21R0203_Attachment A 17 - Deliverables.pdf
PDF 141 KB Posted
- Attached to
- Aviation Into-Plane Reimbursement (AIR) Card® Program Federal contract opportunity
- Solicitation number
- SPE608-21-R-0203
- Issued by
- Defense Logistics Agency Energy
About this file
This document outlines deliverables and due dates for an aviation fuel card program contract. Key deliverables include refund calculation and remittance reports, account setup and activation, training materials, a merchant acceptance plan and coverage list, personnel changes notifications, customer service reports, marketing plans, and quality assurance documentation. Major due dates include deliverables two months before the period of performance, quarterly and semi-annual reports, personnel change notifications ten days in advance, and annual plans and assessments. The related solicitation seeks an offeror to provide payment solutions and transaction processing services for Department of Defense and federal civilian customers utilizing aviation fuel and services worldwide through the Defense Logistics Agency Energy Fuel Card Program.
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AIR Card® Deliverables
Section Deliverable Frequency Due Date/Instructions Deliver to Refunds Refund Calculation Reports Quarterly 5th calendar day following fiscal reporting period PM and COR
Refunds Refund Remittance for Fuel Quarterly 2 business days following PM approval AIR Card® Fuel Refund Remittance Instruction
Refunds Refund Remittance for Ancillary Quarterly 2 business days following PM approval AIR Card® Ancillary Refunds Remittance Instruction
Refunds Refund Payment Confirmation Quarterly 2 business days following PM approval PM and COR
Transition Account Setup 2 months prior to start of the transactional period of performance.
PM, KO, and Government Test Group
Transition Account Activation Not earlier than the transactional period of performance.
AIR Card® EAS users
Transition Electronic Access System 2 months prior to start of the transactional period of performance.
PM, KO, and Government Test Group
Transition Data Transmission and Storage 2 months prior to start of the transactional period of performance.
PM, KO and Government Test Group
Transition Card Delivery 25 calendar days prior to transactional period of performance.
Account card shipping address or as specified by PM
Transition Training Materials 2 months prior to start of the transactional period of performance. Obtain PM approval prior to publishing training materials.
PM
Transition Training Sessions EAS training sessions
Upon PM request Contractor presents training of EAS functionality in person at customer facility, contractor facility or webinar as requested by PM
EAS users
Transition Payment and/or Card Acceptance Comprehensive list of merchant coverage
Upon PM request 90 calendar days after contract award the Contractor shall provide a comprehensive list of merchant coverage and (2) business days following PM request. The PM may revise the list content anytime during the performance period and the Contractor shall deliver the updated list within 3 business days.
When PM requests an updated list, during the contract performance period, the Contractor shall deliver within 2 business days.
PM
Transition Contractor Readiness Self-Assessments
Prior to the start of the transactional performance period.
Prior to start of transactional period of performance.
PM
KO approval
Transition Kick-Off Forum Presentation Packages Prior to the Kick-Off Forum Review by PM: 5 business days after notification of contract award.
Distribution: Day of AIR Card® Kick-Off Forum
PM
COR
Transition Post Contract Transition Upon KO written notice 6 months prior to the contract expiration date, Contractor provide phase-out services.
KO
Transition Contract Close-Out Requirements Expiration date of Contract, contractor shall deactivate/close all AIR Card® accounts.
PM
COR
KO
Purchase Solutions Purchase Solutions Contractor shall submit practical purchase solutions with proposal and during contract performance period.
PM
COR
Card Requirements AIR Card® Design Three sample card designs Final card design
Contractor shall revise upon PM request The Contractor shall submit three sample card designs 30 calendar days after contract award.
The final design due 60 calendar days after contract award for written PM approval.
