21R1010_Atch 1_SOW_10May21.pdf
PDF 448 KB Posted
- Attached to
- Architect-Engineer (A-E) Title I & II Services Federal contract opportunity
- Solicitation number
- FA486121R1010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 21R1010_Atch 2_SF330.pdf | ||
| 21R1010_Atch 3_PPQ.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 1
STATEMENT OF WORK
ARCHITECT-ENGINEER, TITLE I & TITLE II SERVICES
IDIQ
10 May 2021
INDEX SECTION
1. SCOPE OF SERVICES
2. GENERAL INFORMATION
3. PROJECT MANAGEMENT
4. SERVICES REQUIRED
5. DESIGN CRITERIA
6. PRE-DESIGN RESPONSIBILITIES
7. DESIGN SCHEDULE
8. SECURITY INFORMATION
9. MISCELLANEOUS
10. STANDARD BASE DESIGN CONSIDERATION
11. POST DESIGN RESPONSIBILITIES
12. TITLE II SERVICES
13. NELLIS/CREECH BUILDING INFORMATION MODELING (BIM) REQUIREMENTS
STATEMENT OF
WORK
ARCHITECT-ENGINEER, TITLE I & TITLE II
SERVICES IDIQ
1. SCOPE OF SERVICE:
a. The Architect-Engineer (A-E) shall perform Title I, DESIGN SERVICES, and/or Title II, INSPECTION SERVICES, as may be ordered by the Contracting Officer. Such services shall consist of architectural, civil, structural, mechanical, electrical, environmental, landscape, fire protection, communications, planning and topographical cadastral, geotechnical surveys and utility surveys of existing conditions or facilities and field surveys for topographic or locative purposes; development of documentation and reports for conceptual solutions, area development plans (ADP), planning charrette reports (PCR) or concept report, comprehensive/master plans, aviation airspace plans, Dormitory Master Plan, pavement condition inspections (PCI), design criteria, environmental assessments, and impact analysis; producing economic analysis, detailed cost estimates, construction drawings and specifications, bid schedules, color boards and renderings, and any other documentation necessary to execute a maintenance, repair, alteration, and/or construction project. These include services of an architectural or engineering nature or services incidental thereto (including studies, investigations, surveying and mapping, tests, evaluations, consultations, comprehensive planning, program management, conceptual designs, development of design criteria, and other related services) that logically or justifiably require performance by registered architects or engineers or their employees. The area of work shall include, but not be limited to, Nellis and Creech Air Force Bases and portions of the Nevada Test and Training Range (NTTR).
b. The A-E shall perform other A-E services that are not Title I Services as ordered by the Contracting Officer.
Such services may include, but not be limited to, review of contract submittals, review of shop drawings, and preparation of change orders, fact-finding studies, surveys, investigations, developing design criteria, interior design, and preparing base comprehensive plans (BCP), and other professional A-E services not necessarily connected with a specific construction project. Environmental work may include remediation projects and hazardous, toxic, and radioactive waste (HTRW) studies. Testing to determine environmental work needed for a project may be included in scope of work.
c. Work may include developing Requests for Proposals for design-build projects or developing more extensive designs to be used in design-bid-build contracts. In a design-build project, A-E would provide a 15% or 35% design package along with a detailed project Scope of Work for bidding by design-build contractors. In a design-bid-build project, A-E would provide a 65%, 90%, or 100% design package along with a detailed Scope of Work for bidding.
d. Work may also include planning documents such as Charrette Reports Charrette reports would include documents such as: cost estimate, 15% conceptual layout and drawing set, design considerations and recommendations, maps and siting information, meeting minutes, briefings and other information and requirements gathered, all tabs in support of the Department of Defense Form (DD Form) 1391; facility space and mission requirements analysis; facilitation of planning workshops, economic analysis and, parametric and programmatic cost estimates, as well as the documentation and validation analysis leading up to a fully developed DD Form 1391 aligned with service department processes and protocols.
e. Work may also include planning documents such as Area Development Plans (ADP) and District Plans that develop the installation into logical increments for efficient and focused planning efforts; create Sustainability Component Plans (SCPs) for the different districts to provide an executable plan to reduce the impacts on energy, water, waste, storm water, etc. to allow the installation to meet present mission requirements without compromising its ability to meet future requirements. As part of the Installation Development Plan, installations shall develop District Plans for all districts on installations. Regular Air Force and AFR installations shall update applicable information in the Comprehensive Planning Platform. District Plans shall address the planning strategies outlined in UFC 2-100-01. At a minimum, District Plans will include the following elements: Regulating Plan, Alternatives Analysis, Illustrative Plan, Execution Plan, and Capacity Plan. District plans bridge the gap between installation-wide planning and site-plans. Planning at the district level focuses efforts on areas needing planning attention due to mission requirements or command priorities. An installation is divided into districts in the Installation Development Framework. A District Plan designates assigned real estate to allocated discrete geographic areas within each installation. UFC 1-200-01, Installation Master Planning, uses the terms District Plans and Area Development Plans (ADP) interchangeably; the AF has refined the scope of District Plans and the two are no longer synonymous. The AF uses the term “District Plan” because it is more accurate in describing the plan’s scope and it allows the term area planning to be used generically as any plan that is limited in scope between the installation-wide IDP and the project-specific Site Plan.
