24-31156_Landing_Gear_F-15 LGIP PWS Final.pdf
PDF 192 KB Posted
- Attached to
- Landing Gear Improvement Program (Final Report)
- Solicitation number
- FD2060-24-31156
About this file
This document is a Performance Work Statement (PWS) for the Landing Gear Improvement Program (LGIP) for the F-15 aircraft. The objective is to provide engineering services to develop and execute improvements to the F-15 landing gear in accordance with military standards for aircraft structural and mechanical integrity programs. The key tasks include providing fatigue analysis, safe life assessment, risk analysis and mitigation, and final findings and recommendations reports. The PWS specifies the required deliverables, performance standards, and government-furnished information. The contract has a 9-month period of performance and is a pre-solicitation for the Department of the Air Force Materiel Command Lifecycle Management Center at Robins Air Force Base.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR: FD2060-24-31156 PWS REVISION: 0 1
Performance Work Statement for
Landing Gear Improvement Program
Purchase Request: FD2060-24-31156
1-February-2024
PR: FD2060-24-31156 PWS REVISION: 0 2
1.0 Description of Services
1.1 Objective(s): This Performance Work Statement (PWS) describes the services required to research, analyze, advise, and develop deliverables to advance related scientific and technical information (STI) through the application of knowledge and resources in achieving the requiring activity's mission requirements defined herein.
The objective of this PWS is to provide engineering services in support of the F-15 SPO objective of developing and executing F-15 improved landing gear OSS&E in accordance with
MIL-STD-1530, Aircraft Structural Integrity Program (ASIP) and MIL-STD-1798 Mechanical
Equipment and Subsystems Integrity Program (MECSIP).
This effort will result in the final delivery of four reports consisting of the final F-15 C/D and
E Fatigue Analysis Report, Safe Life Assessment Report and Risk Analysis and Mitigation
Report Update, the Final Findings and Recommendations Report, and the Risk Analysis and
Mitigation Report
1.2 Benefit to United States Air Force (USAF): This acquisition will benefit the United States
Air Force (USAF) by supporting the future needs in accomplishing this effort to sustain the existing systems and provide for their long term sustainability on the F-15E.
1.3 Background:
The F-15 LGIP is intended to develop and execute objectives for the F-15 landing gear in accordance with MIL-STD-1530, Aircraft Structural Integrity Program (ASIP) and MIL-STD-
1798 Mechanical Equipment and Subsystems Integrity Program (MECSIP). Air Force ASIP and
MECSIP requirements specify that structural and functional integrity be maintained for the life of the aircraft to ensure operational safety, suitability, and effectiveness (OSS&E) of the weapon system. This requires that the safe-life and service history of safety-of-flight and mission-critical landing gear parts are known and monitored. However, the critical landing gear structural parts and processes have not been efficiently tracked and monitored since the F-15 was introduced into service, resulting in aircraft flying with an unknown risk associated with the landing gear integrity. It is also possible that F-15 operational loads and fatigue spectrum have shifted over time, and the remaining safe-life of landing gear parts needs to be analyzed, again putting an unknown risk on the warfighter. The LGIP was undertaken to ensure OSS&E throughout the weapon system’s remaining life. Efforts have been completed to date for the LGIP are the
Probabilistic Age Assessment; Reliability, Availability, and Maintainability (RAM) Analysis;
and Fatigue Analysis with OEM assumed spectrum.
2.0 Services Summary
2.1 Task/Description of Services
2.1 Objective(s): This Performance Work Statement (PWS) describes the services required to provide engineering services in support of the F-15 SPO and 417 SCMS objective of developing and executing F-15 improved landing gear OSS&E in accordance with MIL-STD-1530, Aircraft
PR: FD2060-24-31156 PWS REVISION: 0 3
Structural Integrity Program (ASIP) and MIL-STD 1798 Mechanical Equipment and Subsystems
Integrity Program (MECSIP).
2.2 Service Summary:
Performance Objective PWS
Reference
Performance Threshold
Provide timely delivery of monthly LGIP data.
4.1 By the 10th of each month. Reports must be
delivered on time 90% of the time.
Quality of CDRL deliverable
2.2.1
4.3.1
Standard: CDRLs are timely, complete, and accurate.
Threshold: No more than one rejection per quarter.
No more than two errors per month. An error is defined as an incorrect statement or the omission of required information. A corrected MSR shall be submitted within five business days of identification of an error.
Receipt of CDRL deliverable
2.2.2
4.3.2
Standard: are timely, complete, and accurate.
