238350_NEBE_Specifications_revised_07-16-2021.pdf

PDF 4 MB Posted

Attached to
HPTC-NEBE BANK VISITOR CENTER PAINT/PLAS
Solicitation number
140P2121R0029
Issued by

About this file

This document outlines specifications for a federal construction contract to perform plaster repairs, painting, and window repair at the Historic Bank Building Visitor Center in New Bedford, Massachusetts. The work includes plaster repairs on ceilings, walls, and ornamental plaster; painting walls, ceilings, doors, windows, and other architectural features; and optional restoration of Window 101. The contract will be awarded as a single prime contract by the National Park Service. The response due date is not specified. Work must be performed according to historic preservation standards and comply with various regulations including OSHA, NFPA, and state and local codes. The contractor must develop an accident prevention plan, safety procedures, and environmental protection measures.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTERIOR REHABILITATION OF

THE HISTORIC BANK BUILDING

- VISITOR CENTER

PMIS No. 238350

NEW BEDFORD WHALING

NATIONAL HISTORICAL PARK

NEW BEDFORD, MA

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

HISTORIC PRESERVATION TRAINING CENTER

JULY 16, 2021

Instructions & Table of Contents (TOC)

Specifications Table of Contents (TOC)

Table of Contents (TOC) 01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures

DIVISION 2 – EXISTING CONDITIONS

02 83 13 Lead Hazard Controls

DIVISION 6 – WOOD, PLASTICS AND COMPOSITES

06 03 12 Historic Wood Repair 06 10 00 Rough Carpentry 06 20 00 Finish Carpentry

DIVISION 9 – FINISHES

09 03 20 Historic Treatment of Plaster and Stucco 09 80 02 Encapsulation 09 91 00 Painting and Finishing

NEBE 238350 01 11 00 - 1

SUMMARY OF WORK

NPS Division 1 Specifications National Park Service

NEBE NHP – Visitor Center PMIS 238350

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Site Examination

5. Government-Furnished Materials

6. Protection of Property

7. Project Historical Characteristics

8. Contractor Use of Site

9. Public Use of Site

10. Occupancy Requirements for Buildings

11. Conduct of Operations

12. Work Restrictions

13. Additional Reports

14. Project Standards

15. Work included in Contract

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: New Bedford, MA Whaling National Historical Park Visitor Center, 33 Williams Street, New Bedford, MA 02740

B. The Work consists of:

1. Perform plaster repairs to ornamental plaster, coffered ceilings, and walls. Prepare and paint ornamental plaster, coffered ceilings, and walls. Prepare and paint baseboard, decorative architecture on the north wall, all windows and trim, doors 101A, 101B, 101C, and 101D and associated trim, and brick wall, handrail, and stair carriage at basement.

2. Option 1: Restoration of Window 101.

C. Project will be constructed under a single prime contract.

D. Background: Completed in 1836, the U.S. Custom House in New Bedford is the oldest continuously operating custom house in the nation. It is also the largest of the four granite Greek

NEBE 238350 01 11 00 - 2

Revival custom houses in New England designed by Robert Mills between 1834 and 1836.

Robert Mills is the first internationally recognized architect that was both born and trained in America. He is most known for his designs in Washington D.C., including the Washington Monument, the Patent Office, the U.S. Treasury, and the General Post Office.

The New Bedford Custom House was authorized by Congress on July 3, 1832. The site for the building was purchased on April 22, 1833 for $4,900. The cost of the finished building was approximately$25,500.

Historically, whaling masters registered their ships and cargo at the two-storied, columned New Bedford Custom House. It also housed the city's first postal service. Although it is no longer a post office, today's commercial fishing and cargo ships continue to log duties and tariffs here, as it still serves as the New Bedford office of the U.S. Customs Service. The building also offices the National Marine Fisheries Service

E. Existing Historical Information

1. Project includes construction activities involving a property listed on the National Register of Historic Places as determined by the United States of America, Department of the Interior (DOI), National Park Service (NPS).

1.3 WORK PHASES

A. The Work shall be conducted in 2 phases in the following order, with each phase substantially complete before beginning next phase:

1. Plaster repairs: Repair of cracks on plaster on ceiling and walls.

Painting: Painting of walls, ceiling ornamental plaster, doors and windows and other described in drawings (Painting includes lead encapsulation of all areas described in this section). The remaining Work shall be substantially complete and ready for occupancy at time of Substantial Completion.

