8-2025 ADA Curb Ramp Project BT-26WX 1756231669.2768633.pdf

PDF 176 KB Posted

Attached to
2025 ADA Curb Ramp Project
Solicitation number
US.195932
Issued by
Dauphin County, Pennside CDP, Pennsylvania

View the file

Other files

File Type Posted
6-Proposal Contract.pdf PDF
5-MS944 Anti-Collusion Aff.pdf PDF
2-BID BOND.pdf PDF
4-Attach 1A Special Prov.pdf PDF
3-Workmens Comp Aff.pdf PDF
1-Employment Verification.pdf PDF
7-Paxtang Borough 2025 ADA Curb Ramp Project.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2025 ADA Curb Ramp Project (BT-26WX)

Legend

The green cells with bolded numbers indicate that this bid was the lowest price.

The orange cells indicate that this item from that vendor was selected.

The green cells with orange outline indicate that this item from that vendor was selected, and has the lowest price.

$ 123

Total Cost

Selected #

Selected ($)

# Locked Items Selected Lowest UnitofMeasure QuantityRequired UnitPrice TotalCost

#1-1 FALSE Mobilization and demobilization including bonds and insurances$ 0 $ 5,000.0 LS 1 $ 12,500.0 $ 12,500.0

#1-2 FALSE Work zone traffic control$ 0 $ 0 LS 1 $ 2,400.0 $ 2,400.0

#1-3 FALSE Concrete curb, complete in place$ 0 $ 16,740.0 LF 180 $ 220 $ 39,600.0

#1-4 FALSE Concrete sidewalk, complete in place$ 0 $ 21,800.0 SF 1090 $ 32 $ 34,880.0

#1-5 FALSE Detectable warning surface (DWS), complete in place$ 0 $ 2,400.0 SF 96 $ 170 $ 16,320.0

#2-1 FALSE Work zone traffic control$ 0 $ 0 LS 1 $ 800 $ 800

#2-2 FALSE Concrete curb, complete in place$ 0 $ 6,510.0 LF 70 $ 220 $ 15,400.0

#2-3 FALSE Concrete sidewalk, complete in place$ 0 $ 6,800.0 SF 340 $ 32 $ 10,880.0

#2-4 FALSE Detectable warning surface (DWS), complete in place$ 0 $ 1,000.0 SF 40 $ 185 $ 7,400.0

#3-1 FALSE Work zone traffic control$ 0 $ 0 LS 1 $ 800 $ 800

#3-2 FALSE Concrete sidewalk, complete in place$ 0 $ 4,600.0 SF 230 $ 40 $ 9,200.0

#3-3 FALSE Detectable warning surface (DWS), complete in place$ 0 $ 400 SF 16 $ 250 $ 4,000.0

#4-1 FALSE Work zone traffic control$ 0 $ 0 LS 1 $ 800 $ 800

#4-2 FALSE Concrete curb, complete in place$ 0 $ 3,720.0 LF 40 $ 230 $ 9,200.0

#4-3 FALSE Concrete sidewalk, complete in place$ 0 $ 5,200.0 SF 260 $ 42 $ 10,920.0

#4-4 FALSE Concrete cheekwall, complete in place$ 0 $ 800 LF 20 $ 150 $ 3,000.0

#4-5 FALSE Detectable warning surface (DWS), complete in place$ 0 $ 600 SF 24 $ 200 $ 4,800.0

Base Bid Pricing (5)

Alternate Bid No. 1 (4)

Alternate Bid No. 2 (3)

Alternate Bid No. 3 (5)

$ 0

$ 182,900.0

Construction Masters Services, LLC

UnitPrice TotalCost UnitPrice TotalCost UnitPrice TotalCost UnitPrice TotalCost UnitPrice

$ 15,000.0 $ 15,000.0 $ 14,088.0 $ 14,088.0 $ 10,000.0 $ 10,000.0 $ 7,100.0 $ 7,100.0 $ 15,000.0

