20R0016-DB_Picayne_Strand_SPECS_V2_30APR20.pdf
PDF 5 MB Posted
- Attached to
- PICAYUNE STRAND RESTORATION PROJECT, US41 AND CR92 CONVEYANCE FEATURES, DESIGN-BUILD CONTRACT
- Solicitation number
- W912EP20R0016
About this file
This document outlines a federal design-build contract opportunity for the Picayune Strand Restoration Project in Collier County, Florida. The principal work includes constructing new culverts under US Route 41 and County Road 92 to provide hydraulic connectivity. A pre-proposal teleconference will be held on May 14, 2020. The solicitation number is W912EP20R0016. Proposals are due by June 1, 2020 for the total small business set-aside contract valued between $5-10 million. The period of performance is 1,080 calendar days from notice to proceed. The North Atlantic Division of the U.S. Army Corps of Engineers and Florida Department of Transportation are the federal agencies involved. Interested parties must register on Sam.Beta.Gov to receive any amendments to the forthcoming request for proposal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912EP20R0016 Picayune Strand Pre Proposal Attendees List.xlsx | XLSX spreadsheet | |
| W912EP20R0016 Picayune Strand Pre Proposal Attendees List.xlsx | XLSX spreadsheet | |
| W912EP20R0016-0001A.pdf | ||
| 20R0016-DB_Picayne_Strand_Solicitation_V1_30APR20.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EP20R0016
Jacksonville District
Design-Build for Picayune Strand Conveyance Features
Collier County, Florida
Construction Solicitation and Specifications Volume 2 of 2
See Volume 1 of 2 for issue date 30 April 2020
Picayune Strand Conveyance Features W912EP20R0016 Collier County, Florida
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 33 50 WEATHER AND WATER STAGE DATA
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 22 00 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 16 DESIGN AFTER AWARD
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04 CONTRACTOR QUALITY CONTROL
01 50 02 TEMPORARY CONSTRUCTION FACILITIES
01 52 10 CONTRACTING OFFICER'S FIELD OFFICE
01 57 20 ENVIRONMENTAL PROTECTION
01 57 25 TURBIDITY MONITORING
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 02 CLOSEOUT SUBMITTALS
01 90 00 ATTACHMENT A
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 33 50
WEATHER AND WATER STAGE DATA
PART 1 GENERAL
1.1 Water stage and weather data
-- End of Section Table of Contents --
DOCUMENT 00 33 50 Page 1
SECTION 00 33 50
WEATHER AND WATER STAGE DATA
PART 1 GENERAL
1.1 Water stage and weather data
1. The project area for Picayune Strand Conveyance Features is in Collier County in the vicinity of existing US Route 41 (US41) and existing County Road 92 (CR92/San Marco Drive) as indicated in the Plans and Specifications.
2. Water stages in the project area are mainly affected by rainfall, runoff, evapotranspiration, and groundwater flow.
3. Do not expect that water levels/flows will be manipulated for contractor. Do not expect no flow or dry conditions during the contract period. Obtain hydrometeorological data from the Jacksonville District, Water Management Section's website, which can be found at https://www.saj.usace.army.mil/waterManagement/ and also the SFWMD's website which can be found at https://www.sfwmd.gov/
4. Water levels and flows in the project area may change suddenly. There may be extended periods of high flows during the contract period, depending on hydrometeorologic conditions.
5. Obtain information concerning rain and wind. Reference is made to the National Oceanic and Atmospheric Administration (NOAA) publication entitled Local Climatological Data - Monthly Summary, which contains climatological and meteorological observations and data, including wind, rain, and temperature data. Subscription price and ordering information is available from the National Centers for Environmental Information, Federal Plaza, 151 Patton Avenue, Asheville, North Carolina 28801-5001.
NOAA also has an internet information page at: https://www.ncdc.noaa.gov/
6. The climate of the project area is essentially subtropical and humid.
Temperatures below freezing are rare. The wet season is from May through October. The hurricane season is from June through November. In general, the winter months constitute the dry season, and rainfall is usually associated with mid-latitude systems (fronts and low-pressure systems) and is distributed in a spatially uniform pattern. The summer months comprise the wet season and rainfall is closely associated with convective activity. These rainfall events are normally of short duration, and amounts are quite variable spatially. The project site is subject to tropical storms and hurricanes from June through November, and to windy and/or rainy weather throughout the year. Weather forecasts as well as actual rainfall information from the National Weather Service Miami South Florida forecast office can be found at: https://www.weather.gov/mfl/.