2. Phase (Option 1). Window 101 repairs

1.4 SITE EXAMINATION

A. Visit and examine existing conditions of Project prior to submission of Of-fer in order to better understand Work, verify quantities, and aid in forming any questions prior to the submission of offer.

B. Be aware of all conditions of Site and Project and verify quantities and lo-cations of Work intended.

1. Failure to verify does not:

a. Waive obligations to furnish labor, materials and appurte-nances required to perform the Work, or https://www.nps.gov/wamo/index.htm https://www.nps.gov/wamo/index.htm

NEBE 238350 01 11 00 - 3

b. Constitute grounds for a claim after Contract award.

2. See FAR 52.237-1 Site Visit.

C. To perform a Site Examination prior to Offer submission, contact Contract-ing Officer to coordinate a time during normal Park hours:

1.5 GOVERNMENT-FURNISHED MATERIALS

A. In case of Government -furnished materials:

1. None

1.6 PROTECTION OF PROPERTY

A. All work executed to comply with the National Park Service Organic Act of 1916 , et seq., also known as 16 USC § 1, 2, 3 and 4, conserving the scenery, the natural and historic objects and wildlife within the Park, Roger Williams National Memorial.

B. Government is not liable for loss, damage, or destruction of equipment furnished due to negligence of and during execution of procedures.

C. In addition to Federal Acquisition Regulation (FAR) 52.236-9 Protection of Existing Vegetation, Structures, Equipment Utilities and Improvements:

1. Perform removal of materials and execute Work in a manner to prevent injury or damage to existing work / historic fabric indicated / scheduled to remain.

2. Repair or replace existing work / historic fabric that may be altered during construction.

a. Match existing and adjoining as closely as possible.

b. Upon completion, conditions shall be equal to or better than conditions prior to execution.

1.7 PROJECT HISTORICAL CHARACTERISTICS

A. Subject is a historically significant structure, and has been determined as a Cultural Resource that is not only an asset to the local community, the State of Massachusetts and the United States of America, being an instrument that physically conveys the unique period, and aspects of American culture and heritage to the public.

1. As determined by Government, the Cultural Resource must be preserved, maintained, and protected appropriately to ensure future generations educational and recreational enjoyment derived from the Cultural Resource shall endure.

https://www.acquisition.gov/far/current/html/52_233_240.html http://www.nps.gov/grba/parkmgmt/organic-act-of-1916.htm http://uscode.house.gov/download/pls/16C1.txt https://www.acquisition.gov/far/current/html/52_233_240.html https://www.acquisition.gov/far/current/html/52_233_240.html https://www.acquisition.gov/far/current/html/52_233_240.html

NEBE 238350 01 11 00 - 4

2. Due to historic significance, aspects of Work, and other activities, may not be executed in a manner or with methods commonplace of the contemporary construction industry.

3. Execute Project in a manner that respects and preserves the historical significance and fabric of the Project subject, Site and surrounds where Work shall be performed.

4. Confirm and receive approval of means and methods planned to be utilized to execute Project from Government prior to the commencement of Work.

1.8 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to Visitor Center and basement beneath visitor center indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to visitor center and basement.

B. Storage of Materials: Confine storage of materials to basement of visitor center.

C. Parking: On street parking is available with paid Meter. Parking garage is one block away, charge for parking garage is $18 a day or $45 a month, with the first month costing $55 to pay for garage pass.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within park will not be permitted.

1.9 PUBLIC USE OF SITE

A. The Visitor center will be closed to the public during the duration of rehabilation repairs.

Permeant fixed exhibits in visitor center will not be moved. Contractor will protect exhibits during renovation. Non-fixed exhibits will be moved out of visitor center by NPS Staff prior to commencement of work.

1.10 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not

NEBE 238350 01 11 00 - 5

to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

b. Maintain existing building in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.

1.11 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 5 business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.12 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8 a.m. 430 p.m., Monday through Friday, except when otherwise indicated. Access will be provided by NPS employees and/or COR.

1. Weekend Hours: None

2. Early Morning Hours: None

B. Existing Utilities

1. Contractor will have access to existing electrical and water during construction.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes

1.13 ADDITIONAL REPORTS

A. The Lead Report prepared by Master Lead Paint Inspection is in section02 83 13 with this package.

NEBE 238350 01 11 00 - 6

B. In case of conflict between report and drawings or specifications, drawings and specifications govern.

1.14 PROJECT STANDARDS

A. Execute and complete Work of the Project as depicted by Contract and Project Documents, and as affected by job conditions, and the implied intent of the Project as a whole to ensure the life safety, health and well-being of all end users, while preserving the historic fabric of subject structure and its components.