Threshold: No more than two late submissions quarter.
An error is defined as an incorrect statement or the omission of required information. A corrected report shall be submitted within five business days of identification of an error.
2.2.1 Contractor shall provide a detailed status for each task within the PWS as well as capture an overall status of the TO. The contractor shall deliver the MSR by the 15th of each month.
Specific MSR format, and any additional content not specified in this section, shall be mutually agreed upon by the contractor and COR. The MSR reports cost, schedule, and performance against the PMP baseline and identifies planned versus actual expenditures per project; total monthly and cumulative ODC expenditures; status of known risks and risk mitigation efforts;
deliverable(s) funded, technical progress made, and schedule status per deliverable(s); title, date, and number of deliverable(s) completed; and deliverable(s) scheduled to be delivered during the upcoming month. The MSR shall report all funding received and shall detail the tasks supported by such funding, the date received, and the funding source (if known). If the MSR shows that a task is not meeting the performance standards set forth in the PWS, the contractor shall provide the rationale and circumstances preventing the standards from being met. (CDRL A001, DI-
MGMT-80368A, Monthly Status Report)
2.2.2 Analyze the performance of structural components leveraging the Aircraft Structural
Integrity Program (ASIP) as defined by AFI 63-140, Aircraft Structural Integrity Program, and MIL-STD-1530D, Aircraft Structural Integrity Program (ASIP). Access and analyze
PR: FD2060-24-31156 PWS REVISION: 0 4
performance data to identify failure modes and trends. Recommend technical order updates, repairs, or maintenance process changes to maintain the integrity of structural components and improve maintainability and reliability. Documents investigations and assessments addressing maintenance practices, structural design and loads, repair processes, failure modes and patterns, safety and risk areas, training and technical publication considerations, obsolescence issues, proof of concept designs, system malfunctions, and other maintenance and logistical issues with recommendations to address deficiencies and improve service life for systems, subsystems, and components. Includes baseline analysis, gap analysis, root cause analysis, FMECA, trend analysis, mitigation, and prioritization recommendations, and AoA of aircraft systems, subsystems, and components. Includes identification of potential impacts to all required aircraft certifications such as airworthiness, information assurance, joint interoperability, frequency allocation, and supporting compliance documentation as well as methods of verification.
Documentation supports approvals through all required CCB and CRB reviews.
3.0 Government Property: Government Furnished Information
The USAF will provide, or assist Contractor in obtaining, the following Government Furnished
Information (GFI). All GFI is required within two weeks of request.
• Applicable Existing/Original Equipment Manufacturer (OEM) Drawings
• Applicable USAF Commodity and Field Level Technical Orders
• Applicable Existing/OEM Limit and Ultimate Loads Data and Limit and Ultimate Stress
Analyses
• Applicable Existing/OEM Fatigue Spectrum and Fatigue Analyses
• Other applicable existing/OEM manuals, as necessary
• Other applicable USAF Technical Orders, as necessary
4.0 Technical Requirements
4.1 This effort is comprised of completing the analysis, evaluating results, and recommendations to finalize the reports specified in the following four tasks.
4.1.1 Task 1 – Provide F-15 C/D and E landing gear fatigue analysis report to F-15 SPO.
Contractor shall use the previously developed operational spectrum to perform the following (CDRL A002, DI-MISC-80508B/T, Fatigue Analysis):
• Contractor shall perform finite element analysis on the F-15 C/D and E landing gear components using operational loads on the aircraft.
• Contractor shall use existing F-15 C/D and E landing gear fatigue issues for incorporation into the analysis as required.
• Contractor shall perform all required programming and apply the operational loads spectrum to complete fatigue analysis of landing gear components using HBM nCode.
• Contractor shall perform additional evaluation as-required, where fatigue failure is shown to potentially exist
PR: FD2060-24-31156 PWS REVISION: 0 5
• Contractor shall detail and summarize the data for use in updating the Safe Life and
Risk Analysis Reports.
• Contractor shall prepare and write the Fatigue Analysis Report.
4.1.2 Task 2 - Provide F-15 C/D and E Safe Life Assessment Report and Risk Analysis and
Mitigation Report Update to F-15 SPO. Contractor shall use fatigue analysis results to update the Safe Life Assessment Report and the Risk Analysis and Mitigation Report: (CDRL A003, DI-MISC-80508B/T, Safe Life Assessment Report):
• Contractor shall update the fatigue analysis results within the existing Safe Life Report for landing gear components that indicate fatigue issues not previously reported in the Safe Life Report
• Contractor shall update the safe life assessment sheets in the report for the same components.
