204107001_JHW AFI Hangar_Project Manual.pdf

PDF 8 MB Posted

Attached to
Airport Facilities Improvements--Hangar
Solicitation number
PW-6-26 JHW
Issued by
Chautauqua County, New York

About this file

This is a Project Manual for the Airport Facilities Improvements (Hangar) construction project at Chautauqua County Airport in Jamestown, New York, issued by the Chautauqua County Division of Purchasing in coordination with C&S Engineers, Inc. The project encompasses the construction of a hangar facility with associated mechanical, electrical, and plumbing work. The Invitation to Bid (ITB) No. PW-6-26 JHW was issued on October 15, 2026, with questions due by November 12, 2026, a pre-bid meeting scheduled for October 27, 2026 at 11:00 a.m. at Chautauqua County Airport, and sealed bids due at 2:00 p.m. on November 19, 2026. The contract will end on December 31, 2028. Bids must be submitted to the Chautauqua County Department of Finance-Purchasing Division at 454 N. Work Street, Falconer, New York 14733. The project is identified under Comptroller's Contract No. K007529 and NYSDOT Project No. 5903.57, with the project manual referencing prevailing wage requirements and multiple federal and state compliance certifications.

The bid documents require a bid guaranty of not less than ten percent (10%) of the total base bid amount in the form of a certified check, bank draft, or irrevocable letter of credit. The project includes set-asides for Minority-owned Business Enterprises (10%), Women-owned Business Enterprises (15%), and Service-Disabled Veteran-Owned Businesses (6%). The successful bidder must provide performance and payment bonds each in an amount not less than one hundred percent (100%) of the total contract amount, along with proof of required insurance prior to contract execution. The contract documents specify compliance with New York State prevailing wage rates, Article 8 Labor Law requirements, and multiple state and federal regulations including OSHA, environmental protection standards, and non-discrimination provisions. No specific contract value is stated in the document. The County reserves the right to terminate the contract at any time for any reason upon thirty (30) days' written notice, and all awards are subject to available funding.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DOCUMENTS

FOR THE CONSTRUCTION OF

AIRPORT FACILITIES IMPROVEMENTS

(HANGAR)

CHAUTAUQUA COUNTY AIRPORT - JAMESTOWN

CHAUTAUQUA COUNTY

JAMESTOWN, NEW YORK

COMPTROLLER’S CONTRACT NO. K007529

NYSDOT PROJECT NO. 5903.57

OCTOBER 2026

CONTRACT DOCUMENTS

FOR THE CONSTRUCTION OF

AIRPORT FACILITIES IMPROVEMENTS

(HANGAR)

CHAUTAUQUA COUNTY AIRPORT - JAMESTOWN

JAMESTOWN, NEW YORK

COMPTROLLER’S CONTRACT NO. K007529

NYSDOT PROJECT NO. 5903.57

OCTOBER 2026

C&S ENGINEERS, INC.

499 COL. EILEEN COLLINS BLVD.

SYRACUSE, NY 13212

Michael W. LaMontagne – N.Y.S.R.A. Lic. No. 031950

PROJECT NO. 204.107.001

NO ALTERATION PERMITTED HEREIN EXCEPT AS PROVIDED UNDER SECTION 7209

SUBDIVISION 2 OF THE NEW YORK STATE EDUCATION LAW..

2018 TOC-1

TABLE OF CONTENTS

CHAUTAUQUA COUNTY CONTRACT REQUIREMENTS

PROPOSAL

ATTACHMENTS TO PROPOSAL

Non-Collusive Bidding Certificate

Resolution for Corporate Bidders

Buy American Certification

Certifications:

- Certification of Non-Segregated Facilities

- Debarment & Suspension Certification

Bidder’s Statement of Previous Contracts Subject to EEO Clause as Described in Special

Certification for Receipt of Addenda

Statement of Surety’s Intent

Iranian Energy Sector Divestment Statement

Certification of Compliance with the Iran Divestment Act

Disadvantaged Business Enterprise Statement

Bidder’s List Collection Form (Bidder’s Information)

Bidder’s List Collection Form (Subcontractor’s Information)

Prevention of Sexual Harassment Statement”

New York State MWBE Participation, Certification of Bidder

NYSDOT DOT Forms

Form AAP10LL –Solicitation Log

Form AAP19LL – Schedule of Utilization (Part 1 - MBE)

Form AAP19LL – Schedule of Utilization (Part 2- WBE)

Form AAP19LL – Schedule of Utilization (Part 3- SDVOB)

Form AAP23LL – Pre-Award Trucking Commitment Information

CONTRACT FORM

SPECIFICATIONS

PART 1 - GENERAL CONTRACT PROVISIONS

Section 10 Definition of Terms

Section 20 Proposal Requirements and Conditions

20-01 - Advertisement (Notice to Bidders)

20-02 - Qualifications of bidders

20-03 - Contents of proposal forms

20-04 - Issuance of proposal forms

20-05 - Interpretation of estimated proposal quantities

20-06 - Examination of plans, specifications and site

20-07 - Preparation of proposal

20-08 Responsive and responsible bidder

20-09 - Irregular proposals

20-10 - Bid guarantee

20-11 - Delivery of proposal

2018 TOC-2

20-12 - Withdrawal or revision of proposals

20-13 - Public opening of proposals

20-14 - Disqualification of bidders

20-15 - Discrepancies and omissions

Section 30 Award and Execution of Contract

30-01 - Consideration of proposals

30-02 - Award of contract

30-03 - Cancellation of award

30-04 - Return of proposal guarantee

30-05 - Requirements of contract bonds

30-06 - Execution of contract

30-07 - Approval of contract

30-08 - Failure to execute contract

Section 40 Scope of Work

40-01 - Intent of contract

40-02 - Alteration of work and quantities

40-03 - Omitted items

40-04 - Extra work

40-05 - Maintenance of traffic

40-06 - Removal of existing structures

40-07 - Rights in and use of materials found in the work

40-08 - Final cleanup

Section 50 Control of Work

50-01 - Authority of the Resident Project Representative (RPR)