7. The following data are provided:
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS
BASED ON 5-DAY WORK WEEK
The average number of work days in each calendar month with precipitation
DOCUMENT 00 33 50 Page 2 greater than or equal to 0.10 inches is provided for the project area in the below table. This information is based on data obtained from Station NAPLES located at latitude: 26.1686 and longitude: -81.7158.
Average Number of Days per Month With Precipitation >= 0.10 Inches
Station Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
NAPLES 2 3 2 2 4 8 9 10 9 4 2 2
The data was obtained from Climatography of the United States No. 20 Monthly Station Climate Summaries for Florida, published by the National Climatic Data Center, NOAA, for the period of record 1981-2010. The values in this table have been rounded to the nearest whole number.
-- End of Section --
DOCUMENT 00 33 50 Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.2.3 Safety Requirements
1.2.4 Design-Build Project Scope
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
1.5 PHYSICAL DATA
1.5.1 Contractor Investigation
1.6 LAYOUT OF WORK
1.7 EXISTING WORK
1.8 DAMAGE TO WORK
1.9 LOCATION OF UNDERGROUND FACILITIES
1.9.1 Notification Prior to Excavation
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
1.10.1 Schedule of Monthly Anticipated Adverse Weather Delays
1.10.2 Contractor Responsibility
1.11 UNITS OF MEASURE
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The principal intent of this project is to provide hydraulic connectivity through the addition of new culverts under or adjacent to existing US Route 41 (US41) and existing County Road 92 (CR92/San Marco Dr.) in Collier County. See Attachment A for a detailed project description.
1.2.2 Location
The project is located in Collier County, Florida. See Exhibit A of the Attachment A for the location map.
1.2.3 Safety Requirements
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1 .
1.2.4 Design-Build Project Scope
The Design-Build Project Scope is provided in Attachment A.
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
Read this paragraph in conjunction with the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
Refer to the Clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.5 PHYSICAL DATA
Read this paragraph in conjunction with the Clause PHYSICAL DATA (FAR 52.236-4) of Section 00700 CONTRACT CLAUSES in Volume 1.
SECTION 01 11 00 Page 2
1.5.1 Contractor Investigation
Refer to the Clause SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (FAR 52.236-3) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6 LAYOUT OF WORK
Read this paragraph in conjunction with the Clause LAYOUT OF WORK (FAR 52.236-17) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.7 EXISTING WORK
In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, return existing work in a condition equal to or better than that which existed before new work started.
1.8 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work shall be as set forth in Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES in Volume 1. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such work, an equitable adjustment pursuant to Clause CHANGES of Section 00700 CONTRACT CLAUSES in Volume 1 will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or job prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
1.9 LOCATION OF UNDERGROUND FACILITIES
Obtain digging permits prior to start of excavation by calling 811, 15 calendar days in advance. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be installed.
1.9.1 Notification Prior to Excavation
Notify the Contracting Officer at least 7 days prior to starting excavation work. Contractor is responsible for locating and marking all unmarked utilities.
SECTION 01 11 00 Page 3
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Clause DEFAULT (FIXED-PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
1.10.1 Schedule of Monthly Anticipated Adverse Weather Delays
See section 00 33 50 WEATHER AND WATER STAGE DATA for a schedule of Monthly Anticipated Weather Delays.
1.10.2 Contractor Responsibility
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the Contract, record on the daily Contractor Quality Control (CQC) report the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the Contractor's schedule of monthly anticipated adverse weather delays (rounded to the nearest whole number), the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Clause DEFAULT (FIXED PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.11 UNITS OF MEASURE
The standard U.S. system shall be utilized by the Contractor in the performance of his work. All survey records, official documentation, engineering data, and all correspondence, including any submittals and shop drawings, must clearly denote which system of measure is being utilized, referenced or discussed. Any omission, unprofessional or inaccurate use of a unit of measure on the part of the Contractor will not relieve the Contractor of their responsibilities under the contract terms. The unit of measure used in this specification is the standard U.S. system. The contract drawings denote standard U.S. system. If no unit of measure is indicated on the drawing such as on ranges, stations, slope elevations, and distance numbers, then they are to be considered the standard U.S. system.