PM
COR
Card Requirements Back Side of AIR Card® AIR Card® magnetic stripe layout
Upon PM request The Contractor shall provide the magnetic stripe layout within 1 business day
PM
Card Requirements Sample Card Requirements Sample card(s)
Upon PM request 1 business day Address provided by PM
Card Requirements Vanity Card Requirements Vanity card(s)
Upon PM request 1 business day Address provided by PM
Card Requirements Card Quality Assurance Quality assurance checks
Upon PM request The Contractor shall perform and pass pre-approved quality assurance checks on all AIR Cards® during contract performance period. Upon PM request, contractor shall provide detailed QA checks and results within 2 business days.
PM
Card Requirements Card Quality Assurance Plan
Upon PM request QA plan due 6 weeks after contract award. PM
Card Requirements Card Issuance and Delivery Upon approval of card request Same business day of approval As specified by the account/customer
Card Requirements Card Issuance and Delivery Test plan and successful results
Upon PM request The Contractor shall deliver the test plan with successful results that ensure the purchase tools are operational 2 months prior to start of performance period.
PM
COR
Card Requirements Card Packaging Card user guides are Issued with each card and upon customer request
Same business day when card approved or customer request
Same business day of card approval or customer request
PM approval due 2 months prior to contract performance period.
As specified by the account/customer
Customer Invoice Customer Invoice The Contractor shall generate an invoice at the end of each billing cycle.
Email invoices within 1 calendar day following end of billing cycle
Day and time contractor billing cycle ends
The Contractor shall email invoices to the customers that have selected this delivery method within 1 calendar day following end of billing cycle.
The Contractor shall provide the day and time the weekly billing cycle occurs.
As specified by the account/customer
Customer Invoice Customer Invoice Application of credits to customer account
Same billing cycle the credit is processed The Contractor shall apply all credits to customer account within the same billing cycle the credit is processed
Customer account
Customer Invoice Customer Invoice Draft of customer invoice Final customer invoice approved by PM
Draft due 1 month prior to start of contract performance period.
Revisions complete within 5 business days
The draft customer invoice is due 1 month prior to the start of the contract performance period.
Revisions requested by the PM shall be complete within 5 business days.
PM and PM approval
Delinquency Control Delinquency Control Delinquency balance report
Upon PM request Delinquency balances reported by BOS and account due 2 calendar days upon request from PM
PM
Delinquency Control Reconciliation Assistance Reconciliation assistance procedures
2 months prior to start of contract performance period
Reconciliation Assistance Procedures due 2 months prior to start of contract performance period.
Revisions due 25 calendar days prior to implementation for PM approval
14th business day after dispute initiation, unresolved dispute transaction charged back during the current billing cycle.
Contractor revisions due 25 calendar days prior to implementation for approval by
PM.
On the 14th business day following dispute initiation, unresolved disputed charged back during the current billing cycle. Email with dispute details to PM, COR.
Foreign Currency Conversion Foreign Currency Conversion Bank name and evidence of conversion rates
3 months prior to start of the contract performance period
3 business days upon PM request
The Contractor shall deliver the bank name and complete evidence of the conversion rates 3 months prior to the start of the contract performance period and within 3 business days upon PM request.
PM
Merchant Acceptance Merchant Acceptance Merchant recruitment upgrade plan
Upon PM request 90 calendar days after contract award
Merchant recruitment upgrade plan, 90 calendar days after contract award and as revised. Revisions shall be provided to PM with 5 business days.
PM
COR
Merchant Acceptance Merchant Acceptance Upload to transaction the merchant proper invoice documentation
24 hours of contractor receipt Upload merchant proper invoice documentation 24 hours of receipt
EAS
Merchant Acceptance Merchant Acceptance Comprehensive list of current global merchant coverage
30 calendar days after contract award
2 business day following PM request
Comprehensive list of current global merchant coverage 30 calendar days following contract award and 2 business days upon PM request
PM
COR
Merchant Acceptance Merchant Acceptance Merchant agreements and merchant onboarding packages
2 business days following PM request 30 calendar days after contract award
The Contractor shall provide merchant agreements and merchant onboarding packages to the PM for revising/approval 30 calendar days after contract award and 2 business days upon PM request.
PM
COR
Merchant Acceptance Price Reasonableness Plan 5 business days following PM revisions Contractor’s price reasonableness plan is due with proposal.