f. Work may also include Facility Utilization Surveys (FUS). These surveys will consist of compiling a variety of data elements to include unit space allocations, authorizations and building utilization rates. Documents would include accurate, updated building floor plans based on assessments of the facility and unit telework analysis and plans.
g. Work may also include studies such as creating base or district wide utility, traffic or system analysis and preparing a 5-year roof or waterline replacement plan or a traffic report. Studies would include documents such as: data evaluated, existing system condition, computer models, maps and drawings, BUILDER/PAVER data sheets, Geospatial mapping data, load analysis, assumptions, recommendations for future repairs or new installations, economic evaluations, environmental or utility savings considerations, and cost/value tradeoffs.
h. Specific work requirements will be provided to the A-E by the Contracting Officer in the form of written Task
Orders issued as individual delivery orders to this contract.
2. GENERAL INFORMATION:
a. The A-E shall be an individual or firm, or any duly authorized representative thereof, professionally engaged in the practice of architecture and/or engineering, qualified by registration and experience to perform all professional engineering work necessary to provide the requirements of the services hereinafter specified.
b. Any topographic surveys, excavations, verifications of existing underground utility locations, soil borings, soil analysis, hazardous material tests, laboratory tests, pressure tests, electrical tests, corrosion and cathodic protection tests, and any other tests required for a complete design of each project will be the responsibility of the A-E. A-E shall obtain required permits for these tests/surveys and provide information to the Base Civil Engineer Project Manager (CENMP) through the Contracting Officer.
c. The contract will be administered by the Contracting Officer. All instructions to the A-E will be made by the
Contracting Officer who is the only individual authorized to direct work or make any changes.
d. The Government retains the right to continue to provide input and finalize the concepts up through the (35%) Design Stage. This applies when the nature of the input falls within the intent of the "Project Description and Criteria," is minor in nature, and does not increase, change, or modify the direction of major portions of the work. These inputs will be at no additional cost to the Government. Examples include, but are not limited to moving minor walls, adjusting exits, doorways and door swings, adding, changing or deleting finish materials, adjusting HVAC air flow, adjusting light fixture and electrical outlet locations, adjusting site features, increasing or decreasing facility footprint up to 20%, and complying with technical directives and regulations.
e. The A-E is responsible for addressing/resolving all design comments after each design review meeting with follow-up minutes. The outcome of all comments must be incorporated into the design before the next design submittal is due. All Government design comments shall be complied with or resolved with the individual who made the comment or their representative prior to proceeding to the next submission. If designs are submitted before all design comments have been resolved, or if submitted designs do not accurately reflect the agreed-upon changes, then the Government can reject submission of designs and A-E is responsible for making required changes and resubmitting at no cost to the Government.
3. PROJECT MANAGEMENT:
a. Upon issuance of written tasking to design a project, the A-E shall appoint a Project Manager for each project to serve as the single point of contact and liaison between the A-E and the Government. The A-E shall further advise the Contracting Officer in writing of the name of the individual so designated. The A-E’s Project Manager will be responsible for the complete coordination of all work required for the project.
b. The Base Civil Engineer (BCE) office will appoint a Project Manager (CENMP) for each project. The CENMP will provide technical support to the Contracting Officer and serve as the point of contact for the A-E on all technical matters; all work performed by the A-E will be coordinated with the CENMP through the Contracting Officer.
c. If available, the CENMP, through the Contracting Officer, will furnish the A-E limited as-built or record drawings for reference and other available information. The A-E shall be responsible for determining which, if any, record drawings will be required. Assistance in locating the record drawings will be provided by the CENMP. The A-E shall be responsible for the verification of all existing conditions, dimensions, and measurements. Utility maps of the project site(s) provided to the A-E are to be used for reference only.
d. The Government will notify the A-E at the beginning of the project design if the project involves “new construction” and is subject to the applicable statutory limit. As of February 2021, the cost limit for new construction is $2M x ACF (area cost factor). The current ACF for Nellis is 1.19. The Local Approval limit for design is (.9 X $2M X ACF). Repair, renovation, and sustainment projects typically do not have a set cost limit.
e. The CENMP, through the Contracting Officer, will provide technical control and surveillance of each Task
Order placed against this Contract. All requests for necessary technical information will be made to the CENMP through the Contracting Officer.
4. SERVICES REQUIRED:
a. Services of one or more disciplines may be required by individual Task Orders. Disciplines may include architectural, civil, structural, mechanical, electrical, environmental, planning, landscape, fire protection, communications, and Title II services.
b. The services performed by the A-E may include, but not necessarily be limited to, the following:
(1) Field Surveys and Investigations:
(a) The A-E shall visit the project site(s) as necessary for effective completion of each Task Order.
(b) Site investigation shall include testing suspect materials for asbestos, lead, or other hazardous or contaminated material, and submittal of test results to the Contracting Officer.
