Naval Computer and Telecommunications Area Master Station, Atlantic Combined Synopsis and Solicitation Notice Information
1. This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.
2. The solicitation number is N7027222Q0016 and is being issued as a Request for Quotes (RFQ).
3. The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2022-04 Effective 30 Jan 2022 2021 and DFARS DPN 20211230 (Effective 30 Jan 2022) Edition located on https://www.acquisition.gov
4. The associated NAICS code is 811310 and the associated PSC code is J059 for this procurement:
|_| is not being set-aside for small businesses
|X| is being set-aside for small businesses. The small business size standard is $8 MIL.
5. The Statement of Work ( SOW) below lists the required services to be performed:
NCTAMSLANT Facilities Department Statement of Work Repair Switchgear & Generator Controls Building 315 NCTAMS LANT DET - Djibouti
1. SCOPE:
This statement of work provides the requirements for repairing the existing Utility and Generator Control System housed in the Main Switchboard. Existing electronic controls have failed and are not operating correctly. The design of the new automatic and manual control system needs to be verified and/or reprogrammed for the correct operation of the switchboard.
Project site is located at DET Djibouti, Africa. Existing switchgear drawings are available upon request. The Scope shall include all required design, drawings, and specifications; labor, equipment, tools and material for installation; testing; on-site training; and a cost estimate for work accomplishment. The existing commercial power source is adequate to support this project.
2. BACKGROUND:
Naval Facilities Engineering Service Center, Energy and Utilities Department to provide installation and engineering support for the installation of the utility and generator control system and final testing was completed. These control problems started within a year of the contractors final annual testing requirements and continue to have problems with the Gens & switchgear not responding when needed.
Currently, site personnel are having difficulty operating, maintaining, and troubleshooting the existing utility and generator control system is now out of service! The HMI screens are blank (No Display).
3. LOCATION:
The work shall be located at NCTAMS LANT (NCTL) DET – Djibouti building 315 at Camp Lemonier Djibouti, Republic of Djibouti.
4. PERIOD OF PERFORMANCE:
The contractor shall complete the work as soon as possible after notification to proceed. No work may begin without concurrence of the site Project Manager and/ or NCTL Site representative. Completion shall include full operation of the Utility and Generator Control System, final cleanup of job site, and completion of all work.
5. DRAWINGS:
Generator switchgear and one-line drawings are available upon request.
6. DESCRIPTION OF WORK:
All work will require close coordination with and approval of the site Project Manager and/or NCTL Site Representative. The contractor must be qualified to perform, operate, and modify electronic work on the Utility and Generator Control System to ensure that the building critical power grid is not to be jeopardized during work evolutions. The MSLC/DSLC are not sending start / stop signal correctly, Firmware for the components are out of date and will require the most current firmware from the OEM.
In addition to the above, complete the following:
A: Test breakers with secondary injection test set, megger, and contact resistance.
B: Replace secondary contacts on breakers with ones designed for low voltage dc (government furnished and are on site)
C: Input wires are improperly terminated, Remove from current location causing stress on the switchboard components. Remove from current location, reroute through additional cable through, and add ferrules to the wires and re-terminate.
D: Output wires are improperly terminated, Remove from current location causing stress on the switchboard components. Remove from current location, reroute through additional cable through, and add ferrules to the wires and re-terminate.
E: Relabel Input and output wires according to the schematic.
G: Procure updated software and programming cable from Woodward in order to properly adjust/troubleshoot/repair.
H: Firmware for the components are out of date and will require the most current firmware from the OEM to prevent further issues.
I: Inspect communications devices to verify they are all working as required.
J: Operate generator system and verify operation, tune if required.
K: Check displayed voltage and current levels to verify correct readings (may use fluke to compare to display).
L: Update components in fuel tank controller to allow automatic operation of day tanks.
7. QUALITY ASSURANCE.
Follow the attached sequence of operation after repairs to ensure proper operation in all scenarios of the test plan.
SCADA START-UP
A. Tie, Load Bank, and Feeder Breaker Operation
1. Verify each feeder breaker F4B (UPS BYPASS), F4C (UPS ISOLATION), F5A (MDP2), F5C (UPS2), F6B (MDP1), F6C (UPS1) can be closed and opened via SCADA.
2. Verify the Tie breaker (T5B) can be closed and opened via SCADA.
3. Verify the Load Bank breaker (F4D) can be closed and opened via SCADA.
B. Preferred Source Operation – Open Transition
1. Verify Utility No. 1 and Utility No. 2 are available.
2. Verify Auto Control Mode = Off
3. Verify M1 And M2 Breaker Control Switches placed In “Trip” Position.
4. Place M1 and M2 Breaker Control Switches in the “Close” position.
5. Select GENERATOR G1, G2, G3 CONTROL MODE = OFF.
6. Select UTILITY SOURCE TRANSFER MODE = OPEN TRANSITION.
7. Select AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE. Verify M1 CB closes.
8. Select AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE. Verify M1 CB opens and after 6 sec delay M2 CB closes.