The Contractor shall implement the price reasonableness plan 5 business days following PM revisions.
PM
Contractor Personnel Replace Key Personnel Key personnel removed, resign, replaced, or reassigned permanently or temporarily
See Due Date/Instructions 10 business days before key personnel are removed, resign, replaced, or reassigned permanently or temporarily.
PM
KO
Contractor Personnel Replace Key Personnel Key personnel qualifications
Prior to filling key personnel role See Due Date/Instructions
Potential key personnel qualifications submitted for PM and KO approval.
Contractor Personnel Additional Contractor Personnel Support personnel resumes
Support personnel no longer support the program or contract.
Support personnel roster
See Due Date/Instructions
Contractor shall inform and provide support personnel resumes within 2 business days.
Contractor shall report when support personnel no longer support the contract within 2 business days.
Contractor shall provide an updated support personnel roster within 5 business days prior to contract performance period and 5 business days when new support personnel are assigned.
Customer Service Customer Service Report Due 4pm ET every Friday Customer Service Report containing customer service inquiries and resolutions.
Customer Service Customer Service Metrics Semi annual Contractor shall develop customer service metrics. Contractor shall implement PM or KO revisions within 30 business days.
Training Electronic Access System Training Conference attendance, training and marketing materials, tutorials, user guides
See Due Date/Instructions PM shall review/approve all Contractor conference attendance, training, marketing materials and methods 10 business days prior to training, distribution, and presentation. PM revisions to materials shall be made by Contractor within 2 business days and prior to usage.
EAS tutorials, user guides shall be reviewed and approved by PM prior to use and posting.
PM
COR
Training Training Conference training Presentation materials
PM request/PM approval See Due Date/Instructions
Contractor shall provide conference training only when requested by PM.
Presentation materials submitted to PM for approval 2 weeks prior to training date.
PM
COR
Marketing Marketing Plan Survey results Contract materials that reference the AIR Card® program Document summarizing contractor and industry discussions
See Due Date/Instructions Contractor marketing plan due 60 calendar days following start of contract performance period and 3 days following Contractor updates
Original unaltered survey results due 2 business days after Contractor receipt.
Contractor materials that reference the AIR Card® program shall be approved by PM prior to usage or distribution.
Document providing a detailed summarization of Contractor AIR Card® discussions at aviation industry tradeshows, merchant meetings delivered within 5 business days of event.
Tax Exempt and Tax Reclamation Tax Exempt Status Exemption documentation
1 business day following PM or KO request Contract shall distribute exemption documentation to merchant(s).
Applicable merchant
PM
Tax Exempt and Tax Reclamation Tax Reclamation Merchant documents
10 business day following PM or DLA Energy Tax team request
Contractor shall provide merchant documents within 10 business days. If merchant requires additional time to deliver documents, Contractor shall provide new delivery date to requestor (PM or DLA Energy tax team).
PM
DLA Energy Tax Team
Software Quality Assurance Quality Assurance Software quality defect report
2 business days following PM request and when defects are identified by Contractor
Software quality defect report due within 2 business days upon PM request and when contractor identifies defects.
PM
COR
Software Quality Assurance Test and Evaluation Master Plan See Due Date/Instructions Due 90 calendar days after contract award and every FY quarter. FY quarter due dates are the 5th calendar day of January, April, July and October.
PM
COR
Software Quality Assurance Defect Management Plan See Due Date/Instructions Defect Management Plan due 90 calendar days after contract award and then annually on the 15th calendar day of October.
Software Quality Assurance Web Application Security and Systems Security Vulnerabilities Test Plan
See Due Date/Instructions Test plan is due 90 calendar days after contract award and then annually on the 15th calendar day of October.
PM
COR
Software Quality Assurance Risk Mitigation Assistance Risk mitigation solution
See Due Date/Instructions Risk mitigation solution due 90 calendar days following contract award and 3 business days following PM request.
PM
KO
Continuity of Operations Continuity of Operations Contingency plan
With proposal and annually on June 30 Contingency Plan due with proposal and annually on June 30th.