(c) The adequacy of existing safety, mechanical, electrical, environmental control, and monitoring equipment shall be determined by the A-E. Systems shall be examined, analyzed, and evaluated for adequacy and compliance with existing codes and standards (e.g., Air Force Instructions (AFIs), Unified Facilities Criteria (UFC), National Fire Protection Code, National Safety Code, National Electric Code, OSHA Regulations, etc.). The A-E shall notify the CENMP office, through the Contracting Officer, in writing of deficiencies identified during the process of design and/or while investigating the existing conditions.
(d) The A-E shall be responsible for verification of all dimensions, utilities, measurements, regulatory criteria, and equipment through as-built drawings, on-site investigations, and coordination with applicable manufacturers for design information or guidance as necessary. A-E shall provide this information to the CENMP through the Contracting Officer. A-E shall notify CO in writing of any conditions that were discovered during site investigations that differ from government furnished data.
(e) Topographic surveys shall be performed by a licensed surveyor. A-E shall use conventional surveying and other methods, such as a total station or Global Positioning Systems (GPS) for field data collection at an accuracy level in accordance with “Geospatial Positioning Accuracy Standards, Part 3:
National Standard for Spatial Data Accuracy,” published by the Federal Geographic Data Committee (FGDC), dated most recent. All Survey data collected shall be provided to the Government in a digital format with an attached Survey Report identifying survey method, equipment list, calibration documentation, survey layout, description of control points, control diagrams, and field survey data. A
Survey Control Database (consisting of a survey marker database and a survey traverse database) will be produced for all survey control points established under this contract, and delivered in a .dbf or ASCII comma-delimited format. If GPS is used, A-E shall use survey grade GPS, at an accuracy level of +/- 2cm, when appropriate, to collect data to be overlaid onto the installation’s orthophotograph and/or base map.
(2) Drawings:
(a) A-E prepared drawings shall be well-arranged and placed for ready reference, so they present complete information. Drawings shall be complete so that the work can be constructed without any additional assistance from the A-E or the necessity to issue modifications to correct design deficiencies.
Drawings shall be detailed to the extent that an accurate estimate can be prepared and shop drawings can be checked.
(b) Design drawings shall be developed using Building Information Modeling (BIM) when possible. The spatial coordination (coordinates) of the master BIM file shall be set at the beginning of the project. All Air Force design and/or construction projects must utilize advanced modeling to generate design, construction, record, and space utilization drawings deliverables as prescribed in USACE Engineering Construction Bulletin (ECB) 2018-7. Contract requirements and other resources are available at the CAD-BIM Technology Center. Drawing submittals must utilize the Autodesk product line and be compatible with 2020 versions of software. They must also be appropriately sized and suitable for half-size (11”x17”) scaled reproduction. Drawings shall be designed in English Standard Units and/or Metric System International, as specified in each Task Order. The location plan(s), drawing index, legend, haul route plan, and general notes, as applicable, shall be located on the first drawing sheet (title sheet) or the second sheet.
All sections shall be of adequate size, detail, and clarity to enable proper and satisfactory completion of the project. All digital data shall be delivered in a format that is directly compatible with the CADD/GIS Technology Center’s Spatial Data Standards (using latest version available) and the A/E/C CAD Standard (using latest version available). All linkages of non-graphical data with graphic elements, relationships between data objects and attributes, and report formats shall be maintained. More information on the USACE’s AEC standards for CAD/BIM can be found here: https://www.wbdg.org/ffc/af-afcec/bim
(c) The following procedures shall be performed prior to a digital file being place on a CD-ROM:
(1) Include all files, both graphic and non-graphic, required for the project;
(2) Verify all files are in the same directory, and that references to those files do not include device or directory specifications;
(3) Ensure all reference (external reference) files are attached and without device or directory specifications;
(4) Remove all extraneous graphics/text outside the project border area, and set the active parameters to a standard setting (or the setting contained in the seed or prototype file);
(5) Include any standards sheets (abbreviations, symbols libraries, font libraries, color tables, pen tables, plot configuration files, user command files, etc.) necessary for a complete project;
(6) Compress and/or reduce all files using the appropriate utilities (a digital media copy of the decompression utility should be provided with the delivered data, if necessary);
(7) Establish Model and Sheet file drawing organization for all A-E data files; and
(8) Provide detailed model file external reference guide for all sheet file configurations (Ref.
A/E/C CAD Standard, Chapter 2).
(d) CD-ROM must have an external label listing format and version of the operating system on which the media was created, utility (command) used for writing the files to the media, a short description of https://www.wbdg.org/ffc/af-afcec/bim contents, and a sequence number if there are multiple volumes, and date CD was created. A transmittal sheet must accompany the media containing the information included on the external labels, total number of volumes being delivered, and a list of file names and file descriptions on each volume. The transmittal sheet must also include instructions for reading, restoring, or transferring the files from the media, and certification that all delivery media is free of known computer viruses - including the name(s) of the virus scanning software and the date the virus scan was performed.