9. Select AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE. Verify M2 CB opens and after 6 sec delay M1 CB closes.
10. Place M1 Breaker Control Switch in “Trip” position. Verify M1 CB opens and after 6 sec delay M2 CB closes.
11. Verify AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE
12. Place M1 Breaker Control Switch in “Close” position. Verify M2 CB remains closed.
13. Place M2 Breaker Control Switch in “Trip” position. Verify M2 CB opens and after 6 sec delay M1 CB closes.
14. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE
15. Place M2 Breaker Control Switch in “Close” position. Verify M1 CB remains closed.
16. Remove the M1 Utility voltage source by either pulling the PS3-HM1 pullout switch or deenergizing the PMT-1 primary. Verify M1 CB opens and after 6 sec delay M2 CB closes.
17. Verify AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE
18. Restore M1 utility voltage. Verify M2 CB remains closed.
19. Remove the M2 Utility voltage source by either pulling the PS3-HM2 pullout switch or deenergizing the PMT-2 primary. Verify M2 CB opens and after 6 sec delay M1 CB closes.
20. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE
21. Restore M2 utility voltage. Verify M1 CB remains closed.
22. Continue to “Preferred Source Operation – Closed Transition”.
C. Preferred Source Operation – Closed Transition
1. Verify Utility No. 1 and Utility No. 2 are available.
2. Verify M1 and M2 Breaker Control Switches placed In “Close” Position.
3. Verify GENERATOR G1, G2, G3 CONTROL MODE = OFF.
4. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
5. Verify M1 CB is closed.
6. Select UTILITY SOURCE TRANSFER MODE = CLOSED TRANSITION.
7. Select AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE. Verify M2 CB closes followed immediately by M1 CB opens.
8. Select AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE. Verify M1 CB closes followed immediately by M2 CB opens.
9. Place M1 Breaker Control Switch in “Trip” position. Verify M1 CB opens and after 6 sec delay M2 CB closes.
10. Verify AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE
11. Place M1 Breaker Control Switch in “Close” position. Verify M2 CB remains closed.
12. Place M2 Breaker Control Switch in “Trip” position. Verify M2 CB opens and after 6 sec delay M1 CB closes.
13. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE
14. Place M2 Breaker Control Switch in “Close” position. Verify M1 CB remains closed.
15. Remove the M1 Utility voltage source by either pulling the PS3-HM1 pullout switch or deenergizing the PMT-1 primary. Verify M1 CB opens and after 6 sec delay M2 CB closes.
16. Verify AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE
17. Restore M1 utility voltage. Verify M2 CB remains closed.
18. Remove the M2 Utility voltage source by either pulling the PS3-HM2 pullout switch or deenergizing the PMT-2 primary. Verify M2 CB opens and after 6 sec delay M1 CB closes.
19. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE
20. Restore M2 utility voltage. Verify M1 CB remains closed.
21. Place M1 Breaker Control Switch in “Trip” position. Verify M1 CB opens and after 6 sec delay M2 CB closes.
22. Place M2 Breaker Control Switches in “Trip” position. Verify M2 CB opens. Auto Control Mode = Off.
23. Place M1 Breaker Control Switch in “Close” position.
24. Select AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE. Verify M1CB closes.
25. Place M2 Breaker Control Switches in “Close” position.
D. Loss of Utility Generator Start Tests
1. Verify Utility No. 1 and Utility No. 2 are available.
2. Verify M1 and M2 Breaker Control Switches placed In “Close” Position.
3. Verify GENERATOR G1, G2, G3 Breaker Control Switches placed In “Close” Position.
4. Verify GENERATOR G1, G2, G3 CONTROL MODE = AUTO.
5. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
6. Verify M1 CB is closed.
7. Select generator priority G1, G2, G3.
8. Remove the M2 Utility voltage source by either pulling the PS3-HM2 pullout switch or deenergizing the PMT-2 primary.
9. Remove the M1 Utility voltage source by either pulling the PS3-HM1 pullout switch or deenergizing the PMT-1 primary. Verify:
a. Connected utility source circuit breaker opens
b. All available generators are started and connected to the bus.
c. After the “Off Delay for Low Priority Generators” expires the second and third priority generators are unloaded, disconnected from the bus, and the start command is removed
10. Cause an engine alarm (by generator startup engineer) condition for the Lead generator. Observe the next priority generator starts, is connected to the bus and become the “lead” generator. The “alarmed” generator shall be unloaded, disconnected from the bus, and the start command removed.
11. Cause an engine shutdown condition (by generator startup engineer) for the Lead generator. Observe all available generators are started and connected to the bus, after the “Off Delay for Low Priority Generators” expires the low priority generator is unloaded, disconnected from the bus, and the start command is removed.
12. Remove the alarm and shutdown conditions.
13. Restore the M2 Utility voltage. Observe after the “RETURN TO UTILITY DELAY TIMER” expires the generator is synchronized with the M2 utility and the M2 circuit breaker is closed, the generator is unloaded, disconnected from the bus, and the start command is removed.
