20b6 Presolicitation Attachment 1 - Specifications.pdf
PDF 1 MB Posted
- Attached to
- Convert Steam to Hot Water, Building 101 Federal contract opportunity
- Solicitation number
- FA875120BA006
About this file
This document provides information regarding a federal contract opportunity to convert the heating system in Building 101 at the Air Force Research Laboratory Rome Research Site in Rome, New York from steam to hot water. The solicitation will require converting an existing loading dock into a new boiler room, providing new heating terminals, pumps, controls and a hot water distribution system, removing the existing steam distribution system, providing boilers, venting and boiler controls. Bids are due approximately 30 days after the invitation for bid is posted on the beta.SAM website on or around May 7, 2020. Award will be a firm fixed-price contract to the lowest priced responsible bidder whose bid is responsive. Interested parties can register contact information on the beta.SAM website to receive updates and facilitate subcontracting opportunities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 20b6 Presolicitation Attachment 2 - Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONVERT BUILDING 101 STEAM TO HOT WATER HEATING
100% SCHEMATIC DESIGN
TECHNICAL SPECIFICATIONS
For
AIR FORCE RESEARCH LABORATORY
ROME RESEARCH SITE
ROME, NEW YORK 13441
PROJECT NUMBER: ULDF 16-0003AE
Prepared By
TOWNE ENGINEERING
CONSULTING ENGINEERS
18 South Street Utica, New York 315.733.9000
August 26, 2016
PROJECT MANUAL
TABLE OF CONTENTS
PROJECT MANUAL TOC -1
SPECIFICATIONS
Division 1 ------ General Requirements Division 2-14 ---- General Construction Division 21 ------ Fire Protection Division 23 ------ Mechanical Division 26 ------ Electrical
DIVISION 01 – GENERAL REQUIREMENTS
SECTION TITLE PAGES
GENERAL REQUIREMENTS TOC - 1
01 00 10 Project Provisions 8
01 01 20 Summary 2
01 06 00 Regulatory Requirements 1
01 07 00 Hazardous Material Identification and Material Safety Data 2
AFRL, Bldg. 101, Convert Steam to Hot Water Heating PROJECT PROVISIONS
SECTION 01 00 10 - 1
SECTION 01 00 10
PROJECT PROVISIONS
1.01 SCOPE
A. The work covered under this Contract consists of furnishing all labor, equipment, devices, and materials and performing all work required to provide new heating plant in accordance with these technical specifications and applicable drawings.
1.02 REFERENCED CODES AND STANDARDS
A. Codes and standards referred to in this specification shall be the latest adopted issue at the Date of Bid, unless otherwise specifically indicated.
1.03 LOCATION
A. The work areas are located in Building 101 at Air Force Research Laboratory, Rome Research Site, Rome, New York.
1.04 PRINCIPAL FEATURES
1.05
A. The work to be performed involves the following principal features:
1. Convert existing loading dock into new Boiler Room.
2. Provide new heating terminals, pumps, and controls and hot water distribution system.
3. Provide power for new heating equipment.
4. Remove existing steam distribution system.
5. Provide boilers, venting and boiler controls.
6. Make up air unit, and associated ductwork heat exchanger, piping and pumps (alternate).
B. The above description of work is for the purpose of general information only and is not intended to include and describe every feature of work or to define the scope of the work.
C.
WORK BY OTHERS
A. The following work will be performed by the Government:
1. Natural gas utility to facility.
1.06 MATERIAL FURNISHED BY OTHERS
SECTION 01 00 10 - 2
A. The following material will be furnished by the Government:
1. None.
1.07 UTILITIES
A. All reasonable quantities of electricity and water will be made available to the Contractor without cost to the Contractor. The Contractor will be responsible for all connections of utilities from the existing supply points. The Government will identify service tie-in points. The Government will not be held responsible for interruptions of utility service and will not be liable for Contractor delays, damages, or increased costs occasioned by any such interruption of service.
1.08 SANITARY FACILITIES
A. The Contractor and his work force may use the existing sanitary facilities in the various work area buildings, subject to the regulations governing their use by Government personnel. Maintain in a sanitary condition at all times.
1.09 FIRE PROTECTION
A. The Contractor shall perform all work in a fire-safe manner in accordance with fire prevention standards of the Rome Research Site. The Contractor shall have an approved fire extinguisher at the site at all times during working operations.
HALON AND C02 TYPE FIRE EXTINGUISHERS ARE NOT AUTHORIZED FOR USE. The Contractor will call the City of Rome Fire Department, 315-339-7734, before working with any flame or spark producing equipment such as tar buckets, grinders, or welders, for approval of the contractors safety measures and to obtain a "Burn Permit" for this type of work.
1.10 POLLUTION CONTROL
A. The Contractor will perform all work consistent with the requirements of all Federal, State and Local laws, rules and regulations pertaining to pollution control.
1.11 WORK CONDITIONS
A. All work on this project will be performed while the building work areas and rooms adjacent to the work areas are occupied by military and civilian personnel. The Contractor is required to protect persons and property throughout the progress of the work. The work area will be kept clean of all debris at all times. All flammables and combustibles stored on-site must be kept in a locker and area, both of which are approved by the Contracting Officer or his designated representative.
1.12 WORKMANSHIP
A. All work to be performed under this Contract shall be under the supervision of workmen skilled in the trades involved. Special qualifications for certain work are listed in the appropriate sections of this specification.
1.13 SUBMITTALS
A. All items indicated in the Schedule of Material Submittals shall be submitted for approval:
SECTION 01 00 10 - 3
1. Any other items required, per specifications, that cannot be visually verified shall be submitted for approval when requested by the Contracting Officer or the designated representative.
2. Submittals which may be required by this Contract, if submitted in printed matter, shall be made in four copies. One copy of the printed submittals will be returned to the Contractor.
3. The Contractor must submit for approval those items which deviate from the specifications. Submission will be on an AF Form 3000.
