2121291PMW098_SOW.DOC
DOC document 119 KB Posted
- Attached to
- Metal Utility Shed
- Solicitation number
- 70Z02921QPMW09800
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF18_REQUEST FOR QUOTATION.pdf | ||
| 2121291PMW098_SOW.DOC | DOC document | |
| SF18_REQUEST FOR QUOTATION.pdf | ||
| 2121291PMW098_WDOL.txt | TXT text file | |
| OF336_Continuation Sheet.pdf | ||
| Construction Clauses Provisions FAC 2021-04.doc | DOC document | |
| SF18_REQUEST FOR QUOTATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work Replacement of Metal Utility Shed at USCG ANT Colfax, LA
1.0 General
1.1 Scope: The scope of work for this project includes the removal and replacement of ANT Colfax’ metal utility shed. The contractor shall provide all labor and equipment to accomplish the scope of this work.
1.2 Location of Site: U.S. Coast Guard ANT Colfax is located at:
350 Control House Rd.
Colfax, LA 71417
1.3 Examination of Site: It is recommended that bidders carefully inspect the work in place and verify the amount of work necessary to complete the job. Prospective bidders may arrange for a conducted tour of the job site by calling the point of contact (Petty Officer Dedinsky, telephone, (318) 627-2783, at least 3 working days in advance.
1.4 Availability of Utilities: Water and electric are available in reasonable quantities at the site.
1.5 Contractor Use of Premises: The Contractor will be working on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the Contracting Officer’s Representative (COR).
1.6 Storage Area: The Contractor will be provided a storage area in a location determined by the COR. The Contractor shall be responsible for restoring the area to its original condition at the completion of work. The Contractor shall be responsible for protecting materials stockpiled against weather, damage, theft, and other risk of loss.
1.7 Clean Up: The Contractor shall keep the work area, including the storage area, free from accumulation of waste materials and comply with all federal, state and local regulations pertaining to the storage, transport and disposal of wastes.
1.8 Final Inspection and Acceptance: When the work is complete and ready for final inspection submit a written request 5 days prior final inspection to the Contracting Officer.
1.9 Warranties: All warranties and/or guarantees, either implied or expressed, for individual equipment shall be endorsed to the Government.
1.10 Storm Protection: Should warnings of wind of gale force or stronger be issued, the contractor shall take every practicable precaution to minimize danger to persons, the work and adjacent property. Precautions shall include, but not be limited to, closing all openings, removing all loose materials, tools and equipment from exposed locations, and removing or securing temporary work.
1.11 Underground and Concealed Utilities: Upon conclusion of the project, contractor will ensure utilities are in the same condition as before work was started.
1.12 Utility Outages: Before interrupting or shutting down any utility, make a request for the interruption to the COR at least two (2) working days before anticipated interruption. Identify utility, reason for interruption, proposed time of interruption, and duration of interruption.
2.0 Removal of Old Shed
2.1 The Contractor shall remove all debris, materials pertaining to the remains of the old shed. Contractor shall sweep parking lot and area for any metal nails, screws or hardware that could be a hazard to personnel or equipment. Contractor shall use a rolling magnet to pick up any roofing screws or nails.
2.2 Disposal of Old Shed: The Contractor shall dispose of the old shed off Government property and in accordance with all federal, state, and local regulations.
3.0 Installation of New Shed
3.1 The Contractor shall install a replacement metal shed 26’L x 20’W x 13’H. The new shed shall be installed in same location as the old shed. Shed is to be insulated inside with a 12’W x 12’H Mechanical Roll up door and a walk-in door 36” x 80”. Contractor shall install the shed on the government’s property. The COR will provide guidance on the exact location for the shed and the limits of the government’s property.
3.2
3.3
4.0 Execution
4.1 Installation of new shed shall be in accordance with the manufacturer’s specifications.
4.2 Removal of Debris/Material: The Contractor shall clear any interferences or debris to enable the safe installation of new shed.
4.3 Reinforcement: The Contractor shall install anchors to affix to concrete surface. Contractor shall follow the manufacturer’s guidelines to ensure structure is anchored down properly. Structure shall have a Hurricane rating of 140 mph or higher + 30 PSF.
4.4 Fabric: The Company installing will use the material in accordance with approved estimate. Metal Framing Gauge 14 or higher shall be used.
4.5 Ground Clearance: The bottom of the frame shall be anchored and not protrude onto any adjacent soil or soft ground.
4.9 Flashing: Install Roof Flashing IAW Manufacturer’s specifications.
4.10 Utility Lines: Protect existing utility lines. Notify COR immediately of damage to or an encounter with an unknown existing utility line. The contractor shall ensure upon completion of the project that all utilities are in the same condition as before commencing work.