14. Select generator priority G2, G3, G1. Repeat steps 9-13 for Remove the M2 Utility voltage and Restore the M1 Utility voltage. Select the “RETURN TO UTILITY DELAY BYPASS”. Verify the immediate return to utility operation.
15. Repeat steps 9-13 for Remove the M1 Utility voltage and Restore the M1 Utility voltage. After the generator is unloaded, disconnected from the bus, and the start command is removed, but before the generator cooldown time expires, repeat step 9 for Remove the M1 Utility voltage.
16. Repeat step 13 for Restore the M1 Utility voltage.
17. Select generator priority G3, G1, G2. Repeat step 9 for Remove the M1 Utility voltage and step 13 for Restore the M1 Utility voltage. Cause an engine shutdown condition for the Lead generator before the “return to utility delay timer” expires. Verify the M1 circuit breaker is closed and
AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
18. Select generator priority G1, G2, G3. Repeat step 9 for Remove the M1 Utility voltage. Cause a “Fail to Start Fault” for the lead generator (by generator startup engineer). Verify the second and third priority generators become the first and second priority generators.
19. Repeat step 13 for Restore the M1 Utility voltage.
20. Restore the M2 Utility voltage.
E. Generator Maintenance Test
1. Verify Utility No. 1 and Utility No. 2 are available.
2. Verify M1 and M2 Breaker Control Switches placed In “Close” Position.
3. Verify GENERATOR G1, G2, G3 Breaker Control Switches placed In “Close” Position.
4. Verify GENERATOR G1, G2, G3 CONTROL MODE = AUTO.
5. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
6. Verify M1 CB is closed.
7. Select UTILITY SOURCE TRANSFER MODE = CLOSED TRANSITION.
8. Select generator priority G1, G2, G3.
9. Select Generator G1 & G2 for Generator Maintenance Test.
10. Place the UPS into ByPass Mode. Close the UPS ByPass Breaker (52F4B).
11. Verify “GENERATOR MAINTENANCE TEST” is disabled.
12. Open the UPS ByPass Breaker. Place the UPS into Normal Mode.
13. Open the MDP 1 Breaker (52-F6B). Close the MDP 2 Breaker.
14. Verify “GENERATOR MAINTENANCE TEST” is disabled.
15. Open the MDP 2 Breaker. Close the MDP 1 Breaker (52-F6B).
16. SELECT GENERATOR MAINTENANCE TEST = ON. Verify the Tie circuit breaker opens and the selected available generators are started and connected to the bus.
17. Close the load bank circuit breaker.
21. SELECT GENERATOR MAINTENANCE TEST = OFF. Verify:
a. The load bank circuit breaker opens
b. All generator circuit breakers open.
c. All generator start commands are removed.
d. The Tie circuit breaker is closed.
18. SELECT GENERATOR MAINTENANCE TEST = ON. Verify the Tie circuit breaker opens and the selected available generators are started and connected to the bus.
19. Remove the M1 Utility voltage source by either pulling the PS3-HM1 pullout switch or deenergizing the PMT-1 primary. Verify M1 CB opens and after 6 sec delay M2 CB closes.
22. Remove the M2 Utility voltage source by either pulling the PS3-HM2 pullout switch or deenergizing the PMT-2 primary. Verify:
a. Connected utility source circuit breaker opens
b. Load Bank circuit breaker opens
c. Tie circuit breaker closes
d. All available generators are started and connected to the bus.
e. After the “Off Delay for Low Priority Generators” expires the second and third priority generators are unloaded, disconnected from the bus, and the start command is removed
20. Restore the M1 Utility voltage. Select “RETURN TO UTILITY DELAY BYPASS”. Observe the generator is synchronized with the M1 utility and the M1 circuit breaker is closed, the generator is unloaded, disconnected from the bus, and the start command is removed.
21. Restore the M2 Utility voltage.
F. EPO Activated
1. Verify Utility No. 1 and Utility No. 2 are available.
2. Verify M1 and M2 Breaker Control Switches placed In “Close” Position.
3. Verify GENERATOR G1, G2, G3 CONTROL MODE = AUTO.
4. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
5. Verify M1 CB is closed.
6. Select UTILITY SOURCE TRANSFER MODE = CLOSED TRANSITION.
7. Select generator priority G1, G2, G3.
8. Select Generator G1 G2 G3 for Generator Maintenance Test.
9. SELECT GENERATOR MAINTENANCE TEST = ON. Verify the Tie circuit breaker opens and the selected available generators are started and connected to the bus.