B. At the pre-construction conference, the Contractor, Contracting Officer’s Technical Representative, and the Contract Administrator will review the submittal requirements. The Contractor must be prepared to discuss the delivery dates for those submittals which are required, or for the items the Contractor plans to submit for approval. Once approved, the submission deadlines shall be incorporated into the Schedule of Materials submittals.
C. The Contractor is reminded that any item(s) installed prior to the Contracting Officer's approval is being done at his/her own risk. If any item does not meet the Contract requirements as determined by the Contracting Officer, the Contractor will be required to remove same at his/her own expense.
D. Equipment submittals, unless otherwise specified, shall conform with the following:
1. Submittals shall be complete with the manufacturer's product description literature. SUBMITTALS WITH INSUFFICIENT LITERATURE WILL BE
DISAPPROVED.
2. Submittals shall include a complete listing of all associated parameters contained in the Technical Specifications and Drawings (materials, finishes, capacities, temperatures, pressures, electrical characteristics, etc.). THE
CONTRACTING OFFICER OR HIS TECHNICAL REPRESENTATIVE WILL NOT
TRANSFER INFORMATION FROM THE TECHNICAL SPECIFICATIONS AND
DRAWINGS TO THE SUBMITTALS. INCOMPLETE SUBMITTALS WILL BE
DISAPPROVED.
3. Submittals shall be clearly marked to differentiate between the applicable and extraneous portions. THE CONTRACTING OFFICER OR HIS TECHNICAL
REPRESENTATIVE WILL NOT MARK THE SUBMITTALS. UNMARKED
SUBMITTALS WILL BE DISAPPROVED.
1.14 INTERRUPTION OF UTILITIES
A. No utility services shall be interrupted to make connections, to relocate, or for any purpose, without approval of the Contracting Officer.
B. Request for permission to shut down services shall be submitted in writing to the Contracting Officer fourteen (14) days prior to date of proposed interruption. The request shall give the following information:
1. Location of shut-off.
2. Services affected.
SECTION 01 00 10 - 4
3. Hours and date of shut-off.
4. Approximate length of time shut-off will be in effect.
C. Services shall not be interrupted until receipt of approval of the proposed hours and date from the Contracting Officer.
1.15 FIELD MEASUREMENTS
A. The Contractor shall verify all measurements and be responsible for dimensions, fitting and proper trimming of items directly connected with all work described in this Contract. The Contractor shall immediately notify the Contracting Officer of any discrepancy prior to starting the work.
1.16 SECURITY REQUIREMENTS
A. The work to be done on this project is located within areas that are under security.
To gain access to the areas to examine the work to be done for estimating purposes, arrangements must be made with the Contracting Officer. Contractor personnel will be granted escorted entry into the areas. Prior to initial work commencement, the Contractor shall supply the Contracting Officer a letter identifying all personnel employed during construction. Each time additions or deletions to the letter occur, an updated letter shall be forwarded to the Contracting Officer. Identification data shall include name, social security account number and company name/phone number of each person.
B. All buildings in the project are Controlled Areas and Contractor personnel shall stay in their work areas and not wander freely throughout the buildings. Names of the Contractor personnel who will be working during non-duty hours shall be furnished in writing at least one week in advance. Access to Rome Research Site (RRS) facilities is controlled by a card entry system. Contractor personnel shall be required to obtain magnetic entry cards for all personnel who will be involved in the work and who need to have access to the building. The magnetic entry cards can be obtained from the RRS Security Office, AFRL/RIOF, in Building 3. These cards shall be returned to the Contracting Officer’s Technical Representative before completion of the final inspection.
1.17 DELIVERY AND STORAGE
A. Materials shall be delivered to the work area in undamaged condition, stored in fully covered, well ventilated areas, and protected from extreme changes in humidity and temperature.
B. The Contractor is responsible for securing materials in the storage area to protect from pilferage and vandalism.
C. The storage areas for this project are located as shown on the Drawing Title Sheet.
Access to these work areas is provided off main routes within the Griffiss Business and Technology Park Complex.
1.18 SAFETY
A. The Contractor shall:
1. Comply with all safety and health requirements necessary for the protection of personnel, facilities and equipment including, but not limited to all applicable
SECTION 01 00 10 - 5
Occupational Safety and Health Administration (OSHA) standards, while performing this contract at the Air Force Research Laboratory (AFRL), Rome Research Site (RRS) in Rome, NY.
2. Maintain a written Safety Program, as required by OSHA and make said plan available for review by the government upon request by the contracting officer.
3. In the event of a mishap during the performance of this contract on AFRL RRS premise, notify the contracting officer in an expeditious manner. Notification shall include the following information:
a. Contract, contract number, name and title of person(s) reporting.
b. Date, time and exact location of accident/incident.
c. Brief narrative of accident/incident (events leading to accident/incident).
d. Cause of accident/incident (if known).
e. Type of injury sustained and/or estimated cost of accident/incident (material and labor to replace/repair) when damage is to government property.
f. Nomenclature of equipment and personnel involved in accident/incident.
g. Corrective actions (taken or proposed).
h. Other pertinent information.
1.19 PROPRIETARY EQUIPMENT
A. Reference to any equipment, material, article or patented process by trade name, mark or catalog number shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may use any equipment, material article or process which is equal to that named as approved by the Contracting Officer.
1.20 PROTECTION
A. Protection of existing work:
1. The Contractor shall take all necessary precautions to insure against damage to the existing work to remain in place, to be reused, or to remain the property of the Government; i.e. walls, light fixtures, carpet, etc.
2. The Contractor shall insure that structural elements are not overloaded and additional structural supports required as a result of any cutting, removal, or demolition work performed under any part of this Contract are added.
B. Protection of buildings from the weather:
1. The interior of the building and all materials and equipment shall be protected from the weather at all times.
C. Dust control:
SECTION 01 00 10 - 6
1. The amount of dust resulting from demolition shall be controlled to prevent the spread of dust to occupied portions of the building and to avoid creation of a nuisance in the surrounding areas.
D. Temporary closures:
1. The Contractor shall provide temporary closures at all openings in outside walls affected by their work to maintain weather protection and security.