(e) Drawing Scales: Shall be sufficiently large to clearly portray the work. Building system schematics shall be large enough so that relative features are proportionate and easily related to architectural plans and features. Scales indicated in the following list shall, in general, be used for all drawings:
(i) Vicinity Map: Furnished by CENMP
(ii) Layout Plan: 1” = 20'
(iii) Grading and Drainage Plan: 1" = 20’
(iv) Landscape Plan: 1” = 20’
(v) Utility Plan: 1” = 20'
(vi) Road Plan and Profile: 1” = 50' Horizontal, 1” = 5’ Vertical
(vii) Key and Composite Floor Plans: As large as practical
(viii) Floor Plans: 1/4" = 1’ or 1/8" = 1’ for large facilities
(ix) Roof Plan: 1/8" = 1’
(x) Mechanical and Electrical Equipment Rooms: 1/4" = 1’
(xi) Exterior Elevations: 1/8" = l'
(xii) Interior Elevations: 1/8" = 1’
(xiii) Building/Cross Sections: 1/4" = 1’ or 1/8” = 1’ for large facilities
(xiv) Wall Sections: 3/4” = l’ or 1-1/2" = 1’ for enlarged details
(xv) Reflected Ceiling Plans: 1/8" = 1’
(xvi) Details: As required for clarity
(f) Drawings shall be prepared for half size reduction (11” X 17”), remaining clear and legible when reduced. New work shall be clearly distinguished from existing features and must be clearly legible when reduced to half size. All drawings shall be marked with the applicable submittal percentage and “NOT FOR CONSTRUCTION” stated on all drawings. After submittal to the Contracting Officer at each scheduled submittal for review, review comments will be provided to the A-E for necessary revisions, corrections and additions. Final drawings shall be stamped and signed by the appropriate registered professional(s) and “FOR CONSTRUCTION” stated on the cover sheet.
(3) Specifications:
(a) The A-E will be responsible for the accurate preparation of the technical specifications using the most up to date CSI Masterformat format. Specifications shall be adapted from the latest edition of MASTERSPEC. If a Nellis AFB requirement can’t be addressed in MASTERSPEC, then a new section will be written incorporating requirements and formatted to MASTERSPEC. These specifications will not be provided by the CENMP and must be independently obtained. The specifications shall be edited to be clear, concise, and complete and shall not be subject to interpretation. Specifications shall be well coordinated with the drawings and include detailed requirements for materials and equipment. Descriptions shall permit full and free competition among potential suppliers of components, materials, and equipment, with the exception of a few items: all HVAC units shall be Carrier brand unless otherwise specified or approved by base mechanical engineer. All Fire Alarm Panels and Mass Notification Systems (MNS) shall be Monaco Brand and be compatible with existing systems, unless otherwise specified or approved by base fire protection engineer Federal and military specifications or Industry Standards shall be used wherever possible.
Specifications shall be tailored to each specific project prepared in accordance with the instructions and standards specified by the Task Order, as amended by design reviews, and as identified herein. A cover page and an index of the specification numbers/titles shall be provided. Cover page shall state the applicable submittal percentage and state “NOT FOR CONSTRUCTION”. Final specifications shall have “FOR CONSTRUCTION” stated on the cover page and be stamped and signed by the appropriate registered professional(s).
(b) Outline Specifications shall be submitted as part of the concept design documents and will list those specification sections that have been selected for use and provide a description of any specifications which must be developed for the project.
(c) Specifications shall be written and saved using MS-Word 2016 or higher and prepared in the number specified in the Task Order with at least one of the final sets in a 3-ring binder and suitable for reproduction. Specifications shall conform to the following criteria.
(i) Printed in black ink;
(ii) Font, Times New Roman;
(iii) Unless otherwise noted, font size, 12 pt;
(iv) Printed on good grade (e.g., 25 pound/ream), letter quality, (8-1/2" X 11”) bond paper;
(v) With a one inch (1”) right and left margin;
(vi) With a one and one-half inch (1-1/2") top and bottom margins;
(vii) Each page shall include Project Number, Title, Location, Contract IFB Number, Section
Number, Page Number, and date;
(viii) Project Number and Title shall be left justified /9pt/ bold with Contract IFB Number right justified /9pt/ bold on same line within header;
(ix) Project location shall be left justified /9pt/ bold next line within header;
(x) Section Number hyphen Page shall be centered, bold within footer;
(xi) Date shall be right justified within footer.
(d) Government may also provide specifications in MS Word format to A-E and A-E will be responsible to edit for a specific project.
(4) Cost Estimates:
(a) A-E prepared cost estimates shall be current, accurate, complete, and prepared by personnel competent in construction cost estimating. Estimates must reflect the expected cost to the Government to perform the work by contract and include all reasonable costs which a prudent, experienced, and well-equipped Contractor might include in his bid.
(b) Cost estimates shall be submitted in accordance with the design schedule and should be as detailed as the level of design will permit.
(c) Cost estimates for construction projects shall be submitted using the Air Force Construction
Cost Estimate Breakdown format and saved using format in MS-Excel 2016 or higher and marked "FOR OFFICIAL USE ONLY". The cost estimate shall be separated by divisions arranged in the same manner as the specifications. Project estimates shall be assembled using PACES parametric cost engineering tool unless otherwise specified. Total project cost shall be the sum of each division's cost estimate and included as the first page of the cost estimates.