$ 1,500.0 $ 1,500.0 $ 775 $ 775 $ 1,000.0 $ 1,000.0 $ 10,800.0 $ 10,800.0 $ 500

$ 145 $ 26,100.0 $ 93 $ 16,740.0 $ 160 $ 28,800.0 $ 215 $ 38,700.0 $ 107

$ 25 $ 27,250.0 $ 36.5 $ 39,785.0 $ 26 $ 28,340.0 $ 35 $ 38,150.0 $ 20.5

$ 45 $ 4,320.0 $ 55.53 $ 5,330.88 $ 70 $ 6,720.0 $ 35.5 $ 3,408.0 $ 28.5

$ 1,200.0 $ 1,200.0 $ 575 $ 575 $ 1,000.0 $ 1,000.0 $ 8,650.0 $ 8,650.0 $ 950

$ 145 $ 10,150.0 $ 93 $ 6,510.0 $ 165 $ 11,550.0 $ 230 $ 16,100.0 $ 125

$ 25 $ 8,500.0 $ 36.5 $ 12,410.0 $ 27 $ 9,180.0 $ 55.5 $ 18,870.0 $ 35

$ 45 $ 1,800.0 $ 55.53 $ 2,221.2 $ 45 $ 1,800.0 $ 35.5 $ 1,420.0 $ 28.5

$ 1,300.0 $ 1,300.0 $ 575 $ 575 $ 1,000.0 $ 1,000.0 $ 1,450.0 $ 1,450.0 $ 100

$ 25 $ 5,750.0 $ 36.5 $ 8,395.0 $ 34 $ 7,820.0 $ 59 $ 13,570.0 $ 35

$ 45 $ 720 $ 55.53 $ 888.48 $ 45 $ 720 $ 35.5 $ 568.0 $ 28.5

$ 1,200.0 $ 1,200.0 $ 575 $ 575 $ 1,000.0 $ 1,000.0 $ 1,150.0 $ 1,150.0 $ 1,400.0

$ 145 $ 5,800.0 $ 93 $ 3,720.0 $ 175 $ 7,000.0 $ 217 $ 8,680.0 $ 125

$ 25 $ 6,500.0 $ 36.5 $ 9,490.0 $ 28 $ 7,280.0 $ 47 $ 12,220.0 $ 35

$ 90 $ 1,800.0 $ 136.16 $ 2,723.2 $ 160 $ 3,200.0 $ 70 $ 1,400.0 $ 115

$ 45 $ 1,080.0 $ 55.53 $ 1,332.72 $ 45 $ 1,080.0 $ 35.5 $ 852.0 $ 28.5

$ 0 $ 0 $ 0 $ 0 $ 0

0 0 0 0

Mid-State Paving, LLC

$ 119,970.0 $ 126,134.48 $ 127,490.0 $ 183,088.0 $ 109,671.0

Doug Lamb Construction, Inc.Final Grade Excavation, LLC JVI Group INC Kinsley Construction Site York

TotalCost UnitPrice TotalCost UnitPrice TotalCost

$ 15,000.0 $ 5,000.0 $ 5,000.0 $ 8,000.0 $ 8,000.0

$ 500 $ 2,500.0 $ 2,500.0 $ 0 $ 0

$ 19,260.0 $ 150 $ 27,000.0 $ 100 $ 18,000.0

$ 22,345.0 $ 22.5 $ 24,525.0 $ 20 $ 21,800.0

$ 2,736.0 $ 50 $ 4,800.0 $ 25 $ 2,400.0

$ 950 $ 1,250.0 $ 1,250.0 $ 0 $ 0

$ 8,750.0 $ 175 $ 12,250.0 $ 100 $ 7,000.0

$ 11,900.0 $ 30 $ 10,200.0 $ 20 $ 6,800.0

$ 1,140.0 $ 50 $ 2,000.0 $ 25 $ 1,000.0

$ 100 $ 1,250.0 $ 1,250.0 $ 0 $ 0

$ 8,050.0 $ 30 $ 6,900.0 $ 20 $ 4,600.0

$ 456.0 $ 50 $ 800 $ 25 $ 400

$ 1,400.0 $ 1,250.0 $ 1,250.0 $ 0 $ 0

$ 5,000.0 $ 175 $ 7,000.0 $ 100 $ 4,000.0

$ 9,100.0 $ 30 $ 7,800.0 $ 20 $ 5,200.0

$ 2,300.0 $ 150 $ 3,000.0 $ 40 $ 800

$ 684.0 $ 50 $ 1,200.0 $ 25 $ 600

0 0 0

$ 0 $ 0 $ 0

Mid-State Paving, LLCPorter Construction LLC & ConcretePro’s Concrete

$ 109,671.0 $ 118,725.0 $ 80,600.0

Legend
Sheet 1

File details come from the government source that posted it. Updated .