E. Protection of personnel:
1. Where the safety of non-Contractor personnel is endangered in the area of removal work and new construction, barricades shall be used.
1.21 REMOVED MATERIALS AND EQUIPMENT
A. General:
1. All materials and equipment indicated to be removed as part of the work become the property of the Contractor for removal from the job site at the Contractor’s expense, unless otherwise shown on the drawings or specified.
B. Items re-used as part of the work:
1. Items indicated to be re-used will be stored by the Contractor until such time as they may be reinstalled.
1.22 DISPOSAL OF REMOVED MATERIALS
A. General:
1. Materials removed from the project which are designated as unusable by the Government shall be disposed of by the Contractor at his own expense off the Griffiss Business and Technology Park in accordance with applicable regulations.
2. All debris to be removed from the work site shall be transported in canvas covered trucks with the canvas tied down to prevent loss of materials while in route to the disposal areas.
3. The Contractor shall police the truck routes continuously and all debris which has dropped shall be picked up immediately.
B. Materials for Contractor salvage:
1. This material shall be removed from Government property before completion of the Contract.
2. Materials for salvage shall not be sold on the site.
1.23 REMOVAL AREAS
A. Patch existing construction and finishes damaged or left incomplete due to removals. Patching, unless otherwise indicated, will be limited to areas where removals occurred and will match existing in material, color and finish.
SECTION 01 00 10 - 7
B. Cap or otherwise terminate existing utility services to removed equipment on all utilities that are to remain active.
1.24 SPECIAL CONDITIONS
A. Should any materials be encountered during construction which are suspected to contain hazardous materials and are not indicated as such on the drawings, immediately stop work in that area and report the encountered condition to the Contracting Officer’s Technical Representative.
1.25 SEQUENCING AND SCHEDULING
A. Provisions must be made to leave each entrance secured at the end of work each day and to minimize the duration of time each entrance is worked on from start to completion. Any work which affects the use of a required building exit must be coordinated with the Rome Research Site Safety Office.
B. The Contractor is required to maintain circulation corridors, exits and exit stairs in all building areas occupied by the Government.
C. Traffic control:
1. Routes of ingress and egress on the grounds and within existing buildings to the location of the work shall be over routes as directed by the Government.
2. Areas for parking vehicles belonging to the Contractor and his employees will be designated by the Contracting Officer’s Technical Representative. Maintain the parking areas free of debris and obstructions, including snow.
1.26 CONSTRUCTION SCHEDULING
A. The Contractor may be paid for materials on site, however, they must appear on the Contract Progress Schedule and be inventoried by the Contracting Officer’s Technical Representative prior to payment.
1.27 WORK SCHEDULE
A. Working hours for the Contractor will normally be between the hours of 0700 and 1600 hours (7:00 a.m. and 4:00 p.m.), excluding Saturdays, Sundays and Federal holidays.
B. If the Contractor desires to work during periods other than above, additional government inspection forces may be required:
1. The Contractor must make his/her request to the Contracting Officer three (3) days in advance of his/her intention to work during other periods to allow assignment of additional inspection forces.
2. If such force is reasonably available, the Contracting Officer may authorize the Contractor to perform work during periods other than normal duty hours/days.
3. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of inspection at overtime rates will be charged to the Contractor. These
SECTION 01 00 10 - 8
adjustments to the Contract Price may be made periodically as directed by the Contracting Officer.
1.28 REMOVAL OF TEMPORARY FACILITIES
A. Maintain all temporary facilities and controls as long as needed for the safe and proper completion of the work.
B. Remove all such temporary facilities and controls as rapidly as progress of the work will permit or as directed by the Contracting Officer.
1.29 CLEAN-UP
A. Debris and rubbish control:
1. Remove all debris and rubbish daily from the site.
2. Remove debris and rubbish into a dumpster; then transport in a manner that will prevent spillage on streets or adjacent areas.
3. The Contractor shall make his/her own arrangements for dumping off the Griffiss Business and Technology Park.
4. Burning of waste material on Griffiss Business and Technology Park is prohibited.
B. Regulations:
1. All disposal and hauling equipment and methods used shall comply to Federal, State, OSHA, and local regulations.
C. If the Contractor utilizes a collector box, it must be provided with a cover.
D. The Contractor shall protect and restore lawn areas and plant materials during the course of this Contract. Lawn areas shall be protected and restored to a condition equal to that prior to the start of work of this Contract.
END OF SECTION
AFRL, Bldg. 101, Convert Steam to Hot Water Heating SUMMARY
SECTION 01 01 20 - 1
SECTION 01 01 20
SUMMARY
PART 1 – GENERAL
1.01 PROJECT
A. Project Name: Convert Steam to Hot Water Heating, Bldg. 101
B. Project Location: Building 101, Air Force Research Laboratory, Rome, NY
C. Owner’s Name: Air Force Research Laboratory, Rome Research Site, Rome, NY.
D. Architect/Engineer: Towne Engineering, 18 South Street, Utica, NY 13501.
E. The Project generally consists of the upgrade of the heating system in Building 101 at Air Force Research Laboratory, Rome Research Site, Rome, NY.
1.02 CONTRACT DESCRIPTION
A. Contract Type: A single prime contract based on a Stipulated Price.
1.03 EXISTING ITEMS
A. To be determined.
1.04 OWNER OCCUPANCY
A. Government intends to occupy the Project upon Substantial Completion.
B. Cooperate with Contracting Officer’s Representative to minimize conflict and to facilitate Government’s operations.
C. Schedule the Work to accommodate Government occupancy.
1.05 CONTRACTOR USE OF SITE AND PREMISES
A. Construction Operations: Limited to Project work area. Work in areas surrounding Project work area shall be scheduled in advance with Contracting Officer’s Representative.
B. Utility Outages and Shutdown:
1. Schedule in advance with Contracting Officer’s Representative and disruption of utility services outside work area.
2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Contracting Officer’s Representative.