(d) The cost estimate shall be based on material prices (prevailing in the project locality), labor
(using the most current hourly Construction Wage Rates (AKA Davis-Bacon Act) citing the applicable date, type and number of wage rates from WDOL.gov), other direct costs (e.g., equipment, transportation, etc.), and shall include overhead, general and administrative expenses, profit, insurance, permits, taxes, labor burden, and bonds. The cost estimate shall be all inclusive with sufficient detail to include all distinct operations of work required, including material quantities, installed or provided equipment, hourly work estimates, and unit costs. Lump sum line items should not be used. Contingency costs should not be included with the exception of MILCON projects.
(e) The cost estimate must separately identify the work items and totals for each project and/or each additive or deductive item, as included in the project. If a design-build project, the estimated remaining design cost must also be stated.
(5) Design/Technical Analysis:
(a) The A-E shall submit design calculations and technical analysis at each required submission.
The design analysis is a written explanation of project design containing the design criteria and justification for the major material and systems selections and the basis for the costs used in preparing the cost estimate.
Architectural, civil, structural, mechanical, electrical, telecommunications, fire protection, planning, landscape, and energy/environmental work shall be identified and explained, appropriate to the level of design. The design/technical analysis will not be part of the project bid documents.
(b) Design analysis calculations and/or calculations shall be prepared by design professionals licensed to perform such work. Standard 8-1/2” X 11” computation forms shall be used. Calculations need not be typed, but must be clear and fully legible and shall incorporate all engineering calculations necessary to demonstrate the adequacy and safety of the proposed design. All designs shall be based on the criteria set forth in this Statement of Work and other standard practices or methods used in modern engineering design.
Engineering properties used and sources shall be listed. Computer design may be used provided the source program is stated and a professional engineer verifies its accuracy and appropriate use. The resulting design shall incorporate all engineering computations necessary for the complete project as proposed and shall include sketches, formulas, data sources and other information necessary to clearly express the designer's intentions and methods.
(c) Site Descriptions: Include earthwork calculations, site restrictions, utility connections, storm drainage, parking/paving, topography survey, soil tests/reports, landscape work, and other important topics.
(d) Architectural and Structural Descriptions: Include space relationships, accessibility accommodations, rationale for finish materials and interior design, roof type selection, sound attenuation design with supporting calculations, and design relationships to existing area facilities. Include structural calculations and design loads, seismic design considerations, soil boring data, foundation design loads, rationale for use of structural materials, and manufacturer’s catalogue data on materials and systems. Include building code and life safety design considerations.
(e) Mechanical and Plumbing Descriptions: Include HVAC load calculations, ductwork/piping sizing calculations, rationale for selection of one system over other systems, energy monitoring control system data, fire protection system explanation, and manufacturer’s catalogue data on materials, equipment, and systems.
(f) Electrical and Telecommunications Descriptions: Include load calculations, rationale for materials, fixtures, and lighting selection, system layout/arrangement, and manufacturer’s catalogue data on material and equipment. Include security system information.
(g) Fire Protection Descriptions: Include class of construction, occupancy, load calculations, summary of code and regulation requirements, explanation of systems used, and manufacturer’s catalogue data on material and equipment.
(h) Energy Conservation and Environmental Descriptions: Include consideration for solar and/or alternate energy use plus calculations for economic payback, consistent with Federal Life Cycle Cost Methodology and Procedures, 10 CFR, Part 436, Subpart A. Include information on hazardous material surveys, abatement, and concerns.
(6) Other Requirements:
(a) The A-E shall provide soil sampling, boundary or cadastral surveys, and other specialized services necessary to support a construction design or as otherwise ordered by the Contracting Officer.
Geotechnical borings for soil samples require a digging permit approved through the base where the digging shall occur. The A-E shall be responsible for completing an AF Form 103 dig request and submitting it to the appropriate CE Customer Service desk for coordination and approval. Allow 30 days from submittal of AF103 to receipt of an approved dig permit.
(b) The A-E shall provide a full Request for Proposal package, including a statement of work, bid schedule, and listing of submittals to be provided by the construction contractor for each project. The statement of work and bid schedule shall be written and saved using MS-Word 2016 or higher, and as directed or approved by the Contracting Officer. The listing of submittals shall use the Air Force Material Submittal Schedule format and be saved using MS-Excel 2016 or higher.
(d) Color Board Binder (Government Option): A-E submittal shall include 8.5” X 11” color boards enclosed in one binder and showing interior materials and colors associated with the project/facility being designed. The number of boards in the binder is dependent on the size and scope of the project or Task Order but typical project may have 2 or 3 boards to be able to show all the materials. Materials shall be the latest products produced with those specified in the design. The color boards shall be laid out to show the primary relationships of materials and colors. The room finish schedule shall be the primary reference for all materials and colors shown on the color boards. Materials’ manufacturer, product, and color name shall be stated on the front or back of the boards. Development of finish schedule and color boards shall include meeting with Using Agency and/or Base Architect to establish finish preferences and direction. Color boards shall be submitted in accordance with the requirements of the Task Order. Some Task Orders may include A-E providing more than one copy of the binder/color boards. Color boards may be returned to A-E after government review for revisions as required and then A- E shall resubmit revised boards.