10. Activate EPO.
11. Observe circuit breakers F4B (UPS BYPASS), F4C (UPS ISOLATION) , F5A (MDP2), F6B (MDP1) open
12. Observe all generator circuit breakers open.
13. Observe all generators are stopped.
14. Observe AUTOMATIC CONTROL = OFF
G. Power Loss Tests
1. Verify Utility No. 1 and Utility No. 2 are available.
2. Verify M1 and M2 Breaker Control Switches placed In “Close” Position.
3. Verify GENERATOR G1, G2, G3 CONTROL MODE = AUTO.
4. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
5. Verify M1 CB is closed.
6. Select UTILITY SOURCE TRANSFER MODE = CLOSED TRANSITION.
7. Select generator priority G1, G2, G3.
8. Select POWER LOSS TEST= START. Verify:
a. Connected utility source circuit breaker opens
b. All available generators are started and connected to the bus.
c. After the “Off Delay for Low Priority Generators” expires the second and third priority generators are unloaded, disconnected from the bus, and the start command is removed
9. Select POWER LOSS TEST = OFF. Observe the generator is synchronized with the M1 utility and the M1 circuit breaker is closed, the generator is unloaded, disconnected from the bus, and the start command is removed.
10. Select POWER LOSS TEST= START. Verify:
a. Connected utility source circuit breaker opens
b. All available generators are started and connected to the bus.
c. After the “Off Delay for Low Priority Generators” expires the second and third priority generators are unloaded, disconnected from the bus, and the start command is removed
11. Remove the M1 Utility voltage source by either pulling the PS3-HM1 pullout switch or deenergizing the PMT-1 primary.
12. Remove the M2 Utility voltage source by either pulling the PS3-HM2 pullout switch or deenergizing the PMT-2 primary.
13. Restore the M2 Utility voltage.
14. Verify AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE.
15. Select RETURN TO UTILITY DELAY BYPASS. Observe the generator is synchronized with the M2 utility and the M2 circuit breaker is closed, the generator is unloaded, disconnected from the bus, and the start command is removed.
16. Restore the M1 Utility voltage.
H. Source Transfer Tests
1. Verify Utility No. 1 and Utility No. 2 are available.
2. Verify M1 and M2 Breaker Control Switches placed In “Close” Position.
3. Verify GENERATOR G1, G2, G3 CONTROL MODE = AUTO.
4. Verify AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
5. Verify M1 CB is closed.
6. Select UTILITY SOURCE TRANSFER MODE = CLOSED TRANSITION.
7. Select generator priority G1, G2, G3.
8. Select AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE.
9. Select SOURCE TRANSFER = TRANSFER TO GENERATORS. Verify: a. The highest priority (“lead”) generator shall be started and connected to the bus.
b. M1 utility shall be unloaded and the M1 circuit breaker shall be opened.
10. Select SOURCE TRANSFER = TRANSFER TO UTILITY. Observe the generator is synchronized with the M1 utility and the M1 circuit breaker is closed, the generator is unloaded, disconnected from the bus, and the start command is removed.
11. Select AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE. Verify M2 CB closes followed immediately by M1 CB opens.
12. Select SOURCE TRANSFER = TRANSFER TO GENERATORS. Verify: a. The highest priority (“lead”) generator shall be started and connected to the bus.
b. M2 utility shall be unloaded and the M2 circuit breaker shall be opened.
13. Remove the M1 Utility voltage source by either pulling the PS3-HM1 pullout switch or deenergizing the PMT-1 primary.
14. Remove the M2 Utility voltage source by either pulling the PS3-HM2 pullout switch or deenergizing the PMT-2 primary.
15. Restore the M1 Utility voltage.
16. Restore the M2 Utility voltage.
17. Select SOURCE TRANSFER = TRANSFER TO UTILITY. Observe the generator is synchronized with the M2 utility and the M2 circuit breaker is closed, the generator is unloaded, disconnected from the bus, and the start command is removed.
Communication Failures
1. Maintenance Start Generator G1. Disconnect control power to DSLC-1. Verify the following operation; a. GENERATOR CONTROL MODE = OFF
b. Generator circuit breaker opens
c. Generator start command is removed
d. DSLC Fail Alarm is triggered
e. System Update required “POPUP”
f. Restore power connection.
g. Execute System Update
h. Repeat for DSLC2 & 3.
2. Maintenance Start Generator G1. Disconnect control power to MSG-1. Verify the following operation; a. GENERATOR CONTROL MODE = OFF
b. Generator circuit breaker opens
c. Generator start command is removed
d. MGS Fail Alarm is triggered
e. Restore power connection.
f. Repeat for MSG2 & 3.
3. Maintenance Start Generator G1. Disconnect control power to ES-G1. Verify the following operation; a. GENERATOR CONTROL MODE = OFF
b. Generator circuit breaker opens
c. Generator start command is removed
d. ES-G1 Fail Alarm is triggered
e. System Update required “POPUP”
f. Restore power connection.
g. Execute System Update
h. Repeat for ES-G2 & 3.
4. Disconnect control power to MSLC-1. Verify the following operation; a. Go to AUTOMATIC CONTROL MODE = M2 PREFERRED UTILITY SOURCE
b. MSLC-1 Fail Alarm is triggered
c. System Update required “POPUP”
d. Restore power connection.
e. Execute System Update
5. Disconnect control power to MSLC-2. Verify the following operation; a. Go to AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE
b. MSLC-2 Fail Alarm is triggered
c. System Update required “POPUP”
d. Restore power connection.
e. Execute System Update
6. Disconnect control power to MSG-M1. Verify the following operation; a. Go to SYSTEM CONTROL = OFF
b. MSG-M1 Fail Alarm is triggered
c. Restore power connection.