1.06 HAZARDOUS MATERIALS
AFRL, Bldg. 101, Convert Steam to Hot Water Heating SUMMARY
SECTION 01 01 20 - 2
A. Shown or noted on drawings and specifications.
PART 2 – PRODUCTS
PART 3 – EXECUTION
AFRL, Bldg. 101, Convert Steam to Hot Water Heating REGULATORY REQUIREMENTS
SECTION 01 06 00 - 1
SECTION 01 06 00
REGULATORY REQUIREMENTS
PART 1 - GENERAL
1.01 CODES
A. Conform to the requirements of all Federal, State and Local Codes and Ordinances, unless otherwise noted below.
B. Conform to the requirements of all public utility companies.
C. The requirements of Military Handbook 1008B, the Uniform Building Code, National Fire Protection Association Codes and National Electric Code apply to this project.
D. Conform to OSHA requirements, including Part 1910, General Industry, and Part 1926, Construction.
1.02 PERMITS, FEES AND INSPECTIONS
A. All permits (other than building permits), fees and inspections required by Governmental agencies, regulatory agencies, utility companies or others during the course of the work shall be obtained by the Contractor.
B. The Contractor shall arrange for and pay all costs of such permits, fees and inspections.
1.03 REFERENCED CODES AND STANDARDS
A. Codes and standards referred to in this specification shall be the latest adopted issue at the Date of Bid, unless otherwise specifically indicated.
PART 2 - PRODUCTS
2.01 Asbestos:
A. Products containing Asbestos shall not be utilized or brought onsite by any Contractor.
PART 3 - EXECUTION
3.01 CONFLICTING REQUIREMENTS
A. In the event of conflict between applicable Codes and Regulations and the requirements of the referenced Standards or these specifications, the provisions of the more stringent shall govern.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating HAZARDOUS MATERIAL IDENTIFICATION
SECTION 01 07 00- 1
SECTION 01 07 00
HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFTEY DATA
PART 1 – GENERAL
1.01 REQUIREMENTS
A. “IAW FAR Clause 52.223-3, each Contractor must provide the Contracting Office
(CO) with a list of proposed Hazardous Materials (HAZMAT) that it plans to use on the installation during the performance of the contract. IAW AFI 32-7086, contractors must obtain Air Force authorization prior to using HAZMAT on an Air Force installation, and must report usage data to the Environmental and Occupational Health Office (RIOCV). This includes fuels used to run generators and other construction/maintenance equipment.
1. Contractors shall submit through the CO to RIOCV, Safety Data Sheets
(formerly known as Material Safety Data Sheets or MSDS’s), for all potentially hazardous materials/products that will be brought on to the installation.
2. RIOCV will review all potentially hazardous materials and identify the materials deemed as HAZMAT that require tracking. RIOCV may remove any materials from consideration for use by the Contractor that contain ingredients prohibited buy the AF or other regulatory agency.
3. RIOCV will communicate to the Contracting Officer Representative the list of
HAZMAT that will require AF-EESOH-MIS tracking. Those materials will require the completion of one Hazardous Materials Worksheet per HAZMAT by the Contractor (except for portions reserved by RIOCV). RIOCV will provide the Hazardous Material Worksheet to the Contractor and can assist the Contractor with this documentation if requested.
4. RIOCV will complete their portion on the Hazardous Material Worksheet and load all information from the Worksheets into the AF-EESOH-MIS data system. The Contractor will retain a copy of their Hazardous Material Worksheet for the duration of the specified project.
5. If the contractor needs to bring a material on the installation that was not included in the original HAZMAT listing, the contractor must first notify the CO and then obtain prior authorization, if RIOCV determines the material to be a
HAZMAT.
6. The Contractor will submit a Contractor Material Usage Data Sheet provided by RIOCV to the CO once a month for contracts over 60 days. For contracts less than 60 days, a Material Usage Data Sheet will be submitted by the Contractor to CO at the completion of the contract.
7. The CO will provide a copy of the Usage Data Sheet to RIOCV.
8. Any HAZMAT brought on site for the contract and not used in its entirety will be removed from the installation by the Contractor. If HAZMAT can be used in another contract at this installation, please contact RIOCV for assistance.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating HAZARDOUS MATERIAL IDENTIFICATION
SECTION 01 07 00- 2
9. RIOCV is ready to assist the CO and Contractor in any way to simplify and expedite this reporting and tracking procedure. Please contact RIOCV’s Jakki Holbritter or Carol Hoyt by email or phone (330-2098) with any questions.”
DIVISIONS 02 - 14 – GENERAL CONSTRUCTION
SECTION 02 00 00 – 14 09 99
TABLE OF CONTENTS
SECTION TITLE PAGES
AFRL, Bldg. 101, Convert Steam to Hot Water Heating
GENERAL CONSTRUCTION TOC - 1
02 00 00 General Provisions, Divisions 2 through 14 2
02 00 10 Cleaning Up 3
02 00 45 Cutting and Patching 4
02 01 11 Selective Demolition 2
05 04 00 Lightgage Metal Framing Systems 3
08 01 10 Steel Doors 4
08 01 11 Steel Door Frames 4
09 02 60 Gypsum Board Systems 2
09 09 00 Painting 4
AFRL, Bldg. 101, Convert Steam to Hot Water Heating GENERAL PROVISIONS
DIVISIONS 2 THROUGH 14
SECTION 02 00 00 - 1
SECTION 02 00 00
GENERAL PROVISIONS
PART 1 - GENERAL
1.01 SCOPE
A. Furnish and install all equipment and materials required to provide the general construction work shown on the drawings and herein specified.
1.02 FABRICATION DRAWINGS, MATERIAL LISTS AND EQUIPMENT SUBMITTALS
A. Unless otherwise noted or herein specified, the following are required:
1. Material lists:
a. Suspended ceiling systems.
b. Paint.
c. Doors and Door Hardware.
d. Fire Stopping.