SECTION 01 11 00 Page 4
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 11 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
b. All work shall be coordinated with the Florida Department of Transportation or Collier County, as applicable.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
1.2.2 Instructions
1.3 SUBMITTALS
1.4 JOB PAYMENT ITEMS
1.4.1 Design (Line Item 0001)
1.4.2 Construction of County Road 92 Culvert (Line Item 0002)
1.4.3 Construction of US 41 Culvert (Line Item 0003)
1.4.4 Construction of Tamiami Trail Canal Culvert (Line Item 0004)
1.4.5 Environmental Species Monitoring (Line Item 0005)
1.4.6 Liability Insurance Policy (Line Item 0008)
1.5 UNIT PRICE PAYMENT ITEMS
1.5.1 Contracting Officer's Field Office (Line Item 0006)
1.5.1.1 Payment
1.5.1.2 Measurement
1.5.1.3 Unit of Measure
1.5.2 Partnering Regroup (Line Item 0007)
1.5.2.1 Payment
1.5.2.2 Measurement
1.5.2.3 Unit of Measure
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
3.1.1 Requesting Progress Payment
3.1.2 Options and Modification CLINS
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.
Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved. Unless there is a specific Line Item for administrative costs, such as Quality Control and Safety, allocate such costs proportionally across all Line Items.
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
The terms Contract Line Item Number (CLIN) and Line Item are interchangeable herein (e.g.: CLIN 0001 is Line Item 0001). The term CLIN is a contracting term used in the Resident Management System (RMS) payment data base.
1.2.2 Instructions
See Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for more information on CLINs, schedule of values of pay activities and construction schedule, and payment procedures. The Contractor mode user manual with in-depth instructions can be downloaded from the RMS web site indicated in Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE
(RMS CM).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittal the following items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
Schedule of Values ; G, RO
SD-07 Certificates
Request for Progress Payment ; G, RO
SECTION 01 22 00 Page 2
1.4 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE with the unit JOB and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
Progress payments for job CLINs will be made in accordance with the Payments Under Fixed-Price Construction Contracts clause of Section 00700 CONTRACT CLAUSES in Volume 1. Submit Schedule of Values for Government approval with the baseline schedule submittal (see Section 01 32 01 PROJECT SCHEDULE). Include a list of pay activities to breakdown bid for each job CLIN as part of the RMS Schedule. Schedule of Values will become basis for CLIN and Pay Activity data in the RMS payment data base. An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, take into account the amount reserved for contract payments when preparing the construction schedule.
1.4.1 Design (Line Item 0001)
Payment for this CLIN includes work associated with Design, Design Data Collection, Preparation of all Professional Work Products for all design submittals, Permit preparation, Permit application submittal including all filing fees, as well as all Professional Engineering, Geotechnical, Land Surveyor, and other professional services required during construction.
It includes the Professional services of the Design Quality Control Manager. It includes any and all testing required to support the development of the design.
1.4.2 Construction of County Road 92 Culvert (Line Item 0002)
Payment will be made for all costs associated with and incidental to the construction of the culvert structure under CR92. It includes maintenance of traffic, culvert construction, utility relocation, reconstruction of the roadway fill, subbase, base, and paving, and all other activities necessary to construct the culvert.
1.4.3 Construction of US 41 Culvert (Line Item 0003)
Payment will be made for all costs associated with and incidental to construction of the three culvert structures under US41. It includes maintenance of traffic, culvert construction, utility relocation, reconstruction of the roadway fill, subbase, base, and paving, and all other activities necessary to construct the culverts.
1.4.4 Construction of Tamiami Trail Canal Culvert (Line Item 0004)
Payment will be made for all costs associated with and incidental to construction of the culvert structure in the Tamiami Trail Canal at the private driveway. It includes maintenance of traffic, culvert
SECTION 01 22 00 Page 3 construction, utility relocation, reconstruction of the private drive, coordination with the adjacent residents, and all other activities necessary to construct the culvert.
1.4.5 Environmental Species Monitoring (Line Item 0005)
Payment will be made for costs associated with and incidental to endangered or protected species monitoring. See Section 01 57 20
ENVIRONMENTAL PROTECTION.
1.4.6 Liability Insurance Policy (Line Item 0008)
Payment will be made for costs associated with the complete liability insurance policy. This policy must meet all the requirements of FAR 52.228-5 in Section 00700 CONTRACT CLAUSES and Section 00800 SPECIAL
CONTRACT REQUIREMENTS.
1.5 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
Each Unit Price CLIN may be a single pay activity item or may be broken down into pay activities with smaller quantities equal to CLIN total.
Contract unit price multiplied by agreed quantity is full compensation.