7. Disconnect control power to MSG-M2. Verify the following operation; a. MSG-M2 Fail Alarm is triggered
b. Restore power connection.
8. Disconnect control power to ES-M1. Verify the following operation; a. Go to SYSTEM CONTROL = OFF
b. ES-M1 Fail Alarm is triggered
c. System Update required “POPUP”
d. Restore power connection.
e. Execute System Update
9. Disconnect control power to ES-M2. Verify the following operation: a. Go to AUTOMATIC CONTROL MODE = M1 PREFERRED UTILITY SOURCE
b. ES-M2 Fail Alarm is triggered
c. System Update required “POPUP”
d. Restore power connection.
e. Execute System Update
10. Disconnect control power to the Primary PLC. Verify the following operation: a. Primary PLC Fail Alarm
b. Backup PLC becomes active.
c. Restore power to Primary PLC
d. Go to SYSTEM CONTROL = OFF
e. Press the PLC Synch button.
f. Primary PLC becomes active. PLC Synch button disappears.
11. Disconnect control power to the Backup PLC. Verify the following operation: a. Backup PLC Fail Alarm
b. Restore power to backup PLC.
c. Go to SYSTEM CONTROL = OFF
d. Press the PLC Synch button.
e. PLC Synch button disappears.
I. UPS ByPass Operation
Verify the following operation;
a. Open Tie breaker (T5B) and breakers F4B (UPS BYPASS) and F4C (UPS ISOLATION).
b. Place UPS1 in Normal Mode. Verify the SKRU key is captured.
c. Place UPS2 in Normal Mode. Verify the SKRU key is captured.
d. Close breaker F4C (UPS ISOLATION). Verify breaker F4B (UPS BYPASS) cannot be closed.
e. Place UPS1 in ByPass Mode. Verify the SKRU key is captured.
f. Place UPS2 in ByPass Mode.
g. Retrieve interlock key and Turn PPS to “Bypass Interlock Disabled. Verify Bypass Interlock Disabled alarm.
h. Verify UPS1 cannot be placed into Normal Mode.
i. Verify UPS2 cannot be placed into Normal Mode.
j. Close Bypass circuit breaker.
k. Open the maintenance isolation circuit breaker
l. Close the maintenance isolation circuit breaker.
m. Open the Bypass circuit breaker.
n. Turn PPS to enable Interlock. Verify Bypass circuit breaker will not close.
o. Return interlock key to SKRU and switch to “trapped” position.
p. Return UPS1 to Normal Mode. Verify key is captured.
J. Discrete Alarms
a. Battery charger #1 trouble (install jumper from terminal 1 to 3 at charger no.1).
a. Battery charger #2 trouble (install jumper from terminal 1 to 3 at charger no.2).
b. Generator breaker control switch G1 in trip position.
c. Generator breaker control switch G2 in trip position.
d. Generator breaker control switch G3 in trip position.
8. SPECIAL REQUIREMENTS:
A. The access to the work site and the equipment room are restricted. NCTAMS LANT DET - Djibouti will provide any required escorts. The contractor shall schedule work with the Site Manager to ensure access.
B. The Contractor is responsible for the safety of his employees. The Contractor shall determine if any confined space is a “permit required” confined space. The Contractor shall ensure his employees are adequately trained and qualified to work in confined spaces. The Contractor shall provide a copy of his Confined Space Entry Program to the Contracting Officer prior to starting work, if required.
C. The Contractor shall follow all OSHA and NCTAMS LANT DET – Djibouti safety regulations pertaining to the control of hazardous energy, (lockout-tag out). The Contractor shall provide a copy of his Energy Control Program to the Site Manager before work commences. The plan shall contain information sufficient to ensure government employees safety and identify lockout-tag out procedures for hazardous energy sources.
D. The Contractor shall submit a list with the names and Social Security numbers of all personnel who will be working on the contract job site to the Site Manager for access.
E. The Contractor must demonstrate to the Site Manager that he is certified to perform the required emergency service work. All work shall be completed as per the latest edition of the National Electrical Code and the National Safety Code.
F. All Contractors and their employees must report to the Security Office for access to base. A photo ID or an attesting company representative is required for employee identification. At this time the Contractor and employees will be required to identify and register any private or company vehicles that will be on base in association with the contract. Thereafter, while on base all contractors and their employees must have Base issued ID in their possession at all times and all vehicles must have decals or temporary passes. Immediately report instances of lost or stolen badges, decals or passes to the Project Manager and/ or NCTL Site representative. The Contractor will be held accountable for any problems associated with the misuse of lost IDs, decals or passes. Upon completion of the contract and/or termination of the service of any employee, the Contractor shall return the IDs and decals or passes to the Security Office. Compliance with this requirement is mandatory and certification thereof to the Contracting Officer is required prior to submitting final invoices.