PART 2 - PRODUCTS
2.01 ACCEPTABLE MANUFACTURERS
A. All materials and equipment shall be in strict accordance with the parameters herein specified.
2.02 ACCESSORIES
A. It is the intent of this specification that all systems and equipment shall be complete with the necessary quantity of all accessories and components required to ensure a properly functioning installation.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Unless otherwise noted or herein specified, all materials and equipment shall be installed in strict accordance with the manufacturer's recommendations.
B. All electrical work herein specified and/or noted shall be executed in strict conformance with the National Electrical Code.
3.02 RECORD DRAWINGS
SECTION 02 00 00 - 2
A. Promptly record (in a neat, legible and red color only accentuated fashion, on a complete, designated set of contract documents containing no other markings) all significant differences reflected by the actual installation (sizes, capacities, locations and features of distribution systems and equipment).
B. Thoroughly review such recordings weekly with the Contracting Officer’s Technical
Representative and submit the completed set at the completion of work.
3.04 MAINTENANCE MANUAL
A. Near the completion of work, submit two bound, neatly arranged, indexed maintenance manuals for approval.
B. Manuals shall contain copies of all approved fabrication drawings, material lists and equipment submittals; equipment operation/ maintenance bulletins and names, addresses and telephone numbers relative to parts and service.
3.05 INSTRUCTION
A. Provide thorough, organized instruction regarding equipment and systems operation to the Contracting Officer’s authorized representative (secure written acknowledgement and forward to the Contracting Officer).
AFRL, Bldg. 101, Convert Steam to Hot Water Heating CLEANING UP
SECTION 02 00 10 - 1
SECTION 02 00 10
CLEANING UP
1.01 DESCRIPTION
A. Related requirements specified elsewhere:
1. Safety Standards, Section 01 10 10
2. Cutting and Patching, Section 02 00 45
3. Cleaning for specific products or work: the respective section of the specifications.
B. Maintain premises and public properties free from accumulations of waste, debris and rubbish caused by operations.
C. At completion of work, remove waste materials, rubbish, tools, equipment, machinery and surplus materials and clean all sight exposed surfaces; leave project clean and ready for occupancy.
1.02 SAFETY REQUIREMENTS
A. Standards:
1. Maintain project in accordance with safety and insurance standards.
B. Hazards control:
1. Store volatile wastes in covered metal containers and remove from premises daily.
2. Prevent accumulation of wastes that create hazardous conditions.
3. Provide adequate ventilation during use of volatile or noxious substances.
C. Conduct cleaning and disposal operations to comply with local ordinances and anti-pollution laws.
1. Do not burn or bury rubbish and waste materials on project site.
2. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains.
3. Do not dispose of wastes into streams or waterways.
PART 2 – PRODUCTS
SECTION 02 00 10 - 2
2.01 MATERIALS
A. Use only cleaning materials recommended by manufacturer of surface to be cleaned.
B. Use cleaning materials only on surfaces recommended by cleaning material manufacturer.
3.01 EACH CONTRACTOR, DURING CONSTRUCTION
A. Execute cleaning to ensure that building, grounds and public properties are maintained free from accumulation of waste materials and rubbish.
B. Wet down dry materials and rubbish to lay dust and prevent blowing dust. Erect dustproof barriers to keep dust from drifting through building.
C. At reasonable intervals during progress of work, clean site and public properties and dispose of waste materials, debris and rubbish.
D. Provide containers for collection of waste materials, debris and rubbish.
E. Remove waste materials, debris and rubbish from site and legally dispose of at public or private dumping areas off Government’s property.
F. Vacuum clean interior building areas when ready to receive finish painting and continue vacuum cleaning on an as-needed basis until building is ready for substantial completion or occupancy.
G. Handle materials in a controlled manner with as few handlings as possible; do not drop or throw materials from heights.
H. Schedule cleaning operation so that dust and other contaminants resulting from cleaning process will not fall on wet, newly painted surfaces.
3.02 FINAL CLEANING
A. Each Contractor shall:
1. Employ experienced workmen or professional cleaners for final cleaning.
2. In preparation for substantial completion or occupancy, conduct final inspection of sight-exposed interior and exterior surfaces and of concealed spaces.
3. Remove grease, dust, dirt, stains, labels, fingerprints and other foreigh materials from sight-exposed interior and exterior finished surfaces; polish surface to designated shine finish.
4. Maintain cleaning until project, or portion thereof, is occupied by Government.
SECTION 02 00 10 - 3
5. Repair, patch and touchup marred surfaces to specified finish to match adjacent surfaces.
B. General Contractor shall:
1. Broom clean paved surfaces affected by Contractor’s operations.
2. Wash glass, inside and out, as part of this work.
3. Vacuum clean carpeting.
4. Wash and wax resilient floor tile.
C. Mechanical Contractor shall:
1. Clean mechanical equipment that was operated during construction.
2. Replace filters used during construction.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating CUTTING AND PATCHING
SECTION 02 00 45 - 1
SECTION 02 00 45
CUTTING AND PATCHING
1.01 DESCRIPTION
A. Related work specified elsewhere:
1. Safety Standards, Section 01 10 10.
B. Cutting and patching covers adjustment to, and necessary reworking of, elements of construction in both new and existing work. The following definitions for cutting and patching apply to this Contract:
1. Cutting:
a. Physical modification of construction work, both new and existing, or removal of existing or installed materials, excluding excavation and earthwork.
2. Patching:
a. Restoration or replacement and installation of construction material, both new and existing, including finishing and patching.
C. Provide equipment, labor and incidentals necessary for cutting and patching as required for the installation of all work.
D. Provide lintels capable of supporting wall construction above openings that are cut in existing walls.
E. UNLESS OTHERWISE NOTED OR DETAILED ON THE DRAWINGS, THE GENERAL
CONTRACTOR IS RESPONSIBLE FOR CUTTING AND PATCHING REQUIRED FOR ALL
TRADES.