50-02 - Conformity with plans and specifications

50-03 - Coordination of contract, plans and specifications

50-04 - List of Special Provisions

50-05 - Cooperation of Contractor

50-06 - Cooperation between contractors

50-07 - Construction layout and stakes

50-08 - Authority and duties of Quality Assurance (QA) inspectors

50-09 - Inspection of the work

50-10 - Removal of unacceptable and unauthorized work

50-11 - Load restrictions

50-12 - Maintenance during construction

50-13 - Failure to maintain the work

50-14 - Partial acceptance

50-15 - Final acceptance

50-16 - Claims for adjustment and disputes

Section 60 Control of Materials

60-01 - Source of supply and quality requirements

60-02 - Samples, tests and cited specifications

60-03 - Certification of compliance/analysis (COC/COA)

60-04 - Plant inspection

60-05 - Engineer/ Resident Project Representative (RPR) field office

60-06 - Storage of materials

60-07 - Unacceptable materials

2018 TOC-3

60-08 - Owner furnished materials

Section 70 Legal Regulations and Responsibility to Public

70-01 - Laws to be observed

70-02 - Permits, licenses and taxes

70-03 - Patented devices, materials and processes

70-04 - Restoration of surfaces disturbed by others

70-05 - Federal participation

70-06 - Sanitary, health and safety provisions

70-07 - Public convenience and safety

70-08 - Construction Safety and Phasing Plan (CSPP)

70-09 - Use of explosives

70-10 - Protection and restoration of property and landscape

70-11 - Responsibility for damage claims

70-12 - Third party beneficiary clause

70-13 - Opening sections of the work to traffic

70-14 - Contractor’s responsibility for work

70-15 - Contractor’s responsibility for utility service and facilities of others

70-16 - Furnishing rights-of-way

70-17 - Personal liability of public officials

70-18 - No waiver of legal rights

70-19 - Environmental protection

70-20 - Archaeological and historical findings

Section 80 Execution and Progress

80-01 - Subletting of contract

80-02 - Notice to proceed

80-03 - Execution and progress

80-04 - Limitation of operations

80-04.1 - Operational safety on airport during construction

80-05 - Character of workers, methods and equipment

80-06 - Temporary suspension of the work

80-07 - Determination and extension of contract time

80-07.1 - Contract time based on Calendar Days

80-08 - Failure to complete on time

80-09 - Default and termination of contract

80-10 - Termination for national emergencies

80-11 - Work area, storage area and sequence of operations

Section 90 Measurement and Payment

90-01 - Measurement of quantities

90-02 - Scope of payment

90-03 - Compensation for altered quantities

90-04 - Payment for omitted items

90-05 - Payment for extra work

90-06 - Partial payments

90-07 - Payment for materials on hand

90-08 - Payment of withheld funds

90-09 - Acceptance and final payment

90-10 - Construction warranty

2018 TOC-4

90-11 - Contractor Final Project Documentation

SPECIAL PROVISIONS TO THE GENERAL CONTRACT PROVISIONS

SP 20-16 Addenda and interpretation

SP 20-17 Sales tax exemption

SP 30-09 Conformed Contract Documents

SP 30-10 Issued for Construction Contract Documents

SP 50-17 Additional Survey Requirements

SP 50-18 Removal of water

SP 50-19 Sheeting and bracing

SP 60-09 Shop and setting drawings and catalogue data

SP 60-10 Electrical shop drawings

SP 60-11 Substitute items

SP 60-12 Submittal procedure

SP 70-22 Additional sanitary, health, and safety provisions

SP 70-24 New York State Department of Transportation (NYSDOT) standard clauses for New York state contracts

1. Executory Clause

2. Non-Assignment Clause

3. Comptroller's Approval

4. Workers' Compensation Benefits

5. Non-Discrimination Requirements

6. Wage and Hours Provisions

7. Non-Collusive Bidding Certification

8. International Boycott Prohibition

9. Set-Off Rights

10. Records

11. Identifying Information and Privacy Notification

12. Equal Employment Opportunities for Minorities and Women

13. Conflicting Terms

14. Governing Law

15. Late Payment

16. No Arbitration

17. Service of Process

18. Prohibition on Purchase of Tropical Hardwoods

19. MacBride Fair Employment Principles

20. Omnibus Procurement Act of 1992

21. Reciprocity and Sanctions Provisions

22. Compliance with New York State Information Security Breach and

Notification Act

23. Compliance with Consultant Disclosure Law

24. Procurement Lobbying

25. Certification of Registration to Collect Sales and Compensating Use Tax by Certain Contractors, Affiliates and Subcontractors

SP 70-25 NYSDOT terms and conditions

SP-70-26 Labor affidavits, New York State Laws of 1988

SP 90-12 Security for construction warranty

SP 90-13 Lien law

SUBCONTRACTOR’S PROMPT PAYMENT CERTIFICATION

STATE WAGE RATES

2018 TOC-5

SPECIAL NOTE NEW YORK STATE DEPARTMENT OF LABOR PREVAILING

WAGE RATES

PRIME CONTRACTOR’S CERTIFICATION (NEW YORK STATE LABOR LAW

SECTION 220-a)

SUBCONTRACTOR’S CERTIFICATION (NEW YORK STATE LABOR LAW

SECTION 220-a)

PART 2 – GENERAL CONSTRUCTION ITEMS

Item Number Description

Item C-105 Mobilization

TECHNICAL SPECIFICATIONS

ITEM NUMBER DESCRIPTION

DIVISION 02 – EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 22 – PLUMBING

220529 SUPPORTS AND ANCHORS

221123 FACILITY NATURAL-GAS PIPING

DIVISION 23 – HEATING, VENTILATION, AND AIR CONDITIONING

233113 METAL DUCTS

235533 GAS-FIRED UNIT HEATERS

DIVISION 26 – ELECTRICAL

260519 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGARS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533.13 CONDUITS FOR ELECTRICAL SYSTEMS

