This is a Solicitation Addendum No. 1 issued by the Beaverton School District's Business Services Procurement and Contracting office for ITB 24-0022 concerning renovation work at Highland Park Middle School involving the creation of a new conference room and construction of walls. The addendum modifies the original invitation to bid and clarifies project specifications, including revised drawings that address low voltage cable removal and retention, new conduit installation above the ceiling, and photographic documentation of cable removal in the library office. The project encompasses three areas requiring painting updates: the accordion wall area (new wall surfaces only), the new library conference space (ceiling, walls, and door/window frames), and additional work areas. The addendum clarifies that salvageable doors and windows will be reused if they meet condition standards and proper swing specifications, contingent on confirmation from Beaverton School District regarding salvage condition. The district will remove all furniture and equipment prior to construction commencement. The bid closing date is March 13, 2025, at 2:00 PM Pacific Time, and bidders must acknowledge receipt of this addendum on the Bidder Certification form to avoid bid rejection.
The addendum does not specify pricing information, set-asides, or funding sources. All bidders must comply with the clarifications and modifications outlined in the addendum, particularly regarding electrical work specifications shown in the revised drawings (E-200 Overall Floor Plan, E-210 Enlarged Electrical Plans, and E-400 Electrical Details). The successful contractor will be responsible for contract abatement in both project spaces. Failure to acknowledge receipt of this addendum may result in offer rejection.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sole Source Notification.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Business Services Procurement and Contracting 1260 NW Waterhouse Avenue
Beaverton, OR 97006
(503) 356-4324
March 6, 2025
SOLICITATION ADDENDUM NO. 1
ITB 24-0022
Highland Park Middle School- New Conference Room & Walls
THE FOLLOWING CHANGES/ADDITIONS TO THE ABOVE CITED SOLICITATION ARE ANNOUNCED:
This Addendum modifies the Invitation to Bid (ITB) document(s) only to the extent indicated herein. All other areas not changed or otherwise modified by this Addendum shall remain in full force and effect. This Addendum is hereby made an integral part of the ITB document. Bidder must be responsive to any requirements of this Addendum as if the requirements were set forth in the ITB.
Failure to do so may result in Bid rejection. See the ITB regarding requests for clarification or change and protests of this Addendum, and the deadlines for the foregoing.
This addendum is to be acknowledged in the space provided on the Bidder Certification form supplied in the solicitation document.
Failure to acknowledge receipt of this addendum may be cause to reject your offer.
The closing date Is:
March 13, 2025 at 2:00 PM Pacific Time
CLARIFICATIONS
Modification to Drawings
Revised drawings providing clarification for which low voltage cables need to remain, and which are to be removed. Revision also defines protections means for these existing cables through the project area.
a. Removal of low voltage cables and surface raceway in library office.
b. Provide new conduit from existing low voltage wireway above new ceiling.
c. Addition of photos to help understanding of what is included in the cable removal.
QUESTIONS
QUESTION: Will the man door and windows be reused and placed into the new wall?
ANSWER: If the door and window condition looks like a new product when salvaged, and if the door swing is correct, both of those items can be reused. Please confirm with BSD about the Salvaged condition.
QUESTION: Are both project areas receiving new paint on the walls, ceilings, and door frames?
ANSWER: Yes, painting of all three areas are to be done to create a new condition when completed. See Update below:
Painting of the accordion wall area will not be necessary other than both sides of the new wall itself.
Painting in the new Library conference space should include the Ceiling, Walls, and Door/Window Frames (Touched up as needed if Salvaged).
QUESTION: Will the rooms be empty of furniture and equipment when the contractor arrives?
ANSWER: BSD will have the furniture and equipment removed prior to start of construction. Note: The successful proposer will be responsible for the contract abatement in both spaces.
ATTACHMENTS
*E-200 Overall Floor Plan- First Floor *E-210 Enlarged Electrical Plans *E-400 Electrical Details