This document is the contract documents for the New River Regional Water Authority (NRRWA) Water Treatment Plant Expansion project located in Austinville, Virginia. The project involves expanding the existing 4.0 MGD water treatment plant to 6.33 MGD capacity, including improvements to the raw water intake, chemical feed and mixing systems, sedimentation and sludge collection systems, gravity filters, finished water pumping system, solids handling basins, and electrical and control systems. Additionally, new solids handling and sludge dewatering facilities will be constructed. Bids will be received until 2:00 PM local time on May 9, 2024, with a pre-bid conference scheduled for April 18, 2024. The contract will be awarded to the responsible bidder submitting the lowest responsive bid. The work must be substantially complete within 545 days and ready for final payment within 590 days after the contract times commence.

The contract price is a lump sum, and the project will be partially funded by the U.S. Department of Commerce Economic Development Administration. The project is not exempt from sales tax, so bidders must include all sales tax in their bids. Liquidated damages of $500 per day for failure to achieve substantial completion and $250 per day for failure to complete the remaining work on time will be assessed against the contractor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DOCUMENTS

NEW RIVER REGIONAL WATER AUTHORITY

WATER TREATMENT PLANT EXPANSION

EDA PROJECT NO.: 01-01-15370

March 12, 2024

Prepared for:

New River Regional Water Authority

289 Kohler Ave.

Austinville, VA 24312

Prepared by:

PEED & BORTZ, LLC

Civil and Environmental Engineers 20 Midway Plaza Drive Christiansburg, Virginia

22-18

New River Regional Water Authority Water Treatment Plant Expansion 3/11/2024

TABLE OF CONTENTS 00000-1

TABLE OF CONTENTS

CONTRACT DOCUMENTS PAGE

Document 00000 – Table of Contents 00000–1 Document 00130 – Advertisement for Bids 00130–1 Document 00200 – Instructions to Bidders 00200–1 Document 00410 – Bid Form 00410–1 Document 00430 – Bid Bond 00430–1 Document 00451 – Contractor Qualification Statement 00450–1 Document 00510 – Notice of Award 00510–1 Document 00520 – Agreement between Owner and Contractor 00521–1 Document 00550 – Notice to Proceed 00550–1 Document 00610 – Performance Bond 00610–1 Document 00615 – Payment Bond 00615–1 Document 00620 – Application for Payment 00620–1 Document 00625 – Certificate of Substantial Completion 00625–1 Document 00626 – Notice of Acceptability of Work 00626–1 Document 00700 – General Conditions of the Construction Contract 00700–1 Document 00800 – Supplementary Conditions 00800–1 Document 00810 – EDA Contract Inserts 00810–1 Document 00940 – Work Change Directive 00940–1 Document 00941 – Change Order 00941–1 Document 00942 – Field Order 00942–1

TECHNICAL SPECIFICATIONS PAGE

Document 01100 – Summary of the Work 01100–1 Document 01330 – Submittal Procedures 01330–1 Document 01450 – Testing Laboratory Services 01450–1 Document 01453 – Code Required Special Inspections 01453–1 Document 01610 – Delivery, Storage, and Handling 01610–1 Document 02080 – Utility Pipe and Materials 02080–1 Document 02085 – Valves 02085–1 Document 02200 – Site Preparation 02200–1 Document 02300 – Earthwork 02300–1 Document 02510 – Water Distribution 02510–1 Document 02700 – Bases, Ballasts, Pavements, and Appurtenances 02700–1 Document 02821 – Chain Link Fences 02821–1 Document 02920 – Seeding 02920–1 Document 03100 – Concrete Forming And Accessories 03100–1 Document 03200 – Concrete Reinforcing 03200–1 Document 03300 – Cast–In–Place Concrete 03300–1 Document 03400 – Precast Concrete Structures 03400–1 Document 03420 – Precast Post-Tensioned Concrete 03420–1 Document 04100 – Concrete Masonry Units 04100–1 Document 05213 – Pipe and Tube Railings 05213–1 Document 05500 – Metal Fabrications 05500–1 Document 06110 – Wood Framing and Construction 06110–1 Document 07100 – Dampproofing and Waterproofing 07100–1 Document 07210 – Building Insulation 07210–1 Document 07310 – Roofing Shingles 07310–1 Document 07460 – Vinyl Siding and Soffits 07460–1

