23043_230831_CD_Specs.pdf

PDF 2 MB Posted

Attached to
District-Wide Door Hardware Upgrades
Solicitation number
RFP - WBL - 240000000380
Issued by
Huron County, Michigan

About this file

This document is a project manual for the District-Wide Door Hardware Upgrades project for the West Bloomfield School District located in West Bloomfield, Michigan. The project involves building construction, site development, renovation, and demolition work, including general construction, structural, mechanical, and electrical work. Bids will be received until a specified date and time, and a pre-bid conference is scheduled prior to the bid due date. The successful bidder will be required to provide performance and payment bonds. The project specifications detail the requirements for demolition, hollow metal doors and frames, flush wood doors, door hardware, glazing, and interior painting.

The bid form includes a base bid and an alternate, with the contractor required to provide pricing for both. Pricing shall be inclusive of all applicable taxes, permits, and fees. The contractor must also comply with prevailing wage requirements and the Iran Economic Sanctions Act. The contract will be awarded to the responsible bidder submitting the lowest responsive bid.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Copyright (c) 2023 TMP Architecture, Inc.

PROJECT MANUAL

PROJECT:

DISTRICT-WIDE DOOR HARDWARE UPGRADES

OWNER:

WEST BLOOMFIELD SCHOOL DISTRICT

5810 Commerce Road West Bloomfield, Michigan 48324

TMP PROJECT NO.: 23043

DATE: August 31, 2023

ISSUED FOR: Construction Documents

ARCHITECT

TMP ARCHITECTURE, INC.

1191 West Square Lake Road Bloomfield Hills, Michigan 48302-0374

PH 248-338-4561

Email info@tmp-architecture.com

Refer to Section 00 0103 - Project Directory for Consultants

DOOR HARDWARE CONSULTANT

JENOSKY CONSULTING

43422 West Oaks Drive Novi, Michigan 48377-3300

PH 248-496-7900

Email dave@jenoskyconsulting.com

TMP Architecture, Inc. TMP23043

08-31-23 CONSTRUCTION DOCUMENTS TABLE OF CONTENTS

00 0110-1

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

Section Title Issued

00 0101 Title Page CD 00 0110 Table of Contents CD 00 0115 List of Drawings CD 00 1113 Advertisement for Bids CD 00 2113 Instructions to Bidders CD 00 4100 Bid Form CD 00 5000 Contracting Forms and Supplements CD 00 7200 General Conditions CD 00 7300.01 Supplementary Conditions (AIA A104 2017) CD

AIA201-2017 General Conditions CD 00 7343 Wage Rate Requirements CD 00 8200 Availability of Electronic Files CD 00 8200.01 Electronic Files Release Form CD

SPECIFICATIONS GROUP

GENERAL REQUIREMENTS SUBGROUP

DIVISION 01 - GENERAL REQUIREMENTS

Section Title Issued

01 1000 Summary CD 01 2300 Alternates CD 01 2500 Substitution Procedures CD 01 2500.01 TMP Substitution Request Form CD 01 3000 Administrative Requirements CD 01 3000.01 TMP Submittal and Sample Transmittal

Form

CD

01 4000 Quality Requirements CD 01 4100 Regulatory Requirements CD 01 4216 Definitions CD 01 4219 Reference Standards CD 01 6000 Product Requirements CD 01 7000 Execution and Closeout Requirements CD

08-31-23 CONSTRUCTION DOCUMENTS TABLE OF CONTENTS

00 0110-2

FACILITY CONSTRUCTION SUBGROUP

DIVISION 02 – EXISTING CONDITIONS

Section Title Issued

02 4100 Demolition CD

DIVISION 03 – DIVISION 07

Not Used

DIVISION 08 - OPENINGS

Section Title Issued

08 1113 Hollow Metal Doors and Frames CD 08 1416 Flush Wood Doors CD 08 7100 Door Hardware CD 08 8000 Glazing CD

DIVISION 09 - FINISHES

Section Title Issued

09 9123 Interior Painting CD

DIVISION 10 - DIVISION 33

Not Used

APPENDIXES

APPENDIX 1

Not Used

END OF SECTION

08-31-23 CONSTRUCTION DOCUMENTS LIST OF DRAWINGS

00 0115-1

SECTION 00 0115 - LIST OF DRAWINGS

LIST OF DRAWINGS

1.01GENERAL

A. Drawings: Drawings consist of the Contract Drawings including drawings listed on the TITLE

SHEET page of the separately bound drawing set titled District-Wide Door Hardware Upgrades, dated 08-31-2023 and any subsequent Addenda and Contract modifications which may occur.

08-31-23 CONSTRUCTION DOCUMENTS ADVERTISEMENT FOR BIDS

00 1113-1

SECTION 00 1113 - ADVERTISEMENT FOR BIDS

GENERAL

DATE: District-Wide Door Hardware Upgrades

PROJECT: District-Wide Door Hardware Upgrades

OWNER: West Bloomfield School District 5810 Commerce Rd.

West Bloomfield, Michigan 48324

ARCHITECT:TMP Architecture, Inc.

1191 West Square Lake Road Bloomfield Hills, Michigan 48302

BIDS RECEIVED

Bid Proposals will be received until the following date and local time:

DATE: __________

TIME: __________

Sealed Bids will be received at the following location:

LOCATION: West Bloomfield School District 5810 Commerce Rd.

West Bloomfield, Michgan 48324

At which time and place Bids will be publicly opened and read aloud.

A bid tabulation summary will be made available within one working day of the bid opening.

DOCUMENT AVAILABILITY

Bid Documents will be available for examination and distribution on or after __________.

Bid Documents are available online at:

Website Address: __________ Username: __________ Password: __________

Bid Documents may be examined at the following locations:

The Offices of the Architect: TMP Architecture, Inc., 1191 West Square Lake Road, Bloomfield Hills, Michigan 48302 (by appointment).

Construction Association of Michigan, 43636 Woodward Ave., Bloomfield Hills, Michigan 48302, (248) 972-1000.