B. Align Work performed under this Contract with:

1. Historical requirements:

a. National Historic Preservation Act. National Historic Preservation Act of 1966 (16USC470) (nps.gov) https://www.nps.gov/history/local-law/nhpa1966.htm

b. The United States Secretary of the Interior's Standards for the Treatment of Historic Properties, with Guidelines for Preserving, Rehabilitating, Restoring, and Reconstructing Historic Buildings; https://www.nps.gov/tps/standards/treatment-guidelines-2017.pdf

C. Comply with

1. National Environmental Protection Act.

2. Building Codes:

a. International Building Code (IBC), 2009, with State of Massachusetts amendments for construction of the Project

3. William-Steiger Occupational Safety and Health Act (OSHA) of 1970, as amended, and modified to date.

4. Health and safety regulations and requirements, as applicable, of all other authorities having jurisdiction.

5. State labor laws and regulations.

1.15 WORK INCLUDED IN CONTACT

A. Work will be constructed under a single prime contract.

B. Work of Project / Contract consists of construction and related services indicated on Project Drawings and described in Technical Specifications. Refer to Drawings for building data and additional general information concerning Work.

C. Work of Project includes, but is not limited to:

1. Basic Requirement – Repair and painting of Bank Building Visitor Center Interior

a. Division 01: General Requirements items of the Contract.

b. Division 028313 - Renovation painting over existing lead paint.

c. Section 090320 – Historic Treatment of Plaster and Stucco: Plaster repairs on damaged plaster ceiling, ornamental plaster and walls.

https://www.nps.gov/history/local-law/nhpa1966.htm https://www.nps.gov/history/local-law/nhpa1966.htm https://www.nps.gov/history/local-law/nhpa1966.htm https://www.nps.gov/tps/standards/treatment-guidelines-2017.pdf https://www.nps.gov/tps/standards/treatment-guidelines-2017.pdf

NEBE 238350 01 11 00 - 7

d. Section 099100 – Painting and Finishing – Preparation and paint of designated interior doors, windows, walls, ceiling, ornamental plaster, bottom of stairs brick and architectural decorative features

2. Option 1 – Restoration of Window 101

a. Section 060312 – Historic Wood Repair- Repair of historic wood window 101

b. Section 061000 – Rough Carpentry – Repairs on wood window

c. Section 062000 – Finished Carpentry – Finished repairs on wood window

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

NEBE 238350 01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

NPS Division 1 Specifications

NEBE NHP – Visitor Center PMIS 238350

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

NEBE 238350 01 26 01 - 2

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

NEBE 238350 01 26 01 - 3

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

NEBE 238350 01 26 01 - 4

Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 18 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region) http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|

NEBE 238350 01 26 01 - 5

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit…………………...10%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

NEBE 238350 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

NEBE 238350 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

NPS Division 1 Specifications National Park Service

NEBE NHP – Visitor Center PMIS 238350

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 0001

1. This item consists of Performing plaster repairs to ornamental plaster, coffered ceilings, and walls. Prepare and paint coffered ceilings, ornamental plaster, and walls. Prepare and paint baseboard, decorative architecture on the north wall, all windows and trim, doors and trim on 101A, 101B, 101C, and 101D, and brick wall at stair.

2. Measurement for payment will be on a percent complete basis.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item Number 0002 with Option A

1. This item consists of performing restoration of Window 101.

2. Measurement for payment will be on a percent complete basis.

3. Payment will be made at the contract option sum price, END OF SECTION 01 27 00

NEBE 238350 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

NPS Division 1 Specifications National Park Service

NEBE NHP – Visitor Center PMIS 238350

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. Project Meetings

7. Environmental Coordination

8. Permits

B. Related Requirements:

1. Section 01 32 18 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Make provisions to accommodate items scheduled for later installation.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

NEBE 238350 01 31 00 - 2

1. Preparation of Contractor's Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

9. Commissioning activities

1.3 SUBMITTALS

A. Division 1 documents: The following items shall be submitted before commencement of rehabilitation.

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Indoor Air Quality (IAQ) Management Plan

11. Contractors Commissioning Plan

12. Historic Preservation Treatment Plan (HPTP)

13. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

B. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI from via email.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

NEBE 238350 01 31 00 - 3

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract

Time or Contract Sum, Contractor shall state impact in RFI.

8. Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.

1.5 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

NEBE 238350 01 31 00 - 4

5. Coordination of Subcontractors

6. Labor law application

7. Modifications

8. Payments to Contractor

9. Payroll reports

10. Contract time

11. Contractor Performance Evaluation

12. Display of Hotline posters

13. Notice to proceed

14. Correspondence procedures

15. Acceptance/rejection of work

16. Progress meetings

17. Submittal procedures

18. Environmental requirements

19. Permit requirements

20. As-constructed drawings/operation and maintenance (O&M) manuals.

21. Saturday, Sunday, holiday and night work.

22. Reference materials

23. Schedule of Values

B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings

b. Submittal status

c. Delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)

h. Construction Schedule update.

i. Other business relating to work.

j. Permit requirements

C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.

NEBE 238350 01 31 00 - 5

2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:

a. Contract Documents

b. Options

c. Related RFIs

d. Related Change Orders

e. Purchases

f. Deliveries

g. Submittals

h. Review of mockups

i. Possible conflicts

j. Compatibility requirements

k. Time schedules

l. Weather limitations

m. Manufacturer's written instructions

n. Warranty requirements

o. Compatibility of materials

p. Acceptability of substrates

q. Temporary facilities and controls

r. Space and access limitations

s. Regulations of agency(ies) with jurisdiction

t. Testing and inspecting requirements

u. Installation procedures

v. Coordination with other work

w. Required performance results

x. Protection of adjacent work

y. Protection of construction and personnel

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.

1.6 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate on-site party (ex. Shared position such as site supervisor) responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

NEBE 238350 01 31 00 - 6

b. Implementation of Waste Management Plan (WMP).

c. Implementation of Indoor Air Quality (IAQ) Management Plan.

d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.

e. Training for Contractor personnel in accordance with position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements

2. Regulatory Requirements

3. Indoor Air Quality (IAQ) Management

4. Noise and Acoustics Management

5. Construction Waste Management

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:

1. Overview of environmental issues related to building industry.

2. Overview of environmental issues related to Project.

3. Review of site-specific procedures and management plans:

a. Construction Waste Management

b. Indoor Air Quality (IAQ) Management

c. Noise and Acoustics Management

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

NEBE 238350 01 32 18 - 1

CONSTRUCTION SCHEDULE

NPS Division 1 Specifications National Park Service

NEBE NHP – Visitor Center PMIS 238350

SECTION 01 32 18 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of Construction Schedule requirements including:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.

1.2 DEFINITIONS

A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.

The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.

E. Float: Measure of leeway in starting and completing an activity.

NEBE 238350 01 32 18 - 2

1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.

2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.

F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: Schedules and reports submitted shall be electronically emailed to all required parties including CO and COR. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.

B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit [two] <2> paper copies of baseline schedule, large enough to show entire schedule for entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule.

D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit [two] 2 paper copies of the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of activities sorted in ascending order of total float.

E. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent completion of each schedule activity and necessary supporting data.

Provide two paper copies.

F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision, submit [two] 2 paper copies of a Time Impact Analysis. Incorporate a Fragmentary Network (Fragnet) into currently accepted Construction Schedule that demonstrating how Contractor proposes to incorporate a modification, change, delay, or Contractor request.

NEBE 238350 01 32 18 - 3

1.4 QUALITY ASSURANCE

A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:

1. Review software limitations, content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including phasing and work stages.

4. Review time required for review of submittals and re-submittals.

5. Review requirements for tests and inspections by independent testing and inspecting agencies.

6. Review time required for completion and startup procedures.

7. Review time required for obtaining and activating permits.

8. Review and finalize list of construction activities to be included in schedule.

9. Review baseline schedule comments, resolve issues and progress on incorporating them

10. Review procedures for updating schedule.

11. Discuss reporting requirements and establish protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction Schedule. Submit resume outlining qualifications of Scheduler to Contracting Officer for acceptance. Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency of using scheduling software. Authorized representative will be responsible for preparing the Baseline Schedule, required updates, revisions, Time Impact Analyses, and reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of work from parties involved.

3. Coordinate each construction activity in network with other activities and schedule in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values shall

NEBE 238350 01 32 18 - 4

be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. Total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments and the Construction Schedule.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-based, time-scaled Critical Path Method network analysis diagram for the Work.

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than [30] days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.

2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using preliminary Critical Path Method network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the Critical Path Method schedule…