1.02 SUBMITTALS
A. Prior to cutting that affects structural safety of project, submit written notice to
Contracting Officer or his/her authorized representative requesting consent to proceed with cutting, including:
1. Identification of project.
2. Description of affected work.
3. Necessity for cutting.
4. Effect on other work of structural integrity of project.
SECTION 02 00 45 - 2
5. Description of proposed work, designate:
a. Scope of cutting and patching.
b. Contractor and trades to execute work.
c. Products proposed to be used.
d. Extent of refinishing.
6. Alternatives to cutting and patching.
B. Should conditions of work or schedule indicate change of materials or methods, submit written recommendation to Contracting Officer or his/her authorized representative, including:
1. Conditions indicating change.
2. Recommendations for alternative materials or methods.
3. Submittals as required for substitutions.
C. Submit written notice to Contracting Officer or his/her authorized representative designating time work will be uncovered, to provide for observation.
2.01 MATERIALS FOR REPLACEMENT OF WORK REMOVED
A. Comply with specifications for type of work to be done.
3.01 INSPECTION
A. Prior to cutting, drilling or removal, investigate both sides of the surface involved.
Determine the exact location of structural members.
B. Inspect existing condition of work, including elements subject to movement or damage during cutting and patching.
C. After uncovering work, inspect conditions affecting installation of new products or performance of the work.
3.02 PREPARATION
A. Provide shoring, bracing and supports as required to maintain structural integrity of existing construction.
B. Provide protection for materials on adjacent surfaces from damage.
SECTION 02 00 45 - 3
C. Provide protection when work will be exposed to the elements.
3.03 PERFORMANCE
A. Each trade shall be responsible for the moving, removal, cutting, patching, and repair to work under his supervision including coordination with other trades so as to cause the least damage to each type of work encountered, and so as to return the building as much as possible to the appearance of new work. Patching of finish materials shall be assigned to mechanics skilled in the work of the finish trade involved.
B. Patching:
1. Where any portion of an existing finished surface is damaged, lifted, stained, or otherwise made or found to be imperfect, patch or replace the imperfect portion of the surface with matching material.
2. Provide adequate support or substrate for patching of finishes.
3. If the imperfect surface was a painted or coated one, repaint or recoat the patch portion in such a way that uniform color and texture over the entire surface results.
4. Where the surrounding surface cannot be matched, repaint or recoat the entire adjoining floor, wall or ceiling.
5. Fit work airtight to pipes, sleeves, ducts, conduit and other penetrations through surfaces.
C. Transitions:
1. Where new work abuts or finishes flush with existing work, make the transition as smooth and workmanlike as possible. Patched work shall match existing adjacent work in texture and appearance to make the patch or transition reasonably imperceptible to the eye.
2. Where masonry, or other finished surface is cut in such a way that a smooth transition with new work is not possible, terminate the existing surface in a neat fashion along a straight line at a natural line of division and provide trim appropriate to the finished surface as approved by the Contracting Officer or his/her authorized representative.
3. Where two or more spaces are indicated to become one space, rework floors and ceiling so that horizontal planes are without breaks, steps or bulkheads.
4. Mechanically or chemically treat existing substrates to obtain compatibility with newly applied materials.
D. Matching:
1. Restore existing work damaged during construction to a condition acceptable to the Contracting Officer or his/her authorized representative.
SECTION 02 00 45 - 4
2. Where partitions or walls are removed, patch the floors, walls and ceilings with finish materials to match adjacent finishes.
3. Remove existing surfacings which may tend to cause delaminations of new surfacings from existing substrates.
E. Overall requirement that the work be completed:
1. Where a product or type of construction occurs in the existing building, and it is not specified as a part of the new work, provide such products or types of construction as needed to patch, extend or match the existing work.
F. Exercise extreme care to maintain the integrity of dampproofing, waterproofing, and roofing materials. Repair defective existing materials damaged by penetrations and preparations required for installation of the new work.
3.04 REPAIR
A. Replace work damaged in the course of alterations.
B. If the repaired work is not brought up to the standard for new work, the
Contracting Officer or his/her authorized representative will direct that it be cut out and replaced with new work.
3.05 FIRE/SMOKE PENETRATIONS
A. All penetrations through fire-rated or smoke partitions require sleeves, fire-taping and fire-safing:
1. Fire-tape and seal between drywall and sleeve.
2. Fire-safe between the sleeve and the pipe, duct, conduit, etc.
B. Penetrations through the existing concrete floor require fire-safing/sealant:
1. Maintain fire rating of system that has been penetrated.
C. Products:
1. USG Fire Stop System.
2. Tremco Fire Stopping Systems.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating SELECTIVE DEMOLITION
SECTION 02 01 11 - 1
SECTION 02 01 11
SELECTIVE DEMOLITION
1.01 SUMMARY
A. In accordance with pertinent provisions of this section, carefully demolish and remove from the site those items scheduled to be so demolished and removed.
B. Related work:
1. Documents affecting work of this section include, but are not limited to, General Conditions, Supplementary Conditions and Sections of Division 1 of these specifications.
2. Section 02 00 45, Cutting and Patching.
1.02 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and methods needed for proper performance of the work of this section.
Not Used
3.01 SURFACE CONDITIONS
A. Examine the areas and conditions under which work of this section will be performed and correct conditions detrimental to timely and proper completion of the work. Do not proceed until unsatisfactory conditions are corrected.
3.02 DEMOLITION
A. By careful study of the Contract Documents, determine the location and extent of selective demolition to be performed.
B. In company with the Contracting Officer or his/her authorized representative, visit the site and verify the extent and location of selective demolition required:
1. Carefully identify limits of selective demolition required.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating SELECTIVE DEMOLITION
SECTION 02 01 11 - 2
2. Mark interface surface as required to enable workmen to also identify items to be removed and items to be left in place intact.
C. Prepare and follow an organized plan for demolition and removal of items:
1. Shut off, cap and otherwise protect existing public utility lines in accordance with the requirements of the public agency or utility having jurisdiction.
2. Completely remove all items scheduled to be demolished and removed, leaving surfaces clean, solid and ready to receive new specified materials.