260533.16 BOXES AND COVERS FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

262726.11 GENERAL-USE SWITCHES, DIMMER SWITCHES, AND FAN-SPEED

CONTROLLER SWITCHES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

CONTRACT DRAWINGS

Refer to Contract Drawings For Sheet List

END OF TABLE OF CONTENTS

DIVISION OF PURCHASING

INVITATION TO BID

AIRPORT FACILITIES IMPROVEMENTS--HANGAR

ITB No. PW-6-26 JHW

Contact Person: Becky Anderson, Purchasing Manager, andersob@chqgov.com

Issue Date: 10/15/2026 Questions Due By: 11/12/2026 Pre-Bid Meeting: 10/27/2026 at 11:00am at Chautauqua County Airport - Jamestown Bid Opening Date (2:00PM): 11/19/2026

Sealed bids are to be remitted no later than the due date and time to:

Purchasing Manager Chautauqua County

Dept of Finance—Purchasing Division 454 N. Work Street Falconer, NY 14733

Paul M. Wendel, Jr.

County Executive

Kitty Lyons

Director of Finance

Becky Anderson

Brandi McIntyre

Purchasing Agent

Nicole Pattison

Tina Huckabone mailto:andersob@chqgov.com

NOTICE TO BIDDERS

Publish Date: October 15, 2026

Chautauqua County is accepting sealed bids for:

INVITATION TO BID

NO. PW-6-26 JHW

AIrport Facilities Improvements--Hangar

Invitation to Bid (ITB) Documents are available at the County’s Purchasing Office, 454 N. Work Street, Falconer, NY 14733, may be downloaded from Bidnetdirect.com/new-york, or may be requested by email from andersob@chqgov.com. Chautauqua County is not responsible for the completeness or accuracy of ITB documents received from any other source, and the successful bidder shall be subject to official County ITB terms and conditions.

Bids must be received by the County’s Purchasing Office no later than 2:00 P.M. on November 19, 2026, at which time they will be publicly opened and read. Each bid envelope must be plainly marked with the proposal number and the item bid therein.

mailto:andersob@chqgov.com

Invitation to Bid No. PW-6-26 JHW Bids Due:

At Chautauqua County Finance Department, Purchasing Division

454 N. Work Street, Falconer NY 14733

2:00 PM

THE FOLLOWING FORMS MUST BE SUBMITTED

BID FORM

SEALED SUBCONTRACTORS LIST

NON-COLLUSION BIDDING CERTIFICATION

AFFIDAVIT'S

ACKNOWLEDGEMENT'S

By submission of this bid, the bidder and each person signing on behalf of the bidder certifies that they have read and adhere to all the terms and conditions as proposed in the attached Invitation for PW-6-26 JHW and any addendums received for the Airport Facilities Improvements—Hangar.

Submittal Page:

COMPANY NAME________________________________________________

SIGNED________________________________________________________

PRINT NAME OF SIGNER_________________________________________

TITLE_________________________________________________________

E-MAIL_______________________________________________________

FEDERAL ID NO.______________________________________________________________

Public Work Contractor and Subcontractor Registry

All contractors and subcontractors submitting bids or performing construction work on “Public Work” projects or private projects covered by Article 8 of the Labor Law are required to register with the New York State Department of Labor (NYSDOL) under Labor Law Section 220-i. This requirement does not apply to Building Service Contracts covered by Article 9 of the Labor Law.

The New York Labor Law does not expressly define “public works.” However, New York’s highest court has articulated a three-pronged test to determine whether a particular project is subject to the Labor Law Section 220 prevailing wage requirements: “First, a public agency must be a party to a contract involving the employment of laborers, workers, or mechanics. Second, the contract must concern a project that primarily involves construction-like labor and is paid for by public funds. Third, the primary objective or function of the work product must be the use or other benefit of the general public.” De La Cruz v. Caddell Dry Dock & Repair Co., Inc., 21 N.Y.3d 530, 538 (2013).

The law defines a “contractor” as any entity entering into a contract to perform construction, demolition, reconstruction, excavation, rehabilitation, repair, installation, renovation, alteration, or custom fabrication. The law defines “subcontractor” as any entity subcontracting with a contractor to perform construction, demolition, reconstruction, excavation, rehabilitation, repair, installation, renovation, alteration, or custom fabrication, which is subject to Article 8 of the Labor Law. Contractors are responsible for verifying that any subcontractors they work with are registered.

Contractors need to register before submitting any bids or commencing work on a covered project. Subcontractors need to register before commencing work on a covered project. NYSDOL encourages all contractors and subcontractors to register as soon as possible to obtain a Certificate of Registration to avoid negatively impacting a bidding period or project schedule.

Pursuant to Labor Law Section 220-j, all submissions of certified payroll records will be collected through New York’s online database. For more information, please see:

https://dol.ny.gov/Electronic-Payroll.

The Bureau of Public Work & Prevailing Wage Enforcement at the New York State Department of Labor is responsible for enforcing prevailing wage laws in New York State, and publishes the annual prevailing wage schedule every year on July 1. For prevailing wage rates for your area, or for contact information for your local Public Works and Prevailing Wage Enforcement District Office, please email labor.sm.pwask@labor.ny.gov.

https://www.nysenate.gov/legislation/laws/LAB/A8 https://www.nysenate.gov/legislation/laws/LAB/220-I https://dol.ny.gov/Electronic-Payroll mailto:labor.sm.pwask@labor.ny.gov

ATTENTION BIDDERS – BID RESPONSE FORM

If you find that you are not interested in bidding/quoting this particular project please indicate your reasons below. If you wish to be removed from our bidders list, please fill in this sheet and return by emailing or faxing to: andersob@chqgov.com.

Bid Number: PW-6-26 JHW Name of Project being bid: Airport Facilities Improvements--Hangar

VENDOR NAME: ______________________________________

COMPANY: ______________________________________

ADDRESS: ______________________________________

PHONE:____________________/Email: _____________________________

For purposes of facilitating your firm's response to our invitation to bid, the County of Chautauqua is interested in hearing reasons for your not wishing to be on the bid list.