G. Proper operator licensing for vehicle operators is mandatory.
9. COVID PROTOCOL:
The following information pertains to COVID restrictions required for Djibouti (Camp):
Fully vaccinated;
1. Negative COVID 19 test within 72 hrs.
2. Negative test registered with the hospital here.
3. No ROM requirement.
4. Completed DD Form 3150, signed by authorized company representative.
NOT fully vaccinated;
1. Negative COVID 19 test to travel.
2. ROM required for 10 days.
3. Negative COVID 19 test within 72 hrs of base entry.
4. Negative test registered with the hospital in Djibouti.
5. Base access.
(Information above should be utilized for offer submission in respect to pricing/cost and proposed period of performance. The contractor is responsible to abide by any host nation rules, which are separate and independent of the base entry requirements.)
10. Working Hours.
Monday through Friday 0700-1530 Weekends, After Hours and Holidays must coordinated with site manager.
11. WARRANTY OF SERVICES:
The Contractor shall warrant all work against defects in material and workmanship for one year from the date of Government acceptance. The Contractor shall correct any defects in material or workmanship or any recurring maintenance problems caused by defects in material or workmanship within the warranty period by repair or replacement at no additional cost to the Government. If the defect results in any damage to Government or private property, the damage shall be corrected by repair or replacement at the option of the owner, at no additional cost to the Government. The Contractor shall respond and correct all warranty repairs within one business day from the date of notification by the Government. Should the contractor not make the required repairs in a timely manner, the Government reserves the right to have the services performed by others and bill the contractor for actual costs incurred.
12. POINTS OF CONTACTS: TBD
Note for shipping:
The Government requests that shipping costs be incorporated into the price of each item rather than a separate line for total shipping costs. The Government will spread the shipping costs across all lines upon award if quoted as a separate line item.
TOTAL: ___________
Estimated POP if Different than Requested Date____________
Provide the following information with your quote plus any additional information which is applicable to the materials list. Any items that are not applicable please designate with N/A.
Provide any contract numbers for purchase orders in which you have previously performed this work: ______________________________________________.
Firm Fixed Price Total (includes all charges): $_____
Company Name: __
CAGE Code:
DUNS Number: ___
Tax Identification Number: __
6. The government intends on awarding a Firm-Fixed Price contract on this requirement.
7. The required delivery and acceptance date is TBD
| Performance of services will occur at; |
| NCTAMS LANT, DET – Djibouti, Africa |
8. The provision at FAR 52.212-1, Instructions to Offerors – Commercial applies to this acquisition and is incorporated by reference. The provision is amended as follows:
52.212-1 (ADDENDUM) ADDITIONAL INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS
a. Any inconsistency between FAR Provision 52.212-1 and the Addendum to FAR 52.212-1 shall be solved by giving precedence to the Addendum to FAR 52.212-1.
b. After receipt of quotes the Government may, with or without notice, negotiate with and, if desired, seek quote revisions from as many or as few quoters as it, in its discretion, deems appropriate.
c. The term “offeror” or “offer” as used in FAR 52.212-1 shall be understood to mean “quoter” and “quote,” respectively. Further, the term “award” shall be understood to describe the Government’s issuance of an order.
d. The Government will consider all quotes that are timely received and may consider late quotes. Failure of a quote to address any items required in the submission package may make a quote unacceptable.
e. Paragraph (b) of FAR Provision 52.212-1, Submission of Offers, is amended as follows:
| In addition to the quote submission requirements stated in FAR provision 52.212-1, quoters shall provide the following, as part of the quote submission package, no later than the required time and date for quote submission: |
| Responsible sources shall provide the following: |
1. Price quote which identifies the requested item(s), unit price inclusive of shipping (if any), and extended price
2. Total Firm Fixed price
3. Any Discount Terms
4. Estimated time of delivery
5. Technical Submission Requirements
a. For Parts/Supply buy, the quote shall contain a description including part number and title for each item listed in the solicitation to allow the Government to verify that the quoted parts match the requirements listed in the requirements schedule.
b. For a Services buy, the quote shall contain all pre-award submission/certification requirements as defined in the statement of work (SOW).
c.
6. Responses to the solicitation are due 21 March 2022 @ 1400 pm EST. Quotes may be e-mailed to nancy.purvis..civ@us.navy.mil To be considered timely, an E-mail quote must be received in its entirety in the designated E-mail inbox by the due date and time for quote submission. Quotes received after that time will be considered at the Government’s sole discretion. Please reference the solicitation number on your quote.
| Primary Point of Contact: nancy.purvis.civ@us.navy.mil |
| Secondary Point of Contact: robert.p.joas.civ@us.navy.mil |
| The Government will consider all quotes that are timely received and may consider late quotes in accordance with 52.212-1. Failure of a quote to address any items listed in the attached submission package may make a quote unacceptable. |
9. Provision 52.212-2 Evaluation—Commercial Items (Oct 2014) applies to this acquisition.
(a) The Government may award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
(i) technical capability of the item offered to meet the Government requirement;
(ii) price;
Award shall be made to the lowest priced technically acceptable offeror in LPTA solicitations.