Plan Room, MHC/ReproMAX (McGraw Hill Construction), 36060 Industrial Drive., Livonia, Michigan, 48150, (734) 464-2959, (734) 464-3104 fax.

08-31-23 CONSTRUCTION DOCUMENTS ADVERTISEMENT FOR BIDS

00 1113-2

Bidders, upon payment of a $100 deposit per set, may obtain bidding documents from the Office of the Architect.

Deposits will be refunded upon return of the Bidding Documents to the Architect within five (5) working days after bid proposals are received, provided the documents are complete, in clean and usable condition, and free of marks or other defacement.

PRE-BID CONFERENCE

A pre-bid conference is scheduled for __________ at __________ local time. All interested Bidders are required to attend. Bidders shall meet at the following location:

West Bloomfield High School 4925 Orchard Lake Rd.

West Bloomfield, Michigan 48323

BID PROPOSALS

Bid Proposals shall be on forms furnished within the Project Manual.

Each Bidder shall agree not to withdraw a Bid Proposal for a period of thirty (30) calendar days after date for receipt of bids.

Each bid proposal shall be accompanied by a Bid Security Deposit in the form of a bid bond or certified check made payable to __________ for not less than five percent (5%) of the Base Bid sum as a bid guarantee.

Familial Disclosure Statement: A sworn and notarized statement in compliance with Michigan Compiled Laws, MCL.380.1267, disclosing any familial relationship existing between the Bidder, or any employee of the Bidder, and any member of the Board of Education of the School District or the Superintendent of the School District, must accompany each Bid Proposal.

The Iran Economic Sanctions Act: A sworn and notarized statement in compliance with Michigan Public Act No. 517 of 2012 must accompany each Bid Proposal.

The Owner will not accept a bid that does not include all of these forms and statements.

The successful Bidder shall provide a Performance Bond and a Labor and Material Payment Bond, each in the amount of one hundred percent (100%) of the contract amount. The cost of such bonds shall be included in the Bid Proposal.

The Bid Security Deposits will be returned to Bidders promptly after successful Bidder executes a contract with the Owner and has delivered to the Owner all required bonds and insurance certificates.

The amount of the Bid Security Deposit shall be forfeited to the Owner if the successful Bidder fails to enter into a contract and furnish required bonds and insurance certificates within ten

(10) calendar days of award of contract.

The Owner reserves the right to reject any or all Bid Proposals, either in whole or in part, and to waive any informalities and irregularities in the Bid Proposals and in the bidding.

08-31-23 CONSTRUCTION DOCUMENTS INSTRUCTIONS TO BIDDERS

00 2113-1

SECTION 00 2113 - INSTRUCTIONS TO BIDDERS

SUMMARY

1.01DOCUMENT INCLUDES

A. Invitation

1. Bid Submission

2. Intent

3. Work Identified in Contract Documents

4. Contract Time

B. Bid Documents and Contract Documents

1. Definitions

2. Contract Documents Identification

3. Availability

4. Examination

5. Inquiries/Addenda

6. Product/Assembly/System Substitutions

C. Site Assessment

1. Site Examination

2. Prebid Conference

D. Bid Submission

1. Submission Procedure

2. Bid Ineligibility

E. Bid Enclosures/Requirements

1. Security Deposit

2. Performance Assurance

3. Insurance

4. Bid Form Requirements

5. Familial Disclosure Statement

6. Iran Economic Sanctions Act

7. Taxes

8. Permits and Fees

9. Fees for Changes in the Work

10. Bid Form Signature

11. Additional Bid Information

F. Offer Acceptance/Rejection

1. Duration of Offer

2. Acceptance of Offer

3. Execution of Agreement

1.02 RELATED DOCUMENTS

A. Document 00 1113 - Advertisement for Bids.

B. Document 00 4100 - Bid Form.

C. Document 00 7300 - Supplementary Conditions:

INVITATION

2.01 BID SUBMISSION

A. Refer to Section 00 1113 - Advertisement for Bids for bid submission date, time, and location.

2.02 INTENT

A. The intent of this Bid request is to obtain an offer to perform work to complete a project located at ________ for a Stipulated Sum contract, in accordance with the Contract Documents.

2.03 WORK IDENTIFIED IN THE CONTRACT DOCUMENTS

A. Work of this proposed Contract comprises building construction, site development, renovation, and demolition, including general construction, structural, mechanical, and electrical Work.

00 2113-2

2.04 CONTRACT TIME

A. Complete the work on or before the Completion Date stated in 00 4100 - Bid Form.

BID DOCUMENTS AND CONTRACT DOCUMENTS

3.01 DEFINITIONS

A. Bid Documents: Consists of the Contract Documents supplemented with Invitation to Bid, Instructions to Bidders, Bid Form, and Appendixes in the Project Manual.

B. Contract Documents: Consists of the Drawings, Owner-Contractor Agreement, General Conditions of the Contract for Construction, Supplementary Conditions, Specifications within the Project Manual, Appendixes within the Project Manual, and Addenda issued prior to execution of the Contract

C. Bid, Offer, or Bidding: Act of submitting an offer under seal.

D. Bid Amount: Monetary sum identified by the Bidder in the Bid Form.

E. Base Bid: Monetary amount stated in the Bid Form for which the Bidder offers to perform the work as described in the Bidding Documents as the base, to which work may be added to or deleted from, by the amounts stated in the Alternates or Unit Pricing.

F. Alternate: Monetary amount stated in the Bid Form to be added to or deducted from the amount of the Base Bid if the Alternate is accepted.

G. Unit Price: Monetary amount stated in the Bid Form as a price per unit of measurement for materials, equipment, services, or a portion of the work as described in the Bidding Documents to which the the Base Bid will be adjusted according to the amount of units used.

H. Accepted Bidder: Bidder to whom the Owner proposes to award the Contract.

I. Bid Closing (submission date and time): Date and time after which bids are no longer accepted.

3.02 CONTRACT DOCUMENTS IDENTIFICATION

A. The Contract Documents are identified as Project Number ____, as prepared by Architectwho is located at 1191 West Square Lake Road, Bloomfield Hills, Michigan, 48302, and with contents as identified in the Project Manual.