1.5.1 Contracting Officer's Field Office (Line Item 0006)
Payment will be made for costs associated with and incidental to providing, maintaining, and final disposition of the Contracting Officer's field office including all costs for rent and provision of all services indicated in Section 01 50 02 TEMPORARY CONTRUCTION FACILITIES and Section 01 52 10 CONTRACTING OFFICER'S FIELD OFFICE. Costs for such provision and maintenance of the Contractor's own field office and other facilities will not be paid for under this line item. For purposes of bidding, Contractor shall assume the amount of time that the Contracting Officer's space in the Contractor's field office is available to the Government within the period of performance of the contract.
1.5.1.1 Payment
Payment will be made for costs associated with or incidental to providing and maintaining the Contracting Officer's Field Office space as described in Section 01 52 10 CONTRACTING OFFICER'S FIELD OFFICE.
1.5.1.2 Measurement
Payment for the Contracting Officer's Field Office will be made at the contract unit price per month.
1.5.1.3 Unit of Measure
Month.
SECTION 01 22 00 Page 4
1.5.2 Partnering Regroup (Line Item 0007)
1.5.2.1 Payment
Payment will be made for costs associated with or incidental to conducting a partnering regroup. See Section 01 30 00 ADMINISTRATIVE PROCEDURES.
The initial partnering meeting will not be paid for under this line item as it is a distributed cost mandatory action item.
1.5.2.2 Measurement
The basis for payment will be for the completion of each partnering regroup meeting and Government receipt of all completed work products.
1.5.2.3 Unit of Measure
Each.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
Upon receiving initial Resident Management System import file, go to PAY ACTIVITIES and establish a link between bid breakdown schedule of values of PAY ACTIVITIES to contract CLINs using SCHEDULE ACTIVITIES data entry page.
3.1.1 Requesting Progress Payment
For progress payments, ensure ACTIVITY SCHEDULE, FEATURE SCHEDULE, submittal register, and punchlists are all up to date. Use PROGRESS PAYMENTS to REQUREST ACTIVITY for both ACTIVITY EARNINGS data entry page and OTHER EARNING. Provide hard copies of supporting invoices and quantity measurements to support all requested earnings. Ensure that sums of payment activities do not exceed contract award CLIN funding amounts, or unbalanced CLINs error will prevent processing the payment. Submit a request for progress payment monthly in accordance with Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS of Section 00700 CONTRACT CLAUSES. In addition to the items listed in Clause 52.232-5(b)(1), submit the following in the request for progress payment:
a. Approved construction schedule.
b. Up-to-date payroll records.
c. Current submittal register.
d. QA/QC deficiency tracking list.
e. Current as-built drawings.
f. Environmental reports.
g. Progress photographs.
Once the complete pay application package is received to include the Contractor's signed ENG 93, the 14 calendar days will commence.
3.1.2 Options and Modification CLINS
When additional work is added by modification, existing CLINs funding amounts must be updated, or new CLINs for modification will be created.
SECTION 01 22 00 Page 5
If contract has option CLINs not yet awarded, option CLINs will appear as zero dollar CLINs until option is awarded by modification. No payment may be requested for Options or Modification CLINs until contract modification has been funded and signed.
SECTION 01 22 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
1.3 PROJECT COORDINATION
1.3.1 Resident Management System (RMS)
1.3.2 Access by Others
1.3.3 Inspections by Others
1.4 PROJECT MEETINGS
1.5 PRECONSTRUCTION CONFERENCE
1.5.1 Preconstruction Conference Minutes
1.5.2 Preconstruction Conference Submittals
1.5.2.1 Other Division 01 Submittals
1.5.2.2 Divisions 02 through 48 Submittals
1.6 PARTNERING
1.6.1 Initial Partnering Meeting
1.6.2 Partnering Regroups
1.7 NOTICE TO PROCEED
1.8 COORDINATION MEETING
1.9 PROGRESS MEETINGS
1.9.1 Progress Meeting Participants
1.10 CONTRACTOR PERFORMANCE EVALUATIONS
1.10.1 Training
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL MEETING REQUIREMENTS
3.2 PROGRESS MEETING AGENDA
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
Manage project and coordinate activities of own employees, subcontractors, suppliers and offsite fabricators. Contractor shall use computers, E-mail, and Internet resources for administrative work. Notify Contracting Officer of important meetings, schedule events and activities. Furnish labor and materials and equipment required to plan and execute project management functions and coordination. Coordinate activities and manage resources to construct project conforming to contract, on time and within budget. Related Sections are 01 45 04
CONTRACTOR QUALITY CONTROL.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
List of Subcontractors
Documentation of compliance with Clauses SUBCONTRACTS (LABOR STANDARDS) and LIMITATIONS ON SUBCONTRACTING of Section 00700 CONTRACT CLAUSES in Volume 1, and, if included, paragraph
LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR
SUBCONTRACTORS of Section 00800 SPECIAL REQUIREMENTS in Volume 1.