WE ARE NOT INTERESTED BECAUSE:

_____ Service requested is not provided by our Company.

_____ Services and/or materials do not meet your specifications.

_____ Specifications are not clearly understood or applicable _____too vague _____ too rigid.

_____ Job/Project is too small

_____ Insurance Requirement

_____ Other reason not listed above (or) elaborate on the checked marked reason above:

RESPONSE CHECKLIST - ITB NO. PW-6-26 JHW

Please note below a list of documents which must be submitted in full as part of this bid. Failure to submit any of the documents as part of your bid or failure to acknowledge any addendum in writing with your bid may be cause for rejection of the bid.

Please check each item indicating your compliance:

THIS CHECKLIST MUST BE SUBMITTEDAS PART OF YOUR BID.

_____RESPONSE CHECKLIST

_____NON-COLLUSION CERTIFICATE

_____IRANIAN DIVESTMENT CERTIFICATE

_____FINANCIAL AFFIDAVIT

_____ AFFIDAVIT OF A FOREIGN CORPORATION

_____CORPORATE ACKNOWLEDGEMENT CERTIFICATE

_____EXCLUSION CHECK

_____BID FORM

_____REQUIRED FORMS AS LISTED IN THE SPECIFICATIONS AS APPLICABLE

_____ADDENDUM(S) ACKNOWLEDGE (IF APPLICABLE)

_____ONE (1) ORIGINAL AND ONE (1) COPY OF YOUR SUBMITTED BID

_____INSURANCE CERTIFICATES

COMPANY

TELEPHONE NUMBER

ADDRESS

EMAIL ADDRESS

AUTHORIZED REPRESENTATIVE (PRINT) TITLE

AUTHORIZED SIGNATURE

DATE

INSTRUCTIONS TO BIDDERS

Enclosed with these Instructions are:

(a) A Copy of the Public Notice identifying goods and/ or services being sought and specifying the date, time and location of receipt and examination of bids by Chautauqua County;

(b) Specification(s) for item(s) on which bids are being solicited; and

(c) Non-Collusion Bidding Certification, Bid Response Form, Bid Form, Sealed Subcontractors list

(as applicable), Corporate Affidavit, Affidavit of Financial Records, and Iranian Divestment

Certification Pursuant to Section 103-g, all of which must be completed and returned with each bid submitted. Product Data Sheets may also be submitted when applicable.

1. Bidders are responsible for submitting their bids to the appropriate location at or prior to the date and time set forth in County’s bid documents. No bids will be accepted after the designated date and time. Delay in mail delivery is not an exception to this rule. BIDS WILL NOT BE

ACCEPTED VIA FACSIMILE OR E-MAIL. Bids which are not timely submitted will be returned unopened.

2. ADDENDUMS/MODIFICATIONS: Questions must be submitted by November 12, 2026 as specified on the front sheet of this invitation to bid. All questions must be sent to the Purchasing

Manager or Agent. The questions will be forwarded to the department or Engineering Firm for clarification. The clarifications shall be sent via email to all plan holders and posted on Bidnet. The

Engineering firm may disperse clarifications on behalf of the Purchasing Manager or Agent.

• “From the time of issuance of a County Invitation for Bid until final determination of the successful vendor, all prospective vendor questions and communications shall be directed to the Purchasing Manager and/or agent. Contacting any other County employee prior to County’s issuance of a bid award may result in rejection of a bid.”

Only those bidders who obtain documents from the Purchasing Division and Bidnet are guaranteed to receive addendum information.

3. Bids must be submitted in a sealed envelope plainly marked with the title of the bid and the bid number. Bidder’s name and complete mailing address must be included on the outside of the envelope.

and/or Agent in Charge:

Bid Title: Airport Facilities Improvements—Hangar

ITB No. PW-6-26 JHW

4. As set forth in General Municipal Law §109, bid awards may not be assigned, transferred, conveyed, sublet or otherwise disposed of without County’s express written consent. Awards are subject to available funding.

5. Please complete the Bid Response form and email to andersob@chqgov.com. Chautauqua County encourages all qualified applicants, including Minority-owned Business Enterprises, Women-owned

Business Enterprises, Small Business Enterprises and Disadvantaged Business Enterprises, to partake in the bidding of this and all other commodities. The successful Bidder must be an EOE.

6. Chautauqua County is exempt from all Federal and State taxes.

7. By submitting a bid, you are asking the county of Chautauqua to accept your offer for the sale of goods or services. It is important that you READ and UNDERSTAND all terms and conditions herein as well as understand the laws that govern Municipal Purchasing which can be found at http://public.leginfo.state.ny.us. All awards are subject to available funding. Each project will be bid individually and awarded as such.

8. The enclosed bid forms must be used and may not be substituted amended, or altered. Bids submitted that are not on the enclosed forms will not be considered. All bid documents must be submitted for each bid, and must be signed by an authorized individual. Documents with a place for a notary signature must be notarized. Copies of bid documents obtained from any other source are not official copies.

9. Bid Guaranty: Where applicably indicated, each Proposal must be accompanied by a bid guaranty which shall not be less than ten percent (10%) of the total base bid amount. The guaranty may be a certified check, bank draft, or standard form Irrevocable Letter of Credit. If the specified form of bid guaranty is a Bid Bond, such Bond shall be secured by a guaranty or surety company authorized to do business in the State of New York as a surety. Proposals received without the specified guaranty may be deemed non-responsive. Certified check or bank draft must be payable to the order of "Chautauqua County Director of Finance." Cash deposits will not be accepted. The bid guaranty shall insure the execution of the Agreement and the furnishing of the surety bond or bonds and insurance by the successful Contractor, all as required by the Contract Documents.

Bid guaranties in the form of certified check, bank draft or letter of credit will be returned to bidders other than the successful Contractor within ten (10) days after the contract is awarded. The bid guaranty of the successful Contractor will be returned upon execution of the Contract and submission of required bonds and insurance. All awards are subject to available funding.