(e) Color Rendering (Government Option): A-E submittal shall include an exterior or interior color perspective rendering showing the different architectural features, materials, and colors associated with the facility being designed. Submittal shall include two matching 11” X 17” (minimum size) high quality color hard copies printed on photo paper with mounting board and also electronic copies in .jpg format. The rendering shall be done in a medium that best presents the type of materials, construction, and design. The color rendering shall be developed to show the primary relationships of form, materials, and colors. The interior finish schedule shall be the primary reference for all materials and colors shown on an interior color rendering. The color rendering shall be submitted in accordance with the requirements of the Task Order.
(f) The A-E shall provide digital “before” photos of the project site. The photos will be in .jpg format and saved on a CD-ROM. The number and particulars of photos required will be determined with each Task Order. Photos will normally be limited to renovation projects.
(g) Internal Design Review Statement: A-E shall provide a signed letter at each submittal stating that all disciplines have reviewed and crosschecked the submittal documents and that all errors and omissions that were discovered have been corrected.
5. DESIGN CRITERIA:
a. The A-E shall prepare all design documents in conformance with the applicable portions of the latest editions of the following at the time of Task Order award. The most up to day UFC’s are located here:
https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc. Listed references may not be all inclusive, and it is the responsibility of the A-E to meet all government regulations:
(1) Air Force Engineering Technical Letters.
(2) Provisions for the physically handicapped will be included in accordance with the Architectural
Barriers Act.
(3) International Building Code, Life Safety Code NFPA 101 (and other NFPA codes), and other current national codes, regulations, and specifications involving the architectural, civil, mechanical, and electrical disciplines and associated crafts applicable to the design and construction of the project.
(4) National Electric Code.
(5) All seismic designs shall conform to the National Earthquake Hazard Reduction Program (NEHRP)
“Provisions for New Buildings and Other Structures”
(6) Unified Facilities Criteria (UFC)
(7) ASHRAE and ANSI Building Design Codes
(8) Nellis and Creech Installation Facility Standards (IFS)
(9) DoD Antiterrorism and Force Protection Standards
(10) All other DoD and USAF documents deemed applicable by the Contracting Officer or CENMP for each Task Order.
6. PRE-DESIGN RESPONSIBILITIES:
a. The Contracting Officer will notify the A-E when selected to do a specific Task Order. The notification will contain a project specific statement of work that will define the nature and scope of the work. The A-E will normally be requested to attend a pre-design conference to participate in discussions prior to preparation of a fee proposal and actual negotiations.
b. Negotiation meetings will be held either virtual, over the phone or in the Civil Engineering or Contracting
Officer's offices at Nellis AFB. The purpose of the negotiation meeting is to assure a mutual understanding between the A-E and the Government on the scope of the work, to set project schedules, and to reach an agreement on a fair and reasonable fee.
7. DESIGN SCHEDULE:
a. The A-E will be required to complete the design for each project and deliver the submittals to the Contracting Officer in accordance with the following design schedule. The performance period for each phase, in calendar days, will be indicated in each Task Order. All drawings and documents shall be provided electronically in Adobe Acrobat PDF format on CD-ROM and via a secure web service, as well as in hard copy format for 100% designs and upon request via Task Order. The Government may ask that all electronic submittals at all stages of design also include files in its editable native format. The number of paper copies and CD-ROMs of drawings and documents as well as deletions, additions, or changes to this schedule will be indicated with each Task Order:
(1) Concept Design and/or Planning Charrette Submittal: 15% Complete. (Government Option) A-E shall include the following but is not limited to:
(a) Site Plans: Utilize scale which shows building site, relation to adjacent structures, existing utilities, additional utilities required, and other major site features. Scales for site plans shall be sufficiently large to clearly delineate building location, topographical, utilities, streets, roads and parking, vegetation and https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc other pertinent data. Show all site amenities.
(b) Plans and Elevations: Shall portray general layout and interfacing features even if such features are not in the contract area. Equipment to be included in the project shall be accurately located and scaled.
All areas and equipment shall be identified. Areas shown on the floor plan but not included in the project shall be so designated by shading, outlining, or other clean concise means.
(c) Other Drawings: Shall depict the project accurately and shall show details that convey the intended appearance of the project. Detail references, notes, and material indications shall be sufficient to thoroughly describe and index the work. Exterior and/or interior elevations shall be submitted when the project involves work on such surfaces. Provide interior and exterior finish schedule, door schedule, and building sections.
(d) Scales: Shall be sufficiently large to clearly portray the work. Mechanical and electrical schematics shall be large enough so that relative features are proportionate and easily related to architectural plans and features.