TABLE OF CONTENTS 00000-2

Document 07600 – Flashing and Sheet Metal 07600–1 Document 07900 – Joint Sealers 07900–1 Document 08100 – Steel Doors and Frames 08100–1 Document 08360 – Overhead Doors 08360–1 Document 08700 – Finish Hardware 08700–1 Document 09910 – Exterior Painting 09910–1 Document 09920 – Interior Painting 09920–1 Document 11015 – Miscellaneous Equipment 11015–1 Document 11210 – Water Pumps 11210–1 Document 11220 – Static Mixers 11220–1 Document 11224 – Gravity Dual Media Filter 11224–1 Document 11240 – Chemical Feeding Equipment 11240–1 Document 11310 – Wastewater Pumps 11310–1 Document 11390 – Sludge Dewatering Equipment 11390–1 Document 11610 – Conical Disc Mixer 11610–1 Document 11680 – Sludge Collector 11680–1 Document 11690 – Tube Settlers 11690–1 Document 12300 – Manufactured Casework 12300–1 Document 13340 – Frame Supported Membrane Structure 13340–1 Document 15250 – Pipe Supports 15250–1 Document 15400 – Plumbing 15400–1 Document 16100 – Electrical General Provisions 16100–1 Document 16120 – Coordination 16120–1 Document 16130 – Reworking Existing System 16130–1 Document 16173 – Power System Analysis 16173–1 Document 16180 – Acceptance Testing 16180–1 Document 16200 – Electric Service 16200–1 Document 16201 – Metallic Raceway 16201–1 Document 16202 – Nonmetallic Raceway 16202–1 Document 16219 – Wire, Cable, and Wiring (Single-Conductor) 16219–1 Document 16220 – Multi-Conductor Cable 16220–1 Document 16221 – Grounding 16221–1 Document 16280 – Low Voltage Active Harmonic Filter 16280–1 Document 16300 – Supporting Devices 16300–1 Document 16301 – Pull and Junction Boxes 16301–1 Document 16302 – Wiring Device Boxes 16302–1 Document 16400 – Underground Ducts 16400–1 Document 16401 – Underground Pull Boxes 16401–1 Document 16482 – Variable Frequency Drives 16482–1 Document 16500 – Dry Type Transformers 16500–1 Document 16501 – Panelboards 16501–1 Document 16502 – Wiring Devices 16502–1 Document 16503 – Safety Switches 16503–1 Document 16504 – Fuses 16504–1 Document 16505 – Molded Case Circuit Breakers (MCCB) 16505–1 Document 16506 – Motor Starters 16506–1 Document 16507 – Surge Protective Devices (SPD’s) 16507–1 Document 16600 – Lighting 16600–1 Document 16900 – Controls and Instrumentation 16900–1

New River Regional Water Authority Water Treatment Plant Expansion 3/12/2024

ADVERTISEMENT FOR BIDS 00130 - 1

SECTION 00130 ADVERTISEMENT FOR BIDS

Owner:

New River Regional Water Authority(NRRWA), Austinville, VA

Separate sealed Bids will be received for the NRRWA Water Treatment Plant Expansion at the existing facility located at 289 Kohler Ave. Austinville, VA 24312 to expand capacity from 4.0 to 6.33 MGD. Work includes replacement of chemical feed pumps, installation of sedimentation basin sludge collectors and tube settlers, development of a fourth gravity sand filter and refurbishment of existing filters, installation of an additional finished water pump, construction of sludge thickener tanks, and construction of sludge dewatering facilities. Work also includes pump replacement and improvements at the remote raw water intake on the New River at 243 Store Hill Rd.

Bids will be received by Michael Watson, Chairperson, at:

New River Regional Water Authority 289 Kohler Ave.

Austinville, VA 24312 until 2:00 PM local prevailing time on Thursday May 9, 2024, and then publicly opened and read aloud at said location.

The Contract Documents may be examined at the following locations:

Peed & Bortz, LLC, Civil & Environmental Engineers, 20 Midway Plaza Drive, Ste. 100 Christiansburg, VA 24073 Austinville Water Treatment Plant, 289 Kohler Ave. Austinville, VA 24312

Digital copies of Bidding Documents may be obtained at no charge from the Peed & Bortz website at http://peed-bortz.com/request-for-bids/. Prospective Bidders are urged to register with Peed & Bortz, LLC as a plan holder, even if Bidding Documents are obtained from a plan room or source other than the designated website in either electronic or paper format. The designated website will be updated periodically with addenda and other information relevant to submitting a Bid for the Project. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if any, obtained or omitted from sources other than the designated website.

A Pre-Bid Conference shall be held at 1:00 PM local prevailing time Thursday April 18, 2024 at the Austinville Water Treatment Plant, 289 Kohler Ave. Austinville, VA 24312. Attendance at the pre-bid conference is encouraged, but not required.

Withdrawal of bids due to error shall be in accordance with Virginia Code Section 2.2-4430.B.1.

Should the apparent low bid exceed available funds, the Owner reserves the right to negotiate with the apparent low bidder to obtain a contract price within available funds.