3.03 AVAILABILITY

A. Refer to Section 00 1113 - Advertisement for Bids for availability of Bid Documents.

B. Bid Documents are made available only for the purpose of obtaining offers for this project. Their use does not grant a license for other purposes.

3.04 EXAMINATION

A. Upon receipt of Bid Documents verify that documents are complete. Notify Architect should the documents be incomplete.

B. Immediately notify Architect upon finding discrepancies or omissions in the Bid Documents.

3.05 INQUIRIES/ADDENDA

A. Direct questions to ________, email; __________.

B. Addenda may be issued during the bidding period. All Addenda become part of the Contract

Documents. Include resultant costs in the Bid Amount.

C. Verbal answers are not binding on any party.

D. Clarifications requested by bidders must be in writing not less than 7 days before date set for receipt of bids. The reply will be in the form of an Addendum, a copy of which will be forwarded to known recipients and bidders.

3.06 PRODUCT/ASSEMBLY/SYSTEM SUBSTITUTIONS

A. Where the Bid Documents stipulate a particular product, substitutions will be considered up to

10 days before receipt of bids.

00 2113-3

B. Submit substitution requests by completing the form in Section 01 2500.01 - TMP Substitution Request Form. Use only this form; other forms of submission are unacceptable. See Section 01 2500 - Substitution Procedures for additional information and instructions.

C. When a request to substitute a product is made, Architect may approve the substitution and will issue an Addendum to known bidders.

D. The submission shall provide sufficient information to determine acceptability of such products.

E. Provide complete information on required revisions to other work to accommodate each proposed substitution.

F. Provide products as specified unless substitutions are submitted in this manner and accepted.

G. See Section 01 6000 - Product Requirements for additional requirements.

SITE ASSESSMENT

4.01 SITE EXAMINATION

A. Examine the project site before submitting a bid.

B. Refer to Section 000 1113 - Advertisement for Bids for Pre-Bid Conference date, time, and location.

4.02 PREBID CONFERENCE

A. Refer to Section 00 1113 - Advertisement for Bids for Pre-Bid Conference date, time, and location.

B. Representatives of Architect will be in attendance.

C. Summarized minutes of this meeting will be circulated to all known bidders. These minutes will form part of the Contract Documents.

D. Information relevant to the Bid Documents will be recorded in an Addendum, issued to all known bidders.

BID SUBMISSION

5.01 SUBMISSION PROCEDURE

A. In submitting a bid the Bidder is stating the following:

1. Bidder has read and understands the Bidding Documents, including the Drawings, and Specifications.

2. Bid is made in compliance with the Bidding Documents.

3. Bidder understands existing conditions and limitations under which the Work is to be performed, including the overall construction timeframe and completion date, and includes in the Bid a sum(s) to cover the costs necessary to perform the Work as set forth in the Bidding Documents.

B. Bidders shall be solely responsible for the delivery of their bids in the manner and time prescribed.

C. Submit two copies of the executed offer on the Bid Forms provided, signed and sealedwith the required security deposit in a closed opaque envelope, clearly identified with bidder's name, project name and Owner's name on the outside.

D. Double Envelope: Insert the closed and sealed Bid Form envelope plus requested security deposit, in a large opaque envelope and label this envelope as noted above.

E. Improperly completed information, irregularities in security deposit, may be cause not to open the Bid Form envelope and declare the bid invalid or informal.

F. Bids submitted by telephone, fax or email will not be accepted.

G. Modifications to a submitted bid will be permitted if received in writing prior to bid closing and if endorsed by the same party or parties who signed and sealed the offer. A change shall be worded as not to reveal the amount of the original Bid.

00 2113-4

H. Bids may be voluntarily withdrawn at anytime before the bid closing if endorsed by the same party or parties who signed and sealed the offer. Withdrawals may be done in person or by written request. Withdrawn Bids may be resubmitted at anytime before the bid closing.

I. Bids received after the submission date and time will not be considered and will not be opened.

J. A bid tabulation summary of submitted bids will be made available to all bidders following bid opening. Refer to Section 00 1113 - Advertisement for Bids.

5.02 BID INELIGIBILITY

A. Bids that are unsigned, improperly signed or sealed, conditional, illegible, obscure, contain arithmetical errors, erasures, alterations, or irregularities of any kind, may at the discretion of the Owner, be declared unacceptable.

B. Failure to provide security deposit, bonding or insurance requirements may, at the discretion of Owner, invalidate the bid.

C. Failure to attend mandatory pre-bid conferences will at the discretion of Owner invalidate the bid.

BID ENCLOSURES/REQUIREMENTS

6.01 BID SECURITY DEPOSIT

A. Bids shall be accompanied by a security deposit as follows:

1. Bid Bond or certified check of a sum no less than 5 percent of the Bid Amount.

B. Endorse the Bid Bond in the name of the Owner as obligee, signed and sealed by the principal (Contractor) and surety.

C. Endorse the certified check in the name of the Owner.

D. The security deposits will be returned to Bidders after Accepted Bidder executes the Contract

Agreement, delivers to Owner required Performance Bond and Labor and Material Payment Bond, and provides specified Certificate of Insurance.

E. The security deposit of the Accepted Bidder shall be retained as liquidated damages by the Owner if the Accepted Bidder fails to execute the Contract Agreement, fails to furnish Performance Bond and Labor and Material Payment Bond, or fails to provide Certificate of Insurance as specified, within 10 days after notification of the award of Contract.

F. Include the cost of bid security in the Bid Amount.

G. If no contract is awarded, all security deposits will be returned.

H. If period in which bids cannot be withdrawn passes, all security deposits will be returned.

6.02 PERFORMANCE ASSURANCE

A. Accepted Bidder: Provide a Performance Bond and a Labor and Material Payment Bond each in the amount of one hundred percent (100%) of the contract amount.

B. Include the cost of the Performance Bond and the Labor and Material Payment Bond in the Bid

Amount.

6.03 INSURANCE

A. Provide an executed "Undertaking of Insurance" on a standard form provided by the insurance company stating their intention to provide insurance to the Accepted Bidder in accordance with the insurance requirements of the Contract Documents.