(e) Structural/Mechanical/Electrical: Provide general layout of major systems, utility support, and major design features. Connection points and method of connection to existing utilities shall be shown. List of each discipline used in the project and approximate work scope.
(f) Communication Drawings: Telecommunication drawings/sheets, T-1 through T-(x) must be included. Show required spaces for installation of telecommunication systems. Basic OSP installation and routes and connection points.
(g) General Cost Estimate or Estimates if multiple courses of action (COA) required.
(h) List of Government Furnished Government Installed (GFGI) equipment and Government
Furnished Contractor Installed (GFCI) equipment.
(i) Color Rendering (Government Option)
(j) Design/Technical Analysis
(i) Problem Identification: Description of work and how the proposed design will meet the objective(s).
(ii) Site Description: Existing features and new work.
(iii) Architectural and Structural: Structural calculations including design loads;
Consideration for seismic design; Consideration for facility use by handicapped; Rationale for finish material and color selection; Rationale for roof type selection; Rationale for use of structural materials;
Design relationships to existing area facilities; Manufacturers catalog cuts on appropriate materials.
(iv) Mechanical: Heating and air conditioning load calculations; Ductwork/piping sizing calculations; Rationale for selection of system operation mode over other system modes; Rationale for selection of system materials and components; Corrosion control and cathodic protection procedures;
Energy monitoring control system capability; Type of control system; Facility ventilation requirements and rationale and description of system selected to provide required ventilation;
Description of system interconnection to fire protection system; Manufacturer’s catalog cuts on materials and equipment.
(v) Electrical: All facility load calculations; Rationale for selection of materials and fixtures;
Rationale for type of lighting selected; Manufacturer’s catalog cuts on material and equipment.
(vi) Communications Data and Analysis: Rationale for selection of system, material and devices.
(vii) Water Supply and Waste Treatment Systems: Type of occupancy; Rationale for type of systems installed.
(viii) Fire Protection System and Life Safety: Requirements as indicated in regulations; Single line drawing indicating arrangement of automatic sprinkler system, smoke and/or heat detectors, special extinguishing systems and alarm systems; Schedule of fire resistance ratings for fire walls, interior partitions and fire doors; An analysis of fire exit requirements and building code requirements.
(ix) Environmental Consideration
(x) Energy Conservation
(k) Review Conference (Government Option)
(l) Government Review Period (may vary by task order, but typically 14 days)
(2) Preliminary Design Submittal: 35% Complete. A-E shall include the following, but is not limited to:
(a) All required documents and information from previous submittal including list of previous review comments with A-E responses. Previous review comments incorporated into design as appropriate.
(b) Site Plans: All required controlling dimensions. Site plan showing proposed location of work including benchmarks, access from main roads, north arrow, bar scale, and surface or sub-surface drainage concepts. Utilize scale which shows building site, relation to adjacent structures, existing utilities, additional utilities required, and other major site civil features. Include profiles of pipelines. Scales for site plans shall be sufficiently large to clearly delineate building location, topographical, utilities, streets, roads and parking, vegetation and other pertinent data. Show new and existing site amenities. Show project location map, haul route and contractor’s storage site.
(c) Plans and Elevations: Floor plans with dimensions and functional arrangement of all areas;
including corridors, exits, stairs, and utility spaces properly related to exterior access, roads, parking, and service areas, etc. Individual treatment shall be given to items involving special design and/or deviations from accepted standards and of complex design. Gross floor areas shall be shown for each floor and for the entire building. Floor and roof framing, and loadings shall be indicated. Built-in, installed, and specialized portable equipment shall be indicated to scale. Pertinent information regarding fire prevention and safety requirements shall be shown. Design live and wind loads shall be shown. Elevations shall include story heights, penetration, and adaptation to finished grades at the site. All plans and elevations shall portray general layout and interfacing features even if such features are not in the contract area. Equipment to be included in the project shall be accurately located and scaled. All project areas and project systems and equipment shall be identified. Areas shown on the floor plan but not included in the project shall be so designated by shading, outlining, or other clean concise means.
(d) Other Drawings: Depict the project accurately and shall show sufficient detail to convey the intended appearance and work scope of the project. Detail references, notes, and material indications shall be sufficient to thoroughly describe and index the work. Exterior and/or interior elevations shall be submitted when the project involves work on such surfaces. Provide demolition drawings as required. Provide interior and exterior finish schedule and door and hardware schedule. Provide sections of structures, including framing, partitions, suspended ceilings, ducts, etc. Provide typical wall sections that show material and thickness, methods of attachment, type of windows, and relation thereof to supporting columns or walls.
Provide cover sheet and drawing sheet index.
(e) Scales: Shall be sufficiently large to clearly portray the work and include detailed schedules and legends appropriate to describe the design. Mechanical and electrical schematics shall be large enough so that relative features are proportionate and easily related to architectural plans and features. Hard copies shall be clearly readable. The use of redline schematics shall not be acceptable. Submission of drawings in the incorrect scale shall result in disapproval of the submittal.
(f) Structural, Mechanical, Plumbing, Fire Protection, and Electrical: Provide general layout of major systems, utility support, and major design features. Clearly show and describe project scope.