As part of the RMS schedule, submit a list of proposed subcontractors with company name, person to contact, street address, mail address, phone number, type of specialty and estimated subcontract quote.
Liability Insurance Policy ; G, DO
The Contractor shall provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required herein or elsewhere in the contract for work within the Florida Department of Transportation (FDOT) US Route 41(US41) Right-of-Way.
(a) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change shall not be effective (1) for
SECTION 01 30 00 Page 2 such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(b) The Contractor shall insert the substance of this requirement, in the subcontracts under this contract that require work within the FDOT US Route 41(US41) Right-of-Way and shall require subcontractors to provide and maintain the insurance required in this paragraph or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
(c) Any Contractor and subcontractors in connection with activities undertaken in connection with the require work within the FDOT US Route 41(US41) Right-of-Way:
(i) Provide a certificate of insurance evidencing worker's compensation insurance in the amount prescribed by Chapter 440, Florida Statutes;
(ii) At all times during the term of this Permit maintain Employer's liability of $ 100,000 and comprehensive general liability insurance full policy with minimum limits of coverage in the amount of $ 1,000,000 (Combined as Bodily injury per occurrence $ 500,000 and Property damage per occurrence $ 500,000) Refer to SECTION 00800 - SPECIAL REQUIREMENTS;
(iii) Obtain and maintain business automobile liability insurance with minimum limits of coverage in the amount of $720,000 per occurrence, combined single limit for bodily injury liability and property damage liability. Refer to SECTION 00800 -
SPECIAL REQUIREMENTS;
(iv) Shall name the Florida Department of Transportation, Collier County, and the U.S. Army Corps of Engineers as additional insured under such contractor's liability insurance.
SD-07 Certificates
Signature Authority
Furnish a power of attorney or a notarized letter of authority from Contractor identifying local representatives authorized to sign contract documents.
Drug-Free Work Place Record
Documentation of compliance with Clause DRUG-FREE WORKPLACE of Section 00700 CONTRACT CLAUSES in Volume 1 (see subparagraphs (b)(1) through (b)(7)).
1.3 PROJECT COORDINATION
1.3.1 Resident Management System (RMS)
Contractor shall use Corps of Engineers' Resident Management System for construction information management. See Section 01 45 00 RESIDENT
SECTION 01 30 00 Page 3
MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM).
1.3.2 Access by Others
Maintain access to power poles and other items owned or operated by utility companies. Coordinate with utility companies. Coordinate emergency incident response with local law enforcement and fire rescue authorities. Notify Contracting Officer in writing of coordination problems encountered affecting work.
1.3.3 Inspections by Others
During construction period, inspection or maintenance work will be performed by others within the construction limits. The Contractor will be responsible for neatly mowing all grass and vegetation (not to include established trees or other protected vegetation designated as wetland areas) within the construction limits for the duration of the contract.
Areas not accessible to mowers shall be edged or trimmed neatly. Mowing or trimming shall be performed every three weeks or when vegetation exceeds twelve inches in height.
1.4 PROJECT MEETINGS
Contracting Officer requires following types of project meetings:
-- Preconstruction Conference -- Partnering Meeting -- Partnering Regroup Meetings -- Coordination Meeting -- Preparatory and Initial Phase meeting for each feature of work -- Project Progress Meetings
Project meetings are described in detail in subparts below.
1.5 PRECONSTRUCTION CONFERENCE
Contracting Officer will conduct a Preconstruction Conference for this project in accordance with Clause PRECONSTRUCTION CONFERENCE of Section 00700 CONTRACT CLAUSES in Volume 1. Preconstruction Conference will be held within 30 calendar days after issuance of the Notice to Proceed (NTP). (Refer to subparagraph "Preconstruction Conference Submittals" below.) Contracting Officer will notify Contractor of time, place, and agenda. Contractor shall notify key subcontractors and suppliers to attend. Contracting Officer will discuss contract "ground rules" and general issues including:
-- Lines of Contracting Officer authority -- Lines of Contractor authority -- 00700 Contract Clauses -- 00800 Special Contract Requirements -- Contract Administration -- Progress Payment -- Correspondence Procedures -- Project Schedule -- Submittal Register -- Labor requirements -- General Site Safety -- Permit Requirements
SECTION 01 30 00 Page 4
1.5.1 Preconstruction Conference Minutes
Contracting Officer will take detailed minutes of Preconstruction Conference discussions and may use an audio or video tape. Copies of typed minutes will be provided to the Contractor to review for accuracy, sign and return. Signed minutes become part of the contract file. Audio or video tapes, if used, will be made available for Contractor to review or copy at Area Office.