6.04 BID FORM REQUIREMENTS

A. Complete all requested information in the Bid Form electronically or by hand in ink.

B. Amounts shall be expressed in both words and figures. In case of a discrepancy the amount stated in words shall govern.

C. All Alternates must be bid. If no change in the Base Bid is required, enter “No Change to Base

Bid” for the respective Alternate.

D. All Unit Pricing must be bid.

00 2113-5

6.05 FAMILIAL DISCLOSURE STATEMENT

A. Each Bid shall be accompanied by the Familial Disclosure Statement in compliance Michigan

Compiled Laws, MCL.380.1267. The Bid proposal must be accompanied by a sworn and notarized statement disclosing Familial Relationship that exists between the Bidder or any employee of the Bidder and any member of the Board of Education of the School District or the Superintendent of the School District. The School District will not consider a Bid Proposal that does not include this sworn and notarized Disclosure Statement.

6.06 IRAN ECONOMIC SANCTIONS ACT

A. Each Bidder shall be in compliance with Michigan Public Act No. 517 of 2012. The Bid proposal must be accompanied by a sworn and notarized statement that certifies, represents, and warrants that the Bidder (including its officers, directors and employees) is not an “Iran Linked Business” within the meaning of the Iran Economic Sanctions Act, Michigan Public Act No. 517 of 2012, and that in the event Bidder is awarded a Contract, the Bidder will not become an “Iran Linked Business” at any time during the course of performing under the Contract.

6.07 TAXES

A. All Bids shall include all applicable taxes, including social security unemployment, and sales or use taxes, and any other taxes specifically levied on the work or on wages by local, city, state, or federal government, except real property taxes on the site. Bids shall also include all premiums, assessments, and other like payments, charges, and costs incidental to the work covered by the Bidding Documents.

6.08 FEES FOR CHANGES IN THE WORK

A. Include the fees for overhead and profit on own Work and Work by subcontractors, identified in

Document 00 7300 - Supplementary Conditions .

6.09 PERMITS AND FEES

A. All Bids shall include costs of all applicable permits and fees.

6.10 BID FORM SIGNATURE

A. The Bid Form shall be signed by the Bidder, as follows:

1. Bid form shall be signed personally by the Bidder and by a partner or by a duly authorized officer for the corporation their normal signatures. Insert the capacity in which the signing officer acts, under each signature. Affix seal.

OFFER ACCEPTANCE/REJECTION

7.01 DURATION OF OFFER

A. Bids shall remain open to acceptance for a period of 30 calendar days after the bid closing date.

7.02 ACCEPTANCE OF OFFER

A. Owner reserves the right to reject any or all Bid Proposals, either in whole or in part, and to waive any informalities and irregularities in the Bid Proposals and in the bidding.

B. Owner reserves the right to accept Alternates in any order or combination in order to determine the low bidder.

C. Owner reserves the right to negotiate with any Bidder without rebidding the project in whole or in part.

D. Owner reserves the right to award the Contract to whomever it may select.

E. After acceptance by Owner, Architect on behalf of Owner, will issue to the successful bidder, a written notice of award.

00 2113-6

7.03 EXECUTION OF AGREEMENT

A. Accepted Bidder will be required to execute Standard Form of Agreement between Owner and

Contractor, AIA Document A101-2017in conjunction with General Conditions of the Contract for Construction, AIA Document A201-2017.

B. The Accepted Bidder to whom the Contract is awarded shall, within 10 calendar days after notice of award and receipt of Agreement forms from the Owner, sign and deliver required copies to the Owner.

C. Accepted Bidder shall deliver specified Certificates of Insurance to the Owner within 10 calendar days after notification of the award of Contract.

1. Work shall not commence before receipt of the certificates.

D. Accepted Bidder shall deliver Performance Bond and a Labor and Material Payment Bond to the Owner within 10 calendar days after notification of the award of Contract.

1. Work shall not commence before receipt of the bonds.

08-31-23 CONSTRUCTION DOCUMENTS BID FORM

00 4100-1

SECTION 00 4100 - BID FORM

THE PROJECT AND THE PARTIES

1.01TO:

A. Owner

West Bloomfield School District 5810 Commerce Rd.

1.02 FOR:

A. Project: District-Wide Door Hardware Upgrades B. Architect's Project Number: 23043

1.03 DATE: ______________ (BIDDER TO ENTER DATE)

1.04 SUBMITTED BY: (BIDDER TO ENTER NAME AND ADDRESS)

A. Bidder's Full Name _________________________

1. Address _________________________

2. City, State, Zip_________________________

1.05 OFFER

A. Having examined the Place of The Work and all matters referred to in the Instructions to Bidders and the Bid Documents prepared by TMP Architecture for the above mentioned project, we, the undersigned, hereby offer to enter into a Contract to perform the Base Bid Work for the Sum of:

B. _________________________________________________________ _________________________________________________________ dollars ($______________________), in lawful money of the United States of America.

C. We, the undersigned, hearby offer to enter into a Contract to perform the work described in Alternate No. 1 for the sum of:

D. ________________________________________________________ _________________________________________________________ dollars ($______________________), in lawful money of the United States of America.

E. We have included the required performance assurance bonds in the Bid Amount as required by the Instructions to Bidders.

F. All applicable federal taxes are included and State of Michigan taxes are included in the Bid Sum.

1.06 ACCEPTANCE

A. This offer shall be open to acceptance and is irrevocable for thirty days from the bid closing date.

B. If this bid is accepted by Owner within the time period stated above, we will:

1. Execute the Agreement within seven days of receipt of Notice of Award.

2. Furnish the required bonds within seven days of receipt of Notice of Award.

3. Commence work within seven days after written Notice to Proceed of this bid.

C. If this bid is accepted within the time stated, and we fail to commence the Work or we fail to provide the required Bond(s), the security deposit shall be forfeited as damages to Owner by reason of our failure, limited in amount to the lesser of the face value of the security deposit or the difference between this bid and the bid upon which a Contract is signed.