To be considered a technically acceptable solution for a parts procurement, the quoted parts shall meet the solicitation requirements including required parts, delivery dates, and terms and conditions stated in the solicitation. To be considered a technically acceptable solution for a service, the quoted service shall meet the solicitation requirements including terms and conditions stated in the solicitation. The quote shall state that all aspects of the technical requirement, including required delivery date and part numbers, can be met.
If utilized, a past performance evaluation will be conducted in accordance with FAR 13.106-2(b)(3)(ii)(C). The Government intends to utilize the Government Wide Past Performance Information Retrieval System (PPIRS) for past performance evaluations as a basis for anticipating successful/unsuccessful performance on this required effort. To be considered acceptable for past performance, a search of the PPIRS must reveal no negative past performance information for the recent and relevant records. In the event there are no recent and/or relevant PPIRS records, the quoter may submit information on recent and relevant subcontracts and/or commercial contracts. If no recent and relevant contracts are available in PPIRS or submitted by the offeror, the quoter’s past performance record shall be considered “unknown.” In the context of acceptable or unacceptable, “unknown” past performance shall be considered “acceptable.” To be considered recent, the effort must either still be in progress or have been completed within the previous three (3) years from date of this draft award notice. To be considered relevant the record should be similar in terms of complexity, scope, and magnitude. “Scope” is defined as experience in areas defined in the SOW. “Magnitude” is defined as the measure of similarity of the volume, dollar value, and/or duration of work actually performed under the quoter’s submitted contracts to the SOW. At the quoter’s discretion, additional past performance information may be submitted with the quote as a supplement to PPIRS. If furnished, this submission will be evaluated in accordance with the procedures described above.
The Government will evaluate quoted pricing for reasonableness utilizing techniques described in FAR 13.106-3.
(b) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror by the Government within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
10. All Offerors must include a completed copy of FAR 52.212-3, Offeror Representations and Certifications – Commercial Items with its offer.
11. Clause 52.212-4 Contract Terms and Conditions – Commercial items, applies to this acquisition.
Offers/quotes submitted in response to this solicitation shall not contain nor be subject to the offeror's/vendor's standard commercial terms and conditions. Any offer/quote submitted in response to this solicitation which includes the offeror's/vendor's standard commercial terms and conditions may be considered a material defect and may be rejected as being non-responsive to the solicitation.
12. Clause 52.212-5, Contract Terms and Conditions Required to Implement Statutes or Executive Orders – Commercial Items, applies to this acquisition along with the following FAR Clauses cited in the clause are applicable.
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)
(3) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(4) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77, 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the contracting officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
___ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).
___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub L. 111-5) (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009).
__XX__ (4) 52.204-10, Reporting Executive compensation and First-Tier Subcontract Awards (Oct 2016) (Pub. L. 109-282) (31 U.S.C. 6101 note).
___ (5) [Reserved] ___ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
___ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
_XX__ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Oct 2015) (31 U.S.C. 6101 note).
___ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Jul 2013) (41 U.S.C. 2313).
___ (10) [Reserved] ___ (11) (i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).
___ (ii) Alternate I (Nov 2011) of 52.219-3.
___ (12) (i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Oct 2014) (if the offeror elects to waive the preference, it shall so indicate in its offer)(15 U.S.C. 657a).
___ (ii) Alternate I (Jan 2011) of 52.219-4.
___ (13) [Reserved] _XX__ (14) (i) 52.219-6, Notice of Total Small Business Aside (Nov 2011) (15 U.S.C. 644).
___ (ii) Alternate I (Nov 2011).
___ (iii) Alternate II (Nov 2011).
___ (15) (i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).
___ (ii) Alternate I (Oct 1995) of 52.219-7.
___ (iii) Alternate II (Mar 2004) of 52.219-7.
___ (16) 52.219-8, Utilization of Small Business Concerns (Nov 2016) (15 U.S.C. 637(d)(2) and (3)).
___ (17) (i) 52.219-9, Small Business Subcontracting Plan (Jan 2017) (15 U.S.C. 637 (d)(4)).
___ (ii) Alternate I (Nov 2016) of 52.219-9.
___ (iii) Alternate II (Nov 2016) of 52.219-9.
___ (iv) Alternate III (Nov 2016) of 52.219-9.
___ (v) Alternate IV (Nov 2016) of 52.219-9.
___ (18) 52.219-13, Notice of Set-Aside of Orders (Nov 2011) (15 U.S.C. 644(r)).
___ (19) 52.219-14, Limitations on Subcontracting (Jan 2017) (15 U.S.C. 637(a)(14)).
___ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).
___ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Nov 2011) (15 U.S.C. 657f).
_XX_ (22) 52.219-28, Post Award Small Business Program Rerepresentation (Jul 2013) (15 U.S.C. 632(a)(2)).
___ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Dec 2015) (15 U.S.C. 637(m)).
___ (24) 52.219-30, Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Dec 2015) (15 U.S.C. 637(m)).
_XX_ (25) 52.222-3, Convict Labor (June 2003) (E.O. 11755).