10. Contract Term:

a.) The Contract Time shall be as defined in Section 80. The contract will end December 31, 2028.

b.) Chautauqua County reserves the right to terminate this contract at any time for any reason in whole or in part upon thirty (30) days’ written notice to the successful Contractor. The County also reserves the right to cancel the contract immediately for breach or non-performance.

http://public.leginfo.state.ny.us/

11. Withdrawal of Bids: Negligence on the part of the Bidder in preparing his bid confers no right for the withdrawal of the bid after it has been opened. Any Bidder, upon his properly notarized written request, will be given permission to withdraw his bid not later than the time set for opening. At the time of opening of the bids, when such bid is included, it will be returned to the Bidder unopened.

Pursuant to General Municipal Law, Section 105, Contractor may not withdraw its bid within forty-five (45) days after the bid opening.

12. Execution of Agreement:

a. The Bidder, whose proposal has been accepted, shall have a legally authorized representative execute the Agreement and submit it to the County Legal department as directed as such

Department.

b. In addition, the successful Bidder, within the period stipulated in the Notice of Award, shall procure, execute, and deliver to the County and maintain, at its own cost and expense, until the Final

Completion date of the work covered by this Agreement, proof of insurance as required on the attached Appendix “C”, and a performance and payment bonds submitted by a surety company authorized to do business in the State of New York as a Surety:

• Chautauqua County requires the bonds and insurance prior to execution of the Agreement.

These documents will be considered as part of the final contract.

• Please note that contracts $10,000.00 or less are not subject to performance and payment bonds.

• Contractor shall not perform any work pursuant to the Agreement, and shall not be entitled to any payment under the Agreement, unless and until County is in possession of all requested Bond Certificates.

(1) Performance Bond - in an amount not less than one-hundred percent (100%) of the total amount payable to the Contractor by the terms of the contract.

(2) Labor and Material Bond - in an amount not less than one hundred percent (100%) of the total amount payable to the Contractor by the terms of the contract.

13. Award:

Each project will be awarded separately. All awards are subject to available funding.

GENERAL CONDITIONS OF THE CONTRACT

INDEX

GENERAL PROVISIONS

1. Introduction

2. Definitions

3. Intent of Documents and Instructions

4. Contract Drawings and Technical Specifications

5. Errors and Discrepancies

6. Industry Standards, Codes, and Specifications

7. Record Drawings

ADMINISTRATIVE PROVISIONS

8. Insurance

9. Royalties and Patents

10. Permits and Laws

11. Assignment

12. Title to Project Materials

13 Exemption from Sales and Compensating Use Taxes and Surcharges

14. Liens

PROSECUTION AND PROGRESS

15. Preconstruction Conference

16. On-Site Job Meetings

17. Construction Schedule

18. Subcontractors

19. Coordination with other Contractors, Utilities, and Owner Forces

20. Correction of Work

21. Payments to the Contractor

22. Payments Withheld

23. Temporary Suspension of Work

24. Changes to the Work

25. Emergencies

26. Differing Site Conditions

27. Claims for Extra Cost

28. Delays and Extension of Time

29. Delay Damages

30. Right to Use Work

31. Guarantee Period

32. Owner's Right or Terminate and/or Complete Contract

33. Removal of Equipment and Supplies

MATERIAL AND WORK REQUIREMENTS

34. Workmanship

35. Shop Drawings

36. Samples

37. General Arrangement

38. Standard Products and Materials

39. Certificates

40. Tests

41. Equivalents and Substitutions

42. Additional Engineering Services

43. Structural Design

44. Dimensions

45. Maintenance and Operations Manual/Spare Parts Data

SITE CONDITIONS

46. Site Investigation

47. Location of Existing Utilities

48. Borings and Subsurface Data

49. Survey and Layout

50. Superintendence

51. Safety and Protection

52. Accidents

53. Temporary Services

54. Storage and Handling of Materials

55. Protection of Work, Materials, and Equipment

56. Inclement Weather

57. Protection of Property

58. Cleaning Up

59. Inspection of Work

GENERAL CONDITIONS OF THE CONTRACT

GENERAL PROVISIONS

1. INTRODUCTION

The purpose of the “General Conditions of the Contract” is to set forth the general manner in which Owner, Contractor, and Consultant will perform under the Agreement. The provisions of the “Supplementary General Conditions” may modify specific requirements of these General Conditions.

2. DEFINITIONS

a. “Agreement” or “The Agreement” means the contract executed by Contractor and Owner, including amendments and change orders executed by both parties.

b. “Consultant” means a professional designated by Owner as Owner’s consultant, which may be an engineering, architect, landscape architect, or surveyor firm.

c. “Contract Documents” means documents defined as such in the Agreement, and includes without limitation the Agreement, the Notice to Bidders, Instructions to Bidders, Contractor’s bid, the bid guaranty, bid bonds, General Conditions, Special Conditions, Drawings and Specifications, and all modifications thereof.

d. Contractor” means the bidder which is awarded the Agreement.

e. “Owner” or “County” means the County of Chautauqua.

f. “Project” means all items encompassed by Owner’s bid package and the Contract Documents, including items in Contractor’s Agreement, items in the agreements of other contractors, and items to be addressed by Owner, utility companies, and others.

g. "Work" or “The Work” means all labor, materials, equipment, and other incidentals and things to be done, furnished, or performed by Contractor to construct the Project, pursuant to and in accordance with its Agreement.

3. INTENT OF DOCUMENTS AND INSTRUCTIONS

a. The Specifications, Drawings, and any instructions set forth in the bid package are complemen-tary. They are intended to provide for and include everything necessary for the proper and orderly execution and completion of the Project. Any Work shown in the bid documents for which there are no particular specifications, or the omission from bid Drawings and/or bid Specifications of express reference to any work which obviously was intended to be included in the Project, shall not excuse or relieve Contractor from furnishing the same. Work or materials described in words which have a generally accepted technical or trade meaning, shall be interpreted by such customary and recognized standard of meaning.

b. Wherever the words "directed," "required," "permitted," "ordered," "designated," "prescribed," or words of like import are used in the Specifications or on the Drawings, it shall be understood that the direction, requirement, permission, order, designation, and prescription of Owner is intended.