08-31-23 CONSTRUCTION DOCUMENTS BID FORM

00 4100-2

D. In the event our bid is not accepted within the time stated above, the required security deposit shall be returned to the undersigned, in accordance with the provisions of the Instructions to Bidders; unless a mutually satisfactory arrangement is made for its retention and validity for an extended period of time.

1.07 CONTRACT TIME

A. If this Bid is accepted, we will:

B. Complete the Work in _______ calendar weeks from Notice to Proceed.

1.08 ONE HOUR SEPARATION WALL BETWEEN CONSTRUCTION AND STUDENTS

A. Lump sum bid for temporary separation wall as indicated in the Contract Documents excluding

Base Bid and alternates .

1. _________________________________________________________________Dollars

B. For the above sum and all subsequent sums in this bid form, the sum shall be shown in both words and figures. Amount in words shall govern if there is a discrepancy.

1.09 CHANGES TO THE WORK

A. When Architect establishes that the method of valuation for Changes in the Work will be net cost plus a percentage fee in accordance with General Conditions, our percentage fee will be:

1. 10% percent overhead and profit on the net cost of our own Work;

2. 5% percent on the cost of work done by any Subcontractor.

1.10 ADDENDA

A. The following Addenda have been received. The modifications to the Bid Documents noted below have been considered and all costs are included in the Bid Sum.

1. Addendum # _______ Dated ________________.

2. Addendum # _______ Dated ________________.

3. Addendum # _______ Dated ________________.

1.11 BID FORM SIGNATURE(S)

A. Name of person, partnership, or corporation submitting bid (Check One)

1. ( ) An Individual.

2. ( ) A Partnership.

3. ( ) A Corporation organized and existing under the laws of the State of Michigan.

B. (Bidder - print the full name of your firm) C. was hereunto affixed in the presence of:

D. ____________________________________________ E. (Authorized signing officer, Title)

F. ____________________________________________ G. (Authorized signing officer, Title)

08-31-23 CONSTRUCTION DOCUMENTS CONTRACTING FORMS AND SUPPLEMENTS

00 5000-1

SECTION 00 5000 - CONTRACTING FORMS AND SUPPLEMENTS

PART 1 GENERAL

1.01AGREEMENT AND CONDITIONS OF THE CONTRACT

A. The Agreement and General Conditions are based on AIA A104.

1. Form to be completed upon selection of General Contractor.

1.02 RELATED REQUIREMENTS

A. Section 00 7300.01 - Supplementary Conditions (A104_2017).

1.03 REFERENCE STANDARDS

A. AIA A104 - Standard Abbreviated Form of Agreement Between Owner and Contractor 2017.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

08-31-23 CONSTRUCTION DOCUMENTS GENERAL CONDITIONS

00 7200-1

SECTION 00 7200 - GENERAL CONDITIONS

FORM OF GENERAL CONDITIONS

1.01THE GENERAL CONDITIONS APPLICABLE TO THIS CONTRACT ARE ATTACHED FOLLOWING

THIS PAGE.

A. AIA DOCUMENT A201 - 2017

SUPPLEMENTARY CONDITIONS

2.01 REFER TO DOCUMENT 00 7300 - SUPPLEMENTARY CONDITIONS FOR AMENDMENTS TO

THESE GENERAL CONDITIONS.

08-31-23 CONSTRUCTION DOCUMENTS SUPPLEMENTARY CONDITIONS

00 7300.01-1

SECTION 00 7300.01 - SUPPLEMENTARY CONDITIONS

PART 1 GENERAL

1.01SUMMARY

A. These Supplementary Conditions amend and supplement the General Conditions, AIA

Document A104 - 2017 Standard Abbreviated Form of Agreement Between Owner and Contractor, and other provisions of the Contract Documents as indicated below. Provisions that are not so amended or supplemented remain in full force and effect.

B. The terms used in these Supplementary Conditions that are defined in the General Conditions have the meanings assigned to them in the General Conditions.

1.02 MODIFICATIONS TO GENERAL CONDITIONS

A. ARTICLE 3 - CONTRACT SUM

1. Delete Paragraph 3.3 Cost of the Work Plus Contractor's Fee, and all subparagraphs.

2. Delete Paragraph 3.4 Cost of the Work Plus Contractor's Fee With a Guaranteed

Maximum Price, and all subparagraphs.

B. ARTICLE 7 - GENERAL PROVISIONS

1. Modification to Paragraph 7.1 The Contract Documents:

a. Add subparagraph 7.1.1 as follows:

The Contractor shall not be allowed any extra compensation or time by reason of any matter, or thing, concerning which he or she might have fully informed himself or herself, because of his or her failure to have so informed himself or herself prior to executing the Contract.

b. Add subparagraph 7.1.2 as follows:

The Contract Documents contemplate a finished Work of such quality and design as is described therein and as reasonably inferable from them. The Contractor agrees that the Contract Sum for the Work includes sufficient monetary amounts to make his or her work complete and operable, fitting with the work of other Contractors and the Owner, and in compliance with good practice. He or she agrees that minor discrepancies or omissions, the failure to show repeated details, or the repetition on any drawings of the figures or notes given on another drawing shall not be the cause for additional charges or claims.

c. Add subparagraph 7.1.3 as follows:

The Drawings do not guarantee the exact location of existing work, including but not limited to, piping, sewers, wiring, ducts, walls, structural members and the like shown on the Drawings. The Contractor shall verify the location and accuracy of all existing construction as it relates to the Work before proceeding with the Work.

d. Add subparagraph 7.1.4 as follows:

The Drawings are intended to show the general arrangement, design and extent of the work and are partly diagrammatic. They are not intended to be scaled for roughing-in measurements or to serve as shop drawings.

e. Add subparagraph 7.1.5 as follows:

In the case of an inconsistency between Drawings and Specifications or within either Document not clarified by addendum, the better quality or greater quantity of Work shall be provided in accordance with the Architect's interpretation.

f. Delete Paragraph 7.6 Digital Data Use and Transmission.

g. Delete Paragraph 7.7 Building Information Models and Reliance.