• Contractor shall release the next revision of the Safe Life Assessment Report.
• Contractor shall update the Risk Analysis and Mitigation Report for components that show potential safety issues not previously accounted for in the Report.
• Contractor shall update the Hazard Risk Index and develop a Risk Mitigation plan and release the next revision of the Risk Analysis and Mitigation Report as needed.
4.1.3 Task 3 - Provide F-15 C/D and E Final Findings and Recommendations Report to F-15
SPO. Contractor shall update the report based on findings from the Fatigue Analysis Report, Safe Life/Risk Mitigation Reports (CDRL A004, DI-MISC-80508B/T, Final Findings and
Recommendations Report).
4.1.4 Task 4 - Identify and characterize potential fatigue damage on the landing gears of a combat configured F15E / F-15EX with increased gross weight. (gross weights provided as GFI)
(CDRL A005, DI-MISC-80508B/T, Risk Analysis and Mitigation Report)
4.2 Period and Place of Performance
4.2.1 Contract/Order Period of Performance: The period of performance for the contract/order will be 9 Months.
4.2.2 Place of Performance: Place of performance will be the contractor’s facility.
PR: FD2060-24-31156 PWS REVISION: 0 6
4.3 Contract Data Requirements List(s) (CDRL)
Document
Identifier
Base Year
DID Title PWS Reference(s)
A001 DI-MISC-
80368/T
Monthly Status Report 2.2.1
A002 DI-MISC-
80508B/T
Fatigue Analysis Report 4.1.1
A003 DI-MISC-
80508B/T
Safe Life Assessment Report 4.1.2
A004 DI-MISC-
80508B/T
Final Findings &
Recommendations Report
4.1.3
A005 DI-MISC-
80508B/T
Risk Analysis and Mitigation
Report
4.1.4
A006 DI-SAFT-
81563
Accident/Incident Report 5.5.2
4.3.1 Quality of CDRL Deliverable: There shall be no more than one rejection of any deliverable. There shall be no more than 1 total rejection(s) of deliverables per quarter. The
Government will reject a deliverable if one or more technical errors or two or more minor errors are found within the deliverable. A technical error is defined as the format not being in accordance with the CDRL or the content not being accurate and complete in accordance with the CDRL, PWS or contract. A minor error is exemplified by a typographical error, a grammatical error, etc. The rejected deliverable shall be corrected and resubmitted within 5 business days of notification of Government rejection.
4.3.2 Receipt of CDRL Deliverable: CDRL deliverables shall be submitted via Wide Area
WorkFlow (WAWF) and submitted directly to the MFT member identified on the CDRL. There shall be no more than 2 late submission(s) of deliverables per quarter. The Contractor shall notify the Government if the delivery of any data/document will not meet the scheduled delivery date and negotiate a revised delivery date. The data/document shall be delivered by the revised delivery date acceptable to the Government.
4.4 Travel: Travel is not anticipated for this effort.
5.0 General Information
5.1 Continuation of Mission-Essential Services During a Crisis: The Functional Service
Manager (FSM) has determined these services are not mission-essential and will not continue in the event of a crisis.
5.2 Security Requirements
PR: FD2060-24-31156 PWS REVISION: 0 7
5.2.1 Security Clearance: It is not expected the contractor/subcontractor personnel will require security clearances for proper accomplishment of contract/order requirements.
Contractor/subcontractor personnel shall not be authorized access to classified information and/or Controlled Unclassified Information (CUI) and classified items or be permitted to work on classified projects and/or programs without an appropriate security clearance and a need-to-know.
5.2.2 Access to Government System(s): Access to Government system(s) will not be required to perform tasks under the contract/order.
5.3 Environmental Management System (EMS): These services shall not be performed at a
Government facility; therefore, the EMS requirement does not apply.
5.4 Agency Affirmative Procurement Programs: This acquisition does not require the purchase of Environmental Protection Agency (EPA)-designated products or United States
Department of Agriculture (USDA)-designated products; therefore, the requirement does not apply.
5.5 Safety Requirements
5.5.1 Contractor Environmental, Safety, and Occupational Health Compliance: The
Contractor shall comply with Government Safety and Health regulations including, but not limited to, Public Law 91-596, Occupational Safety and Health Act (OSHA), and DoD Directive
4715.1E, Environmental, Safety, and Occupational Health (ESOH). The Contractor shall establish and maintain a safety and health program detailed in a written Contractor’s Safety and
Health Plan. The Contractor shall require all subcontractors to comply with required safety, health and fire standards.