3. In all activities, comply with pertinent regulations of governmental agencies having jurisdiction.
D. Demolished material shall be considered to be the property of the Contractor and shall be completely removed from the site.
E. Use means necessary to prevent dust becoming a nuisance to the public, neighbors and other work being performed on or near the site.
3.03 REPLACEMENTS
A. In the event of demolition of items not so scheduled to be demolished, promptly replace such items to the approval of the Contracting Officer or his/her authorized representative at no additional cost to the Government.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating LIGHTGAGE METAL FRAMING SYSTEMS
SECTION 05 04 00 - 1
SECTION 05 04 00
LIGHTGAGE METAL FRAMING SYSTEMS
A. Furnish and install lightgage metal framing systems for non-loadbearing walls and partitions in accordance with the parameters shown on the drawings and herein specified.
B. Systems shall be factory fabricated; conform with ASTM Specification C-645;
complete with studs, runners, furring channels, fasteners and sound sealant.
2.01 DESCRIPTION
A. General:
1. Material:
a. Galvanized steel conforming to ASTM Specification A-525.
2. Thickness:
a. Unless otherwise shown:
1) 25 gauge.
b. Utility chases, wall hung cabinets, equipment, fixtures, partitions, etc.:
1) 20 gauge.
B. Studs:
1. Channel shaped, utility openings, stiffener channel compatible.
C. Runners:
1. Dimensionally compatible, notched.
D. Furring channels:
1. Compatible with associated wall (partition) finish system.
E. Fasteners:
1. Corrosion resistant, self-tapping screws.
SECTION 05 04 00 - 2
F. Sound sealant:
1. Non-drying, non-migrating, non-shrinking, paintable.
3.01 COORDINATION
A. Coordinate with associated mechanical and electrical work to assure a well planned, orderly, complete installation.
3.02 INSTALLATION
1. Erect system carefully to assure plumb, true, plane surfaces.
2. Touch-up system component’s finish with appropriate primer or galvanizing repair, as applicable.
B. Studs:
1. Space units 16 inches on center, unless otherwise noted.
2. Provide full-length units whenever possible; splice units (when necessary) with 8 inches, nested lap.
3. Provide supplemental units complete with backup blocking/plating as required to properly address:
a. Doors, windows, openings.
b. Corners (internal, external), intersections, terminations, control joints.
c. Utility chases.
d. Wall hung cabinets, equipment, fixtures, partitions, etc.
C. Runners:
1. Secure units 24 inches on center and within 2 inches of termination.
2. Provide double (nested) units to complement live-load deflection.
D. Horizontal stiffeners:
1. Space units 48 inches on center.
2. Provide units as required to properly address:
a. Utility chases.
SECTION 05 04 00 - 3
b. Wall hung cabinets, equipment, fixtures, partitions, etc.
c. Walls/partitions with gypsum wallboard on one side.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating STEEL DOORS
SECTION 08 01 10 - 1
SECTION 08 01 10
STEEL DOORS
A. Furnish and install steel doors in accordance with the parameters shown on the drawings and herein specified.
B. Units shall be the hollow metal type; factory fabricated and machined; complete with core, rails, stiles, reinforcing, factory applied finish and accessories.
1.02 REFERENCED STANDARDS
A. American National Standards Institute (ANSI):
1. ANSI/UL 10B Fire Tests of Door Assemblies.
2. ANSI/NFPA 80 Fire Doors and Fire Windows.
3. ANSI/NFPA 252 Fire Tests of Door Assemblies.
4. ANSI A250.3 Test Procedure and Acceptance Criteria for Factory Applied
Finish Painted Steel Surfaces for Steel Doors and Frames.
5. ANSI A250.4 Test Procedure and Acceptance Criteria for Physical Endurance for Steel Doors and Hardware Reinforcings.
6. ANSI A250.5 Accelerated Physical Endurance Test Procedure for Steel Doors, Frames and Frame Anchors.
7. ANSI A250.6 Hardware on Steel Doors (Reinforcement – Application).
8. ANSI A250.7 Nomenclature for Standard Steel Doors and Steel Door Frames.
9. ANSI A250.8 – 1998 SDI-100 Recommended Specifications for Standard Steel
Doors and Frames.
10. ANSI A250.10 Test Procedure and Acceptance Criteria for Prime Painted Steel
Surfaces for Steel Doors and Frames.
11. ANSI/DHI A115 Specifications for Hardware Preparations in Standard Steel
Doors and Frames.
12. ANSI/DHI A115.1G Installation Guide for Doors and Hardware.
B. Steel Door Institute (SDI):
SECTION 08 01 10 - 2
1. SDI-100 Recommended Specifications for Standard Doors and Frames (Revised as ANSI A250.8 – 1998).
2. SDI-106 Recommended Standard Door Type Nomenclature.
3. SDI-108-90 Recommended Selection and Usage Guide for Standard Steel
Doors.
4. SDI-111 Recommended Standard Details Steel Doors and Frames.
5. SDI-112-97 Galvanized/Galvannealed Standard Steel Doors and Frames.
6. SDI-117-93 Manufacturing Tolerances Standard Steel Doors and Frames.
7. SDI-118-88 Basic Fire Door Requirements.
8. SDI-122-90 Installation and Troubleshooting Guide for Standard Doors and
Frames.
C. American Society for Testing Materials (ASTM):
1. A366 Standard Specification for Steel, Sheet, Carbon, Cold-Rolled, Commercial Quality.
2. A568 Standard Specification for Steel, Sheet, Carbon, and High-Strength, Low-Alloy, Hot-Rolled and Cold-Rolled, General Requirements.
3. A569 Standard Specification for Steel, Carbon (0.15 Maximum, Percent), Hot-
Rolled Sheet and Strip Commercial Quality.
4. A591 Standard Specification for Steel Sheet, Electrolytic Zinc-Coated, for light
Coating Mass Applications.
5. A620 Standard Specification for Steel, Sheet, Carbon, Cold-Rolled, Drawing
Quality, Special Killed.