Bidders shall comply with Virginia Code Section 54.1-1112 regarding information required with bid. Envelopes containing bids shall be clearly marked with the Bidder’s contractor license number.

This project will be partially funded with Federal funds from the United States Department of Commerce, Economic Development Administration and therefore is subject to the Federal laws and regulations associated with that program. Contractor will be required to maintain an active SAM.gov account throughout the project.

By: Michael Watson, Chairperson Date: March 25, 2024

INSTRUCTIONS TO BIDDERS 00200 - 1

Instructions to Bidders

TABLE OF ARTICLES Page

Article 1— Defined Terms Article 2— Bidding Documents Article 3— Qualifications of Bidders Article 4— PRE-BID CONFERENCE Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site Article 6— Bidder’s Representations and Certifications Article 7— Interpretations and Addenda Article 8— Bid Security Article 9— Contract Times Article 10— Substitute and “Or Equal” Items Article 11— Subcontractors, Suppliers, and Others Article 12— Preparation of Bid Article 13— Basis of Bid Article 14— Submittal of Bid Article 15— Modification and Withdrawal of Bid Article 16— Opening of Bids Article 17— Bids to Remain Subject to Acceptance Article 18— Evaluation of Bids and Award of Contract Article 19— Bonds and Insurance Article 20— Signing of Agreement Article 21— Sales and Use Taxes Article 22— Contracts to Be Assigned Article 23— Federal Requirements

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). It is Bidder’s responsibility to determine that it is using a complete set of documents

INSTRUCTIONS TO BIDDERS 00200 - 2

in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances. Owner and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.

2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid.

Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant.

2.04 Deleted

2.05 Deleted

2.06 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader Version 9 or later. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents; however, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06A above; however, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within 2 days of Owner’s request, Bidder must submit the following information:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.

C. Bidder’s state or other contractor license number, if applicable.

D. Subcontractor and Supplier qualification information.

E. Other required information regarding qualifications.

3.02 Deleted

INSTRUCTIONS TO BIDDERS 00200 - 3

3.03 Deleted

3.04 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.05 No requirement in this Article to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 Deleted

4.02 A non-mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference; however, attendance at this conference is not required to submit a Bid.

4.03 Deleted

4.04 Deleted

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE;

OWNER’S SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

4. Deleted

INSTRUCTIONS TO BIDDERS 00200 - 4

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. In addition to the documents regarding existing Site conditions referred to in Paragraph 5.02.A, the following other documents relating to conditions at or adjacent to the Site are known to Owner and made available to Bidders for reference:

1. Record Drawings – New River Regional Water Authority Austinville Water Treatment Plant (Division I) – For Bid Plan Set Dated October 20, 2006.

Owner will make copies of these other Site-related documents available to any Bidder on request.

B. Owner has not verified the contents of these other Site-related documents, and Bidder may not rely on the accuracy of any data or information in such documents. Bidder is responsible for any interpretation or conclusion Bidder draws from the other Site-related documents.

C. The other Site-related documents are not part of the Contract Documents.

D. Bidders are encouraged to review the other Site-related documents, but Bidders will not be held accountable for any data or information in such documents. The requirement to review and take responsibility for documentary Site information is limited to information in (1) the Contract Documents and (2) the Technical Data.

E. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. A Site visit is scheduled following the pre-bid conference.

C. Deleted

D. Deleted

E. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the Owner or Engineer. Bidder must conduct the required Site visit during normal working hours.

F. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

G. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

Bidder is responsible for establishing access needed to reach specific selected test sites.

H. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

I. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

5.06 Other Work at the Site

INSTRUCTIONS TO BIDDERS 00200 - 5

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing.

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of [number] percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents. Bid security must be at least 5% of the Bidder’s maximum Bid price.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

INSTRUCTIONS TO BIDDERS 00200 - 6

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and

(b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Deleted

9.03 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 Deleted

10.02 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder.

Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders. Bidders cannot rely upon approvals made in any other manner. Substitutes and “or-equal” materials and equipment may be proposed by Contractor in accordance with Paragraphs 7.05 and 7.06 of the General Conditions after the Effective Date of the Contract.

10.03 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda.

Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 Deleted

11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within five days after Bid opening:

A. None

11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

11.05 The Contractor shall not award work to Subcontractor(s) in excess of the limits stated in SC 7.07A.

INSTRUCTIONS TO BIDDERS 00200 - 7

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Bid by an individual must show the Bidder’s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Deleted

13.02 Base Bid with Alternates

A. Bidders must submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form. The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.

INSTRUCTIONS TO BIDDERS 00200 - 8

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.

13.03 Deleted

13.04 Deleted

13.05 Deleted

13.06 Deleted

13.07 Deleted

ARTICLE 14—SUBMITTAL OF BID

14.01 The Bidding Documents include one separate unbound copy (or digital copy) of the Bid Form, and, if required, the Bid Bond Form. The unbound (or printed digital) copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 2 of the Bid Form.