C. ARTICLE 8 - OWNER

1. Modifications to Paragraph 8.1 Information and Services Required of the Owner:

a. Delete subparagraph 8.1.1.

b. Revise subparagraph 8.1.2 to read as follows

The Owner shall furnish all necessary surveys of the site.

c. Add Paragraph 8.4 to read as follows:

00 7300.01-2

Unless otherwise provided in the Contract Documents, the Owner shall furnish to the Contractor an electronic copy of the Contract Documents in the form of pdf files for the purposes of making reproductions pursuant to Section 7.5.2.

D. ARTICLE 9 - CONTRACTOR

1. Modification to Paragraph 9.1 Review of Contract Documents and Field Conditions by

Contractor:

a. Add subparagraph 9.1.1 as follows:

The Contractor shall not be allowed any extra compensation or time by reason of any matter, or thing, concerning which he or she might have fully informed himself or herself, because of his or her failure to have so informed himself or herself prior to executing the Contract.

2. Modifications to Paragraph 9.2 Supervision and Contraction Procedures:

a. Add subparagraph 9.2.3 as follows:

The Contractor shall organize meetings for the purpose of coordinating and expediting the work. The Architect shall be notified of these meetings, and when directed by the Architect, the Contractor shall hold additional meetings as required.

b. Add subparagraph 9.2.3.1 as follows:

The Contractor shall invite all affected Subcontractors and any other person or entity it deems appropriate.

c. Add subparagraph 9.2.3.2 as follows:

The Contractor shall conduct the meeting and keep minutes of all discussions and decisions. The Contractor shall be responsible for distribution of the minutes in writing to all parties in attendance.

3. Modifications to Paragraph 9.3 Labor and Materials:

a. Add subparagraph 9.3.2.1 as follows:

All workers on site shall dress in a neat manner. Clothing depicting foul language or crude behavior will not be tolerated.

b. Add subparagraph 9.3.2.2 as follows:

Foul language or crude behavior will not be tolerated.

c. Add subparagraph 9.3.2.3 as follows:

Possession, sale, or consumption of alcoholic beverages on the Owner’s property is prohibited.

d. Add subparagraph 9.3.2.4 as follows:

The unlawful manufacture, distribution, dispensation, possession, or use of drugs and narcotics on the Owner’s property is prohibited and may result in criminal prosecution.

e. Add subparagraph 9.3.3.1 as follows:

After the Contract has been executed, the Owner and the Architect will consider a formal request for the substitution of products in place of those specified only under the conditions set forth in the General Requirements (Division 01 of the Project Manual). By making requests for substitutions, the Contractor:

f. Add subparagraph 9.3.3.1.1 as follows:

represents that it has personally investigated the proposed substitute product and determined that it is equal or superior in all respects to that specified;

g. Add subparagraph 9.3.3.1.2 as follows:

represents that it will provide the same warranty for the substitution as it would have provided for the product specified;

h. Add subparagraph 9.3.3.1.3 as follows:

certifies that the cost data presented is complete and includes all related costs for the substituted product and for the Work that must be changed as a result of the substitution, except for the Architect’s redesign costs, and waives all claims for additional costs related to the substitution that subsequently become apparent; and

00 7300.01-3

i. Add subparagraph 9.3.3.1.4 as follows:

shall coordinate the installation of the accepted substitute, making such changes as may be required for the Work to be complete in all respects.

j. Add subparagraph 9.3.3.2 as follows:

The Owner shall be entitled to reimbursement from the Contractor for amounts paid to the Architect for reviewing the Contractor’s proposed substitutions and making agreed-upon changes in the Drawings and Specifications resulting from such substitutions.

4. Modification to Paragraph 9.5 Taxes:

a. Add subparagraph 9.5.1 as follows:

Work of this Contract is exempt from State and Local Sales and Use Taxes and Federal Excise Taxes on material used in construction and becoming a permanent part of the work. The Owner’s General Sales Tax Exemption Certification Number will be provided to the Contractor.

5. Modifications to Paragraph 9.6 Permits, Fees, Notices and Compliance with Laws:

a. Add subparagraph 9.6.1.1 as follows:

A General Building Permit, Mechanical Permit and Electrical Permit from the State of Michigan, Department of Licensing and Regulatory Affairs, Bureau of Construction Codes (BCC) are required.

b. Add subparagraph 9.6.1.1.1 as follows:

The Contractor shall pay all permit fees.

c. Add subparagraph 9.6.1.2 as follows:

The State of Michigan, Department of Licensing and Regulatory Affairs, Bureau of Construction Codes will conduct a plan review.

d. Add subparagraph 9.6.1.2.1 as follows:

The Architect will submit Drawings and Specifications, and pay plan review fees.

e. Add subparagraph 9.6.1.3 as follows:

The State of Michigan, Department of Licensing and Regulatory Affairs, Bureau of Fire Services will conduct a plan review and inspect the Work for fire safety.

f. Add subparagraph 9.6.1.3.1 as follows:

The Architect will submit Drawings and Specifications, and pay plan review fees.

E. ARTICLE 13 - CHANGES IN THE WORK

1. Modifications to Paragraph 13.2:

a. Add subparagraph 13.2.1 as follows:

A Construction Change Directive shall also be known as a Field Order.

2. Modifications to Paragraph 13.3:

a. Add subparagraph 13.3.1 as follows:

A minor change in the Work shall also be known as an Architect's Supplemental Instructions.

3. Add subparagraph 13.5 as follows:

A Work Changes Proposal Request, also known as a Bulletin, shall be used to obtain price quotations required in the negotiation of Change Orders.

4. Add subparagraph 13.5.1 as follows:

In order to facilitate checking of quotations for extras or credits, all proposals, except those so minor that their propriety can be seen by inspection, shall be accompanied by a complete itemization of costs including labor, materials and Subcontracts. Labor and materials shall be itemized in the manner prescribed above. Where major cost items are Subcontracts, they shall be itemized also. In no case will a change involving over $1000 be approved without such itemization.

5. Add subparagraph 13.5.2 as follows:

Contractor agrees to obligate subcontractors to charge no higher Fee for Changes in the Work than the Contractor agrees to charge as stated in the Agreement.

