21Q0246_Attachment_2_Specifications.pdf

PDF 76 KB Posted

Attached to
(4) Demineralizers Portsmouth Naval Shipyard (PNSY) in Kittery, Maine
Solicitation number
N3904021Q0246
Issued by

View the file

Other files

File Type Posted
21Q0246_Amendment 0002.pdf PDF
21Q0246_Amendment 0001.pdf PDF
21Q0246_Exhibit_A_Data Requirements.pdf PDF
21Q0246_Attachment_1_PWS.pdf PDF
21Q0246_1449_RFQ.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQ DOC NO. - 1053V000 REV1 ATTACHMENT ___2___

CONTINUATION SHEET CONTRACT NO. - _______________ PAGE _1_ OF _3_

NAME OF OFFER OR/CONTRACTOR

DEMINERALIZER 4 EA

C. DESCRIPTION/SPECIFICATIONS

C.1 DEMINERALIZER: 24 INCH SHIELDED PRESSURE VESSELS

ENCAPSULATED IN OVERPACK WITH LIFTING BASKET AND MEDIA.

C.1.1 DESIGN PRESSURE OF 150 PSI.

C.1.2 DESIGN TEMPERATURE 140OF.

C.1.3 DESIGN FLOW RATE 25 GPM.

C.2 THE DEMINERALIZER SHALL BE FURNISHED COMPLETE WITH 3.5

CUBIC FEET OF TYPE OL, 20 X 50 MESH, GRANULATED, ACTIVATED,

COAL BASED CHARCOAL.

C.2.1 EQUAL TO PITTSBURG ACTIVATED CARBON CO

SPECIFICATION SHEET PAC-5M-167-5 OR BARNEBY & SUTCLIFFE

CORPORATION TYPE 207A, 20 X 50 MESH COAL BASED CARBON,

ACTIVATED CARBON.

C.3 AND 3.5 CUBIC FEET OF RESIN EQUAL TO ROHM & HASS CO

AMBERLITE IRN-150 OR ENERGY SOLUTIONS, CN-300-100 ION

EXCHANGE RESIN.

C.4 THE CHARCOAL SHALL BE LOADED LAST SO THAT IT IS ABOVE THE

RESIN BED.

ITEM # SUPPLIES/SERVICES QTY U/I

C.5 HYDROSTATICALLY TEST DEMINERALIZER ASSEMBLY TO A

MINIMUM OF 150 PSIG FOR 30 MINUTES PRIOR TO INSTALLATION

INTO THE HIGH INTEGRITY CONTAINER (HIC).

C.5.1 ACCEPTANCE CRITERIA: NO VISABLE PERMANENT

DEFORMATION OF PRESSURE BOUNDRY PARTS.

C.5.2 NO LEAKAGE ALLOWED (EXCEPT TEST EQUIPMENT).

C.6 THE VENDOR SHALL PROVIDE WRITTEN STORAGE REQUIREMENTS

FOR THE AS SHIPPED CONDITION OF THE DEMINERALIZER AND HOW

TIME WILL AFFECT THE RESIN FOR THE FOLLOWING CONDITIONS;

AS SHIPPED, FILLED WITH WATER AND PARTIALLY DEWATERED

AFTER USE. ABSENCE OF THE DOCUMENTS LISTED ABOVE SHALL

BE CAUSE FOR REJECTION.

C.7 SEE STATEMENT OF WORK (ATTACHMENT (1)) FOR OTHER

SPECIFICATIONS AND REQUIREMENTS FOR THE DEMINERALIZER.

C.8 THE HIGH INTEGRITY CONTAINER (HIC) LIFTING BASKET MUST

MEET THE REQUIREMENTS OF NAVSEA 0989-030-7000, REV 11 (OR

LATER), LIFTING STANDARD.

C.8.1 THE LIFTING BASKET LIFTING POINTS (LOOPS) AND

SHACKLES MUST BE DESIGNED TO A SAFETY FACTOR OF 10:1 BASED

ON MATERIAL YIELD STRENGTH (MUST SUPPORT TEN TIMES THE

MAXIMUM GROSS WEIGHT, OR 25,000 LB).

C.8.2 LOAD TEST, LIFTING POINTS AND SHACKLES, TO 200% (+5%, -

0%) OF THE RATED LOAD IS REQUIRED, I.E. 5000 LBS - 5250 LBS (2

ATTACHMENTS CARRYING THE LOAD).

C.8.3 AFTER LOAD TESTING, EACH LIFTING POINT, THE AREA

SURROUNDING EACH LIFTING POINT, AND EACH SHACKLE MUST BE

MAGNETIC PARTICLE TESTED TO THE TESTING AND ACCEPTANCE

METHODS OF TECH PUB T9074-AS-GIB-010/271 (PROCEDURE NO. ES-C-

013).

C.8.4 THE MATERIAL COMPOSITION MUST MEET THE TECHNICAL

REQUIREMENTS OF FED. SPEC. RR-C-271 (GRADE A OR B) FOR

CARBON AND ALLOY STEEL OR ASTM A314 FOR STAINLESS STEEL.

C.8.5 SEE STATEMENT OF WORK (ATTACHMENT (1)) FOR OTHER

SPECIFICATIONS AND REQUIREMENTS FOR THE HIC.

C.9 DATA REQUIREMENTS PER EXHIBIT A (DD-1423) & ATTCHMENT #1

C.9.1 CERTIFICATION OF HYDROSTATIC TEST; EXHIBIT A SEQUENCE

A001.

C.9.2 CERTIFICATION OF COMPLIANCE FOR SAFETY FACTOR OF

10:1; EXHIBIT A SEQUENCE A002.

C.9.3 CERTIFICATION OF LOAD TEST, LIFTING POINTS; EXHIBIT A

SEQUENCE A003.

C.9.4 CERTIFICATION OF LOAD TEST, SHACKLES; EXHIBIT A

SEQUENCE A004.

C.9.5 CERTIFICATION OF MAGNETIC PARTICLE TEST, LIFTING

POINT; EXHIBIT A SEQUENCE A005.

C.9.6 CERTIFICATION OF MAGNETIC PARTICLE TEST, AREA

AROUND LIFTING POINT; EXHIBIT A SEQUENCE A006.

C.9.7 CERTIFICATION OF MAGNETIC PARTICLE TEST, EACH

SHACKLE; EXHIBIT A SEQUENCE A007.

C.9.8 CERTIFICATION OF MATERIAL COMPOSTION, RR-C-271 (GRADE

A OR B) OR ASTM A314; EXHIBIT A SEQUENCE A008.

D. PACKING/PACKAGING/MARKING

D.1 CERTIFICATIONS OF COMPLIANCE AND ALL ASSOCIATED

PAPERWORK SHALL BE PLACED INSIDE THE PACKAGING OF THE

DEMINERAIZER AND HIC LIFT BASKET.