Connection points and method of connection to existing utilities shall be shown. Typical wall sections shall be shown at a scale of no less than 3/4 inch = 1 foot. Sections shall include material and thicknesses, methods of attachment, and type of windows with relation to supporting structural columns or walls.
(g) Telecommunications: Detail of all telecommunication space (sizes, heights, width, depths) shall be included. Telecommunications room entrance and backbone diagram shall be shown. Show specific details of all outside plant and inside plant routes and termination points (number, size, types of manholes, hand holes, pedestals, marked splices, number and size of conduits IAW the applicable codes.
(h) Heating, air conditioning, mechanical ventilation, plumbing, and special features such as elevators, hoists, and kitchen equipment: Indicate the location, capacity, and space requirements for all major items of mechanical equipment. Single line indication and riser diagrams of ducts, pipes, and equipment and their approximate location shall also be shown. Indication shall be made as to whether piping and duct work are exposed or concealed. Functional areas where pipes are exposed shall be delineated. Approximate operating range or capacity for heating, ventilation, air conditioning, and refrigeration equipment shall be clearly stated.
(i) Electrical Systems: Indicate lighting arrangements, type of fixtures proposed, general light intensities, special electrical requirements of the user, including communications and electronic facilities where applicable, light and power service entrance and distribution arrangement. Conduits, including those to be wired by others, shall be shown together with indication as to whether conduits are exposed.
Functional areas having exposed conduits shall be delineated. Riser diagrams, showing service equipment, feeders, and panels, other than branch circuits, shall be shown. Cable sizes, current demand factors and the switch and panel board descriptions are not required at this time. Location capacity and space requirements of all major items of equipment shall be shown including interior substations with service equipment and panels. Power, communication, and electronic features shall be indicated in sufficient detail to identify requirements clearly and to indicate the means of satisfying the requirements.
(j) Airfield Projects: In addition to the above, clearly show all existing pavement and new pavement. Indicate grading, drainage, soil profiles, foundation investigations, drainage structures, clear/approach zones, lateral clearances, joint details, tie-down anchor layout, and pavement markings.
(k) Hydrant Refueling Systems Projects: In addition to the above, clearly show the complete layout plan, mechanical details of pump houses, control rooms, tanks, and lateral control pits. Show relative elevations of refueling pump discharge, defueling pump, and profiles of laterals with elevations of refueling hydrant outlets. Indicate electrical layout, wiring diagrams, and size of transformers, cables, and circuit breakers.
(l) Bulk Petroleum, Oil, and Lubricant (POL) Facility Projects: In addition to the above, clearly show the complete layout plan, details of unloading header, pump and tank manifolds, relative elevations of unloading header, unloading pumps and bulk tanks, and profile of transfer line from bulk to operating storage. Indicate electrical layout, wiring diagrams, and size of transformers, cables, and circuit breakers.
(m) Specifications: Outline of specifications proposed for use
(n) Cost Estimate: Expanded and more detailed information from previous.
(o) Provide separate lists of all Government-furnished equipment to be installed by the contractor and equipment furnished and installed by the Government, if applicable.
(p) Design/Technical Analysis:
(i) Problem Identification: Description of work and how the proposed design will meet the objective(s).
(ii) Site Description: Earthwork calculations; New facility orientation; Description of project landscaping, vegetation, and trees; Any applicable site restrictions; Building utility connections to utility runs; Storm drainage (Calculations and materials rationale); Parking and paving;
Topographical survey; Soils test and reports.
(iii) Architectural and Structural: Space relationships and architectural configuration; All structural calculations including design loads; Consideration for seismic design; Consideration for facility use by handicapped; Rationale for finish material and color selection; Rationale for roof type selection; Sound attenuation design and supporting calculations; Soil boring data, foundation design loads; Rationale for use of structural materials; Design relationships to existing area facilities;
Manufacturers catalog cuts on appropriate materials.
(iv) Mechanical: Heating and air conditioning load calculations; Ductwork/piping sizing calculations; Rationale for selection of system operation mode over other system modes; Rationale for selection of system materials and components; Corrosion control and cathodic protection procedures;
Energy monitoring control system compatibility; Type of control system; Facility ventilation requirements and rationale and description of system selected to provide required ventilation;
Description of system interconnection to fire protection system; Manufacturer's catalog cuts on materials and equipment.
(v) Electrical: All facility load calculations; Rationale for selection of materials and fixtures;
Rationale for type of lighting selected; Provisions for communications; Manufacturer’s catalog cuts on material and equipment.
(vi) Communications Data and Analysis: Rationale for selection of system, material and devices; Manufacturer’s catalog cut sheets on equipment and materials.
(vii) Water Supply and Waste Treatment Systems: Type of occupancy; Rationale for type of systems installed; Interconnection to a central alarm panel; Special considerations.
(viii) Fire Protection System and Life Safety: Requirements as indicated in NFPA codes, UFC
3-600-01, UFC 4-021-01, and Nellis/Creech Fire Protection Standards; Single line drawing indicating arrangement of automatic sprinkler system, smoke and/or heat…