6. Add Paragraph 13.6 as follows:

00 7300.01-4

The combined overhead and profit included in the total cost to the Owner for Changes in the Work shall be based on the following schedule:

7. Add subparagraph 13.6.1 as follows:

For the Contractor, for Work performed by the Contractor’s own forces, 15 percent of the cost.

8. Add subparagraph 13.6.2 as follows:

For the Contractor, for Work performed by the Contractor’s Subcontractor, 7-1/2 percent of the amount due the Subcontractor.

9. Add subparagraph 13.6.3 as follows:

For each Subcontractor or Sub-subcontractor, for Work performed by that Subcontractor’s or Sub-subcontractor’s own forces, 15 percent of the cost.

10. Add subparagraph 13.6.4 as follows:

For each Subcontractor, for Work performed by the Subcontractor’s Sub-subcontractors, 7-1/2 percent of the amount due the Sub-subcontractor.

F. ARTICLE 14 – TIME

1. Revise subparagraph 14.3 as follows:

The term "day" as used in the Contract Documents shall mean working day, excluding weekends and legal holidays.

G. ARTICLE 15 – PAYMENT AND COMPLETION

1. Modifications to Paragraph 15.3 Applications for Payment:

a. Add subparagraph 15.3.1.1 as follows:

The form of Application for Payment shall be a notarized AIA Document G702- 1992, Application and Certification for Payment, supported by AIA Document G703-1992, Continuation Sheet.

b. Add subparagraph 15.3.1.2 as follows:

If not stated otherwise in Article 4, retainage shall be 10 percent. Until Substantial Completion, the Owner shall pay 90 percent of the amount due the Contractor on account of progress payments.

c. Add subparagraph 15.3.1.3 as follows:

If not stated otherwise in Article 4, after Substantial Completion, if the manner of completion of the Work and its progress are and remain satisfactory and in the absence of other good and sufficient reasons, retainage shall be reduced to 5 percent until Final Completion and Final Payment.

2. Modification to Paragraph 15.6 Substantial Completion:

a. Add subparagraph 15.6.3.1 as follows:

The Architect will perform no more than two (2) inspections to determine whether the Work or designated portion thereof has attained Substantial Completion in accordance with the Contract Documents. The Owner is entitled to reimbursement from the Contractor for amount paid to the Architect for additional inspections.

3. Modification to Paragraph 15.7 Final Completion and Final Payment:

a. Add subparagraph 15.7.1.1 as follows:

The Architect will perform no more than two (2) inspections to determine whether the Work or designated portion thereof has attained Final Completion in accordance with the Contract Documents. The Owner is entitled to reimbursement from the Contractor for amount paid to the Architect for additional inspections.

H. ARTICLE 17 – INSURANCE AND BONDS

1. Modifications to Paragraph 17.1 Contractor's Insurance:

a. Revise subparagraph 17.1.2. to read as follows:

Commercial General Liability insurance for the Project written on an occurrence form with policy limits of not less than $1,000,000 each occurrence, $1,000,000 aggregate for products-completed operations hazard, providing coverage claims including

00 7300.01-5

b. Subparagraphs 17.1.2.1 through 17.1.2.5 remain as stated.

c. Add subparagraph 17.1.2.6 as follows:

Include coverage for X (explosion), C (collapse) and U (underground hazards).

d. Add subparagraph 17.1.2.7 as follows:

Materials which the Owner has paid for but which are still in transit or not yet permanently attached to the Work or stored on-site, shall be fully insured by the Contractor at the Contractor's expense until the materials are located on-site or permanently attached to the Work.

e. Revise subparagraph 17.1.3 to read as follows:

Automobile Liability covering vehicles owned by the Contractor and non-owed vehicles used by the Contractor, with policy limits of not less than $1,000,000 per accident, for bodily injury, death of any person, and property damage arising out of the ownership, maintenance, and use of those motor vehicles along with any other statutorily required automobile coverage.

f. Revise subparagraph 17.1.6 to read as follows:

Employers' Liability policy with limits not less than $1,000,000 each accident.

g. Delete paragraph 17.1.7.

h. Delete paragraph 17.1.8.

i. Delete paragraph 17.1.9.

2. Modifications to Paragraph 17.3 Performance Bond and Payment Bond:

a. Revise subparagraph 17.3.1 to read as follows:

The Contractor shall furnish a Performance Bond and a Labor and Material Payment Bond covering faithful performance of the Contract and payment of obligations arising thereunder. The Contractor shall purchase and maintain the required bonds from a company or companies lawfully authorized to issue surety bonds in the jurisdiction where the Project is located. The cost thereof shall be included in the Contract Sum. The amount of the bonds shall be equal to 100 percent of the Contract Sum.

I. ARTICLE 19 – MISCELLANEOUS PROVISIONS

1. Add Paragraph 19.7 as follows:

Prevailing Wage Law: The Contractor and all subcontractors shall comply with Act 166 of the Michigan Public Acts of 1965 as amended, for work performed on this Project.

2. Add subparagraph 19.7.1 as follows:

a. The Contractor shall be financially responsible for the payment of prevailing wages and fringe benefits by all subcontractors contracted by him or her for work on the Project.

3. Add Paragraph 19.8 as follows:

a. Contractor shall comply with Michigan Public Act No. 517 of 2012, The Iran

Economic Sanctions Act.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

AIA

Document A201® – 2017 General Conditions of the Contract for Construction

AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 13:27:52 ET on 08/31/2023 under Order No.4104240257 which expires on 02/27/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1701271145)

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an attorney is encouraged with respect to its completion or modification.