Similarly, the words "approved," "acceptable," "satisfactory," and words of like import shall mean approved by, acceptable to, and satisfactory to Owner, unless otherwise expressly stated.

c. References herein to Contractor’s employees shall be deemed to mean any person working on the Project who is under Contractor’s or its subcontractor’s direction and control, or who receives compensation from Contractor.

d. Written notice shall be deemed to have been given: upon receipt, if delivered in person to the individual or to a member of the firm, or to an officer of the corporation, for which it is intended;

on the third day after mailing if sent by first-class mail; upon delivery, if sent by overnight delivery;

on the next business day, if sent via facsimile; or upon receipt of a “delivery receipt,” if sent via e-mail. Notices which are sent via mail shall be sent to the address listed on the first page of the Agreement, or to such alternate address as the recipient has specified in writing. Notices sent via facsimile or e-mail shall be sent to such address as the recipient specifies, in writing.

e. All time limits stated in the Contract Documents are of the essence.

f. All directives to Contractor shall be issued by Owner unless otherwise specified in the bid documents, or in writing by Owner. All Contractor inquiries shall be directed to Owner.

4. CONTRACT DRAWINGS AND TECHNICAL SPECIFICATIONS

a. Contractor will be furnished, without charge, five sets of Contract Drawings, and five sets of Technical Specifications. County will provide such documents either on compact disk or in paper form. Additional sets of documents will be furnished, upon Contractor’s request, at cost.

b. All deviations from the Drawings and Specifications proposed by Contractor, whether prior to or during construction, shall require Owner’s written approval. Contractor’s written deviation request shall be accompanied by complete drawings, details, and specifications covering the proposed Work, all prepared under the supervision of a professional engineer or architect licensed by the State of New York and subject to the approval of Owner, at Contractor’s expense.

5. ERRORS AND DISCREPANCIES

The bid Drawings are intended to agree with the bid Specifications. Should any discrepancy arise between them or any error, discrepancy, or inconsistency appear or occur in Drawings or Specifications or in work performed by other Contractors employed by Owner, Contractor, before proceeding with the Work, shall contact Owner for clarification and in no case shall Contractor proceed with the Work until advised in writing by Owner. Determinations made by Owner in this regard shall be final and conclusive. Where work is shown schematically on the bid Drawings, Contractor shall be responsible for the proper arrangement of its Work to avoid interferences with adjacent work.

6. INDUSTRY STANDARDS, CODES, AND SPECIFICATIONS

a. Wherever reference is made to any published standards, codes, or standard specifications, it shall mean the standard code, specification, or tentative specification of the technical society, organization, or body referred to, which is in effect on the date of the Work. Where specified articles, sections, paragraphs, or other subdivisions of the referenced publications are not stated, the referenced publication shall apply in full. Where a date is indicated for a standard, code, or standard specification, the latest or most recent revision in effect at the date of the Work shall apply.

b. The following is a partial list of typical abbreviations which may be used in the Specifications and the organizations to which they refer:

AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute AGA American Gas Association AIA American Institute of Architects AISC American Institute of Steel Construction ANSI American National Standards Institute API American Petroleum Institute ASTM American Society for Testing and Materials AWS American Welding Society AWWA American Water Works Association Fed. Spec. Federal Specifications NEC National Electric Code NEMA National Electrical Manufacturers Association OSHA Occupational Safety and Health Administration CRSI Concrete Reinforcing Steel Institute

c. Contractor, when required, shall furnish evidence satisfactory to Owner that materials and methods are in accordance with such standards, as required. Such standards, codes, and specifications shall be construed to be the minimum requirements of Contract Documents.

7. RECORD DRAWINGS

a. Contractor shall obtain at its expense one (1) set of construction contract drawings in non-reproducible black and white print for the purpose of recording as-built conditions.

b. Contractor shall perform all survey work required for the location and construction of Work, and for the recording of information necessary for completion of the record drawings. Record drawings shall show the actual location of the Work in the same manner as was shown on the bid drawings.

All elevations and dimensions shown on the drawings shall be verified or corrected so as to provide a complete and accurate record of the facilities as constructed.

c. Contractor shall mark each sheet of the non-reproducible drawings in pencil and record thereon, in a legible manner, any and all approved field changes and conditions as they occur. A complete file of approved field sketches, diagrams, and other changes shall also be maintained and attached to the as-built set of drawings. At completion of the work, each sheet of as-built prints, plus all approved field sketches and diagrams, shall be certified as reflecting as-build conditions and submitted to Owner or Consultant, for its approval and use in preparation of Record Drawings and in establishing the value of the work to be specified in the final certificate.

d. Owner will record all approved field changes and conditions on the reproducible record drawings.

Each sheet will be signed by Owner, and will be certified as reflecting "as-built" conditions by a licensed engineer, architect, landscape architect, or surveyor, as appropriate, employed by Owner.

ADMINISTRATIVE PROVISIONS

8. INSURANCE

Contractor shall furnish the insurance as described in the Agreement. Within ten (10) calendar days of the Notice of Award and prior to the commencement of any work under the Agreement, Contractor shall furnish to Owner a certificate or certificates of insurance in a form satisfactory to the Chautauqua County Attorney, which certificate or certificates evidence the existence of the required insurance coverage, that Owner has been named as an additional insured and that the certificates provide that Owner be given at least thirty (30) days’ notice of any intent to cancel coverage. Failure to supply a satisfactory certificate within ten (10) calendar days after the date of the Notice of Award may result in cancellation of award and forfeiture of CONTRACTOR'S bid security, in the sole discretion of Owner.

9. ROYALTIES AND PATENTS

Contractor shall pay all royalties and license fees. It shall defend all suits or claims for infringement of any patent or other intellectual property rights, and shall indemnify and hold Owner harmless from loss on account thereof.