5.5.2 Mishap Notification/Investigation: The Contractor shall report mishaps including damage to DoD property; occupational illness to DoD military or civilian personnel; injury to on- or off-duty DoD military personnel; injury to on-duty DoD civilian personnel; and damage to public or private property or injury or illness to non-DoD personnel caused by Government operations. In the event of a mishap, the Contractor shall ensure the USAF is notified of the mishap. The Contractor shall contact the organizations listed below within four business hours.
The Contractor shall immediately secure the mishap scene (and damaged property) and impound pertinent maintenance and training records until released by the Government’s Safety Office
(AFLCMC/SE). Such release shall be accomplished through the Contracting Officer. The
Contractor shall cooperate and assist Government personnel in the investigation of the mishap and submit an Accident/Incident Report within 24 hours of the mishap [CDRL A006, DI-SAFT-
81563, Accident/Incident Report].
5.5.2.1. PCO,
5.5.2.2. MFT (COR, if available, or another MFT member),
5.5.2.3. The closest USAF base command post (to relay notification to AFLCMC/SE).
5.5.3 Voluntary Protection Programs (VPP): Contractor personnel performing work on a USAF installation shall participate in the local VPP.
PR: FD2060-24-31156 PWS REVISION: 0 8
5.5.4 VPP Description: In 1982, OSHA created the Voluntary Protection Programs (VPP) to recognize and partner with worksites that implement exemplary systems to manage worker’s safety and health. These sites implement comprehensive Safety and Health Management
Systems that exceed basic compliance with OSHA standards. VPP applies to all personnel at
Robins AFB - civil servants (both bargaining and non-bargaining), active duty (officer and enlisted), reservists and contractor employees. The Contractor shall ensure its employees and managers have a comprehensive understanding of VPP as well as full compliance with OSHA requirements. The Contractor, whether regularly involved in routine site operations or engaged in temporary projects such as construction or repair, shall follow the safety and health rules of the installation or VPP site. Detailed information on VPP is available on the OSHA website at http://www.osha.gov/dcsp/vpp/index.html. The Contractor shall access the site to ensure their understanding of VPP and how their performance is linked to the Air Force installation’s pursuit of VPP recognition.
5.5.5 Department of Labor (DoL) Inspection of Contractor Operations. The Contractor is subject to DoL inspections and enforcement by OSHA health and safety officials while performing work on a Government installation. OSHA health and safety officials may access workplaces on
Government installations at any time, scheduled or unscheduled, during regular work hours.
OSHA health and safety officials must meet security requirements to enter restricted or classified areas. The Contractor shall immediately notify the COR and the contracting unit’s Safety Office upon notification of a visit.
5.6 Inspection of Services: In accordance with the Inspection of Supply/Services clause(s) identified in the contract/order, the Government reserves the right to inspect Contractor performance.
5.7 Service Contract Reporting (SCR): The contract does not meet the DoD Contract
Reporting criteria or reporting dollar threshold; therefore, SCR does not apply.
5.8 Invoicing/Payment and Receipt/Acceptance: The Contractor shall submit/process payment requests and receipt/acceptance documents via WAWF.
5.9 Trafficking in Persons: The Contractor shall comply in accordance with the FAR and applicable supplements and shall be in compliance with all applicable guidance and clauses listed in the contract as it relates to Trafficking in Persons. Additional information about
Trafficking in Persons is available at the site for the Department of State’s Office to Monitor and
Combat Trafficking in Persons. http://www.state.gov/j/tip http://www.state.gov/j/tip
PR: FD2060-24-31156 PWS REVISION: 0 9
6.0 Appendices
6.1 Appendix A, Reference(s)
Document Number Title Date Company
39631R0200001, Rev A F-15 C/D &E Flight Test
Report
TBD US Gov
39631R0300002, Rev A F-15 C/D & E Operational
Loads Spectrum Report
TBD US Gov
39631R0400003. Rev A* F-15 C/D & E Post-Test
Fatigue Analysis Report
TBD US Gov
39631R0600004, Rev A* F-15 C/D & E Final
Findings and
Recommendations Report, TBD US Gov
*Note: 39631R0400003. F-15 C/D & E Post-Test Fatigue Analysis Report and 39631R0600004, F-15 C/D & E Final Findings and Recommendations Report were released partially completed, with all available information at the end of the previous effort.