding Documents – The Bidding Documents include the Invitation for Bids (advertisement);
Instructions to Bidders; Bid Forms and Supplements (including but not limited to the Bid Form; Bid
Schedule(s); and all Bid Certifications and Disclosures); Bid bond or other accepted forms of Bid security; proposed Contract Documents; and issued Addenda.
Contract Documents – The Contract Documents include the Bid submitted by the awarded Contractor; the
Project Manual, other than the supplemental resource material included in the Appendices which provide geotechnical and existing conditions information; the Plans; and issued Addenda.
Project Manual – A comprehensive written manual consisting of the documents that define the technical, contractual, and administrative requirements for procuring and constructing the Project. Contents may be bound in one or more volumes.
BIDDING REQUIREMENTS
Refer to Section 20, Proposal Requirements and Conditions, in Part 1 – General Contract Provisions.
PRE-BID CONFERENCE (NON-MANDATORY)
A pre-bid conference for the Rehabilitate Runway 11-29 Project will be held to discuss the proposed construction, Project Manual, and Plans. All potential Bidders are strongly encouraged to attend. The pre-bid conference details are as follows:
Date: Tuesday, June 23, 2026
Time: 1:00 PM
Format: In-person meeting
Location: Indiana County/Jimmy Stewart Airport – Terminal Conference Room
398 Airport Road
Indiana, Pennsylvania 15701
BIDDER QUESTIONS
A Bidder that has questions regarding the correct meaning of a Project requirement may submit a written request for interpretation. Questions should be sent via email to the Owner's representative in the
"Attention" line listed below and include the Project name; Airport name and location; Delta Project number; and Bidder's name, contact information, and contact phone number.
Attention: David W. Jones, P.E. and Brooke K. Taylor
Via Email: djones@deltaairport.com; btaylor@deltaairport.com
Project Name: Rehabilitate Runway 11-29
Airport Name: Indiana County/Jimmy Stewart Airport
Airport Location: Indiana, Pennsylvania
Delta Project Number: 24039 - IDI
Questions received after 4:00 PM local time on Tuesday, July 7, 2026, may not be answered.
Instructions To Bidders 2
Rehabilitate Runway 11-29 | 24039 - IDI
QUALIFICATION OF BIDDERS
The Bidder must provide evidence of its competency and financial responsibility to perform the Project Work.
Evidence must be submitted to the Owner with the Bid. Refer to Section 20, paragraph 20-02, Qualification of
Bidders, as found in Part 1 – General Contract Provisions for a description of acceptable documentation.
The Owner is subject to public records laws and may be required to release Bid submissions in accordance with the law. Any document submitted as evidence of qualifications that the Bidder deems to be confidential must be clearly identified and marked as such; however, the material may still be subject to public release under applicable law. The Bidder may seek to invoke confidential information protection for submission of any data/material by (1) identifying the data/material in a written description included with the Bid submission, (2) clearly marking the data/material as confidential, and (3) providing a written statement included with the Bid submission detailing the reasons why protection is necessary. The Owner reserves the right to ask for additional clarification prior to establishing protection.
FEDERAL CONTRACT PROVISIONS AND SUBCONTRACTS
In order for the Owner to remain compliant with its Sponsor obligations, federal laws and regulations require the Owner as a recipient of federal assistance to include specific provisions in certain contracts, solicitations, or specifications regardless of whether the Project is federally funded. These clauses are listed in Contract Conditions.
Unless otherwise stated, the Federal Contract Provisions contained within the Bidding and Contract
Documents shall flow down to subcontracts and to sub-tier agreements, and the Contractor shall be responsible for compliance with the Federal Contract Provisions by any subcontractor, lower-tier subcontractor, or service provider.
By signing and submitting a Bid for the Project, the Bidder certifies that it has read, understands, and will comply with all Federal Contract Provisions.
PRIME CONTRACTOR AND SUBCONTRACTOR DATA COLLECTION
The U.S. Department of Transportation, under 49 CFR Part 26 Subpart A, requires the Owner to collect and report certain prime contractor and subcontractor data on its federally assisted projects. The Bidder must submit with its Bid a completed Prime Contractor Data Collection Form for itself and a completed
Subcontractor Data Collection Form for every firm with which it intends to subcontract to perform Work for the Project, regardless of its Disadvantaged Business Enterprise (DBE) status. Both forms are provided herein.
AWARD OF CONTRACT
Refer to Section 30, Award and Execution of Contract, in Part 1 – General Contract Provisions.
OTHER CONTRACT CONDITIONS, INCLUDING INSURANCE REQUIREMENTS
Refer to Section 10, Definition of Terms, and Sections 40 through 90 as found in Part 1 – General
Contract Provisions.
END OF INSTRUCTIONS TO BIDDERS