6. A653 Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or
Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
7. A924 Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process.
D. National Fire Protection Association (NFPA):
1. NFPA 80-95: Fire Doors and Windows.
2. NFPA 101-94: Installation of Smoke-control Door Assemblies.
3. NFPA 101-94: Life Safety Code.
SECTION 08 01 10 - 3
A. American Steel Products, Curries, Republic.
2.02 DESCRIPTION
A. Construction:
1. General:
a. 16 gauge steel.
b. Galvanized subsequent to fabrication.
2. Core:
a. Loose mineral wool.
b. 20 gauge galvanized steel stiffeners, six (6) inches on-center.
3. Stiles and rails:
a. Continuously welded, 16 gauge steel channel.
B. Reinforcing:
1. Hinge:
a. 7 gauge.
b. Angle shape top hinge.
2. Lock sets, closers, concealed holders:
a. 12 gauge.
C. Finish:
1. Phosphatized, red zinc chromate, rust inhibitive primer.
D. Accessories:
1. Vision kits:
a. Two-part, sandwich type.
2. Louvers:
a. Fixed blade, eighty percent free area.
b. Fire rated as scheduled.
E. Label:
SECTION 08 01 10 - 4
1. Underwriters Laboratory (affixed, fire rated units).
A. Rehang or replace units that do not operate properly.
B. Touch-up unit components’ finish with appropriate primer or galvanizing repair, as applicable.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating STEEL DOOR FRAMES
SECTION 08 01 11 - 1
SECTION 08 01 11
STEEL DOOR FRAMES
A. Furnish and install steel door frames in accordance with the parameters shown on the drawings and herein specified.
B. Units shall be the roll formed type; factory fabricated and machined; ANSI/SDI, DHI and NFPA compliant; complete with head, jambs, anchors, reinforcing, factory applied finish and accessories.
1.02 REFERENCED STANDARDS
A. American National Standards Institute (ANSI):
1. ANSI/UL 10B Fire Tests of Door Assemblies.
2. ANSI/NFPA 252 Fire Tests of Door Assemblies.
3 ANSI A250.3 Test Procedure and Acceptance Criteria for Factory Applied
Finish Painted Steel Surfaces for Steel Doors and Frames.
4 ANSI A250.5 Accelerated Physical Endurance Test Procedure for Steel Doors, Frames and Frame Anchors.
5. ANSI A250.7 Nomenclature for Standard Steel Doors and Steel Door Frames.
6. ANSI A250.8 – 1998 SDI-100 Recommended Specifications for Standard Steel
Doors and Frames.
7. ANSI A250.10 Test Procedure and Acceptance Criteria for Prime Painted Steel
Surfaces for Steel Doors and Frames.
8. ANSI/DHI A115 Specifications for Hardware Preparations in Standard Steel
Doors and Frames.
B. Steel Door Institute (SDI):
1. SDI-100 Recommended Specifications for Standard Doors and Frames
(Revised as ANSI A250.8 – 1998).
2. SDI-105-92 Recommended Erection Instructions for Steel Frames.
3. SDI-111 Recommended Standard Details Steel Doors and Frames.
4. SDI-112-97 Galvanized/Galvannealed Standard Steel Doors and Frames.
SECTION 08 01 11 - 2
5. SDI-117-93 Manufacturing Tolerances Standard Steel Doors and Frames.
6. SDI-122-90 Installation and Troubleshooting Guide for Standard Doors and
Frames.
C. American Society for Testing Materials (ASTM):
1. A366 Standard Specification for Steel, Sheet, Carbon, Cold-Rolled, Commercial Quality.
2. A568 Standard Specification for Steel, Sheet, Carbon, and High-Strength, Low-Alloy, Hot-Rolled and Cold-Rolled, General Requirements.
3. A569 Standard Specification for Steel, Carbon (0.15 Maximum, Percent), Hot-
Rolled Sheet and Strip Commercial Quality.
4. A591 Standard Specification for Steel Sheet, Electrolytic Zinc-Coated, for light
Coating Mass Applications.
5. A620 Standard Specification for Steel, Sheet, Carbon, Cold-Rolled, Drawing
Quality, Special Killed.
6. A653 Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or
Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
7. A924 Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process.
D. National Fire Protection Association (NFPA):
1. NFPA 80-95: Fire Doors and Windows.
2. NFPA 101-94: Installation of Smoke-control Door Assemblies.
3. NFPA 101-94: Life Safety Code.
PART 2 – PRODUCTS
2.01 ACCEPTABLE MANUFACTURERS
A. American Steel Products, Curries, Republic.
A. Head, jambs:
1. 14 gauge, cold rolled steel.
2. Precisely mitered, CONTINUOUSLY welded corners, ground smooth.
3. Temporary angle spreader.
4. Closed end, 45 degree, sanitary stops.
SECTION 08 01 11 - 3
5. Galvanized subsequent to fabrication.
B. Anchors:
1. Complementary with designated construction.
2. Four (4) per jamb, two (2) at head.
C. Reinforcing:
1. Hinge:
a. 7 gauge.
2. Strike:
3. Closer:
a. 14 gauge.
4. Flush bolt:
5. Head (greater than 48 inches):
a. 12 gauge, continuously welded angle stiffener.
D. Finish:
1. Phosphatized, red zinc chromate, rust inhibitive primer.
E. Accessories:
1. Pressure applied rubber silencers.
2. Hardware cutout cover boxes.
F. Label:
1. Underwriters Laboratory (affixed, fire rated units).
1. Erect units carefully plumb and true.
SECTION 08 01 11 - 4
2. Touch-up unit components’ finish with appropriate primer or galvanizing repair, as applicable.
B. Provide knocked-down units only where circumstances mandate and approval is granted.
AFRL, Bldg. 101, Convert Steam to Hot Water Heating GYPSUM BOARD SYSTEMS
SECTION 09 02 60 - 1
SECTION 09 02 60
GYPSUM BOARD SYSTEMS
A. Furnish and install gypsum board systems to serve walls and partitions in…
This is the start of the file's text. The full file is on GovTribe.