PM
KO
Continuity of Operations Continuity of Operations Annual contingency test report
Annually on June 30 Annual Contingency Test Report due annually on June 30th.
PM
KO
Electronic Access System Data Dictionary See Due Date/Instructions Due 60 calendar days following the start of contract performance period.
Updates are due within 3 calendar days
PM
COR
Electronic Access System Available 24/7/365 The Contractor shall inform the PM 30 days in advance of system downtime.
Downtime for cases of routine maintenance or periodic upgrades. The Contractor shall post the downtime notice on the EAS dashboard 30 days in advance of downtime.
PM
COR
Electronic Access System Reporting (Standard) Standard reports due 3 months prior to the start of the contract performance period.
Report corrections due 5 business days following PM or KO notification.
Electronic Access System FBO Locator Due the first day of every December and June during the contract performance period. Contractor shall provide an email confirming accurate FBO locator information.
PM
COR
Electronic Access System FBO Locator Contractor shall post to the FBO locator the Canadian Bulletin and into-plane contracts/modifications the day received.
PM
COR
Electronic Access System FBO Locator Contractor email address due 60 days following contract award.
PM
COR
Electronic Access System FBO Locator Merchant discount plan
Upon PM request Merchant discount plan due 90 calendar days following contract award. Revisions complete within 5 business days.
PM
Transaction Authorizations Transaction Authorizations Transaction authorization controls, specifications, and merchant test plan
Upon PM request and upon Contractor updates.
Transaction authorization controls, specifications, and merchant test plan due 90 calendar days following contract award and updates due NLT 30 calendar day prior to contract performance period.
PM
Processing Transactions Processing Transactions Quality controls for manual transaction process
Upon PM request and upon Contractor updates.
Quality controls for manual transaction process due 30 calendar days prior to contract performance period. Contractor recommended updates due 5 business days prior to update for PM approval.
PM
Data and System Management Data Management
Refresh production data to the beta and training environments.
Technical architecture and infrastructure document(s)
Upon PM request and semi-annually.
Contractor shall propose semi-annual refresh schedule.
See Due Date/Instructions
Contractor refresh production data to beta and training environment semi-annually.
Contractor shall propose schedule.
Technical architecture and infrastructure document due 30 calendar days following contract performance period and 5 business days following updates.
Security Requirements Security Requirements Security plan, system security plan, contingency plan, vulnerability scan report, privacy impact assessment, PCI DSS Attestation, penetration test results, vulnerability scan results, security management plan, ROC, AOC
See Due Date/Instructions Security Plan, System Security Plan, Contingency Plan, Vulnerability Scan Report, Privacy Impact assessment due 90 days after contract award. Security Assessment Report and Penetration Test Report due 160 after contract award.
Security Plan due annually by December 15 Risk Assessment report due annually December 15 PCI DSS Attestation, penetration test results, vulnerability scan results, and security management plan due annually by December 15th
Contractor approved usage of service providers shall provide ROC or AOC annually by December 15th.
Security Requirements Security Requirements PCI DSS attestation of compliance PCI report of compliance and supporting artifacts
Upon PM request PCI DSS Attestation of Compliance due contract award.
PCI Report of Compliance and supporting artifacts due contract award and 5 business days following yearly completion
Security Requirements Personnel Security Governance Training, key and supporting personnel NDAs, data classification and data use policy
See Due Date/Instructions Contractor training due 30 calendar day of contract award. Revisions due within 5 business days.
Contractor key personnel and support personnel NDAs provided to PM prior to access to AIR Card® data and systems.
Data classification and data use policy due 30 calendar days of contract award.
PM
COR
KO
Product and Service Controls Product and Service Controls Aviation industry standardized product and service list and definitions.
Standardized aviation industry product/service codes
See Due Date/Instructions Aviation industry standardized product and service list and definitions due with proposal.
Standardized aviation industry product/service codes due with the proposal.
Updates due within 3 business days of industry change for PM approval.