For guidance in modifying this document to include supplementary conditions, see AIA Document A503™, Guide for Supplementary Conditions.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

for the following PROJECT:

(Name and location or address)

THE OWNER:

(Name, legal status and address)

THE ARCHITECT:

(Name, legal status and address)

TABLE OF ARTICLES

1 GENERAL PROVISIONS

2 OWNER

3 CONTRACTOR

4 ARCHITECT

5 SUBCONTRACTORS

6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS

7 CHANGES IN THE WORK

8 TIME

9 PAYMENTS AND COMPLETION

10 PROTECTION OF PERSONS AND PROPERTY

11 INSURANCE AND BONDS

12 UNCOVERING AND CORRECTION OF WORK

13 MISCELLANEOUS PROVISIONS

14 TERMINATION OR SUSPENSION OF THE CONTRACT

15 CLAIMS AND DISPUTES

AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 13:27:52 ET on 08/31/2023 under Order No.4104240257 which expires on 02/27/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1701271145)

INDEX

(Topics and numbers in bold are Section headings.)

Acceptance of Nonconforming Work 9.6.6, 9.9.3, 12.3 Acceptance of Work 9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3 Access to Work 3.16, 6.2.1, 12.1 Accident Prevention Acts and Omissions 3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.3.2, 14.1, 15.1.2, 15.2 Addenda 1.1.1 Additional Costs, Claims for 3.7.4, 3.7.5, 10.3.2, 15.1.5 Additional Inspections and Testing 9.4.2, 9.8.3, 12.2.1, 13.4 Additional Time, Claims for 3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.6 Administration of the Contract 3.1.3, 4.2, 9.4, 9.5 Advertisement or Invitation to Bid 1.1.1 Aesthetic Effect 4.2.13 Allowances 3.8 Applications for Payment 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.5.4, 9.6.3, 9.7, 9.10 Approvals 2.1.1, 2.3.1, 2.5, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10.1, 4.2.7, 9.3.2, 13.4.1 Arbitration 8.3.1, 15.3.2, 15.4

ARCHITECT

Architect, Definition of 4.1.1 Architect, Extent of Authority 2.5, 3.12.7, 4.1.2, 4.2, 5.2, 6.3, 7.1.2, 7.3.4, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.4.1, 13.4.2, 14.2.2, 14.2.4, 15.1.4, 15.2.1 Architect, Limitations of Authority and Responsibility 2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.4, 9.6.4, 15.1.4, 15.2 Architect’s Additional Services and Expenses 2.5, 12.2.1, 13.4.2, 13.4.3, 14.2.4 Architect’s Administration of the Contract 3.1.3, 3.7.4, 15.2, 9.4.1, 9.5 Architect’s Approvals 2.5, 3.1.3, 3.5, 3.10.2, 4.2.7

Architect’s Authority to Reject Work 3.5, 4.2.6, 12.1.2, 12.2.1 Architect’s Copyright 1.1.7, 1.5 Architect’s Decisions 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.4.2, 15.2 Architect’s Inspections 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.4 Architect’s Instructions 3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.4.2 Architect’s Interpretations 4.2.11, 4.2.12 Architect’s Project Representative 4.2.10 Architect’s Relationship with Contractor 1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.3.2, 13.4, 15.2 Architect’s Relationship with Subcontractors 1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3 Architect’s Representations 9.4.2, 9.5.1, 9.10.1 Architect’s Site Visits 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4 Asbestos 10.3.1 Attorneys’ Fees 3.18.1, 9.6.8, 9.10.2, 10.3.3 Award of Separate Contracts 6.1.1, 6.1.2 Award of Subcontracts and Other Contracts for Portions of the Work 5.2 Basic Definitions 1.1 Bidding Requirements 1.1.1 Binding Dispute Resolution 8.3.1, 9.7, 11.5, 13.1, 15.1.2, 15.1.3, 15.2.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.3.3, 15.4.1 Bonds, Lien 7.3.4.4, 9.6.8, 9.10.2, 9.10.3 Bonds, Performance, and Payment 7.3.4.4, 9.6.7, 9.10.3, 11.1.2, 11.1.3, 11.5 Building Information Models Use and Reliance 1.8 Building Permit 3.7.1 Capitalization 1.3 Certificate of Substantial Completion 9.8.3, 9.8.4, 9.8.5

AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 13:27:52 ET on 08/31/2023 under Order No.4104240257 which expires on 02/27/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1701271145)

Certificates for Payment 4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.4 Certificates of Inspection, Testing or Approval 13.4.4 Certificates of Insurance 9.10.2 Change Orders 1.1.1, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.7, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.2, 11.5, 12.1.2 Change Orders, Definition of 7.2.1

CHANGES IN THE WORK

2.2.2, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.5 Claims, Definition of 15.1.1 Claims, Notice of 1.6.2, 15.1.3

CLAIMS AND DISPUTES

3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4 Claims and Timely Assertion of Claims 15.4.1 Claims for Additional Cost 3.2.4, 3.3.1, 3.7.4, 7.3.9, 9.5.2, 10.2.5, 10.3.2, 15.1.5 Claims for Additional Time 3.2.4, 3.3.1, 3.7.4, 6.1.1, 8.3.2, 9.5.2, 10.3.2, 15.1.6 Concealed or Unknown Conditions, Claims for 3.7.4 Claims for Damages 3.2.4, 3.18, 8.3.3, 9.5.1, 9.6.7, 10.2.5, 10.3.3, 11.3, 11.3.2, 14.2.4, 15.1.7 Claims Subject to Arbitration 15.4.1 Cleaning Up 3.15, 6.3 Commencement of the Work, Conditions Relating to 2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.2, 15.1.5 Commencement of the Work, Definition of 8.1.2 Communications 3.9.1, 4.2.4 Completion, Conditions Relating to 3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 14.1.2, 15.1.2

COMPLETION, PAYMENTS AND

Completion, Substantial 3.10.1, 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2 Compliance with Laws 2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3

Concealed or Unknown Conditions 3.7.4, 4.2.8, 8.3.1, 10.3 Conditions of the Contract 1.1.1, 6.1.1, 6.1.4 Consent, Written 3.4.2, 3.14.2, 4.1.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 13.2, 15.4.4.2 Consolidation or Joinder 15.4.4

CONSTRUCTION BY OWNER OR BY

SEPARATE CONTRACTORS

1.1.4, 6 Construction Change Directive, Definition of 7.3.1 Construction Change Directives 1.1.1, 3.4.2, 3.11, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1…