10. PERMITS AND LAWS

Contractor shall comply with all Federal, State, and Local Laws, regulations and ordinances affecting the Work, and shall give proper public authorities all requisite notice in connection with the Work.

Contractor shall, at its own expense, obtain and pay for all necessary licenses, permits, and other needed approvals, authorizations, or permissions, unless otherwise stated in the bid Special Conditions. Contractor shall be solely responsible for any damage resulting from its neglect to obey a law, regulation, rule, requirement, or ordinance. In the event Contractor performs Work called for by Contract Documents, knowing it to be contrary to a law, regulation, rule, requirement, or ordinance, it shall bear all costs, expenses, and damages arising therefrom.

Contractor shall comply with the United States Department of Labor safety and health regulations for construction, as applicable, promulgated under the Occupational Safety and Health Act of 1970 (29 USC 651 et. seq.) and under the Contract Work Hours and Safety Standards Act (40 USC 3701

et. seq., and 29 CFR Part 5), as amended. Nothing in the Act shall be construed to supersede or in any manner affect any worker's compensation law or to enlarge or diminish or affect in any manner the common law or statutory rights, duties, or liabilities of employers and employees under any law with respect to injuries, diseases, or death of employees arising out of, or in the course of, employment. The Prevailing Wage Schedule for this is PRC# 2026027374.

11. ASSIGNMENT

Contractor shall not assign any monies due to it hereunder, without the prior written consent of Owner.

12. TITLE TO PROJECT MATERIALS

a. Title to all materials to be sold by Contractor to Owner pursuant to the Agreement shall immediately vest in and become the sole property of Owner upon delivery of such materials to the site. Notwithstanding such transfer of title, Contractor shall have the sole continuing responsibility to install such materials, protect them, maintain them in proper condition and forthwith repair, replace and make good any damage thereto without cost to Owner, until such time as the Work is fully accepted by Owner. Such transfer of title shall in no way affect any of Contractor’s obligations under the Agreement. In the event that, after title to materials has passed to Owner, any such materials are rejected as being defective or otherwise unsatisfactory, Contractor shall promptly replace the defective or unsatisfactory materials with acceptable materials, at no additional cost to Owner.

b. Contractor shall, upon Owner’s request, furnish to Owner such bills of sale and other instruments as may be requested by Owner, properly executed, acknowledged, and delivered, assuring to Owner unencumbered title to materials incorporated into the completed Project.

Contractor shall mark or otherwise identify all such materials as the property of Owner.

13. EXEMPTION FROM SALES AND COMPENSATING USE TAXES AND

SURCHARGES

a. Owner is exempt from payment of sales and compensating use taxes of the State of New

York and of cities and counties on all materials separately sold to Owner pursuant to the Agreement. This exemption does not, however, apply to tools, machinery, equipment or other property purchased by, or leased by or to Contractor or a subcontractor, or to supplies or materials not incorporated into the completed Project. Contractor and its subcontractors shall pay any and all applicable taxes, including sales and compensating use taxes, on such unincorporated items, it being understood that in no case shall such tax be borne by Owner.

b. County will not pay any type of fuel surcharge unless otherwise stated in in Contract

Documents. Any unauthorized fuel charges included in Contractor’s payment requests will be disregarded.

14. LIENS

Neither the final payment under the Agreement nor any part of the retained percentage shall become due until Contractor delivers to Owner a complete release of all liens arising out of the Agreement, or receipts in full in lieu thereof, and an affidavit which certifies, so upon knowledge and information, that the releases and receipts include all the labor and materials for which a lien could be filed; but Contractor may, if any subcontractor or material supplier refuses to furnish a release or receipt in full, furnish a bond satisfactory to Owner, to indemnify Owner against any lien.

Upon Owner’s request Contractor shall, at its own expense, by bonding or otherwise, secure the prompt discharge of any lien or liens which may be filed against the property, labor, or materials in connection with the Agreement.

PROSECUTION AND PROGRESS

15. PRECONSTRUCTION CONFERENCE

At Owner’s direction, prior to commencement of Work, Contractor and its major subcontractors shall attend a preconstruction conference. The conference may include discussion of proper coordination of Work, maintenance of schedules, and other aspects of the Project.

16. ON-SITE JOB MEETINGS

On-site job meetings will be held during Project construction. Supervisory personnel representing Contractor and its major subcontractors must attend, as required in Owner’s sole discretion.

17. CONSTRUCTION SCHEDULE

a. Before commencing Work, Contractor shall submit to Owner for written approval, a construction schedule showing in detail the proposed sequence of Work, and the estimated date of starting and completing each stage of the Work in order to timely complete the Project. The schedule shall reflect the proposed percent of the value of the Agreement to be accomplished each month. If so required, the schedule shall be revised until it is approved by Owner. It is agreed and understood that Owner’s approval of Contractor’s construction schedule does not relieve Contractor from responsibility for completing its Work in accordance with the time frame specified in the Agreement. The construction schedule shall be coordinated with the proposed schedules of other contractor(s) and County workers, if any, engaged in work at the site. No payment will be made to Contractor until a construction schedule has been so approved.

b. Contractor shall coordinate its work so as to maintain its schedule(s), as approved. Should Contractor fail to adhere to any phase of the approved schedule, Contractor shall promptly adopt such additional means or methods of construction, including overtime, as may be necessary to make up lost time and complete each phase of its Work in accordance with the schedule, all at no additional cost to Owner.

c. The schedule shall be marked by Contractor to indicate progress, shall be resubmitted to Owner monthly, and shall reflect revised estimates and actual durations and percent complete. Resubmitted schedules shall be accompanied by a detailed description of Work to be accomplished during the succeeding month.