1.5.2 Preconstruction Conference Submittals
The timing of submission of submittals and completion of the Preconstruction Conference is intended to allow the Contractor and the Government adequate time to prepare for commencement of work. However, should the Contractor fail to submit required items and receive acceptance and/or approval within the times stated, the Contractor will not be permitted to commence work until these requirements have been satisfied.
Any delays attributable to the Contractor's failure to comply with these pre-work requirements shall be at the Contractor's expense and may be cause for remedial action by the Contracting Officer. Submittals required by this Section are described in paragraph SUBMITTALS above.
1.5.2.1 Other Division 01 Submittals
The Contracting Officer reviews submitted draft plans to prepare Coordination Meeting agenda and understand Contractor procedures. Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:
-- RMS Schedule - See Section 01 32 01 PROJECT SCHEDULE
-- Accident Prevention Plan - See Section 01 35 26 GOVERNMENTAL
SAFETY REQUIREMENTS
-- Quality Control Plan - See Section 01 45 04 CONTRACTOR QUALITY
CONTROL
-- Temporary Facilities Plan - See Section 01 50 02 TEMPORARY
CONSTRUCTION FACILITIES
-- Environmental Protection Plan - See Section 01 57 20
ENVIRONMENTAL PROTECTION
1.5.2.2 Divisions 02 through 48 Submittals
In addition to the above, bring submittal items for materials, workmanship, plans or events required early in project schedule which are ready for transmittal to Contracting Officer. Prepare transmittal of submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
1.6 PARTNERING
Contracting Officer wants to have a bilateral project partnership with Contractor that draws on strengths of both organizations to identify and achieve common goals. Typical partnering goals include:
-- Effective and efficient contract performance -- Project completion on time and within budget -- Construction completed according to plans and specifications
SECTION 01 30 00 Page 5
-- Development of cooperative management teams -- Project success with customer (stakeholders) satisfaction -- Improved Project communication
1.6.1 Initial Partnering Meeting
Contractor, key subcontractors and suppliers shall attend a one-day project "Partnering Meeting". The Partnering Meeting is a project team building workshop facilitated by qualified persons. Contracting Officer attendees and invited persons may include:
Administrative Contracting Officer (Area Engineer) Construction Quality Assurance Representatives Jacksonville District - Construction Branch persons Jacksonville District - Engineering Division Designers Local Sponsor - South Florida Water Management District Owner - Florida Department of Transportation and Collier County
Goal of initial Partnering Meeting is to build trust, identify common goals, and understand individual project members' expectations and organizational values. Usual results include better communication between contract parties, shortened project learning curve and a cohesive two party contract partnership. Participants usually sign a voluntary partnering agreement generally describing mutual obligation to cooperate to achieve project goals and maintain effective communication. The Contractor shall pay costs for workshop site rental and facilitator fees.
The Contractor shall select the facilitator for the Partnering Meeting and Regroups from an approved list of vendors provided by the Contracting Officer.
1.6.2 Partnering Regroups
After initial Partnering Meeting, participation will be voluntary in accordance with a signed Partnering Agreement. Follow on Partnering Regroups will be hosted by the Contractor to include all costs associated with the meetings. It is preferred that the facilitator from the Initial Partnering Meeting be provided for the Partnering Regroups. Partnering Agreements include provisions for Contracting Officer and Contractor to request Partnering Regroups when needed. A Partnering Regroup is usually a short (4 hours - 1 day) informal partnering session where senior level Contractor and Contracting Officer project members and other interested parties review project issues of concern. Issues of conflict are reviewed, attempt to affirm common project goals and understand concerns of other partner.