_XX_ (26) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Oct 2016) (E.O. 13126).
_XX_ (27) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
_XX_ (28) 52.222-26, Equal Opportunity (Sep 2016) (E.O. 11246).
___ (29) 52.222-35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212).
____ (30) 52.222-36, Equal Opportunity for Workers with Disabilities (Jul 2014) (29 U.S.C. 793).
___ (31) 52.222-37, Employment Reports on Veterans (Feb 2016) (38 U.S.C. 4212).
___ (32) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).
_XX_ (33) (i) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).
___ (ii) Alternate I (Mar 2015) of 52.222-50, (22 U.S.C. chapter 78 and E.O. 13627).
___ (34) 52.222-54, Employment Eligibility Verification (Oct 2015). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)
___ (35) 52.222-59, Compliance with Labor Laws (Executive Order 13673) (Oct 2016). (Applies at $50 million for solicitations and resultant contracts issued from October 25, 2016 through April 24, 2017; applies at $500,000 for solicitations and resultant contracts issued after April 24, 2017).
Note to paragraph (b)(35): By a court order issued on October 24, 2016, 52.222-59 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.
___ (36) 52.222-60, Paycheck Transparency (Executive Order 13673) (Oct 2016).
___ (37) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O.13693).
___ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Jun 2016) (E.O. 13693).
___ (40) (i) 52.223-13, Acquisition of EPEAT® -Registered Imaging Equipment (Jun 2014) (E.O.s 13423 and 13514 ___ (ii) Alternate I (Oct 2015) of 52.223-13.
___ (41) (i) 52.223-14, Acquisition of EPEAT® -Registered Television (Jun 2014) (E.O.s 13423 and 13514).
___ (ii) Alternate I (Jun 2014) of 52.223-14.
___ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b).
___ (43) (i) 52.223-16, Acquisition of EPEAT® -Registered Personal Computer Products (Oct 2015) (E.O.s 13423 and 13514).
___ (ii) Alternate I (Jun 2014) of 52.223-16.
_XX_ (44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging while Driving (Aug 2011) (E.O. 13513).
___ (45) 52.223-20, Aerosols (Jun 2016) (E.O. 13693).
___ (46) 52.223-21, Foams (Jun 2016) (E.O. 13696).
___ (47) (i) 52.224-3, Privacy Training (Jan 2017) (5 U.S.C. 552a).
___ (ii) Alternate I (Jan 2017) of 52.224-3.
___ (48) 52.225-1, Buy American--Supplies (May 2014) (41 U.S.C. chapter 83).
___ (49) (i) 52.225-3, Buy American--Free Trade Agreements--Israeli Trade Act (May 2014) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43).
___ (ii) Alternate I (May 2014) of 52.225-3.
___ (iii) Alternate II (May 2014) of 52.225-3.
___ (iv) Alternate III (May 2014) of 52.225-3.
___ (50) 52.225-5, Trade Agreements (Oct 2016) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
_XX_ (51) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
___ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
___ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).
___ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).
___ (55) 52.232-29, Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C. 4505), 10 U.S.C. 2307(f)).
___ (56) 52.232-30, Installment Payments for Commercial Items (Jan 2017) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
_XX_ (57) 52.232-33, Payment by Electronic Funds Transfer— System for Award Management (Jul 2013) (31 U.S.C. 3332).
___ (58) 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management (Jul 2013) (31 U.S.C. 3332).
___ (59) 52.232-36, Payment by Third Party (May 2014) (31 U.S.C. 3332).
___ (60) 52.239-1, Privacy or Security Safeguards (Aug 1996) (5 U.S.C. 552a).
___ (61) 52.242-5, Payments to Small Business Subcontractors (Jan 2017) (15 U.S.C. 637(d)(12)).
___ (62) (i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631).
___ (ii) Alternate I (Apr 2003) of 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or executive orders applicable to acquisitions of commercial items:
___ (1) 52.222-17, Nondisplacement of Qualified Workers (May 2014) (E.O. 13495) ___ (2) 52.222-41, Service Contract Labor Standards (May 2014) (41 U.S.C. chapter 67.).
___ (3) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).
___ (4) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (Multiple Year and Option Contracts) (May 2014) (29 U.S.C.206 and 41 U.S.C. chapter 67).
___ (5) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).
___ (6) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (May 2014) (41 U.S.C. chapter 67).
___ (7) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (May 2014) (41 U.S.C. chapter 67).
___ (8) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2015) (E.O. 13658).
_ (9) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706).
___ (10) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (May 2014) (42 U.S.C. 1792).
___ (11) 52.237-11, Accepting and Dispensing of $1 Coin (Sep 2008) (31 U.S.C. 5112(p)(1)).
(d) Comptroller General Examination of Record The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, and does not contain the clause at 52.215-2, Audit and Records -- Negotiation.
(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.
(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.
(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(e)
(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c) and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (e)(1) in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—
(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).
(ii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.