18. SUBCONTRACTORS

a. Contractor shall notify Owner in writing of the names of proposed subcontractors, noting associated work, and shall not employ any to whom Owner has a reasonable objection.

b. Contractor agrees that it is fully responsible to Owner for the acts and omissions of all subcontractors and of persons either directly or indirectly employed by Contractor, as it is for the acts and omissions of persons directly employed by it.

c. Nothing contained in Contract Documents shall create any contractual relationship between any subcontractor and Owner.

d. Wicks Law (see General Municipal Law § 101[1][a]-[c];[2]; State Finance Law § 135; and Public Authorities Law §§ 1045–i[2–a]; 1048–i[2–a]; 3303[10][c–1]; 3402[9][c–1]; 3603[9][c–1]; 3628[11][c– 1];) requires separate specifications for County public works contracts over a specified dollar threshold. The dollar threshold for Chautauqua County is $500,000.00. Contracts exceeding that amount must include separate bids for the following types of work: plumbing and gas fitting; HVAC (steam heating, hot water heating, ventilation, and air conditioning apparatus); and electrical wiring and standard illuminating fixtures.

Pursuant to GML§101(5) each bidder on a public work contract, where the preparation of separate specifications is not required, shall submit with its bid a separate sealed list that names each subcontractor that the bidder will use to perform work on the contract, and the agreed-upon amount to be paid to each, for: (a) plumbing and gas fitting, (b) steam heating, hot water heating, ventilating and air conditioning apparatus, and (c) electric wiring and standard illuminating fixtures.

After the low bid is announced, the sealed list of subcontractors submitted with such low bid shall be opened and the names of such subcontractors shall be announced, and thereafter any change of subcontractor or agreed-upon amount to be paid to each shall require the approval of County, upon a showing presented to County of legitimate construction need for such change, which shall be open to public inspection. Legitimate construction need shall include, but not be limited to, a change in project specifications, a change in construction material costs, a change to subcontractor status as determined pursuant to paragraph (e) of subdivision two of section two hundred twenty-two of the labor law, or the subcontractor has become otherwise unwilling, unable, or unavailable to perform the subcontract. The sealed lists of subcontractors submitted by all other bidders shall be returned to them unopened after the contract award.

19. COORDINATION WITH OTHER CONTRACTORS, UTILITIES, AND OWNER

FORCES

a. Owner reserves the right to let other contracts in connection with this Project, even of like character to Contractor’s Work. Owner also reserves the right to perform additional Project work using its own forces, or to have additional work performed by utilities. Contractor shall fully cooperate with others performing Project work, to prevent delays and increased Project costs and expenses. Contractor shall familiarize itself with the work of others whose work affects or ties in with its own, and shall be fully responsible for the finished result of its own Work. Contractor shall afford other Project workers adequate opportunity for the introduction and storage of their mate-rials, and the execution of their work, and shall promptly connect and coordinate its work with theirs.

b. If any part of Contractor’s Work depends upon the work of any other Project worker for proper execution or results, Contractor shall inspect and promptly report to Owner any defect in such work that renders such work unsuitable for such proper execution and results. Contactor’s failure to inspect and report shall constitute an acceptance of the other Project worker’s work as fit and proper for the receipt of its Work, except as to defects which may develop in the other Project worker’s work after Contractor’s execution of subsequent work.

c. To ensure the proper execution of Contractor’s subsequent work, Contractor shall measure work already in place, and shall at once report to Owner any measurement discrepancy between the executed work and Contract Documents.

d. Extra costs and expenses, including without limitation additional testing and inspection, and additional Owner, Consultant and other contractor services, which are caused by defective or ill-timed work, or by the neglect or refusal of Contractor to provide or complete any portion of its Work at the proper time and in the proper manner, shall be fully borne by Contactor and at no additional cost to Owner.

20. CORRECTION OF WORK

a. Contractor shall promptly remove from the premises all materials condemned by Owner as failing to meet Contract Document requirements, whether or not incorporated in the Project, and shall promptly replace and re-execute its Work in accordance with Contract Documents, without expense to Owner. Contractor shall bear all associated costs and expenses, including without limitation addi-tional testing, inspection, and Owner and Consultant services, including engineering services, made necessary thereby, and shall bear all costs and expenses of making good all work of other Project workers destroyed or damaged by such removal or replacement.

b. If Contractor does not proceed with the correction of such non-conforming work within seven

(7) days after receipt of written notice from Owner, Owner may after such seven (7) day period give Contractor a second written notice to correct such deficiencies within a second seven (7) day period.

If Contractor within such second seven (7) day period after receipt of such second notice fails to correct any deficiencies, Owner may, without prejudice to other remedies, use whatever means it deems necessary in its sole discretion, including use of its own forces, to correct such deficiencies.

In such case a change order shall be issued deducting from payments then or thereafter due Contractor the costs and expenses of correcting such deficiencies, including compensation for any Consultant, Owner, and/or Project worker’s engineering services, and other services, costs, and expenses, made necessary by failure to correct such defective Work. If payments then or thereafter due Contractor are not sufficient to cover such amounts, Contractor shall immediately pay the difference to Owner. Upon default of immediate repayment Owner may, upon seven (7) calendar days written notice, and in addition to pursuit of other remedies available to it by law, sell non-conforming materials at auction or at private sale, and pay to Contractor the net proceeds thereof, after deducting all the costs and expenses that should have been borne by Contractor.

c. If Owner prefers to accept Work which is not in accordance with Contract Documents, Owner may do so instead of requiring its removal and correction, in which case the Agreement sum will be reduced as appropriate and payment amounts withheld accordingly.

21. PAYMENTS TO THE CONTRACTOR

a. Progress payments will be made by Owner to Contractor as stated in the Agreement, and in accordance with Section 106-b of New York General Municipal Law. At least fifteen (15) days before submission of its first application for payment, Contractor shall furnish to Owner a complete breakdown of all lump sum items in the Agreement. This breakdown, modified where directed by Owner, will be used as a basis for preparing progress payments throughout the duration of the Agreement.

b. No separate payment will be made for Work-related costs or expenses, such as mobilization, materials, insurance or bonds, unless otherwise expressly stated in the Agreement.

c. No payment will be made for modifications until a formal change order for such modification has been fully executed.

d.…

This is the start of the file's text. The full file is on GovTribe.