1.7 NOTICE TO PROCEED
Notice to proceed (NTP) will be issued 15 to 30 calendar days after award or after all required bonds are in place, whichever is later. If the Contractor has failed to submit and receive acceptance and/or approval of specified plans, including, but not limited to, Accident Prevention Plan - Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, Quality Control Plan - Section 01 45 04 , and Environmental Protection Plan - Section 01 57 20 ENVIRONMENTAL PROTECTION, or has not yet received the Contracting Officer's conditional approval to work under an interim plan, the Contractor shall not proceed with the work and shall consider the work to be suspended in accordance with the Suspension Of Work clause of the contract. While the Contractor is working under a conditionally accepted interim plan, funds may be retained from progress payments in accordance
SECTION 01 30 00 Page 6 with the Payments Under Fixed-Price Construction Contracts clause of this contract until such time as the Contractor submits an acceptable plan. If the Contractor does not submit an acceptable plan within a reasonable time, as determined by the Contracting Officer, the Contracting Officer may order the Contractor to suspend work. Any suspension order issued for the Contractor's failure to submit an acceptable plan will not constitute unreasonable delay under the Suspension Of Work clause and the Contractor will not be entitled to an equitable adjustment of either performance period or contract price. Separate Notices To Proceed will be issued for Design phase and Construction phase of the project.
1.8 COORDINATION MEETING
Coordination Meeting is scheduled, convened and conducted by Contracting Officer after a Preconstruction Conference and prior to starting physical construction. Plans submitted after NTP (i.e., Quality Control Plan, Environmental Protection Plan and Accident Prevention Program) will have been reviewed. Coordination Meeting is primarily for on-site Contractor Quality Control staff, including subcontractor and supplier employees performing quality control, to meet and discuss the project in detail with Contracting Officer's Quality Assurance Representatives. Purposes of Coordination Meeting are:
-- Achieve mutual understanding with Contractor of required Quality Control -- Jointly review submitted draft plans; resolve issues of concern -- Discuss project plans and specifications, schedule, documentation -- Establish a good working relationship between the Contractors Quality Control Staff and Quality Assurance Representatives
1.9 PROGRESS MEETINGS
Schedule, convene and preside over progress meetings as required. As project activities increase ("ramp up"), a minimum of one progress meeting per week is typical of a project of this scope. Convene additional meetings as required, or when requested by Contracting Officer. Notify persons needed to be present to discuss agenda issues. Contracting Officer may direct attendance by key Contractor suppliers, or fabricators as needed. A sample meeting agenda is provided in paragraph GENERAL MEETING REQUIREMENTS below. The Contractor shall take minutes of the meetings and distribute copies of the minutes within three working days after the meetings.
1.9.1 Progress Meeting Participants
Typical participants include:
-- Contracting Officer -- Construction Quality Assurance Representatives -- Contractor's Site Superintendent -- Contractor's Quality Control Manager -- Contractor's Safety Coordinator -- Subcontractors, as appropriate to the agenda -- Suppliers, as appropriate to the agenda -- Others as appropriate to the agenda
1.10 CONTRACTOR PERFORMANCE EVALUATIONS
Contractors are given an opportunity to provide and/or enter performance
SECTION 01 30 00 Page 7 evaluation comments directly into the Contractor Performance Assessment Reporting System (CPARS). The system is a web-enabled application that supports the completion, distribution, and retrieval of contract performance evaluations. Provide to the responsible area office the name and email address of the contractor user that will be accessing CPARS.
1.10.1 Training
Contractor online training is available at the following web site:
https://www.cpars.gov/webtrain.htm. Training will give the student an understanding of the Contractor Representative and Contractor Corporate Senior Management levels of access, the policies and regulations governing CPARS, and the electronic workflow with particular attention to the Contractor comment function.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL MEETING REQUIREMENTS
See Section 01 45 04 CONTRACTOR QUALITY CONTROL for Preparatory and Initial Phase meeting checklists. Contractor is responsible for phase and progress meetings to include:
Meeting notification to participants Prepare agenda for meetings Use phase checklists for Preparatory and Initial Phase meetings Physical arrangements for meetings Preside at meetings Record minutes recording proceedings and decisions Copy and send minutes to:
Meeting participants Project parties affected by decisions Contracting Officer (No later than 3 working days)
3.2 PROGRESS MEETING AGENDA
Modify agenda as needed for on-going work.
Review minutes from previous progress meetings Review RMS Contractor Action Item Report Review work progress since previous meeting Review current definable features of work:
-- Identify phases of current features of work -- Identify pending phase changes -- Identify features for discussion in next scheduled meeting
Discuss problem prevention:
-- Field observations -- Deficiencies and tracking -- Procedures working well -- Problems, conflicts -- Methods to improve
Review construction schedule:
-- Identify delays -- Discuss proposed corrective actions to regain schedule
Submittals and Requests for Information (design interpretation):
-- Review submittal register -- Identify submittals to expedite as required
SECTION 01 30 00 Page 8
Review off-site activities:
-- Fabrications -- Material and equipment delivery schedule
Review Testing:
-- Type, Schedule -- Received Results
Review changes to construction schedule:
-- Planned progress during succeeding work period -- Coordination of various schedules -- Effect of changes on construction and completion date
Review site safety Discuss maintaining contract quality for materials and workmanship Discuss pending modifications, changes and substitutions Discuss other business, as appropriate
SECTION 01 30 00 Page 9
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
1.3.1 RMS SCHEDULES
1.3.2 Bar Chart with "S"Curve
1.3.2.1 Sample Bar Chart
1.3.2.2 Sample "S" Curve
1.4 UPDATED SCHEDULES
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Design and Permit Activities
3.3.4 Procurement Activities
3.3.5 Mandatory Tasks
3.3.6 Government Activities
3.3.7 Standard Activity Coding Dictionary
3.3.7.1 Workers Per Day (WRKP)
3.3.7.2 Responsible Party Coding (RESP)
3.3.7.3 Area of Work Coding (AREA)
3.3.7.4 Modification Number (MODF)
3.3.7.5 Bid Item Coding (BIDI)
3.3.7.6 Phase of Work Coding (PHAS)
3.3.7.7 Category of Work Coding (CATW)
3.3.7.8 Feature of Work Coding (FOW)
3.3.8 Contract Milestones and Constraints
3.3.8.1 Project Start Date Milestone and Constraint
3.3.8.2 End Project Finish Milestone and Constraint
3.3.8.3 Interim Completion Dates and Constraints
3.3.8.3.1 Start Phase
SECTION 01 32 01 Page 1
3.3.8.3.2 End Phase
3.3.9 Calendars
3.3.10 Open Ended Logic
3.3.11 Default Progress Data Disallowed
3.3.12 Out-of-Sequence Progress
3.3.13 Added and Deleted Activities
3.3.14 Original Durations
3.3.15 Leads, Lags, and Start to Finish Relationships
3.3.16 Retained Logic
3.3.17 Percent Complete
3.3.18 Remaining Duration
3.3.19 Cost Loading of Closeout Activities
3.3.19.1 As-Built Drawings
3.3.20 Anticipated Adverse Weather
3.3.21 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 RMS Schedule Submission
3.4.2.1 Design Package Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Schedule Log
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Banding
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01 Page 2
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications ; G, RO
RMS Schedule ; G, RO
Initial Project Schedule ; G, RO
SD-07 Certificates
Periodic Schedule Update ; G, RO
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01 Page 3
1.3.1 RMS SCHEDULES
See Section 01 45 04 CONTRACTOR QUALITY CONTROL. After receipt of Notice of Award, create "Activity Schedule" and "Feature Schedule" in RMS, in accordance with the terms of FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS. Submit RMS Schedules as part of initial RMS export. Data can be entered manually or Contractor has option to use standard data exchange format (SDEF.txt file). Cost allocate each "Pay Activity" to an assigned CLIN. Sum of "Pay Activities" must equal CLIN totals so there is no variance. "Features" duration is early start of first "Pay Activity" to late finish date of last "Pay Activity". Primavera P6 v6.x and later versions (v7.x and v8.x) allow export of a file for conversion to standard data exchange format (SDEF.txt) file format. Primavera provides a utility that will convert the export file to an SDEF.txt file. An SDEF.txt file can then be used to directly import the Primavera schedule into RMS. The Contractor shall be responsible for providing all programs and hardware necessary to prepare initial and progress schedules. The required Primavera P6 Activity Code Structure is as follows:
Field # Code Length Field Description 1 WRKP 3 Workers per day 2 RESP 4 Responsibility 3 AREA 4 Area 4 MODF 6 Modification or Claim # 5 BIDI 6 Bid Item 6 PHAS 2 Phase 7 CATW 1 Category of Work 8 FOW 20 Feature of Work
1.3.2 Bar Chart with "S"Curve
Submit the initial Bar Chart with target "S" Curve no later than 20 calendar days after award or 5 calendar days after Notice to Proceed, whichever is later. Contractor may create a manual Bar Chart and "S" curve or use computer software of his choice. Scheduling software allows for easier updates and changes. See sample Bar Chart and "S" Curve below.