14.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid and must be enclosed in a plainly marked package with the Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid must be addressed to the location designated in the Advertisement.

14.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 A Bid may be modified or withdrawn only in accordance with the Code of Virginia.

15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.03 If, as a result of bid withdrawal, the Work is rebid or negotiated, Bidder or Bidders withdrawing a bid will be disqualified from further bidding or negotiating on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

16.02 Deleted

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

INSTRUCTIONS TO BIDDERS 00200 - 9

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. In the comparison of Bids, deductive alternates will be applied in the same order of priority as listed in the Bid Form. To determine the Bid prices for purposes of comparison, Owner will announce to all bidders a “Base Bid with alternates” budget after receiving all Bids, but prior to opening them. For comparison purposes, Base Bids will first be evaluated to identify if the lowest responsive Base Bid is within the announced budget; otherwise, Bids will continue to be reevaluated with each deductive alternate, following the order of priority established in the Bid Form, until an apparent responsive low bidder is within the announced budget, or all deductive alternates have been considered. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and any combination of its deductive alternate Bids for which Owner determines funds will be available at the time of award.

C. Deleted

D. Deleted

E. Deleted

F. Deleted

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement.

Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the

INSTRUCTIONS TO BIDDERS 00200 - 10

Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

ARTICLE 21—SALES AND USE TAXES

21.01 This project is NOT exempt from sales tax. Bidders must include all sales tax in their Bid.

ARTICLE 22—CONTRACTS TO BE ASSIGNED

22.01 Deleted

ARTICLE 23—FEDERAL REQUIREMENTS

23.01 If the contract price is in excess of $100,000, provisions of the Contract Work Hours and Safety Standards Act at 29 CFR 5.5(b) apply.

23.02 Federal requirements at Article 19 of the Supplementary Conditions apply to this Contract.

23.03 This project will be partially funded with Federal funds from the United States Department of Commerce, Economic Development Administration and therefore is subject to the Federal laws and regulations associated with that program.

BID FORM 00410 - 1

BID FORM

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to:

New River Regional Water Authority Attn: Michael Watson, Chairperson 289 Kohler Ave.

Austinville, VA 24312

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids;

C. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids;

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Lump Sum Bids

A. Bidder will complete the Work in accordance with the Contract Documents for the following lump sum (stipulated) price(s). The Deductive Alternate amounts are the amounts subtracted from the Base Bid amount to delete the work associated with that item. Refer to Section 01100 – Summary of Work for additional details on scope of Base Bid and Deductive Alternates.

1. Deleted

2. Lump Sum Price (Base Bid and Deductive Alternates)

Lump Sum Bid Price for Base Bid (All Work) $

Deductive Alternate #1 [Deductive Amount for Deleting Centrifuge & Conveyor] - $

Deductive Alternate #2 [Deductive Amount for Deleting Dry Solids Shelter] - $

ARTICLE 4—DELETED

ARTICLE 5—DELETED

BID FORM 00410 - 2

ARTICLE 6—TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.02 Deleted

6.03 Deleted

6.04 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 7—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND

RECEIPT OF ADDENDA

7.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 90 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

7.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

7.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda: [Bidder is to complete table.]

Addendum Number Addendum Date

ARTICLE 8—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

8.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

BID FORM 00410 - 3

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and (c) Bidder’s (Contractor’s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

8.02 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

BID FORM 00410 - 4

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

Address for giving notices:

Bidder’s Contact:

Name:

(typed or printed)

Title:

(typed or printed)

Phone:

Email:

Address:

Bidder’s Contractor License No.: (if applicable)

New River Regional Water Authority Water Treatment Plant Expansion 3/5/2024

BID BOND 00430-1

BID BOND (PENAL SUM FORM)

Bidder Surety

Name: [Full formal name of Bidder] Name: [Full formal name of Surety]

Address (principal place of business): Address (principal place of business):

[Address of Bidder’s principal place of business] [Address of Surety’s principal place of business]

Owner Bid

Name: New River Regional Water Authority Project (name and location):

Address (principal place of business): New River Regional Water Authority Water Treatment Plant Expansion Austinville, VA 289 Kohler Ave.

Austinville, VA 24312

Bid Due Date: [Enter date bid is due]

Bond

Penal Sum: [Amount]

Date of Bond: [Date]

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

Bidder Surety

(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)

By: By:

(Signature) (Signature) (Attach Power of Attorney)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Attest: Attest:

(Signature) (Signature)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.

BID BOND 00430-2

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond will be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation will be null and void if:

3.1. Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2. All Bids are rejected by Owner, or

3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .