24-SWU15 QA.pdf

PDF 97 KB Posted

Attached to
Stormwater Native Vegetation Installation
Solicitation number
24-SWU15
Issued by
Dane County, Wisconsin

About this file

This document is a Questions and Answers (Q&A) file related to Request for Proposal (RFP) 24-SWU15 issued by the City of Sun Prairie Department of Public Works for the Stormwater Native Vegetation Installation project. The RFP solicits proposals from qualified vendors for the installation and maintenance of native vegetation. The Q&A addresses several key points, including the use of subcontractors, the ability to partner with Disadvantaged Business Enterprises (DBEs), the availability of a water refill facility, and the potential need for the City to approve alternative methods for ground preparation. The related state and local contract opportunity is located in the state of Wisconsin.

The Q&A clarifies that the selected vendor may use subcontractors and partner with a DBE, though the latter will not receive credit in the RFP scoring process. It also confirms the availability of a water refill facility and the City's willingness to approve alternative ground preparation methods, if necessary. The responses aim to provide vendors with the information they need to prepare their proposals for this project.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

608.837-2511 300 E Main St. Sun Prairie, WI 53590 engineering@cityofsunpraicom CityofSunPrairie.com

RFP 24-SWU15

Stormwater Native Vegetation Installation

Questions & Answers

Questions Received by 8/16/2024 Answers Posted by 8/23/2024

1. Can the selected vendor use a subcontractor be used in any capacity? In example: Subcontractor completes bid items 2-8, Prime oversees bid items 2-8, and completes all remaining bid items.

Yes. Please refer to the Draft Contract, Section F - ASSIGNABILITY/SUBCONTRACTING.

2. Can the selected vendor partner with a DBE to perform a percentage of the work?

Yes, the selected vendor may partner with a DBE, however, they will not receive credit in the RFP scoring process.

3. Will the selected vendor be able to use the Public Works facility to refill water during Hydro

Seeding?

Yes, a water refill facility will be made available.

4. With such a specific piece of equipment called out in the Vegetation Restoration and

Management Plan – will the city need to approve an alternative method for ground preparation?

Yes, the City will need to approve alternate methods for ground preparation.